SlideShare ist ein Scribd-Unternehmen logo
1 von 39
3RD ANNUAL ASIA PACIFIC 
DISTRICT COOLING CONFERENCE 
KUALA LUMPUR 
26 – 28TH AUGUST 2014 
DEVELOPMENT OF THE MALAYSIA’S FIRST SATELLITE 
REMOTE CHARGING 100,000RTH CHILLED WATER 
STORAGE SYSTEM AT GAS DISTRICT COOLING (GDC) 
PJP4 AT LOT 4U2, PRECINCT 4, 
PUTRAJAYA CORE ISLAND 
BY 
IR. ARUL HISHAM BIN ABDUL RAHIM 
BSME, P.Eng, FIEM, MASHRAE, MACEM 
PRINCIPAL 
AHAR Consultants 
LEAD CONSULTANT PJP4
BACKGROUND OF AHAR Consultants 
2
COMPLETED PROJECTS 
3
4 OUTLINE
DESIGN DEVELOPMENT 
5
6 
GDC (P) 
SDN BHD 
OWNER 
Putrajaya 
Holdings 
DEVELOPER 
KLCC Projeks 
PROJECT MANAGER 
AHAR 
Consultants 
LEAD CONSULTANT 
Prisma Athira 
Architects 
ARCHITECT 
Total Project 
Solution 
Consultant 
C&S ENGINEER 
AS2 Sdn Bhd 
QUANTITY SURVEYOR 
FVB Energy Inc 
USA 
TECHNICAL ADVISOR 
Sunway 
Construction 
EPCC BUILDER 
AHAR Consultants 
PROCESS AND M&E 
ENGINEER 
PROJECT TEAM ORGANIZATION
DESIGN BRIEF 
UTILIZATION OF PLOT 4U2 FOR FUTURE COOLING LOAD 
OF THE CORE ISLAND, PUTRAJAYA WITH SPACE 
RESERVED FOR FUTURE EXPANSION 
FULL UTILIZATION OF GAS TURBINE AND EQUIPMENT 
FROM PJP2; NO START/STOP TURBINE OPERATION 
MINIMIZE ELECTRICAL POWER IMPORT FROM TNB 
DURING PEAK PERIOD 
REASONABLE CAPEX 
SUSTAINABLE OPEX AND COST OF OWNERSHIP 
7
8 METHODOLOGY 
NEED 
STATEMENT 
CAPACITY 
PLANNING 
(CORE ISLAND) 
HYDRAULIC 
STUDY 
OPTIONS STUDY ON 
TYPE OF SYSTEM 
•GENERATION SYSTEMS 
•PHASING OF EQMT 
•COST OF OWNERSHIP 
•UNIT UTILITY COST 
TANK TYPES OPTIONS 
•STEEL 
•CONCRETE: 
•RECTANGLE 
•CYLINDRICAL 
DETAIL DESIGN TENDER & 
CONSTRUCTION 
TESTING & 
COMMISSIONING 
MONITORING 
OF 
PERFORMANCE
9 LOCATION 
PLOT 4U2 
PLOT 4U2 
PjP4 
PULLMAN 
HOTEL 
MINISTRY OF 
FINANCE
CORE ISLAND CHILLED WATER PIPE 
10 RETICULATION NETWORK 
PjP2 
PjP4 
FUTURE PLANT
11 LOAD PROJECTION & PLANTING UP 
Projection based on 
parcels’ 
development 
schedule 
Historical average 
3,650RT/yr (2003-09) 
WE ARE HERE 
PjP2 Equipment derating 
Tank 1 
Tank 2 
4,000RT/yr
SNAPSHOT OF LOAD PROFILE CORE ISLAND– 
MARCH 2009 
12
PjP2 GENERATING CAPACITY 
Equipment Quantity Generating capacity 
(RT) 
Firm Generating 
Capacity (RT) 
STEAM ABSORPTION 
CHILLER 
11 10 x 2 500 25 000 
ELECTRICAL CHILLER 2 2 x 1 250 2 500 
DIRECT FIRED CHILLER 2 2 x 1 350 2 700 
Σ = 30 200 RT 
GAS TURBINE 2 2 X 4.5 MW 9.0 MW 
13
14 THE SOLUTION
CONCLUSION OF STUDY 
 PJP2 WAS DESIGNED TO GENERATE A MAXIMUM CAPACITY OF 
30,200RT. SINCE THERE IS VERY LITTLE NIGHT LOAD, IT IS 
THEORETICALLY POSSIBLE TO STORE UP TO 300,000RTH OF CHILLED 
WATER FROM PJP2. 
 PJP4 IS DESIGNED AS A HYBRID PLANT CONSISTING OF CHILLED 
WATER STORAGE AND CONVENTIONAL CHILLERS. 
 A SATELLITE STRATIFIED CHILLED WATER STORAGE SYSTEM IS 
SELECTED TO BE INSTALLED AT PJP4 SITE TO STORE THE CHILLED 
WATER GENERATED FROM PJP2 DURING OFF-PEAK PERIOD. 
 OPERATE PJP2 AT NIGHT TO STORE CHILLED WATER AT PJP4 
 PJP2 AND PJP4 OPERATE SIMULTINEOUSLY DURING DAYTIME TO 
MEET COOLING LOAD 
15
PLANT # 4 CHARGE SCENARIO 
EXISTING 
PLANT # 2 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
OPEN 
OPEN 
16 
TES TANK TES TANK 
56⁰F / 13.3 C(RETURN) 
43⁰F / 6.1C (SUPPLY) 
40⁰F / 4.4C (SUPPLY) 
PIPES WITH NO FLOW
PLANT # 4 DISCHARGE SCENARIO 
EXISTING 
PLANT # 2 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
CHILLER 
OPEN 
CLOSED 
TES TANK TES TANK 
56⁰F / 13.3 C(RETURN) 
43⁰F / 6.1C (SUPPLY) 
40⁰F / 4.4C (SUPPLY) 
PIPES WITH NO FLOW 
17
18 PjP4 SITE LAYOUT
19 PLAN EQUIPMENT LAYOUT (ULTIMATE)
PLANT ISOMETRIC PIPING 
(PHASE 1 WITH 1 UNIT STORAGE TANKS) 
20
PLANT ISOMETRIC PIPING 
(ULTIMATE PHASE CHW STORAGE TANKS AND 
ELECTRIC CHILLERS) 
21 
PJP 4 TES CAP 
(RTh) 
ECC (RT) PEAK 
OUTPUT 
(RT) 
PHASE 1 100,000 15,000 
PHASE 2 100,000 15,000 
PHASE 3 12,000 12,000 
TOTAL 42,000 
PJP 2 30,200
22 ARTIST’S IMPRESSION OF ULTIMATE PjP4
23 CONSTRUCTION
24 PLANT CONSTRUCTION 
Tank under construction Stumps for bottom diffuser support 
Installation of top diffuser Installation of bottom diffuser
25 PLANT CONSTRUCTION 
Tank plinth construction 
1200mm pipe installation 
750mm tank wall
26 PLANT COMPLETION
PERFORMANCE ANALYSIS 
27
28 
BASIC CHW TANK OPERATION 
CHARGING MODE 
WARM WATER 
PIPE OUT 
PIPE IN 
THERMOCLINE 
COLD WATER 
DIFFUSER PIPE 
SYSTEM
BASIC CHW TANK OPERATION 
29 DISCHARGING MODE 
WARM WATER 
PIPE IN 
PIPE OUT 
THERMOCLINE 
COLD WATER 
DIFFUSER PIPE 
SYSTEM
30 CHW TANK SPECIFICATIONS AND PERFORMANCE 
Specifications Design Actual 
Rated Storage Capacity 100,000 RTh @ 6.5 C dT 109,012 RTh @ 6.5C dT 
Thermocline Thickness Less than 1.5m Between 0.6 – 1.0m 
Water Volume 14 Mil US Gallons/53,000 
cu.m 
11.62 Mil US 
Gallons/52,862 cu.m 
Figure of Merit More than 90% 92.5% 
Rated discharge 
capacity 
12,000 RT 15,991 RT 
Diffuser Reynolds # Max 2,000 1,991 
Diffuser Froude # Less than 0.5 0.09 
Heat loss over 24 hours 2% of rated capacity 0.57% of rated capacity
31 DIFFUSER THERMOCLINE PERFORMANCE 
 MOST SIGNIFICANTLY IS THE THERMOCLINE THICKNESS AVERAGING 0.8 
METERS THICK COMPARED TO 1.5 – 2 METERS THICKNESS COMMONLY 
ELSEWHERE WORLDWIDE. 
 THIS THIN THERMOCLINE THICKNESS INDICATES THAT THE DIFFUSERS ARE 
WORKING PROPERLY WHERE THE COLD AND WARM WATER BODIES ARE 
PROPERLY STRATIFIED IN THE TANK.
CURRENT 32 OPERATING REGIME 
MONDAY FRIDAY
PjP 2 33 EQUIPMENT OPERATION
34 BENEFITS 
40% OF PEAK 
LOAD BY TES 
4 MW 
LESS CHILLERS 
OPERATING 
DURING PEAK 
PERIOD
PjP4 CARBON FOOTPRINT COMPARISON vs GRID 
CONNECTED CONVENTIONAL CHILLER PLANT 
35 
1,115 tCO2 
PER WK 599 tCO2 
NATURAL GAS 
28,458 GJ 
PER WK 
EMISSION REDUCTION 
23,000 tCO2 P.A. 
GRID ELECTRICITY 
50 MWh 
1,044 tCO2 
PER WK 
GRID ELECTRICITY 
1,409 MWh 
(APPROX) 
-43% 
VS 
1,568,000 RTh 
Cooling Output 
+ Pumping 
440,500 RTh 
Cooling Output 
+ Pumping 
440,500 RTh 
Cooling Output 
+ Pumping
36 WRAP UP
CONCLUSIONS 
 DISTRICT COOLING & THERMAL STORAGE: 
 EXCELLENT TOOL FOR DEMAND SIDE MANAGEMENT 
 SUSTAINABLE ENERGY COST 
 REDUCTION OF ELECTRICITY MAXIMUM DEMAND @ PEAK 
PERIOD 
 INCREASE THE LOAD SUPPLY CAPABILITY AND ENHANCE THE 
RELIABILITY AND AVAILABILITY OF THE CHILLED WATER. 
 IMPROVES REDUNDANCY OF THE SYSTEM AS LESS 
EQUIPMENT IS REQUIRED TO BE RUN DURING PEAK PERIOD 
 BETTER UTILIZATION OF ASSETS 
37
UNIQUENESS OF PjP4 
 PJP4 HAS BEEN IN OPERATION TO SUPPLY CHILLED WATER TO 
PRECINCTS 3 AND 4 IN PUTRAJAYA CORE ISLAND SINCE JANUARY 
2013. 
 OPERATION RESULTS HAVE SHOWN THAT THE OPERATION OF 
THIS CHW SYSTEM HAS ACHIEVED THE EXPECTATIONS OF THE 
OWNER AND DESIGN TEAM. 
 IS THE FIRST REMOTE SATELLITE CHILLED WATER STORAGE SYSTEM FOR A 
DISTRICT COOLING PLANT IN MALAYSIA 
 CHW TANK DIMENSIONS OF 45M DIAMETER AND 32M HIGH (EQUIVALENT TO 
A 10-STOREY HIGH BUILDING); WITH 750MM THICK PRE-STRESSED CONCRETE 
WALL IS BELIEVED TO BE THE BIGGEST REINFORCED CONCRETE CHILLED 
WATER TANK IN MALAYSIA; AS WELL AS IN THE WORLD 
 CARBON EMISSION OF THE PJP4 IS REDUCED BY 43% COMPARED TO GRID 
CONNECTED CONVENTIONAL ELECTRIC CHILLER PLANT 
38
39 THANK YOU We ain’t sell nothing but expertise 
www.aharconsultants.com.my

Weitere ähnliche Inhalte

Was ist angesagt?

TERI-The Energy And Resource Institute
TERI-The Energy And Resource  InstituteTERI-The Energy And Resource  Institute
TERI-The Energy And Resource Institute
Apoorva Gupta
 
What is the eden project
What is the eden project What is the eden project
What is the eden project
Youngman Kim
 
Theory of design- unit 5 Contemporary design thinking process b.arch regulat...
 Theory of design- unit 5 Contemporary design thinking process b.arch regulat... Theory of design- unit 5 Contemporary design thinking process b.arch regulat...
Theory of design- unit 5 Contemporary design thinking process b.arch regulat...
Kethees Waran
 

Was ist angesagt? (20)

Kongu Convention Center
Kongu Convention CenterKongu Convention Center
Kongu Convention Center
 
earth air tunnel latest ppt
earth air tunnel latest pptearth air tunnel latest ppt
earth air tunnel latest ppt
 
Ghsb 130218 design presentation
Ghsb 130218 design presentationGhsb 130218 design presentation
Ghsb 130218 design presentation
 
Oxford golf resort Pune
Oxford golf resort PuneOxford golf resort Pune
Oxford golf resort Pune
 
Water efficiency in green buildings
Water efficiency in green buildingsWater efficiency in green buildings
Water efficiency in green buildings
 
Denver union station
Denver union stationDenver union station
Denver union station
 
TERI-The Energy And Resource Institute
TERI-The Energy And Resource  InstituteTERI-The Energy And Resource  Institute
TERI-The Energy And Resource Institute
 
Sobha City - Bangalore
Sobha City - BangaloreSobha City - Bangalore
Sobha City - Bangalore
 
Building services & Standards For Institutional Building
Building services & Standards For Institutional BuildingBuilding services & Standards For Institutional Building
Building services & Standards For Institutional Building
 
Community park (cl)
Community park (cl)Community park (cl)
Community park (cl)
 
Neighbourhood park
Neighbourhood parkNeighbourhood park
Neighbourhood park
 
What is the eden project
What is the eden project What is the eden project
What is the eden project
 
high rise seismic resistant buildings
 high rise seismic resistant buildings high rise seismic resistant buildings
high rise seismic resistant buildings
 
100 Plus Plants Identification in Malaysia
100 Plus Plants Identification in Malaysia100 Plus Plants Identification in Malaysia
100 Plus Plants Identification in Malaysia
 
District cooling design & case study
District cooling design & case studyDistrict cooling design & case study
District cooling design & case study
 
Long span cable
Long span cableLong span cable
Long span cable
 
Nearly Zero Energy Building (nZEB) in Malaysia
Nearly Zero Energy Building (nZEB) in MalaysiaNearly Zero Energy Building (nZEB) in Malaysia
Nearly Zero Energy Building (nZEB) in Malaysia
 
Theory of design- unit 5 Contemporary design thinking process b.arch regulat...
 Theory of design- unit 5 Contemporary design thinking process b.arch regulat... Theory of design- unit 5 Contemporary design thinking process b.arch regulat...
Theory of design- unit 5 Contemporary design thinking process b.arch regulat...
 
Space frames!
Space frames!Space frames!
Space frames!
 
Thai
Thai Thai
Thai
 

Andere mochten auch

Kompleks Perbadanan Putrajaya
Kompleks Perbadanan Putrajaya Kompleks Perbadanan Putrajaya
Kompleks Perbadanan Putrajaya
Hilmi Awaludin
 
BRIGHT Indonesia Profile
BRIGHT Indonesia ProfileBRIGHT Indonesia Profile
BRIGHT Indonesia Profile
primadi_ws
 
Picc theorizing architecture finalized
Picc theorizing architecture finalizedPicc theorizing architecture finalized
Picc theorizing architecture finalized
Dexter Ng
 
Energy efficiency in malaysia -------ppt
Energy efficiency in malaysia   -------pptEnergy efficiency in malaysia   -------ppt
Energy efficiency in malaysia -------ppt
Bhc Kuala Lumpur
 
Fatty acids and triglycerides
Fatty acids and triglyceridesFatty acids and triglycerides
Fatty acids and triglycerides
Nur Fatihah
 

Andere mochten auch (14)

Putrajaya.ppt
Putrajaya.pptPutrajaya.ppt
Putrajaya.ppt
 
Kompleks Perbadanan Putrajaya
Kompleks Perbadanan Putrajaya Kompleks Perbadanan Putrajaya
Kompleks Perbadanan Putrajaya
 
BRIGHT Indonesia Profile
BRIGHT Indonesia ProfileBRIGHT Indonesia Profile
BRIGHT Indonesia Profile
 
Putrajaya
PutrajayaPutrajaya
Putrajaya
 
Ct report
Ct reportCt report
Ct report
 
PUTRAJAYA SITE ANALSYS - TEAM CY
PUTRAJAYA SITE ANALSYS - TEAM CYPUTRAJAYA SITE ANALSYS - TEAM CY
PUTRAJAYA SITE ANALSYS - TEAM CY
 
Picc theorizing architecture finalized
Picc theorizing architecture finalizedPicc theorizing architecture finalized
Picc theorizing architecture finalized
 
Theorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention CentreTheorizing Architecture : Putrajaya International Convention Centre
Theorizing Architecture : Putrajaya International Convention Centre
 
Development of the Malaysia’s first satellite remote charging District Coolin...
Development of the Malaysia’s first satellite remote charging District Coolin...Development of the Malaysia’s first satellite remote charging District Coolin...
Development of the Malaysia’s first satellite remote charging District Coolin...
 
Energy efficiency in malaysia -------ppt
Energy efficiency in malaysia   -------pptEnergy efficiency in malaysia   -------ppt
Energy efficiency in malaysia -------ppt
 
Petronas towers
Petronas towersPetronas towers
Petronas towers
 
Tourism Impacts Presentation - Malaysia
Tourism Impacts Presentation - MalaysiaTourism Impacts Presentation - Malaysia
Tourism Impacts Presentation - Malaysia
 
Topic 3 District Cooling System
Topic 3 District Cooling SystemTopic 3 District Cooling System
Topic 3 District Cooling System
 
Fatty acids and triglycerides
Fatty acids and triglyceridesFatty acids and triglycerides
Fatty acids and triglycerides
 

Ähnlich wie Case study plant4 putrajaya[arul hisham]

Hisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsHisham hajaj, stanley consultants
Hisham hajaj, stanley consultants
Sarah El Akkad
 
Experimental investigate to obtain the effectiveness of regenerator using Air.
Experimental investigate to obtain the effectiveness of regenerator using Air.Experimental investigate to obtain the effectiveness of regenerator using Air.
Experimental investigate to obtain the effectiveness of regenerator using Air.
IJESFT
 

Ähnlich wie Case study plant4 putrajaya[arul hisham] (20)

Study Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power PlantStudy Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
 
Project ppt
Project pptProject ppt
Project ppt
 
Pearson Star&Alfa District Cooling And Desalination
Pearson Star&Alfa District Cooling And DesalinationPearson Star&Alfa District Cooling And Desalination
Pearson Star&Alfa District Cooling And Desalination
 
6272149
62721496272149
6272149
 
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
A STUDY ON ROLE OF CONDENSER AND NATURAL DRAFT COOLING TOWER ON THE PERFORMAN...
 
Safety and nuclear power plant in india
Safety and nuclear power plant  in india Safety and nuclear power plant  in india
Safety and nuclear power plant in india
 
Experimental Analysis of Refrigeration system using Microchannel condenser & ...
Experimental Analysis of Refrigeration system using Microchannel condenser & ...Experimental Analysis of Refrigeration system using Microchannel condenser & ...
Experimental Analysis of Refrigeration system using Microchannel condenser & ...
 
Industrial training report on NHPC TLD-III
Industrial training report on NHPC TLD-IIIIndustrial training report on NHPC TLD-III
Industrial training report on NHPC TLD-III
 
Harnessing geothermal power in islands and remote areas: The Pico Alto geothe...
Harnessing geothermal power in islands and remote areas: The Pico Alto geothe...Harnessing geothermal power in islands and remote areas: The Pico Alto geothe...
Harnessing geothermal power in islands and remote areas: The Pico Alto geothe...
 
Jeevan joy, spig
Jeevan joy, spigJeevan joy, spig
Jeevan joy, spig
 
This presentation is based on Refrigeration and air conditioning
This presentation is based on Refrigeration and air conditioningThis presentation is based on Refrigeration and air conditioning
This presentation is based on Refrigeration and air conditioning
 
Seminar report on otec
Seminar report on otecSeminar report on otec
Seminar report on otec
 
Seminar Report On OCEAN THERMAL ENERGY CONVERSION
Seminar Report On OCEAN THERMAL ENERGY CONVERSIONSeminar Report On OCEAN THERMAL ENERGY CONVERSION
Seminar Report On OCEAN THERMAL ENERGY CONVERSION
 
Aircooling underground coal mine
 Aircooling underground coal mine Aircooling underground coal mine
Aircooling underground coal mine
 
400 bpm dual filling sytem(completed)
400 bpm dual filling sytem(completed)400 bpm dual filling sytem(completed)
400 bpm dual filling sytem(completed)
 
Hisham hajaj, stanley consultants
Hisham hajaj, stanley consultantsHisham hajaj, stanley consultants
Hisham hajaj, stanley consultants
 
Benfield system
Benfield systemBenfield system
Benfield system
 
Experimental investigate to obtain the effectiveness of regenerator using Air.
Experimental investigate to obtain the effectiveness of regenerator using Air.Experimental investigate to obtain the effectiveness of regenerator using Air.
Experimental investigate to obtain the effectiveness of regenerator using Air.
 
ARCHITECTURE THESIS 2
ARCHITECTURE THESIS 2ARCHITECTURE THESIS 2
ARCHITECTURE THESIS 2
 
JE Final Presentation
JE Final PresentationJE Final Presentation
JE Final Presentation
 

Kürzlich hochgeladen

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Kürzlich hochgeladen (20)

Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 

Case study plant4 putrajaya[arul hisham]

  • 1. 3RD ANNUAL ASIA PACIFIC DISTRICT COOLING CONFERENCE KUALA LUMPUR 26 – 28TH AUGUST 2014 DEVELOPMENT OF THE MALAYSIA’S FIRST SATELLITE REMOTE CHARGING 100,000RTH CHILLED WATER STORAGE SYSTEM AT GAS DISTRICT COOLING (GDC) PJP4 AT LOT 4U2, PRECINCT 4, PUTRAJAYA CORE ISLAND BY IR. ARUL HISHAM BIN ABDUL RAHIM BSME, P.Eng, FIEM, MASHRAE, MACEM PRINCIPAL AHAR Consultants LEAD CONSULTANT PJP4
  • 2. BACKGROUND OF AHAR Consultants 2
  • 6. 6 GDC (P) SDN BHD OWNER Putrajaya Holdings DEVELOPER KLCC Projeks PROJECT MANAGER AHAR Consultants LEAD CONSULTANT Prisma Athira Architects ARCHITECT Total Project Solution Consultant C&S ENGINEER AS2 Sdn Bhd QUANTITY SURVEYOR FVB Energy Inc USA TECHNICAL ADVISOR Sunway Construction EPCC BUILDER AHAR Consultants PROCESS AND M&E ENGINEER PROJECT TEAM ORGANIZATION
  • 7. DESIGN BRIEF UTILIZATION OF PLOT 4U2 FOR FUTURE COOLING LOAD OF THE CORE ISLAND, PUTRAJAYA WITH SPACE RESERVED FOR FUTURE EXPANSION FULL UTILIZATION OF GAS TURBINE AND EQUIPMENT FROM PJP2; NO START/STOP TURBINE OPERATION MINIMIZE ELECTRICAL POWER IMPORT FROM TNB DURING PEAK PERIOD REASONABLE CAPEX SUSTAINABLE OPEX AND COST OF OWNERSHIP 7
  • 8. 8 METHODOLOGY NEED STATEMENT CAPACITY PLANNING (CORE ISLAND) HYDRAULIC STUDY OPTIONS STUDY ON TYPE OF SYSTEM •GENERATION SYSTEMS •PHASING OF EQMT •COST OF OWNERSHIP •UNIT UTILITY COST TANK TYPES OPTIONS •STEEL •CONCRETE: •RECTANGLE •CYLINDRICAL DETAIL DESIGN TENDER & CONSTRUCTION TESTING & COMMISSIONING MONITORING OF PERFORMANCE
  • 9. 9 LOCATION PLOT 4U2 PLOT 4U2 PjP4 PULLMAN HOTEL MINISTRY OF FINANCE
  • 10. CORE ISLAND CHILLED WATER PIPE 10 RETICULATION NETWORK PjP2 PjP4 FUTURE PLANT
  • 11. 11 LOAD PROJECTION & PLANTING UP Projection based on parcels’ development schedule Historical average 3,650RT/yr (2003-09) WE ARE HERE PjP2 Equipment derating Tank 1 Tank 2 4,000RT/yr
  • 12. SNAPSHOT OF LOAD PROFILE CORE ISLAND– MARCH 2009 12
  • 13. PjP2 GENERATING CAPACITY Equipment Quantity Generating capacity (RT) Firm Generating Capacity (RT) STEAM ABSORPTION CHILLER 11 10 x 2 500 25 000 ELECTRICAL CHILLER 2 2 x 1 250 2 500 DIRECT FIRED CHILLER 2 2 x 1 350 2 700 Σ = 30 200 RT GAS TURBINE 2 2 X 4.5 MW 9.0 MW 13
  • 15. CONCLUSION OF STUDY  PJP2 WAS DESIGNED TO GENERATE A MAXIMUM CAPACITY OF 30,200RT. SINCE THERE IS VERY LITTLE NIGHT LOAD, IT IS THEORETICALLY POSSIBLE TO STORE UP TO 300,000RTH OF CHILLED WATER FROM PJP2.  PJP4 IS DESIGNED AS A HYBRID PLANT CONSISTING OF CHILLED WATER STORAGE AND CONVENTIONAL CHILLERS.  A SATELLITE STRATIFIED CHILLED WATER STORAGE SYSTEM IS SELECTED TO BE INSTALLED AT PJP4 SITE TO STORE THE CHILLED WATER GENERATED FROM PJP2 DURING OFF-PEAK PERIOD.  OPERATE PJP2 AT NIGHT TO STORE CHILLED WATER AT PJP4  PJP2 AND PJP4 OPERATE SIMULTINEOUSLY DURING DAYTIME TO MEET COOLING LOAD 15
  • 16. PLANT # 4 CHARGE SCENARIO EXISTING PLANT # 2 CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER OPEN OPEN 16 TES TANK TES TANK 56⁰F / 13.3 C(RETURN) 43⁰F / 6.1C (SUPPLY) 40⁰F / 4.4C (SUPPLY) PIPES WITH NO FLOW
  • 17. PLANT # 4 DISCHARGE SCENARIO EXISTING PLANT # 2 CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER CHILLER OPEN CLOSED TES TANK TES TANK 56⁰F / 13.3 C(RETURN) 43⁰F / 6.1C (SUPPLY) 40⁰F / 4.4C (SUPPLY) PIPES WITH NO FLOW 17
  • 18. 18 PjP4 SITE LAYOUT
  • 19. 19 PLAN EQUIPMENT LAYOUT (ULTIMATE)
  • 20. PLANT ISOMETRIC PIPING (PHASE 1 WITH 1 UNIT STORAGE TANKS) 20
  • 21. PLANT ISOMETRIC PIPING (ULTIMATE PHASE CHW STORAGE TANKS AND ELECTRIC CHILLERS) 21 PJP 4 TES CAP (RTh) ECC (RT) PEAK OUTPUT (RT) PHASE 1 100,000 15,000 PHASE 2 100,000 15,000 PHASE 3 12,000 12,000 TOTAL 42,000 PJP 2 30,200
  • 22. 22 ARTIST’S IMPRESSION OF ULTIMATE PjP4
  • 24. 24 PLANT CONSTRUCTION Tank under construction Stumps for bottom diffuser support Installation of top diffuser Installation of bottom diffuser
  • 25. 25 PLANT CONSTRUCTION Tank plinth construction 1200mm pipe installation 750mm tank wall
  • 28. 28 BASIC CHW TANK OPERATION CHARGING MODE WARM WATER PIPE OUT PIPE IN THERMOCLINE COLD WATER DIFFUSER PIPE SYSTEM
  • 29. BASIC CHW TANK OPERATION 29 DISCHARGING MODE WARM WATER PIPE IN PIPE OUT THERMOCLINE COLD WATER DIFFUSER PIPE SYSTEM
  • 30. 30 CHW TANK SPECIFICATIONS AND PERFORMANCE Specifications Design Actual Rated Storage Capacity 100,000 RTh @ 6.5 C dT 109,012 RTh @ 6.5C dT Thermocline Thickness Less than 1.5m Between 0.6 – 1.0m Water Volume 14 Mil US Gallons/53,000 cu.m 11.62 Mil US Gallons/52,862 cu.m Figure of Merit More than 90% 92.5% Rated discharge capacity 12,000 RT 15,991 RT Diffuser Reynolds # Max 2,000 1,991 Diffuser Froude # Less than 0.5 0.09 Heat loss over 24 hours 2% of rated capacity 0.57% of rated capacity
  • 31. 31 DIFFUSER THERMOCLINE PERFORMANCE  MOST SIGNIFICANTLY IS THE THERMOCLINE THICKNESS AVERAGING 0.8 METERS THICK COMPARED TO 1.5 – 2 METERS THICKNESS COMMONLY ELSEWHERE WORLDWIDE.  THIS THIN THERMOCLINE THICKNESS INDICATES THAT THE DIFFUSERS ARE WORKING PROPERLY WHERE THE COLD AND WARM WATER BODIES ARE PROPERLY STRATIFIED IN THE TANK.
  • 32. CURRENT 32 OPERATING REGIME MONDAY FRIDAY
  • 33. PjP 2 33 EQUIPMENT OPERATION
  • 34. 34 BENEFITS 40% OF PEAK LOAD BY TES 4 MW LESS CHILLERS OPERATING DURING PEAK PERIOD
  • 35. PjP4 CARBON FOOTPRINT COMPARISON vs GRID CONNECTED CONVENTIONAL CHILLER PLANT 35 1,115 tCO2 PER WK 599 tCO2 NATURAL GAS 28,458 GJ PER WK EMISSION REDUCTION 23,000 tCO2 P.A. GRID ELECTRICITY 50 MWh 1,044 tCO2 PER WK GRID ELECTRICITY 1,409 MWh (APPROX) -43% VS 1,568,000 RTh Cooling Output + Pumping 440,500 RTh Cooling Output + Pumping 440,500 RTh Cooling Output + Pumping
  • 37. CONCLUSIONS  DISTRICT COOLING & THERMAL STORAGE:  EXCELLENT TOOL FOR DEMAND SIDE MANAGEMENT  SUSTAINABLE ENERGY COST  REDUCTION OF ELECTRICITY MAXIMUM DEMAND @ PEAK PERIOD  INCREASE THE LOAD SUPPLY CAPABILITY AND ENHANCE THE RELIABILITY AND AVAILABILITY OF THE CHILLED WATER.  IMPROVES REDUNDANCY OF THE SYSTEM AS LESS EQUIPMENT IS REQUIRED TO BE RUN DURING PEAK PERIOD  BETTER UTILIZATION OF ASSETS 37
  • 38. UNIQUENESS OF PjP4  PJP4 HAS BEEN IN OPERATION TO SUPPLY CHILLED WATER TO PRECINCTS 3 AND 4 IN PUTRAJAYA CORE ISLAND SINCE JANUARY 2013.  OPERATION RESULTS HAVE SHOWN THAT THE OPERATION OF THIS CHW SYSTEM HAS ACHIEVED THE EXPECTATIONS OF THE OWNER AND DESIGN TEAM.  IS THE FIRST REMOTE SATELLITE CHILLED WATER STORAGE SYSTEM FOR A DISTRICT COOLING PLANT IN MALAYSIA  CHW TANK DIMENSIONS OF 45M DIAMETER AND 32M HIGH (EQUIVALENT TO A 10-STOREY HIGH BUILDING); WITH 750MM THICK PRE-STRESSED CONCRETE WALL IS BELIEVED TO BE THE BIGGEST REINFORCED CONCRETE CHILLED WATER TANK IN MALAYSIA; AS WELL AS IN THE WORLD  CARBON EMISSION OF THE PJP4 IS REDUCED BY 43% COMPARED TO GRID CONNECTED CONVENTIONAL ELECTRIC CHILLER PLANT 38
  • 39. 39 THANK YOU We ain’t sell nothing but expertise www.aharconsultants.com.my

Hinweis der Redaktion

  1. This is the outline of the presentation
  2. This is the methodology during the development of Plant 4. Upon identifying the needs, we proceeded with the capacity planning study of the Core Island. We also did a hydraulic study on the pipe reticulation network to check the hydraulically remote location. During the Option Study phase, we look at various generation technologies; Steam absorption chillers, direct fired chillers, electric centrifugal chillers, thermal storage and various combinations of these technologies. We also looked at the phasing of equipment in relation to the load growth & utilities price increase to arrive to the most optimal cost of ownership and generation unit cost. We also looked at various tank configurations; cylindrical and rectangular as well as the materials to be used.
  3. This is the aerial view of Putrajaya core island. Plot 4U2 is located mid-way of the core island; behind the Ministry of Youth and Sports building.
  4. This is the chilled water reticulation network at Core Island. The main pipes are 900mm diameter (in blue) running from Plant 2 all the way to the Southern end. PjP2, commissioned in 2003; designed primarily to serve Precinct 2, was extended to provide cooling to Precincts 3 and 4. There is another plot reserved for future plant at the southern end Precinct 4
  5. This is the load projections in 2009. The red line is the load projection based on original individual parcel’s schedule. The historical load growth from 2003 to 2009 was averaging 3,650RT per year. Taking into consideration PjP2’s equipment derating, the decision by GDC to construct PjP4 is timely; as the current load is about 25,000 - 26,000RT. GDC is now able to supply the load with sufficient capacity as buffer
  6. This is a typical weekday cooling load profile of the Core Island in 2009. From 6 to 8 am, the maximum pull down load occurs. Between 6 – 7am much cooling is used to cool the water in the reticulation pipe from 18C down to 6C. The buildings start operation of the air side at about 7am. This load can be as high as 20% of the average load. From 10.30am to 5.30pm, the load is relatively constant. There is very little night load as these buildings are all government offices.
  7. This is PjP2 available rated generating capacity. The electrical and direct fired chillers are mainly used for peaking loads; as they are more costly to operate. Electrical power generated by the GTs are used in-house and not exported.
  8. This is the schematic of the system envisaged for PjP4. Charging of the tank is done at night. CHW at 6C from PjP2 is pumped into the tanks at PJP4. In the ultimate phase, electric chillers at PjP4 can be used to cool the CHW further to 4.4C. This would increase the CHW storage capacity by another 30%.
  9. In the discharging mode, both plants 2 and 4 inject CHW into the reticulation network simultaneously. PJP2 would serve loads at the northern part whilst PjP4 would supply to precincts 3 and 4 at the southern part.
  10. PjP4 was planned as a hybrid plant consisting of chilled water storage and chillers. The construction of the plant shall be phased. For Phase 1, we install 1 unit of chilled water storage tank of nominal rated capacity of 100,000 RTh with associated booster pumps For Future Phases – additional 1 unit chilled water storage tank of nominal rated capacity of 100,000 RTh and/or installation of electric chillers depending on the load growth
  11. This is the internal layout of PjP4. The dotted line indicates future plant area.
  12. This is the pumps layout for Phase 1 and 2
  13. Ultimately, PjP4 is envisioned to generate 42,000 RT from 30,000 RT from chilled water tanks and 12,000 RT from electric chillers.
  14. This is an artist impression of the ultimate plant
  15. These are the photo after the filling up of the tank. The contractor had to use a small boat to go around inside the tank. The middle picture is the inside of the plant building. Currently, only booster pumps are installed with pipe headers ready for connection for future phases.
  16. This is how charging of chilled water tank. Chilled water at 6C is pumped into the tank from the bottom diffuser. Warm water at 12C is extracted out from tank from the top diffuser It is very important that these water bodies do not get mixed up during this process. These chilled and warm water is separated by a layer of thermocline. To ensure proper formation of thermocline, the diffuser must be properly designed to ensure the water flow is laminar and no mixing takes place.
  17. The water flows are reversed during discharging process. Warm water enters the tank from top diffuser and chilled water exits the tank from bottom diffuser. The layer of thermocline moves up and down during the charging and discharging process.
  18. This graph shows detailed equipment operation at PjP2. As can be seen, the chillers output is almost constant day and night at around 15,000RT. By flattening out the chillers output profile, the operation of gas turbine can be better managed as the steam consumption is constant night and day
  19. Peaking morning pull down load is taken up by PjP4 without having to run additional chillers from PjP2. This has reduced the quantity of chillers required to meet the demand; hence, enhancing the reliability and availability of the overall system. PjP4 is currently discharging about 40% of the peak period load demand. Currently, PjP2 is supplying about 15,000RT and PjP4 supplies averaging 10,000RT. PjP4 also reduces the TNB electricity import of PjP2 by 4MW. 4MW can be translated to about RM154,000 per month of maximum demand savings if we use C2 commercial Tariff at RM38.60/kW max demand.
  20. If we compare the carbon emission of PjP4 current cooling output to a grid-connected conventional electrical chiller plant with the same output, there is a 43% reduction of CO2 emission. This translates to approximately a reduction of 123,000 tons CO2 per annum
  21. In summary, using district cooling and thermal storage are excellent tool for electricity demand side management. It helps in the reduction of energy cost by reducing the maximum demand charge during peak period. Having this system, increase the load supply capability and enhance the reliability and availability of the system. Thermal storage also improves the redundancy of the system as less equipment is required during peak period. Therefore, the owner can have standby equipment should any of the machine breaks down.