A) What is the optimal job sequence, the makespan and the deadtime for the following set of Jobs? A) What is the optimal job sequence, the makespan and the deadtime for the following set of Jobs?Duration In Hours OnJob IDMachine #1Machine #2A57B23C61D34E46F84 Solution BDECAF, by the time the Job B is done on machine #2 Job D will be finishing on Machine #1. There is the smallest time gap when ordering them this way..