1. MEASURING QUANTITIES, PRICING & COST ANALYSIS
● Mat Naim bin Abdullah @ Mohd Asmoni
● Diploma QS (UTM), BSc. QS (Glasgow
Caledonian University), M.Eng. Construction
(UTM), PhD Facilities Management (UTM)
● matnaim@utm.my
● amn871969@yahoo.com
● C04-308
● 019-7573760
www.utm.my innovative ● entrepreneurial ● global 1
2. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Assumption No. 1: Total land area = 10m x 10m
Project Title: Construction and completion of
guard house
Owner: Panicsonic Sdn Bhd
Architect: A to Z Sdn Bhd
Drawing Title: Ground beam and foundation plan
-------------------------------------------------------------------------
Drawn by: Sheila
Checked by: Aaron
www.utm.my innovative ● entrepreneurial ● global 2
4. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Construction Method
1. Preliminaries (Initial site works) - % of total cost
2. Site clearance and earthwork
3. Foundation construction (E.g. Piling and footing)
4. Work below lowest floor finish
5. Frame
6. Staircase
7. Upper Floor
8. Roof
9. Wall and partition
10. Door and window
11. Finishes
12. Sundries (Built-in furniture)
13. Building services (M&E, ICT etc)
14. External works (Water reticulation, landscape etc)
www.utm.my innovative ● entrepreneurial ● global 4
5. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
1) Site clearance
1.1) Clear the site including grubbing of Area of the site:
trees, shrubs and demolish any 10 x 10 = 100m2
existing structure and cart away
and dump to the specified
location.
10.00
10.00
----------
100.00 100 m2
----------
www.utm.my innovative ● entrepreneurial ● global 5
7. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.1) Piling including all related works Area of the building:
Length = 3048 + 3048 = 6096
6.10 Width = 3048 + 3048 = 6096
6.10
----------
37.21 37 m2
----------
www.utm.my innovative ● entrepreneurial ● global 7
8. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.2) Excavation for pile cap Size of pile cap = 1219 x 1219
Depth of excavation:
9/1.22 1524 + 50 (lean concrete) = 1574
1.22
1.57
----------
21.03 21 m3
----------
Excavation and Lean concrete as base
for pile cap
www.utm.my innovative ● entrepreneurial ● global 8
10. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.3) Reinforced concrete Grade 30 for Size of pile cap:
pile cap Length = 1219
Width = 1219
9/1.22 Thickness = 305
1.22
0.31
----------
4.15 4 m3
----------
Concrete for pile cap
www.utm.my innovative ● entrepreneurial ● global 10
11. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.4) 50mm thick lean concrete Grade Size of pile cap:
15 for pile cap Length = 1219
Width = 1219
9 / 1.22
1.22
0.05
----------
0.67 1 m3
----------
Excavation and Lean concrete as base
for pile cap
www.utm.my innovative ● entrepreneurial ● global 11
13. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.5) Formwork for pile cap Size of pile cap:
Length = 1219
9 / 4 /1.22 Width = 1219
0.31 Thickness = 305
----------
13.62 14 m2 9/2/1.22
---------- 0.31 6.81
9/2/1.50
0.31 8.37
15.18 15m2
Formwork for pile cap
www.utm.my innovative ● entrepreneurial ● global 13
14. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
2) Foundation
2.6) Reinforcement bar Y12 for pile cap Length:
a c
9/2/ 12/ 1.53
---------- b
330.48m x 0.89 kg/m = 294.13kg = a + b + c – cover
---------- = 305 + 1219 + 305 – 6(50)
= 294 kg = 1829 – 300
= 1529
No. of bars:
= (b/100) + 1
= ((1219 – 2(50)cover )/100 )+1
= 12 nos.
www.utm.my innovative ● entrepreneurial ● global 14
16. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF Taker off : Checked by:
3.1) Column stump Size of column stump:
3.1.1) Reinforced concrete Grade 30 Length = 229
for column stump Width = 229
Height = 1524 – 305 thickness of pile
9/0.23 cap – (351/2) Half of beam’s
0.23 thickness
1.04 = 1043.50
----------
0.50 1 m3
----------
www.utm.my innovative ● entrepreneurial ● global 16
17. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.1) Column stump Size of column stump:
3.1.2) Formwork for column stump Length = 229
Width = 229
9/4/0.23 Height = 1524 – 305 thickness of pile
1.04 cap – (351/2) Half of beam’s
---------- thickness
8.61 9 m2 = 1043.50
----------
www.utm.my innovative ● entrepreneurial ● global 17
18. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Height of column stump
@100 c/c
www.utm.my innovative ● entrepreneurial ● global 18
19. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.1) Column stump Length = a + half beam’s thickness –
3.1.3) Reinforcement bar Y12 for cover + 2 laps
column stump lap
9/4/2.97
---------- a
106.92m x 0.89kg/m = 95.16kg
---------- lap
95kg
= 1524 + (351/2) – 50 + (660x2)
= 2969.50
www.utm.my innovative ● entrepreneurial ● global 19
21. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.1) Column stump Length of link: (length of CS– 2cover) x
3.1.4) R6 link in for column stump 4 +hook Hook
9/6/0.62
----------
33.48m x 0.22kg/m = 7.36kg =(229-100)+(229-100)+(229-100)+(229-
---------- 100)+100=616
7kg
No. of link:
Height of column stump = 1043.50
=(1043.50/229)+1
= 6 nos.
www.utm.my innovative ● entrepreneurial ● global 21
22. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Size of ground beam:
3.2.1) Excavation for ground beam Length=3048+3048=6096
Width = 229
2/3/6.10 Thickness = 351
0.23
0.35
----------
2.95m3
----------
3m3
Excavation for ground beam
www.utm.my innovative ● entrepreneurial ● global 22
23. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Size of ground beam:
3.2.2) Reinforced concrete Grade 30 for Length=3048+3048=6096
ground beam Width = 229
Thickness = 351
2/3/6.10
0.23
0.35
----------
2.95m3 3m3
----------
RC for ground beam
www.utm.my innovative ● entrepreneurial ● global 23
24. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Size of ground beam:
3.2.3) 50mm thick lean concrete Grade Length=3048+3048=6096
15 for ground beam Width = 229
Thickness = 351
2/3/6.10
0.23
0.05
----------
0.42m3 1 m3
----------
RC for ground beam
www.utm.my innovative ● entrepreneurial ● global 24
25. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Assumption No. 1: Total land area = 10m x 10m
Project Title: Construction and completion of
guard house
Owner: Panicsonic Sdn Bhd
Architect: A to Z Sdn Bhd
Drawing Title: Ground beam and foundation plan
-------------------------------------------------------------------------
Drawn by: Sheila
Checked by: Aaron
www.utm.my innovative ● entrepreneurial ● global 25
26. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Height of column stump
@100 c/c
www.utm.my innovative ● entrepreneurial ● global 26
27. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Size of ground beam:
3.2.4) Formwork for ground beam Length=3048+3048=6096
Width = 229
Thickness = 351
2/3/2/6.10
0.35
----------
25.62 26m2
----------
Installation of reinforcement bar and
formwork for ground beam
www.utm.my innovative ● entrepreneurial ● global 27
28. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Length = (length–2cover)+(2bend-
3.2.5) Reinforcement bar Y10 for 2cover)
ground beam =(6096-(2x50))+(2x351)-(4x50)
= 6498
2/3/4/6.50
----------
156.00m x 0.62kg/m = 96.72kg
----------
97kg
www.utm.my innovative ● entrepreneurial ● global 28
29. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.2) Ground beam Length of stirrup:
3.2.6) R6 stirrup for ground beam Hook
2/3/28/0.86
---------- =(229-100)+(351-100)+(229-100)+(351-
144.48m x 0.22kg/m = 31.79kg 100)+100
---------- =860
32kg
No. of stirrup:
Length of grd beam= 6096
=(6096/229)+1
= 28 nos.
www.utm.my innovative ● entrepreneurial ● global 29
30. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab including apron = length x width
3.3.1) Excavation for ground slab Depth of excavation = 500mm
7.30
7.30 BRC A8
150mm thick
concrete slab
0.50
----------
26.65m3 27 m3
---------- 50mm thick
sand
300mm thick
hardcore
DPM
6096 + 1200 (apron) = 7296
Installation of formwork,Damp Proof Membrane
(DPM) and BRC wire mesh for ground slab
www.utm.my innovative ● entrepreneurial ● global 30
31. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.2) Reinforced concrete G30 in Depth of excavation = 500mm
ground slab
150mm thick
BRC A8
concrete slab
7.30
7.30
0.15 50mm thick
---------- sand
7.99m3 300mm thick
hardcore
---------- 8 m3
DPM
www.utm.my innovative ● entrepreneurial ● global 31
32. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.3) Formwork for ground slab Depth of excavation = 500mm
4/7.30 BRC A8
150mm thick
concrete slab
0.15
----------
4.38m2 50mm thick
---------- sand
4 m2 300mm thick
hardcore
DPM
www.utm.my innovative ● entrepreneurial ● global 32
33. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of
Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab including apron
3.3.4) BRC A8 for ground slab Depth of excavation = 500mm
150mm thick
BRC A8
concrete slab
7.30
7.30
---------- 50mm thick
sand
53.29m2 300mm thick
---------- hardcore
53 m2 DPM
Length = 6096 + 1200 = 7296
www.utm.my innovative ● entrepreneurial ● global 33
34. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of
Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.5) DPM for ground slab Depth of excavation = 500mm
150mm thick
BRC A8
53 m2 concrete slab
50mm thick
sand
300mm thick
hardcore
DPM
www.utm.my innovative ● entrepreneurial ● global 34
35. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.6) 50mm sand blinding for ground Depth of excavation = 500mm
slab
150mm thick
BRC A8
53 m2 concrete slab
50mm thick
sand
300mm thick
hardcore
DPM
www.utm.my innovative ● entrepreneurial ● global 35
36. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab Area of slab = length x width
3.3.7) Hardcore for ground slab Depth of excavation = 500mm
7.30 BRC A8
150mm thick
concrete slab
7.30
0.30
---------- 50mm thick
15.99m3 sand
---------- 300mm thick
hardcore
16 m3
DPM
www.utm.my innovative ● entrepreneurial ● global 36
37. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.4) Half round glazeware perimeter Area of slab = length x width
drain size 150mm diameter Depth of excavation = 500mm
4/7.30 BRC A8
150mm thick
concrete slab
----------
29.20m
---------- 50mm thick
29 m sand
300mm thick
hardcore
DPM
www.utm.my innovative ● entrepreneurial ● global 37
38. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME Taker off : Checked by:
4.1) Column Size of column:
4.1.1) Reinforced concrete Grade 30 Length = 229
for column Width = 229
Height = Height of the wall
9/0.23 = 3000mm
0.23
3.00
----------
1.43 1 m3
----------
Installation of reinforcement bar and
formwork for column
www.utm.my innovative ● entrepreneurial ● global 38
39. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME
4.1) Column Size of column:
4.1.2) Formwork for column Length = 229
Width = 229
9/4/0.23 Height = 3000
3.00
----------
24.84 25 m2
----------
www.utm.my innovative ● entrepreneurial ● global 39
40. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME
4.1) Column Length = height of column + half of roof
4.1.3) Reinforcement bar Y12 for beam + 1 lap + bend
column
bend
9/4/4.50
---------- Height of wall
162.00m x 0.89kg/m = 144.18kg
----------
144kg
lap
= 3000+ (0.5x351) + 660 + 660
= 4495.5
www.utm.my innovative ● entrepreneurial ● global 40
41. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME
4.1) Column Length of link: (length of CS– 2cover) x
4.1.4) R6 link in for column 4 +hook
Hook
9/14/0.82
----------
103.32m x 0.22kg/m = 22.73kg =(229-50)+(229-50)+(229-50)+(229-
---------- 50)+100=816
23kg
No. of link:
Height of column = 3000
=(3000/229)+1
= 14 nos.
www.utm.my innovative ● entrepreneurial ● global 41
42. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME
4.2) Roof beam Size of roof beam:
4.2.1) Reinforced concrete Grade 30 for Length=3048+3048=6096
roof beam Width = 229
Thickness = 351
2/3/6.10
0.23
0.35
----------
2.95m3
----------
3m3
www.utm.my innovative ● entrepreneurial ● global 42
43. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME
4.2) Roof beam Size of roof beam:
4.2.2) Formwork for roof beam Length=3048+3048=6096
Width = 229 Side
Thickness = 351
2/3/6.10 Soffit
0.93
----------
34.04 34m2
----------
= 351 + 229 + 351
= 931
www.utm.my innovative ● entrepreneurial ● global 43
44. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME
4.2) Roof beam Length = (length–2cover)+(2bend-
4.2.3) Reinforcement bar Y10 for roof 2cover)
beam =(6096-(2x50))+(2x351)-(4x50)
= 6498
2/3/4/6.50
----------
156.00m x 0.62kg/m = 96.72kg
----------
97kg
www.utm.my innovative ● entrepreneurial ● global 44
45. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
4) FRAME
3.2) Roof beam Length of stirrup:
3.2.5) R6 stirrup for roof beam Hook
2/3/28/1.06
---------- =(229-50)+(351-50)+(229-50)+(351-
178.08m x 0.22kg/m = 39.18kg 50)+100
---------- =1060
39kg
No. of stirrup:
Length of beam= 6096
=(6096/229)+1
= 28 nos.
www.utm.my innovative ● entrepreneurial ● global 45
46. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Assumption No. 1: Total land area = 10m x 10m
Project Title: Construction and completion of
guard house
Owner: Panicsonic Sdn Bhd
Architect: A to Z Sdn Bhd
Drawing Title: Ground beam and foundation plan
-------------------------------------------------------------------------
Drawn by: Sheila
Checked by: Aaron
www.utm.my innovative ● entrepreneurial ● global 46
47. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
5) ROOF = area of roof
=axbx2 a 3m
5.1) Steel roof trusses and corrugated
aluminium steel roof covering
2/8.50 a = 42482 + 30002
5.20
---------- Front and rear elevation
88.40m2 88 m2 a = 5200
----------
b = 6096 +
1200 + b
1200
b = 8496
Right and left elevation
www.utm.my innovative ● entrepreneurial ● global 47
48. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
6) DOOR and WINDOW Door can be
measured either a 3m
6.1) Single leaf panel door size 2100 x 900 in m2 or
including frame and painting number. If
enumerated then
2/2.10 need to state
0.90 type and size
---------- Front and rear elevation
3.78 4 m2 or 2 nos
----------
b
Right and left elevation
www.utm.my innovative ● entrepreneurial ● global 48
49. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
6) DOOR and WINDOW Window can be
measured either a 3m
6.2) Adjustable louvres window 1200 x 600 in m2 or
including frame , painting and glass number. If
enumerated then
need to state
2/6/1.20 type and size
0.60 Front and rear elevation
----------
8.64 8.64 m2 or 12 nos
----------
b
Right and left elevation
www.utm.my innovative ● entrepreneurial ● global 49
50. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
7) WALL AND PARTITION
a 3m
7.1) Half brickwall in comon brick
4/ 6.10
3.00 73.20
Less opening (e.g. door and window) Front and rear elevation
2/2.10
0.90 3.78 (door)
61 m2 b
2/6/1.20
0.60 8.64 (window)
Brickwall
60.78
Right and left elevation
www.utm.my innovative ● entrepreneurial ● global 50
51. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
8) FINISHES Area of plastering
and panting = a 3m
8.1) Wall - Plastering and painting Area of wall x 2
2/ 61m2 122 m2 Area of ceiling =
area of slab
8.2) Floor Finishes – cement render Front and rear elevation
53 m2
b
8.3) Ceiling 53 m2
Brickwall
Right and left elevation
www.utm.my innovative ● entrepreneurial ● global 51
52. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
9) SUNDRIES Assumption.
9.1) Built-in counter size 1800mm x 900mm 1 no of counter for frontdesk.
x 725mm(h).
1
1 no.
www.utm.my innovative ● entrepreneurial ● global 52
53. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
1. Site Clearance
1. 1 Clear the site including grubbing of trees,
shrubs and demolish any existing M2 100 2.40 240.00
structure and cart away and dump to
the specified location.
1. Site Clearance 240.00
2. Foundation
2.1 Piling works
2.2 Excavation for pile cap < 2m deep M3 21 39.50 829.50
2.3 Reinforced concrete G30 M3 4 286.30 1,145.20
2.4 Lean concrete G15 M3 1 194.50 194.50
2.5 Sawn formwork M2 14 29.60 414.40
2.6 Reinforcement bar Y12 Kg 294 3.00 882.00
2. Foundation 3,465.60
www.utm.my innovative ● entrepreneurial ● global 53
54. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
3. WBLFF
3.1 Column Stump
3.1.1 Reinforced Concrete G30 M3 1 297.10 297.10
3.1.2 Sawn formwork M2 9 29.80 268.20
3.1.3 Reinforcement bar Y12 Kg 95 3.00 285.00
3.1.4 Reinforcement bar R6 Kg 7 3.00 21.00
Total 871.30
3.2 Ground beam
3.2.1 Excavation for ground beam < 1m deep M3 3 20.80 62.40
3.2.2 Reinforced concrete G30 M3 3 293.50 880.50
3.2.3 Lean concrete G15 M3 1 201.70 201.70
3.2.4 Sawn formwork M2 26 29.60 769.60
3.2.5 Reinforcement bar Y12 Kg 97 3.00 291
3.2.6 Reinforcement bar R6 Kg 32 3.00 96
Total 2,301.20
www.utm.my innovative ● entrepreneurial ● global 54
55. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
3. WBLFF
3.3 Ground slab
3.2.1 Excavation for ground slab < 1m deep M3 27 20.80 561.60
3.2.2 Reinforced concrete G30 M3 8 293.50 2,348.00
3.2.3 Sawn formwork M2 4 29.60 118.40
3.2.4 BRC A8 M2 53 23.10 1,224.30
3.2.5 DPM M2 53 12.90 683.70
3.2.6 Sand blinding M2 53 2.60 137.80
3.2.7 Hardcore M3 16 51.80 828.80
Total 5,902.60
3.4 Perimeter Drain
Half round glazeware 150mm dia. M 29 11.30 327.70
3. WBLFF 9,402.80
www.utm.my innovative ● entrepreneurial ● global 55
56. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
4. Frame
4.1 Column
4.1.1 Reinforced Concrete G30 M3 1 297.10 297.10
4.1.2 Sawn formwork M2 25 29.80 745.00
4.1.3 Reinforcement bar Y12 Kg 144 3.00 432.00
4.1.4 Reinforcement bar R6 Kg 23 3.00 69.00
Total 1,543.10
4.2 Roof Beam
4.2.1 Reinforced Concrete G30 M3 3 297.10 891.30
4.2.2 Sawn formwork to sides & soffit M2 34 29.80 1,013.20
4.2.3 Reinforcement bar Y10 Kg 97 3.00 291.00
4.2.4 Reinforcement bar R6 Kg 39 3.00 117.00
Total 2,312.50
4. Frame 3,855.60
www.utm.my innovative ● entrepreneurial ● global 56
57. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
5. Roof and covering
5. 1 Steel roof trusses and corrugated
aluminium steel roof covering M2 88 133.30 11,730.40
5. Roof and covering 11,730.40
6. Door and Window
6.1 Single leaf panel door size 2100 x 900
including frame and painting No 2 250.00 500.00
6.2 Adjustable louvres window 1200 x 600
including frame , painting and glass No 12 120.00 1,440.00
6. Door and window 1,940.00
www.utm.my innovative ● entrepreneurial ● global 57
58. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities Unit Quantity Rate Amount
7. Wall and partition
7. 1 Half brickwall in common brick M2 61 39.00 2,379.00
7. Wall and partition 2,379.00
8. Finishes
8.1 Wall finishes – plastering & painting M2 122 17.70 2,159.40
8.2 Floor finishes – cement rendering M2 53 10.60 561.80
8.3 Ceiling – gypsum plaster board M2 53 17.70 938.10
8. Finishes 3,659.30
9. Sundries
9. 1 Built-in counter size 1800mm x 900mm No. 1 1500.00 1,500.00
x 725mm(h).
www.utm.my innovative ● entrepreneurial ● global 58
59. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Summary of Bills of Quantities Amount (RM)
1. Site clearing 240.00
2. Foundation 3,271.1
3. WBLFF 9,402.80
4. Frame 3,855.60
5. Roof and covering 11,730.40
6. Door and window 1,940.00
7. Wall and partition 2,379.00
8. Finishes 3,659.30
9. Sundries 1,500.00
Subtotal #1 37,978.20
10. Building services (5%) 1,898.91
11. External works (3%) 1,139.35
Subtotal #2 41,016.46
12. Preliminaries (3%) 1,230.49
Total 42,246.95
www.utm.my innovative ● entrepreneurial ● global 59
60. MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd GFA = 37m2
Building Cost Analysis Cost/GFA = 1,136.00
Summary Amount (RM) Amount (RM) Actual % Normal % Explanation:
1. Site Clearing 240.00 -under Prelim - -
2. Foundation 3,271.1 3,280.00 8%
10 -20%
3. WBLFF 9,402.80 9,400.00 21%
4. Frame 3,855.60 3,860.00 9% 5-10%
5. Roof and covering 11,730.40 11,730.00 27% 20-25%
6. Door and window 1,940.00 1,940.00 5% 5-10%
7. Wall and partition 2,379.00 2,400.00 6% 5-10%
8. Finishes 3,659.30 3,660.00 9% 6-15%
9. Sundries 1,500.00 1,500.00 4% 1-5%
Subtotal #1 37,978.20
10. Building services (5%) 1,898.91 1,900.00 5% 10-25%
11. External works (5%) 1,139.35 1,140.00 3% 3-7%
Subtotal #2 41,016.46
12. Preliminaries (5%) 1,230.49 1,230.00 3% 3-7%
Total 42,246.95 42,040.00 100
www.utm.my innovative ● entrepreneurial ● global 60