Eric Swisher presented at the 23rd Virginia Environmental Symposium about the Major/Area Source Boiler MACT Rule. The presentation covered the regulatory framework of the rule including emission limitations, compliance options, work practice standards, startup, shutdown, and malfunction, and provided a summary of what the rule means to facilities.
Axa Assurance Maroc - Insurer Innovation Award 2024
Major/Area Source Boiler MACT Rule
1. Major/Area Source
Boiler MACT Rule
Speaker:
Eric Swisher
23rd Virginia Environmental Symposium
April 11, 2012
Your environmental compliance is clearly our business.
2. Overview
Ground Rules
Regulatory Framework
Regulated Pollutants
Emission Limitations
Compliance Options
Work Practice Standards
Startup, Shutdown, and Malfunction
Things to Take Away
2
3. Ground Rules
NHSM
Rule
Fuel is a Solid Waste Fuel is not a Solid Waste
CISWI Boiler MACT
Rule Rules
Area Major
3
4. General Information
Area or Major Source
New, Reconstructed, or Existing
Fuel Type
Design Type
4
6. Facility Type
Area Source Major Source
Not a Major Source >10 tons per year
any single HAP OR
> 25 tons per year of
any combination of
HAPs
6
7. Regulatory Citation
40 CFR Part 63 – National Emission
Standards for Hazardous Air Pollutants for
Source Categories (NESHAP):
• Subpart JJJJJJ – Area Source Boiler MACT
(ASBM)
• Subpart DDDDD – Major Source Boiler MACT
(MSBM)
7
8. History
Area Source Major Source
June 04, 2010 January 13, 2003
March 21, 2011
• Proposed December 23, 2011
• Proposed
• Comments Due March 14, 2003
• Comments Due July 19, 2010
•Promulgated •Proposed
September 13, 2004
• Promulgated
June 09, 2010 • Compliance Date September 13, 2007
• Comment Period Extended to August October 31, 2005
December 23, 2011
03, 2010 February 07, 2012
• Notice of Reconsideration
• Proposed Amendments
July 22, 2010
•Proposed Amendments •No Action Assurance
December 28, 2005
• Final Rule (with Amendments)
• Comment Period Extended to August • Compliance Date September 13, 2007
23, 2010
February 21, 2012
March 21, 2011
Letter
December 06, 2006
• Final Action on Reconsideration
June 04, 2010
• Promulgated
•Comments Due
• Proposed
December 23, 2011 • Comments Due July 19, 2010
June 09, 2010
• Proposed Amendments
• Comment Period Extended to August 03, 2010
March 13, 2012
February 21, 2012 July 22, 2010
• Comment Period Extended to August 23, 2010
• Comments Due
•No Action Assurance
March 13, 2012
March 21, 2011
• Promulgated
• No Action Assurance Letter
Letter
8
9. Act of Congress
March 08, 2012 Senate did not
pass the Collins Amendment to
the Highway Bill that would delay
the MSBM.
9
10. Current Status
Area Source Major Source
Effective Now Proposed Rule
Compliance Date •December 23, 2011
•March 21, 2014 Compliance Date
No Action Assurance •Date to Change
Letter No Action Assurance
•March 13, 2012 Letter
•February 07, 2012
10
11. Source Applicability
Area Source Major Source
Boiler Boiler
Exemptions Process Heaters
Exemptions
11
16. Emission Testing
Area Source Major Source
PM PM or TSM
Hg Hg
CO CO
HCl
16
17. Compliance Options
2. Evaluate Emission Standard Alternatives
Area Source Major Source
None Emission Averaging
Output-based
Emission Standard
• Emission
Reduction Credits
17
18. Emission Averaging
PM, HCl, or Hg
Input or Output-based Emission Standards
Existing Boiler Only
Subcategory Requirements
10% Discount Factor
Common Stack Considerations
Emission Averaging Plan
18
19. Compliance Options
3. Can Not Comply with the Emission Standards
Area Source Major Source
Fuel Management Fuel Management
Fuel Switching Fuel Switching
Controls Controls
Synthetic Minor
Energy Efficiency
Improvements
19
20. Output-based Emission Standards
Output-based Emission Standards
• Incentivizes implementation of energy
efficient technologies to minimize the
generation of emissions
20
21. Output-Based Emission Standards
Fuel Steam
Input Energy (lb Output Energy (lb
pollutant per MMBtu pollutant per MMBtu
heat input) steam output)
21
22. Capital Investment
Add-on Control Energy Efficiency
Device(s) Project(s)
22
23. Output-Based Emission Standards
How were they determined?
• Boiler Efficiency
• Heat-Input Based Limits
Subcategory Hg Emission Hg Emission Boiler
Limit Limit Efficiency
(lb Hg per MMBtu (lb Hg per MMBtu (%)
of heat input) of steam output)
Existing Boiler
Designed to Burn 3.10E-06 3.50E-06 88.6
Solid Fuel
23
24. Output-Based Emission Standards
How are they used?
• Determine Current Boiler Output-Based
Emissions
• Establish Output Energy “Benchmark”
• Investigate Energy Efficiency Projects
• Quantify Emission Reductions
• Apply Percent Reduction to Current
Boiler Output-Based Emissions
24
25. Energy Output Reduction Example
Benchmark Year* = 2,175,000 MMBtu/yr
Year After* = 1,957,500 MMBtu/yr
Tested Hg Tested Hg Adjusted Hg
Emissions Emissions Emissions
(lb Hg per MMBtu of (lb Hg per MMBtu of (lb Hg per MMBtu of
heat input) steam output) steam output)
3.40E-06 3.84E-06
3.45E-06
(Limit 3.10E-06) (Limit 3.50E-06)
*Production is assumed to be the same for both years.
25
26. Energy Output Reduction Example
Subcategory Hg Emission Hg Adjusted Result
Limit Emissions
(lb Hg per MMBtu (lb Hg per MMBtu
of steam output) of steam output)
Existing Boiler
Designed to 3.50E-06 3.45E-06 PASS
Burn Solid Fuel
26
27. Output-Based Other Considerations
Implementation Plan
Pollutant-by-Pollutant Applicability
Emissions Averaging
Shutdown Boilers
Future Boiler Operations
Other Permitting Requirements
Energy Assessment
27
28. What is Left?
Ground Rules
Regulatory Framework
Regulated Pollutants
Emission Limitations
Compliance Options
Work Practice Standards
Startup, Shutdown, and Malfunction
Things to Take Away
28
29. Work Practice Standards
Area Source Major Source
Tune-up Tune-up
Energy Energy
Assessment Assessment
Startup Good Combustion
Shutdown Practices
Startup
Shutdown
29
30. ASBM Tune-ups
Final Rule Amendments
ASBM (March 21, 2011) ASBM (December 23, 2011)
Every 2 years Every 2 years
March 21, 2012 Every 5 years
No Action Assurance (Seasonal Boilers)
Letter March 21, 2013
Fuel Type
Requirements
Common Fuel Meter
30
31. Tune-up Applicability
Area Source Major Source
New or Existing Limited-use Boilers
Coal-fired Boiler <10 Natural gas, Refinery
MMBtu/hr Gas or Gas 1 (Other)
New or Existing Boilers < 5 MMBtu/hr
Biomass-fired Boiler Gas 2 (Other), Light
New or Existing Liquid Boilers
Oil-fired Boiler
31
32. Tune-up Requirements
Area Source Major Source
Burner Inspection Burner Inspection
(1)Flame Pattern the
As applicable, inspect (1)Flame Pattern clean or
Inspect the burner and
burner, and clean or replace any replace any components of the
Inspection
components of the burner as
Inspection
burner as necessary.
Air-to-fuel system
necessary (you may delay the Air-to-fuel system
Inspection
burner inspection until the next Inspection
scheduled unit shutdown, but
CO Optimization CO Optimization
you must inspect each burner
Recordkeeping
at least once every 36 months). Recordkeeping
No Report Submittal Report Submittal
32
33. Energy Assessment
Why?
When and how often?
Who is qualified?
What equipment or systems need to be
included?
What does “cost-effective” mean?
What needs to be done?
33
34. Energy Assessment
Final Rule Amendments
ASBM (March 21, 2011) ASBM (December 23, 2011)
Existing Existing
≥ 10 MMBtu/hr ≥ 10 MMBtu/hr
Boiler System
Boiler System
Energy Use System
Energy Use System
•Onsite Only
Qualified Personnel Qualified Personnel
Maximum Duration Maximum Duration
March 21, 2014 March 21, 2014
34
35. Energy Assessment
Major Source
Scope
Maximum Time
Compliance Date
•Date to Change
Emission Reduction
Credits
35
36. Good Combustion Practices
O2 Trim Systems
• Monitor
• Optimize
• Report
Operator Training
• Startup Procedures
• Shutdown Procedures
36
37. Startup/Shutdown Periods
Boiler MACT standards apply at all times.
No exemptions from Boiler MACT
standards during periods of Startup and
Shutdown.
U.S. EPA requires work practice standards
for periods of Startup and Shutdown in
lieu of numerical emission limits.
37
38. Startup/Shutdown
Area Source Major Source
Minimize the boiler’s Good Combustion
startup and Practices
shutdown periods
following the
manufacturer’s
recommended
procedures.
38
39. Misc. Startup/Shutdown
Area Source Major Source
Startup/Shutdown Startup/Shutdown
Definitions Definitions
No SSM Plans No SSM Plans
39
40. Malfunction
Malfunction means any sudden, infrequent,
and not reasonably preventable failure of
air pollution control and monitoring
equipment, process equipment, or a process
to operate in a normal or usual manner which
causes, or has the potential to cause, the
emission limitations in an applicable standard
to be exceeded. Failures that are caused in
part by poor maintenance or careless
operation are not malfunctions.
40
41. Periods of Malfunction
Boiler MACT standards apply at all times.
No exemptions from Boiler MACT
standards during periods of Malfunction.
U.S. EPA determines if a facility
demonstrated a “good faith effort” to
minimizing emissions and correcting a
Malfunction.
41
42. Malfunction Process
Notification of a Malfunction submitted to
U.S. EPA within two (2) business days.
Follow-up report submitted to U.S. EPA
within 45 business days.
U.S. EPA evaluates the reported information
concerning the Malfunction to determine if
further inquiry or enforcement action is
required.
Facility can only use Affirmative Defense in
response to civil penalties if notification and
report is submitted.
42
43. Affirmative Defense
To use Affirmative Defense facilities
must show a “preponderance” of evidence
that:
• The excess emission was caused by a
malfunction and was not preventable or
reoccurring, and
• The facility expedited repairs, actions were
documented in signed logs, and a root-cause
analysis was completed.
43
44. SSM Plan
No SSM Plan required; however may be
more important now than ever due to
potential enforcement action.
44
45. Things to Take Away
The current status of the Boiler MACT
rules?
Where do I stand now?
What are my compliance options?
What are my compliance plans?
Be in action!
45
46. Questions?
Speaker Contact Info:
Eric M. Swisher
eswisher@all4inc.com
610.933.5246 x17
All4 Inc. - 2393 Kimberton Road - P.O. Box 299 - Kimberton, PA 19442
610.933.5246 - www.all4inc.com
46
Hinweis der Redaktion
Most of you should already know if you are a major source of HAPs or not. Meaning that your facility has a potential to emit, considering controls, of 10 tons per year or more of any single HAP or 25 tons per year or more of any combination of HAPs. If you are not a major source of HAPs then you are an Area Source of HAPs.Since we will be comparing the ASBM and MSBM, I have assigned a visual representation of each rule. For the ASBM I choose the University of Virginia Cavalier and for the MSBM I have chosen the Virginia Tech University Hokie. We you see the Cavalier, it applies to the ASBM. When you see the Hokie, it applies to the MSBM. I did not have any reason for assigning these visual aids to their particular rule other than there is a lot of uncertainty of what the final MSBM is and what a Hokie is.
[Slide No. X – ENERGY OUTPUT REDUCTION EXAMPLE] – ~X min
[SLIDE X TUNE-UPS] – ~2.5 minWhat is required for a boiler tune-up. Let’s compare the ASBM and MSBM.[CLICK] – Burner inspections are required under the ASBM and MSBM with a distinct clarification. Let’s look at the requirement. Again, it is about the language. The ASBM has “but you must inspect each burner at least once every 36 months”. This was removed from the MSBM based on comments so that the boiler does not have to shutdown to complete the burner inspection. Area source boilers will have to shut down to perform the burner inspection.[CLICK] – Flame Pattern Inspection requirement is identical for the ASBM and MSBM. The requirement is to adjust the burner as necessary to optimize the flame patternconsistent with the manufacturer’s specifications.[CLICK] – Air-to-fuel controlling system requirement is identical for the ASBM and MSBM. The requirement is to inspect the system controlling the air-to-fuel ratio and ensurethat it is correctly calibrated and functioning properly.[CLICK] – Both the ASBM and MSBM require an CO optimization as part of the tune-up. An important note on the CO optimization requirement is that you are not trying to “lower” your CO emissions (especially if you are sacrificing NOX). The intent of the CO optimization is only for good combustion practices. This is noted in the preamble to the final ASBM and assumed that it can be applied to the MSBM. The CO and O2 concentration must be measured before and after the tune-up.[CLICK] – Both the ASBM and MSBM require information to be recorded as part of the tune-up. [CLICK] – However, only the MSBM requires the information to be submitted. NOCS.
ASBM (proposed amendments)Startup means the period between the state of no combustion in the boiler to the period where the boiler first achieves 25 percent load (i.e., a cold start).Shutdown means the period that begins when the boiler last operates at 25 percent load and ending with a state of no fuel combustion in the boiler.MSBMStartup means the period between the state of no combustion in the unit to the period where the unit first achieves 25 percent load (i.e., a cold start).Shutdown means the period that begins when a unit last operates at 25 percent load and ending with a state of no fuel combustion in the unit.