Anzeige
 Scuba Duba Corporation uses the following activity rates from its act.pdf
Nächste SlideShare
 Scraper Production Estimating You are using 631E Scrapers for an eart.pdf Scraper Production Estimating You are using 631E Scrapers for an eart.pdf
Wird geladen in ... 3
1 von 1
Anzeige

Más contenido relacionado

Más de ajantawatchkota(16)

Último(20)

Anzeige

Scuba Duba Corporation uses the following activity rates from its act.pdf

  1. Scuba Duba Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Data for one of the company's products follow: How much overhead cost would be assigned to Product I90W using the activity-based costing system? $5,963.20 S63.188.80 $108.20 $253.80 Solution $5,963.20 Activity Cost Pools Activity Rate Basis Activity Overhead Cost Assembling Products 4.70 Assembly hour 530.00 2,491.00 Processing customer orders 89.40 Customer order 36.00 3,218.40 Setting up batches 14.10 Batch 18.00 253.80 Total Overhead Cost 5,963.20