1Q12 Results
May, 2012
1Q12 Highlights


               Investments totaled R$ 21 million, mainly in the modernization of Nova Avanhandava (347 MW) and

                Ibitinga (132 MW) power plants
Operational
               Energy generation 30% higher than physical guarantee and 10% greater than the total generated in

                1Q11


               Net revenue of R$ 540 million, 30% greater than 1Q11

               R$ 20 million increase in expenses with energy purchased for resale and biannual locks
                maintenance and R$ 19 million increase in costs and operational expenses
Financial
               Ebitda reached R$ 423 million, with margin of 78%

               Net income of R$ 246 million, an increase of 27% comparing to 1Q11




               Dividends distribution of R$ 264 million, related to 1Q12 results, corresponding to R$ 0.66 per
Dividends
                 common share and R$ 0.73 per preferred share. Payment will occur on May 25, 2012.


                                                                                                                   2
Despite the comfortable reservoir levels in SIN1 , lower rainfall
                                                    in February, March and April pushed prices in the spot
                                                                                                      market

Reservoirs Level inSIN1                                               PLD2 – Monthly Average (R$/MWh)




                                                    99%   99%                                         193
                        92%
  83%                                         82%
          79%                          76%
                                                                                           125




                               35%                                          48                                                                    46
                                                                                 51                                                         37
                                                                 29                                                32      23   20    21                     44
                                                                  23                  26
                                                                                                 12          17

                                                                      jan    feb      mar        apr        may    jun    jul   aug   sep   oct   nov   dec
 Southeast/               South        Northeast     North
                                                                                                            2010         2011     2012
 Middle-West
                                1Q11   1Q12




 1- Interconnected National System
 2- Spot Market Average Price                                                                                                                            3
High level of Company’s reservoirs and
                                                                                          operational availability

Reservoirs level of AES Tietê’s power plants1                            Energy generation (MW average3)

                                                                                                                           136%
                                                                           130%                                                              130%
                                                                                             125%           124%




                                                      96%
                          100%




                                                                   98%
                                                             99%
             94%
      99%




                                               90%
                                   78%




                                                                                                                                             1,753
                                                                           1,665
                                                                                           1,599            1,582             1,612




A. Vermelha2
A. Vermelha         Promissão2
                     Promissão                B. Bonita2
                                               B. Bonita    Caconde 2
                                                             Caconde       2009            2010              2011             1Q11           1Q12
(11   km3)                (8.1km3)             (3.6km3)      (0.6km 3)


                                       1Q11    1Q12                           Generation - Mwavg                              Generation/Physical guarantee

        Average:                 98%          89%

  1 – As of 03/31/2012
                                                                              3 – Generated energy divided by the amount of period hours
  2 – Reservoirs volume                                                                                                                                4
Investments in 1Q12 mainly oriented to the modernization of
                                                          Nova Avanhandava and Ibitinga power plants

Investments (R$ million)                                                Investments in 1Q12


                            175

                             19
                                                                                         86%


           82
                                     174
           12               156
                                                  38                                             11%
                                                         4    21                          3%
           70
                                                                    2
                                                  34
                                                              19

          2010             2011     2012(e)     1Q11         1Q12
                                                                                   Equipment and Maintenance

                           Investments     New SHPPs 1                             New SHPPs

                                                                                   IT Projects
  1 - Small Hydro Power Plants                                                                                 5
Growth Opportunities and Capacity Expansion Obligation


Termo-SP Project

-   Gas unavailability for A-5 in 2011 and A-3 Energy Auction in 2012

-   Project registered in A-5 in 2012: term to present gas contract expires on June 1st, 2012

-   Injunction suspending the Environmental License. AES Tietê presented its defense on April 27th

-   Fullfillment of conditions to obtain the installation license



Termo Araraquara Project

-   Acquisition of a purchase option in March, 2012

-   Combined cycle, gas-fired power plant, with 579 MW of installed capacity

-   The project has a high sinergy potential with Termo SP and is equally registered in A-5 auction in 2012


Expansion Obligation

-   April 26th: Presentation of the plan to extent the Company’s capacity
                                                                                                              6
Higher energy volume sold in 1Q12 due to the seasonality of
                                            the bilateral contract with AES Eletropaulo, besides the
                                                                                energy sold in ERM*
       Billed Energy (GWh)


                                                                 +34%
                                                                              4,867

                                                       3,645                   162
                                                                               570
                                                         108
                                                         424                 1,256
                                                         587


                                                        2,526                2,879




                                                        1Q11                  1Q12


                          AES Eletropaulo   Energy Reallocation Mechanism*   Spot Market   Other Bilateral Contracts
                                                                                                                       7
*ERM – Energy Reallocation Mechanism
Strategy for energy contracting in 2016: client portfolio
                                                                                         creation
Clients portfolio evolution




                                                                • Goals:

                                                                - Expand and diversify client portfolio by
         Assured Energy (1,282 MW avg)                            2015

                                                                - Allocate most of the assured energy to
                                                                  the free market
                                     Consolidated
                                                                - Opportunity to negotiate the energy
                New client             portfolio
                                                                  from projects that the Company will
                 portfolio
                                                                  develop in coming years

  2012                        2016                   2020
Changes in the seasonality and 8.65% readjustment in AES
                                   Eletropaulo’s contract contributed for the net revenue
                                                                               expansion
Net revenue (R$ million)


                                               +30%
                                                         540
                                                                 46
                                        416                      18
                                               17
                                               14


                                                         477
                                        385




                                       1Q11              1Q12


            AES Eletropaulo     Spot/Energy Reallocation Mechanism    Other bilateral contracts

                                                                                                  9
Increase in expenses with energy purchased and biannual
                                                            locks maintenance, besides the increase in operational
                                                                                              costs and expenses

        Operational costs and expenses¹ (R$ million)


                                                                                                    4                  3
                                                                                  5
                                                                   7
                                                    9
                              11

                                                                                                                      114           117
         78




        1Q11           Energy Purchased           Locks        Operational    Personnel,     Transmission and   Financ. Comp. For   1Q12
                           for Resale          Maintenance   Provisions and   Material and      Connection      Use of Water Res.
                                                             Other Expenses   Third-party
                                                                               services²




1 – Do not include depreciation and amortization                                                                                           10
2 – Personnel, Material and Third-party services
Ebitda margin reached 78% in 1Q12


Ebitda (R$ million)




                      81%
                                      78%




                                    423
                        338




                       1Q11        1Q12
                      EBITDA   EBITDA Margin (%)



                                                                    11
CDI* variation and lower average cash balance
                                                                                        impacted financial result


                                       Financial Result (R$ million)




                                                        1Q11               1Q12




                                                          (11)              (10)




*CDI - Interbank Deposit Certificate                                                                           12
Net income 27% higher in 1Q12, reflecting the good
                                                                        performance of revenues

Net Income (R$ million)

        118%
                                  107%



                                  2.9%                           Distribution of R$ 264 million in dividends related
       2.5%                                                       to 1Q12:

                                                                    - R$0.66 per common share
                                                                    - R$0.73 per preferred share
                                                                    - Ex-dividends: May 04, 2012
                                                                    - Date of Payment: May 25, 2012
                                   246
         193




         1Q11                     1Q12
                         Payout
    Yield Preferred Shares        Net Profit                                                                        13
Cash flow reflects higher revenues from the bilateral contract


Operating Cash Flow (R$ million)                   Final Cash Balance (R$ million)


                +28%                                                      -17%




                             382                                  499
          299                                                                        413



         1Q11               1Q12                                 1Q11                1Q12




                                                                                            14
Low leverage with net debt/Ebitda of 0.3 times



Net Debt (R$ billion)                           Average Cost and Average Term (Principal)


                                                             3.01

            0.4x                                                                              2.01
                          0.3x




                        0.54                                 114%                         115%
             0.45




             1Q11       1Q12                                  1Q11                        1Q12

                                                               14.0%     Effective rate 11.3%
       Net Debt         Net Debt/EBITDA
                                                                                                        1




                                                    1 – Percentage of CDI (Interbank Deposit Certificate)   15
1Q12 Results
The statements contained in this document with regard to the
business prospects, projected operating and financial results,
and growth potential are merely forecasts based on the
expectations of the Company’s Management in relation to its
future performance.
Such estimates are highly dependent on market behavior and
on the conditions affecting Brazil’s macroeconomic
performance as well as the electric sector and international
market, and they are therefore subject to changes.

Weitere ähnliche Inhalte

Was ist angesagt?

Quarterly Report 30 September 2010
Quarterly Report 30 September 2010Quarterly Report 30 September 2010
Quarterly Report 30 September 2010Edison S.p.A.
 
2nd Annual Brazil Conference – Itaú Securities
2nd Annual Brazil Conference – Itaú Securities2nd Annual Brazil Conference – Itaú Securities
2nd Annual Brazil Conference – Itaú SecuritiesEDP - Energias do Brasil
 
Apresentação call tiete 2 q11_final
Apresentação call tiete 2 q11_finalApresentação call tiete 2 q11_final
Apresentação call tiete 2 q11_finalAES Tietê
 
"10th Annual Latin American Conference"
"10th Annual Latin American Conference""10th Annual Latin American Conference"
"10th Annual Latin American Conference"Petrobras
 
Webcast4 t06ingles
Webcast4 t06inglesWebcast4 t06ingles
Webcast4 t06inglesPetrobras
 
Financial analysis paladin energy ltd - paladin energy limited primarily ex...
Financial analysis   paladin energy ltd - paladin energy limited primarily ex...Financial analysis   paladin energy ltd - paladin energy limited primarily ex...
Financial analysis paladin energy ltd - paladin energy limited primarily ex...BCV
 
Quarterly Report 31March 2011
Quarterly Report 31March 2011Quarterly Report 31March 2011
Quarterly Report 31March 2011Edison S.p.A.
 
Apresentação call tiete 4 q11_final
Apresentação call tiete 4 q11_finalApresentação call tiete 4 q11_final
Apresentação call tiete 4 q11_finalAES Tietê
 
el paso 0803ClearyCOGA
el paso  0803ClearyCOGAel paso  0803ClearyCOGA
el paso 0803ClearyCOGAfinance49
 
MAS: Idris Jala 6 Secrets of Business Transformation
MAS: Idris Jala 6 Secrets of Business TransformationMAS: Idris Jala 6 Secrets of Business Transformation
MAS: Idris Jala 6 Secrets of Business TransformationAdzfar 'Ed' Aziz
 
Yngve Myhre - CEO SalMar ASA - How to deliver margins trough low cost product...
Yngve Myhre - CEO SalMar ASA - How to deliver margins trough low cost product...Yngve Myhre - CEO SalMar ASA - How to deliver margins trough low cost product...
Yngve Myhre - CEO SalMar ASA - How to deliver margins trough low cost product...Norwegian Seafood Council
 
Corporate presentation november_2011_4
Corporate presentation november_2011_4Corporate presentation november_2011_4
Corporate presentation november_2011_4NALenergy
 
first energy MorganStanley307
first energy MorganStanley307first energy MorganStanley307
first energy MorganStanley307finance21
 

Was ist angesagt? (18)

Impact Silver Corp. Presentation
Impact Silver Corp. PresentationImpact Silver Corp. Presentation
Impact Silver Corp. Presentation
 
Quarterly Report 30 September 2010
Quarterly Report 30 September 2010Quarterly Report 30 September 2010
Quarterly Report 30 September 2010
 
amd_ar2000
amd_ar2000amd_ar2000
amd_ar2000
 
2nd Annual Brazil Conference – Itaú Securities
2nd Annual Brazil Conference – Itaú Securities2nd Annual Brazil Conference – Itaú Securities
2nd Annual Brazil Conference – Itaú Securities
 
Apresentação call tiete 2 q11_final
Apresentação call tiete 2 q11_finalApresentação call tiete 2 q11_final
Apresentação call tiete 2 q11_final
 
Oi
OiOi
Oi
 
"10th Annual Latin American Conference"
"10th Annual Latin American Conference""10th Annual Latin American Conference"
"10th Annual Latin American Conference"
 
2Q08 Results
2Q08 Results2Q08 Results
2Q08 Results
 
Webcast4 t06ingles
Webcast4 t06inglesWebcast4 t06ingles
Webcast4 t06ingles
 
Financial analysis paladin energy ltd - paladin energy limited primarily ex...
Financial analysis   paladin energy ltd - paladin energy limited primarily ex...Financial analysis   paladin energy ltd - paladin energy limited primarily ex...
Financial analysis paladin energy ltd - paladin energy limited primarily ex...
 
Quarterly Report 31March 2011
Quarterly Report 31March 2011Quarterly Report 31March 2011
Quarterly Report 31March 2011
 
Apresentação call tiete 4 q11_final
Apresentação call tiete 4 q11_finalApresentação call tiete 4 q11_final
Apresentação call tiete 4 q11_final
 
Apre 3 t09
Apre 3 t09Apre 3 t09
Apre 3 t09
 
el paso 0803ClearyCOGA
el paso  0803ClearyCOGAel paso  0803ClearyCOGA
el paso 0803ClearyCOGA
 
MAS: Idris Jala 6 Secrets of Business Transformation
MAS: Idris Jala 6 Secrets of Business TransformationMAS: Idris Jala 6 Secrets of Business Transformation
MAS: Idris Jala 6 Secrets of Business Transformation
 
Yngve Myhre - CEO SalMar ASA - How to deliver margins trough low cost product...
Yngve Myhre - CEO SalMar ASA - How to deliver margins trough low cost product...Yngve Myhre - CEO SalMar ASA - How to deliver margins trough low cost product...
Yngve Myhre - CEO SalMar ASA - How to deliver margins trough low cost product...
 
Corporate presentation november_2011_4
Corporate presentation november_2011_4Corporate presentation november_2011_4
Corporate presentation november_2011_4
 
first energy MorganStanley307
first energy MorganStanley307first energy MorganStanley307
first energy MorganStanley307
 

Andere mochten auch

SharePoint UserGroup Stuttgart - Toni Pohl - Office 365 Development News Over...
SharePoint UserGroup Stuttgart - Toni Pohl - Office 365 Development News Over...SharePoint UserGroup Stuttgart - Toni Pohl - Office 365 Development News Over...
SharePoint UserGroup Stuttgart - Toni Pohl - Office 365 Development News Over...atwork
 
1Q09 Earnings Call Presentation
1Q09 Earnings Call Presentation1Q09 Earnings Call Presentation
1Q09 Earnings Call PresentationAES Tietê
 
Управление репутацией в посике - SERM
Управление репутацией в посике - SERMУправление репутацией в посике - SERM
Управление репутацией в посике - SERMPromodo
 
Marketing of Hand-crafted Products-B.V.Raghunandan
Marketing of Hand-crafted Products-B.V.RaghunandanMarketing of Hand-crafted Products-B.V.Raghunandan
Marketing of Hand-crafted Products-B.V.RaghunandanSVS College
 
AES Tietê 3Q10 Results
AES Tietê 3Q10 Results AES Tietê 3Q10 Results
AES Tietê 3Q10 Results AES Tietê
 
LABEL.ch - Today tomorrow ..
LABEL.ch - Today tomorrow ..LABEL.ch - Today tomorrow ..
LABEL.ch - Today tomorrow ..LABEL
 
Yammer
YammerYammer
Yammeratwork
 
BI-System mit OData und SharePoint Online
BI-System mit OData und SharePoint OnlineBI-System mit OData und SharePoint Online
BI-System mit OData und SharePoint Onlineatwork
 

Andere mochten auch (8)

SharePoint UserGroup Stuttgart - Toni Pohl - Office 365 Development News Over...
SharePoint UserGroup Stuttgart - Toni Pohl - Office 365 Development News Over...SharePoint UserGroup Stuttgart - Toni Pohl - Office 365 Development News Over...
SharePoint UserGroup Stuttgart - Toni Pohl - Office 365 Development News Over...
 
1Q09 Earnings Call Presentation
1Q09 Earnings Call Presentation1Q09 Earnings Call Presentation
1Q09 Earnings Call Presentation
 
Управление репутацией в посике - SERM
Управление репутацией в посике - SERMУправление репутацией в посике - SERM
Управление репутацией в посике - SERM
 
Marketing of Hand-crafted Products-B.V.Raghunandan
Marketing of Hand-crafted Products-B.V.RaghunandanMarketing of Hand-crafted Products-B.V.Raghunandan
Marketing of Hand-crafted Products-B.V.Raghunandan
 
AES Tietê 3Q10 Results
AES Tietê 3Q10 Results AES Tietê 3Q10 Results
AES Tietê 3Q10 Results
 
LABEL.ch - Today tomorrow ..
LABEL.ch - Today tomorrow ..LABEL.ch - Today tomorrow ..
LABEL.ch - Today tomorrow ..
 
Yammer
YammerYammer
Yammer
 
BI-System mit OData und SharePoint Online
BI-System mit OData und SharePoint OnlineBI-System mit OData und SharePoint Online
BI-System mit OData und SharePoint Online
 

Ähnlich wie Apresentação Conference Call 1Q12

Geti 2 t10_call_final_english
Geti 2 t10_call_final_englishGeti 2 t10_call_final_english
Geti 2 t10_call_final_englishAES Tietê
 
Geti 1 q10_call_final
Geti 1 q10_call_finalGeti 1 q10_call_final
Geti 1 q10_call_finalAES Tietê
 
Cr2 Presentation - 3Q12
Cr2   Presentation - 3Q12Cr2   Presentation - 3Q12
Cr2 Presentation - 3Q12CR2
 
AES library.corporate
 AES library.corporate AES library.corporate
AES library.corporatefinance19
 
AES library.corporate
 AES library.corporate AES library.corporate
AES library.corporatefinance19
 
AES library.corporate
 AES library.corporate AES library.corporate
AES library.corporatefinance19
 
30-06-2012 - 2Q12 Results Presentation
30-06-2012 - 2Q12 Results Presentation30-06-2012 - 2Q12 Results Presentation
30-06-2012 - 2Q12 Results Presentationsonaeri
 
Sustainable Renewable Energy Business
Sustainable Renewable Energy BusinessSustainable Renewable Energy Business
Sustainable Renewable Energy BusinessTausif Farooqui, MIET
 
California Cap Trade Webinar 12 1 11
California Cap Trade Webinar 12 1 11California Cap Trade Webinar 12 1 11
California Cap Trade Webinar 12 1 11carriesisto
 
Pulis makakalikasan park
Pulis makakalikasan parkPulis makakalikasan park
Pulis makakalikasan parkPcrg Pnp
 
Apresentação call tiete 3 q11_final
Apresentação call tiete 3 q11_finalApresentação call tiete 3 q11_final
Apresentação call tiete 3 q11_finalAES Tietê
 
CR2 presentation - 4Q12 e 2012
CR2   presentation - 4Q12 e 2012CR2   presentation - 4Q12 e 2012
CR2 presentation - 4Q12 e 2012CR2
 
Latibex – november, 2009
Latibex – november, 2009Latibex – november, 2009
Latibex – november, 2009AES Tietê
 
LATIBEX – novembro de 2009
LATIBEX – novembro de 2009LATIBEX – novembro de 2009
LATIBEX – novembro de 2009AES Tietê
 
LATIBEX – November, 2009
LATIBEX – November, 2009LATIBEX – November, 2009
LATIBEX – November, 2009AES Tietê
 
Apresentacao aes eletropaulo_1_t12_sem discurso_eng_final
Apresentacao aes eletropaulo_1_t12_sem discurso_eng_finalApresentacao aes eletropaulo_1_t12_sem discurso_eng_final
Apresentacao aes eletropaulo_1_t12_sem discurso_eng_finalAES Eletropaulo
 
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...Could Texas Become The Largest Solar Opportunity in the World? An Update on t...
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...Rick Borry
 

Ähnlich wie Apresentação Conference Call 1Q12 (20)

Geti 2 t10_call_final_english
Geti 2 t10_call_final_englishGeti 2 t10_call_final_english
Geti 2 t10_call_final_english
 
Geti 1 q10_call_final
Geti 1 q10_call_finalGeti 1 q10_call_final
Geti 1 q10_call_final
 
Cr2 Presentation - 3Q12
Cr2   Presentation - 3Q12Cr2   Presentation - 3Q12
Cr2 Presentation - 3Q12
 
AES library.corporate
 AES library.corporate AES library.corporate
AES library.corporate
 
AES library.corporate
 AES library.corporate AES library.corporate
AES library.corporate
 
AES library.corporate
 AES library.corporate AES library.corporate
AES library.corporate
 
30-06-2012 - 2Q12 Results Presentation
30-06-2012 - 2Q12 Results Presentation30-06-2012 - 2Q12 Results Presentation
30-06-2012 - 2Q12 Results Presentation
 
Apre 2 t09
Apre 2 t09Apre 2 t09
Apre 2 t09
 
Sustainable Renewable Energy Business
Sustainable Renewable Energy BusinessSustainable Renewable Energy Business
Sustainable Renewable Energy Business
 
3Q12 Presentation
3Q12 Presentation3Q12 Presentation
3Q12 Presentation
 
California Cap Trade Webinar 12 1 11
California Cap Trade Webinar 12 1 11California Cap Trade Webinar 12 1 11
California Cap Trade Webinar 12 1 11
 
Pulis makakalikasan park
Pulis makakalikasan parkPulis makakalikasan park
Pulis makakalikasan park
 
Apresentação call tiete 3 q11_final
Apresentação call tiete 3 q11_finalApresentação call tiete 3 q11_final
Apresentação call tiete 3 q11_final
 
CR2 presentation - 4Q12 e 2012
CR2   presentation - 4Q12 e 2012CR2   presentation - 4Q12 e 2012
CR2 presentation - 4Q12 e 2012
 
Latibex – november, 2009
Latibex – november, 2009Latibex – november, 2009
Latibex – november, 2009
 
LATIBEX – novembro de 2009
LATIBEX – novembro de 2009LATIBEX – novembro de 2009
LATIBEX – novembro de 2009
 
LATIBEX – November, 2009
LATIBEX – November, 2009LATIBEX – November, 2009
LATIBEX – November, 2009
 
Apresentacao aes eletropaulo_1_t12_sem discurso_eng_final
Apresentacao aes eletropaulo_1_t12_sem discurso_eng_finalApresentacao aes eletropaulo_1_t12_sem discurso_eng_final
Apresentacao aes eletropaulo_1_t12_sem discurso_eng_final
 
2Q07 Results
2Q07 Results2Q07 Results
2Q07 Results
 
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...Could Texas Become The Largest Solar Opportunity in the World? An Update on t...
Could Texas Become The Largest Solar Opportunity in the World? An Update on t...
 

Mehr von AES Tietê

Apresentação bradesco ceo_forum2013_final (1)
Apresentação bradesco ceo_forum2013_final (1)Apresentação bradesco ceo_forum2013_final (1)
Apresentação bradesco ceo_forum2013_final (1)AES Tietê
 
Apresentação bradesco ceo_forum2013_final
Apresentação bradesco ceo_forum2013_finalApresentação bradesco ceo_forum2013_final
Apresentação bradesco ceo_forum2013_finalAES Tietê
 
Apresentação call tiete 3 q13_eng_final
Apresentação call tiete 3 q13_eng_finalApresentação call tiete 3 q13_eng_final
Apresentação call tiete 3 q13_eng_finalAES Tietê
 
Apresentação call tiete 1 t13_pt_final
Apresentação call tiete 1 t13_pt_finalApresentação call tiete 1 t13_pt_final
Apresentação call tiete 1 t13_pt_finalAES Tietê
 
Apimec presentation 03-31-2009
Apimec presentation   03-31-2009Apimec presentation   03-31-2009
Apimec presentation 03-31-2009AES Tietê
 
Apimec 31-03-2009
Apimec   31-03-2009Apimec   31-03-2009
Apimec 31-03-2009AES Tietê
 
12 03-2010 - apresentação da teleconferência 2009
12 03-2010  -   apresentação da teleconferência 200912 03-2010  -   apresentação da teleconferência 2009
12 03-2010 - apresentação da teleconferência 2009AES Tietê
 
Apresentação institucional 4_t10_eng
Apresentação institucional 4_t10_engApresentação institucional 4_t10_eng
Apresentação institucional 4_t10_engAES Tietê
 
Apresentação call tiete 2 t12_final
Apresentação call tiete 2 t12_finalApresentação call tiete 2 t12_final
Apresentação call tiete 2 t12_finalAES Tietê
 
Apresentação call tiete 3 t12_eng
Apresentação call tiete 3 t12_engApresentação call tiete 3 t12_eng
Apresentação call tiete 3 t12_engAES Tietê
 
Apresentação call tiete 3 t12_sem discurso
Apresentação call tiete 3 t12_sem discursoApresentação call tiete 3 t12_sem discurso
Apresentação call tiete 3 t12_sem discursoAES Tietê
 
Presentation credit suisse - v brazil equity ideas conference
Presentation   credit suisse - v brazil equity ideas conferencePresentation   credit suisse - v brazil equity ideas conference
Presentation credit suisse - v brazil equity ideas conferenceAES Tietê
 
Apresentação credit suisse - v brazil equity ideas conference
Apresentação   credit suisse - v brazil equity ideas conferenceApresentação   credit suisse - v brazil equity ideas conference
Apresentação credit suisse - v brazil equity ideas conferenceAES Tietê
 
Presentation barclays capital latin america regulated industries conference
Presentation   barclays capital latin america regulated industries conferencePresentation   barclays capital latin america regulated industries conference
Presentation barclays capital latin america regulated industries conferenceAES Tietê
 
Apresentação barclays capital latin america regulated industries conference
Apresentação   barclays capital latin america regulated industries conferenceApresentação   barclays capital latin america regulated industries conference
Apresentação barclays capital latin america regulated industries conferenceAES Tietê
 
Apresentação expo money apimec 2012
Apresentação expo money   apimec 2012Apresentação expo money   apimec 2012
Apresentação expo money apimec 2012AES Tietê
 
Apresentação institucional 3_q12_en_v8
Apresentação institucional 3_q12_en_v8Apresentação institucional 3_q12_en_v8
Apresentação institucional 3_q12_en_v8AES Tietê
 
Apresentação institucional 3_q12_en_v8
Apresentação institucional 3_q12_en_v8Apresentação institucional 3_q12_en_v8
Apresentação institucional 3_q12_en_v8AES Tietê
 
Apresentação institucional 3_q12_en_v11
Apresentação institucional 3_q12_en_v11Apresentação institucional 3_q12_en_v11
Apresentação institucional 3_q12_en_v11AES Tietê
 
Apresentação institucional 3_q12_en_v11
Apresentação institucional 3_q12_en_v11Apresentação institucional 3_q12_en_v11
Apresentação institucional 3_q12_en_v11AES Tietê
 

Mehr von AES Tietê (20)

Apresentação bradesco ceo_forum2013_final (1)
Apresentação bradesco ceo_forum2013_final (1)Apresentação bradesco ceo_forum2013_final (1)
Apresentação bradesco ceo_forum2013_final (1)
 
Apresentação bradesco ceo_forum2013_final
Apresentação bradesco ceo_forum2013_finalApresentação bradesco ceo_forum2013_final
Apresentação bradesco ceo_forum2013_final
 
Apresentação call tiete 3 q13_eng_final
Apresentação call tiete 3 q13_eng_finalApresentação call tiete 3 q13_eng_final
Apresentação call tiete 3 q13_eng_final
 
Apresentação call tiete 1 t13_pt_final
Apresentação call tiete 1 t13_pt_finalApresentação call tiete 1 t13_pt_final
Apresentação call tiete 1 t13_pt_final
 
Apimec presentation 03-31-2009
Apimec presentation   03-31-2009Apimec presentation   03-31-2009
Apimec presentation 03-31-2009
 
Apimec 31-03-2009
Apimec   31-03-2009Apimec   31-03-2009
Apimec 31-03-2009
 
12 03-2010 - apresentação da teleconferência 2009
12 03-2010  -   apresentação da teleconferência 200912 03-2010  -   apresentação da teleconferência 2009
12 03-2010 - apresentação da teleconferência 2009
 
Apresentação institucional 4_t10_eng
Apresentação institucional 4_t10_engApresentação institucional 4_t10_eng
Apresentação institucional 4_t10_eng
 
Apresentação call tiete 2 t12_final
Apresentação call tiete 2 t12_finalApresentação call tiete 2 t12_final
Apresentação call tiete 2 t12_final
 
Apresentação call tiete 3 t12_eng
Apresentação call tiete 3 t12_engApresentação call tiete 3 t12_eng
Apresentação call tiete 3 t12_eng
 
Apresentação call tiete 3 t12_sem discurso
Apresentação call tiete 3 t12_sem discursoApresentação call tiete 3 t12_sem discurso
Apresentação call tiete 3 t12_sem discurso
 
Presentation credit suisse - v brazil equity ideas conference
Presentation   credit suisse - v brazil equity ideas conferencePresentation   credit suisse - v brazil equity ideas conference
Presentation credit suisse - v brazil equity ideas conference
 
Apresentação credit suisse - v brazil equity ideas conference
Apresentação   credit suisse - v brazil equity ideas conferenceApresentação   credit suisse - v brazil equity ideas conference
Apresentação credit suisse - v brazil equity ideas conference
 
Presentation barclays capital latin america regulated industries conference
Presentation   barclays capital latin america regulated industries conferencePresentation   barclays capital latin america regulated industries conference
Presentation barclays capital latin america regulated industries conference
 
Apresentação barclays capital latin america regulated industries conference
Apresentação   barclays capital latin america regulated industries conferenceApresentação   barclays capital latin america regulated industries conference
Apresentação barclays capital latin america regulated industries conference
 
Apresentação expo money apimec 2012
Apresentação expo money   apimec 2012Apresentação expo money   apimec 2012
Apresentação expo money apimec 2012
 
Apresentação institucional 3_q12_en_v8
Apresentação institucional 3_q12_en_v8Apresentação institucional 3_q12_en_v8
Apresentação institucional 3_q12_en_v8
 
Apresentação institucional 3_q12_en_v8
Apresentação institucional 3_q12_en_v8Apresentação institucional 3_q12_en_v8
Apresentação institucional 3_q12_en_v8
 
Apresentação institucional 3_q12_en_v11
Apresentação institucional 3_q12_en_v11Apresentação institucional 3_q12_en_v11
Apresentação institucional 3_q12_en_v11
 
Apresentação institucional 3_q12_en_v11
Apresentação institucional 3_q12_en_v11Apresentação institucional 3_q12_en_v11
Apresentação institucional 3_q12_en_v11
 

Kürzlich hochgeladen

Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWERMadyBayot
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...apidays
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...apidays
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfOrbitshub
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdfSandro Moreira
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
Cyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfCyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfOverkill Security
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfOverkill Security
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024The Digital Insurer
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKJago de Vreede
 

Kürzlich hochgeladen (20)

Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Cyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfCyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdf
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdf
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
 

Apresentação Conference Call 1Q12

  • 2. 1Q12 Highlights  Investments totaled R$ 21 million, mainly in the modernization of Nova Avanhandava (347 MW) and Ibitinga (132 MW) power plants Operational  Energy generation 30% higher than physical guarantee and 10% greater than the total generated in 1Q11  Net revenue of R$ 540 million, 30% greater than 1Q11  R$ 20 million increase in expenses with energy purchased for resale and biannual locks maintenance and R$ 19 million increase in costs and operational expenses Financial  Ebitda reached R$ 423 million, with margin of 78%  Net income of R$ 246 million, an increase of 27% comparing to 1Q11  Dividends distribution of R$ 264 million, related to 1Q12 results, corresponding to R$ 0.66 per Dividends common share and R$ 0.73 per preferred share. Payment will occur on May 25, 2012. 2
  • 3. Despite the comfortable reservoir levels in SIN1 , lower rainfall in February, March and April pushed prices in the spot market Reservoirs Level inSIN1 PLD2 – Monthly Average (R$/MWh) 99% 99% 193 92% 83% 82% 79% 76% 125 35% 48 46 51 37 29 32 23 20 21 44 23 26 12 17 jan feb mar apr may jun jul aug sep oct nov dec Southeast/ South Northeast North 2010 2011 2012 Middle-West 1Q11 1Q12 1- Interconnected National System 2- Spot Market Average Price 3
  • 4. High level of Company’s reservoirs and operational availability Reservoirs level of AES Tietê’s power plants1 Energy generation (MW average3) 136% 130% 130% 125% 124% 96% 100% 98% 99% 94% 99% 90% 78% 1,753 1,665 1,599 1,582 1,612 A. Vermelha2 A. Vermelha Promissão2 Promissão B. Bonita2 B. Bonita Caconde 2 Caconde 2009 2010 2011 1Q11 1Q12 (11 km3) (8.1km3) (3.6km3) (0.6km 3) 1Q11 1Q12 Generation - Mwavg Generation/Physical guarantee Average: 98% 89% 1 – As of 03/31/2012 3 – Generated energy divided by the amount of period hours 2 – Reservoirs volume 4
  • 5. Investments in 1Q12 mainly oriented to the modernization of Nova Avanhandava and Ibitinga power plants Investments (R$ million) Investments in 1Q12 175 19 86% 82 174 12 156 38 11% 4 21 3% 70 2 34 19 2010 2011 2012(e) 1Q11 1Q12 Equipment and Maintenance Investments New SHPPs 1 New SHPPs IT Projects 1 - Small Hydro Power Plants 5
  • 6. Growth Opportunities and Capacity Expansion Obligation Termo-SP Project - Gas unavailability for A-5 in 2011 and A-3 Energy Auction in 2012 - Project registered in A-5 in 2012: term to present gas contract expires on June 1st, 2012 - Injunction suspending the Environmental License. AES Tietê presented its defense on April 27th - Fullfillment of conditions to obtain the installation license Termo Araraquara Project - Acquisition of a purchase option in March, 2012 - Combined cycle, gas-fired power plant, with 579 MW of installed capacity - The project has a high sinergy potential with Termo SP and is equally registered in A-5 auction in 2012 Expansion Obligation - April 26th: Presentation of the plan to extent the Company’s capacity 6
  • 7. Higher energy volume sold in 1Q12 due to the seasonality of the bilateral contract with AES Eletropaulo, besides the energy sold in ERM* Billed Energy (GWh) +34% 4,867 3,645 162 570 108 424 1,256 587 2,526 2,879 1Q11 1Q12 AES Eletropaulo Energy Reallocation Mechanism* Spot Market Other Bilateral Contracts 7 *ERM – Energy Reallocation Mechanism
  • 8. Strategy for energy contracting in 2016: client portfolio creation Clients portfolio evolution • Goals: - Expand and diversify client portfolio by Assured Energy (1,282 MW avg) 2015 - Allocate most of the assured energy to the free market Consolidated - Opportunity to negotiate the energy New client portfolio from projects that the Company will portfolio develop in coming years 2012 2016 2020
  • 9. Changes in the seasonality and 8.65% readjustment in AES Eletropaulo’s contract contributed for the net revenue expansion Net revenue (R$ million) +30% 540 46 416 18 17 14 477 385 1Q11 1Q12 AES Eletropaulo Spot/Energy Reallocation Mechanism Other bilateral contracts 9
  • 10. Increase in expenses with energy purchased and biannual locks maintenance, besides the increase in operational costs and expenses Operational costs and expenses¹ (R$ million) 4 3 5 7 9 11 114 117 78 1Q11 Energy Purchased Locks Operational Personnel, Transmission and Financ. Comp. For 1Q12 for Resale Maintenance Provisions and Material and Connection Use of Water Res. Other Expenses Third-party services² 1 – Do not include depreciation and amortization 10 2 – Personnel, Material and Third-party services
  • 11. Ebitda margin reached 78% in 1Q12 Ebitda (R$ million) 81% 78% 423 338 1Q11 1Q12 EBITDA EBITDA Margin (%) 11
  • 12. CDI* variation and lower average cash balance impacted financial result Financial Result (R$ million) 1Q11 1Q12 (11) (10) *CDI - Interbank Deposit Certificate 12
  • 13. Net income 27% higher in 1Q12, reflecting the good performance of revenues Net Income (R$ million) 118% 107% 2.9%  Distribution of R$ 264 million in dividends related 2.5% to 1Q12: - R$0.66 per common share - R$0.73 per preferred share - Ex-dividends: May 04, 2012 - Date of Payment: May 25, 2012 246 193 1Q11 1Q12 Payout Yield Preferred Shares Net Profit 13
  • 14. Cash flow reflects higher revenues from the bilateral contract Operating Cash Flow (R$ million) Final Cash Balance (R$ million) +28% -17% 382 499 299 413 1Q11 1Q12 1Q11 1Q12 14
  • 15. Low leverage with net debt/Ebitda of 0.3 times Net Debt (R$ billion) Average Cost and Average Term (Principal) 3.01 0.4x 2.01 0.3x 0.54 114% 115% 0.45 1Q11 1Q12 1Q11 1Q12 14.0% Effective rate 11.3% Net Debt Net Debt/EBITDA 1 1 – Percentage of CDI (Interbank Deposit Certificate) 15
  • 16. 1Q12 Results The statements contained in this document with regard to the business prospects, projected operating and financial results, and growth potential are merely forecasts based on the expectations of the Company’s Management in relation to its future performance. Such estimates are highly dependent on market behavior and on the conditions affecting Brazil’s macroeconomic performance as well as the electric sector and international market, and they are therefore subject to changes.