CHAPTER TWO QUESTIONS WITH ANSWERS
Q1. A substation supplies power by four feeders to its consumers. Feeder no 1 supplies six
consumers whose individual demands are 70 kW, 90 kW, 20 kW, 50 kW, 10 kW and 20 kW, while
maximum demand on the feeder is 200kW. Feeder no 2 supplies four consumers whose daily
maximum demands are 60 kW, 40 kW, 70 kW and 30 kW while the maximum demand on feeder no
2 is 160 kW. Feeders no 3 and 4 have daily maximum demands of 150 kW and 200 kW respectively,
while the maximum demand on the station is 600 kW.

Determine the diversity factors for the consumers of feeder no 1 and feeder no 2 and for the four
feeders.

Ans: 1.3; 1.25 and 1.183

Q2. A generating station has the following daily loads:

0 to 6 hr       4000 kW

6 to 8 hr       3000kW

8 to 12 hr      8000kW

12 to 14 hr     2000kW

14 to 18 hr     7500kW

18 to 20 hr     3000kW

20 to 24 hr     4500kW

Sketch load duration curve and determine the load factor and plant capacity factor assuming
capacity of the plant is 11000 kW.

Ans: 0.625, 0.4545

Q3. An industrial consumer having a maximum demand of 100 kW, maintains a load factor 60%. The
tariff rates are Rs. 1500 per KVA of maximum demand per annum plus paise 30 per kWh of energy
consumed. If the average pf is 0.8 lagging, calculate the total energy consumed per annum and
annual bill.



Q4. Compute the cost of electrical energy and average unit cost for consuming 450 kWh under block
rate quoted as below:

First 50 kWh at Rs. 3.80 per kWh

Next 50 kWh at Rs. 3.20 per kWh

Next 50 kWh at Rs. 2.80 per kWh
Next 50 kWh at Rs. 2.40 per kWh

Excess over 200 kWh at Rs. 2.10 per kWh.

Q5. A synchronous motor having a power consumption of 50 kW is connected in parallel with a load
of 200 kW having pf 0.8 lagging. The excitation of motor is adjusted until the combined pf becomes
0.9 lagging. Calculate the kVA input to the motor.

Ans: 57.76 kVA

Q6. It is desired to correct the power factor 0.95 by means of static condensers connected across
each phase of a 3-phase, 400 V, 50 Hz motor installation having a maximum load of 50 kVA at pf of
0.75 lagging. What must be the capacity of each delta – connected capacitor?

Ans: 244 uF

Q7.A factory having a load of 5 MW at 0.8 lagging for 2000 hours per annum buys energy on tariff of
Rs 500 per kVA plus Rs 2.5 per kWh consumed. If the power factor is improved to 0.95 lagging by
means of capacitors costing Rs 1350 per kVA and having a power loss of 200 watts per kVA, calculate
the annual charge for electrical energy (a) before and (b) after the installation of capacitors and (c)
the saving effected by their use. Allow 8% per annum for interest and depreciation on the
capacitors.

Q8. A consumer has an annual consumption of 70080 kWh. The charge is Rs 100 per kW of
maximum demand plus 5 paise per kWh.

(a) Find the annual bill and the overall costs per kWh is the load factor is 40%.

(b) What is the overall cost per kWh if (i) consumption was reduced by 25% with the same load
factor (ii) consumption remains the same as in (a) but the load factor is reduced to 30%?

Ans. (a) Rs 5504; 7.85p (b) (i) 7.85 p (ii) 8.80 p

Q9. A consumer takes a steady load of 1000 kW at a power factor of 0.707 lagging and pays Rs 80
per annum per kVA of maximum demand. Phase advancing plant costs Rs 128 per kVAr. Determine
the capacity of the phase advancing plant required for minimum overall annual expenditure. Interest
and depreciation total 10%. What will be the value of the new power factor of the supply? Deduce
and formula used.

Ans. 838 kVAr; 0.987 (lagging)

Q10     Two 50hp (metric) induction motors are each supplied on a tow part tariff at Rs 80 per kVA
of maximum demand plus 5 paise per kWh. The service needed is 3000 hours per annum at full load.
Motor A has efficiency 0.878 and p.f. 0.83 plus a capacitor costing Rs 75 per kVA to raise the p.f. to
0.91. Motor B with an efficiency 0.888 and p.f. 0.91 costs 1000 more than motor A. Assuming
interest and depreciation to be 12.5 % per annum for each motor and 8% for the capacitor, compare
the annual charges for two arrangements.

Ans. Net annual saving with motor B is Rs 36.80.
Q11      A factory takes a load of 200 kW at 0.85 p.f. lagging for 2500 hours per annum and buys
energy on a tariff of Rs 100 per kVA plus 5 paise per kWh consumed. If the power factor is improved
to 0.90 lagging by means of capacitors costing Rs 350 per kVA and having a power loss of 100 watts
per kVA calculate the annual charge for electrical energy (a) before and (b) after the installation of
capacitors and (c) the saving effected by their use. Allow 8% per annum for interest and depreciation
on the capacitors.

Ans. (a) Rs 48530 (b) Rs 48270 (c) Rs 260

Q12.    A generating station supplies the following loads:

15 MW, 12 MW, 8.5 MW, 6 MW and 0.45 MW. The annual load factor of the power station is 48%.
Calculate (i) the number of units supplied annually (ii) diversity factor and (iii) demand factor, if the
station has a maximum demand of 22 MW.

Ans. (i) 92.5 X 10e6 kWh (ii) 1.907 (iii) 52.5%

Q13. A power station has a maximum demand of 200 MW, a plant load factor of 0.6, a plant
capacity factor of 0.5 and a plant use factor of 0.8. Find (i) the daily energy consumed (ii) the reserve
capacity of the plant and (iii) maximum energy that can be produced daily.

Ans. (i) 2880 MWh (ii) 40 MW (iii) 5706 MWh

Q14. The maximum demand of a power supply system is 30 MW. The annual factors as follows:
Load factor = 60%; Capacity factor = 50%; Use factor = 75%.

Determine (i) the annual energy production (ii) reserve capacity and (iii) the hours during which the
plant is not in service per year.

Ans. (i) 157.68 X 10e6 kWh (ii) 6 MW (iii) 2920 hours.

Q15. The maximum demand of a consumer is 1 MW and the units consumed per annum are
500000 kWh. Calculate the reduction in cost if the power factor is raised from 0.5 to 0.8. The tariff is
Rs 900 per annum per kW demand plus Rs 1.50 per kWh plus Re 0.30 per kVAh reactive. Calculate
the flat rate tariff for a unity power factor load.

Ans. Rs 147310.00; Rs 3.30 per kWh

Q16. A consumer, whose connected load is 400 kVA, consumes 1 X 10e6 kWh per annum and the
maximum demand registered is 250 kVA. He is offered the following two alternative tariffs:

Tariff A: Rs 1000 per annum per kVA of connected load + first 150 kWh per KVA of connected load at
Rs 3.0/kWh, next 50000 kWh at Rs 2.00 per kWh and the rest at Re 1.0/kWh.

Tariff B: Rs 1200 per annum per kVA of maximum demand + first 150 kWh per kVA of maximum
demand at Rs 3.0 per kWh; next 50000 kWh at Rs 2.0/kWh and the rest at Re 1.0/kWh.

Which tariff is economical and what is the annual gain?

Ans. Tariff B is cheaper; Annual gain = Rs 14500000

Weitere ähnliche Inhalte

Was ist angesagt?

Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysis
divyanshuprakashrock
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
michaeljmack
 
Load characteristics and Economic Aspects
Load characteristics and Economic AspectsLoad characteristics and Economic Aspects
Load characteristics and Economic Aspects
Abha Tripathi
 

Was ist angesagt? (20)

Per unit analysis
Per unit analysisPer unit analysis
Per unit analysis
 
Principles of Power Systems V.K Mehta Complete Book - Chapter 6
Principles of Power Systems V.K Mehta Complete Book - Chapter 6Principles of Power Systems V.K Mehta Complete Book - Chapter 6
Principles of Power Systems V.K Mehta Complete Book - Chapter 6
 
Newton Raphson method for load flow analysis
Newton Raphson method for load flow analysisNewton Raphson method for load flow analysis
Newton Raphson method for load flow analysis
 
Lecture 10
Lecture 10Lecture 10
Lecture 10
 
Synchronous generator
Synchronous generatorSynchronous generator
Synchronous generator
 
Townsend ’s theory
Townsend ’s theoryTownsend ’s theory
Townsend ’s theory
 
Harmonics and mitigation techniques
Harmonics and mitigation techniquesHarmonics and mitigation techniques
Harmonics and mitigation techniques
 
Motor Protection
Motor ProtectionMotor Protection
Motor Protection
 
Restricted Earth Fault(REF) Protection.pptx
Restricted Earth Fault(REF) Protection.pptxRestricted Earth Fault(REF) Protection.pptx
Restricted Earth Fault(REF) Protection.pptx
 
Inductance and capacitance
Inductance and capacitanceInductance and capacitance
Inductance and capacitance
 
Dc motors
Dc motorsDc motors
Dc motors
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performance
 
Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factor
 
Per unit representation
Per unit representationPer unit representation
Per unit representation
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAY
 
Circle Diagram
Circle DiagramCircle Diagram
Circle Diagram
 
Generator protection calculations settings
Generator protection calculations settingsGenerator protection calculations settings
Generator protection calculations settings
 
Sample calculation-for-differential-relays
Sample calculation-for-differential-relaysSample calculation-for-differential-relays
Sample calculation-for-differential-relays
 
Load characteristics and Economic Aspects
Load characteristics and Economic AspectsLoad characteristics and Economic Aspects
Load characteristics and Economic Aspects
 
Protection of transformer
Protection of transformerProtection of transformer
Protection of transformer
 

Andere mochten auch

Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagram
nanonon
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
Dinesh Sarda
 

Andere mochten auch (20)

Unit1 And 2 Sample Solutions
Unit1 And 2 Sample SolutionsUnit1 And 2 Sample Solutions
Unit1 And 2 Sample Solutions
 
Questions unit4
Questions unit4Questions unit4
Questions unit4
 
Questions practice unit iv
Questions practice unit ivQuestions practice unit iv
Questions practice unit iv
 
Unit v
Unit vUnit v
Unit v
 
Unit4questions
Unit4questionsUnit4questions
Unit4questions
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothari
 
Practice questions for unit ii
Practice questions for unit iiPractice questions for unit ii
Practice questions for unit ii
 
Solutions -unit4
Solutions  -unit4Solutions  -unit4
Solutions -unit4
 
Practice questions
Practice questionsPractice questions
Practice questions
 
Unit1 8
Unit1 8Unit1 8
Unit1 8
 
Step1 Single Line Diagram
Step1 Single Line DiagramStep1 Single Line Diagram
Step1 Single Line Diagram
 
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
TPs-TDs : Travaux Pratiques & Dérigés (version 2014-2017) Génie Electrique/Ex...
 
Problemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasicoProblemas resueltos cortocircuito trifasico
Problemas resueltos cortocircuito trifasico
 
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCProject report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysis
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
load flow 1
 load flow 1 load flow 1
load flow 1
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 

Ähnlich wie Unit1questions

Ee w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Ee  w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...Ee  w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Ee w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Silvester Van Koten
 
(General aspects of energy)
(General aspects of energy)(General aspects of energy)
(General aspects of energy)
malathi051
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
NBoss
 

Ähnlich wie Unit1questions (20)

Power generation and economics
Power generation and economicsPower generation and economics
Power generation and economics
 
Ch01-ESR-L02.pdf
Ch01-ESR-L02.pdfCh01-ESR-L02.pdf
Ch01-ESR-L02.pdf
 
Ee w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Ee  w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...Ee  w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
Ee w07.1 w_ 2. electricity generation _ part 4 (missing money & capacity pay...
 
How Power Factor corection works.pdf
How Power Factor corection works.pdfHow Power Factor corection works.pdf
How Power Factor corection works.pdf
 
Pv tubewell economics potential pakistan
Pv tubewell economics potential pakistanPv tubewell economics potential pakistan
Pv tubewell economics potential pakistan
 
(General aspects of energy)
(General aspects of energy)(General aspects of energy)
(General aspects of energy)
 
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptxLecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
 
Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1Advanced energy engineering ktu module 1
Advanced energy engineering ktu module 1
 
PROPOSAL
PROPOSALPROPOSAL
PROPOSAL
 
Introduction to ReGenX Generator Innovations & Commercialization Overview 201...
Introduction to ReGenX Generator Innovations & Commercialization Overview 201...Introduction to ReGenX Generator Innovations & Commercialization Overview 201...
Introduction to ReGenX Generator Innovations & Commercialization Overview 201...
 
PV AND OTHER RENEWABLE ENERGY
 PV AND OTHER RENEWABLE ENERGY PV AND OTHER RENEWABLE ENERGY
PV AND OTHER RENEWABLE ENERGY
 
Comparison study of lead-acid and lithium-ıon batteries for solar photovoltai...
Comparison study of lead-acid and lithium-ıon batteries for solar photovoltai...Comparison study of lead-acid and lithium-ıon batteries for solar photovoltai...
Comparison study of lead-acid and lithium-ıon batteries for solar photovoltai...
 
Psoc qp
Psoc qpPsoc qp
Psoc qp
 
Tarrif and load curves
Tarrif and load curvesTarrif and load curves
Tarrif and load curves
 
Wind turbine report
Wind turbine reportWind turbine report
Wind turbine report
 
Load Forecasting Using LSTM Model
Load Forecasting Using LSTM ModelLoad Forecasting Using LSTM Model
Load Forecasting Using LSTM Model
 
Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
Power Factor.ppt
Power Factor.pptPower Factor.ppt
Power Factor.ppt
 
powerfactor.pdf
powerfactor.pdfpowerfactor.pdf
powerfactor.pdf
 
International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)International Journal of Engineering Research and Development (IJERD)
International Journal of Engineering Research and Development (IJERD)
 

Mehr von Abha Tripathi

Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutions
Abha Tripathi
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
Abha Tripathi
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
Abha Tripathi
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit Nagrath
Abha Tripathi
 

Mehr von Abha Tripathi (18)

Questions unit3
Questions unit3Questions unit3
Questions unit3
 
Unit1 and 2 sample solutions
Unit1 and 2 sample solutionsUnit1 and 2 sample solutions
Unit1 and 2 sample solutions
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
 
Renewable Sor
Renewable SorRenewable Sor
Renewable Sor
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
 
Hydro E
Hydro EHydro E
Hydro E
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit Nagrath
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
 
Dc Distributed Load
Dc Distributed LoadDc Distributed Load
Dc Distributed Load
 

Kürzlich hochgeladen

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 

Kürzlich hochgeladen (20)

Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 

Unit1questions

  • 1. CHAPTER TWO QUESTIONS WITH ANSWERS Q1. A substation supplies power by four feeders to its consumers. Feeder no 1 supplies six consumers whose individual demands are 70 kW, 90 kW, 20 kW, 50 kW, 10 kW and 20 kW, while maximum demand on the feeder is 200kW. Feeder no 2 supplies four consumers whose daily maximum demands are 60 kW, 40 kW, 70 kW and 30 kW while the maximum demand on feeder no 2 is 160 kW. Feeders no 3 and 4 have daily maximum demands of 150 kW and 200 kW respectively, while the maximum demand on the station is 600 kW. Determine the diversity factors for the consumers of feeder no 1 and feeder no 2 and for the four feeders. Ans: 1.3; 1.25 and 1.183 Q2. A generating station has the following daily loads: 0 to 6 hr 4000 kW 6 to 8 hr 3000kW 8 to 12 hr 8000kW 12 to 14 hr 2000kW 14 to 18 hr 7500kW 18 to 20 hr 3000kW 20 to 24 hr 4500kW Sketch load duration curve and determine the load factor and plant capacity factor assuming capacity of the plant is 11000 kW. Ans: 0.625, 0.4545 Q3. An industrial consumer having a maximum demand of 100 kW, maintains a load factor 60%. The tariff rates are Rs. 1500 per KVA of maximum demand per annum plus paise 30 per kWh of energy consumed. If the average pf is 0.8 lagging, calculate the total energy consumed per annum and annual bill. Q4. Compute the cost of electrical energy and average unit cost for consuming 450 kWh under block rate quoted as below: First 50 kWh at Rs. 3.80 per kWh Next 50 kWh at Rs. 3.20 per kWh Next 50 kWh at Rs. 2.80 per kWh
  • 2. Next 50 kWh at Rs. 2.40 per kWh Excess over 200 kWh at Rs. 2.10 per kWh. Q5. A synchronous motor having a power consumption of 50 kW is connected in parallel with a load of 200 kW having pf 0.8 lagging. The excitation of motor is adjusted until the combined pf becomes 0.9 lagging. Calculate the kVA input to the motor. Ans: 57.76 kVA Q6. It is desired to correct the power factor 0.95 by means of static condensers connected across each phase of a 3-phase, 400 V, 50 Hz motor installation having a maximum load of 50 kVA at pf of 0.75 lagging. What must be the capacity of each delta – connected capacitor? Ans: 244 uF Q7.A factory having a load of 5 MW at 0.8 lagging for 2000 hours per annum buys energy on tariff of Rs 500 per kVA plus Rs 2.5 per kWh consumed. If the power factor is improved to 0.95 lagging by means of capacitors costing Rs 1350 per kVA and having a power loss of 200 watts per kVA, calculate the annual charge for electrical energy (a) before and (b) after the installation of capacitors and (c) the saving effected by their use. Allow 8% per annum for interest and depreciation on the capacitors. Q8. A consumer has an annual consumption of 70080 kWh. The charge is Rs 100 per kW of maximum demand plus 5 paise per kWh. (a) Find the annual bill and the overall costs per kWh is the load factor is 40%. (b) What is the overall cost per kWh if (i) consumption was reduced by 25% with the same load factor (ii) consumption remains the same as in (a) but the load factor is reduced to 30%? Ans. (a) Rs 5504; 7.85p (b) (i) 7.85 p (ii) 8.80 p Q9. A consumer takes a steady load of 1000 kW at a power factor of 0.707 lagging and pays Rs 80 per annum per kVA of maximum demand. Phase advancing plant costs Rs 128 per kVAr. Determine the capacity of the phase advancing plant required for minimum overall annual expenditure. Interest and depreciation total 10%. What will be the value of the new power factor of the supply? Deduce and formula used. Ans. 838 kVAr; 0.987 (lagging) Q10 Two 50hp (metric) induction motors are each supplied on a tow part tariff at Rs 80 per kVA of maximum demand plus 5 paise per kWh. The service needed is 3000 hours per annum at full load. Motor A has efficiency 0.878 and p.f. 0.83 plus a capacitor costing Rs 75 per kVA to raise the p.f. to 0.91. Motor B with an efficiency 0.888 and p.f. 0.91 costs 1000 more than motor A. Assuming interest and depreciation to be 12.5 % per annum for each motor and 8% for the capacitor, compare the annual charges for two arrangements. Ans. Net annual saving with motor B is Rs 36.80.
  • 3. Q11 A factory takes a load of 200 kW at 0.85 p.f. lagging for 2500 hours per annum and buys energy on a tariff of Rs 100 per kVA plus 5 paise per kWh consumed. If the power factor is improved to 0.90 lagging by means of capacitors costing Rs 350 per kVA and having a power loss of 100 watts per kVA calculate the annual charge for electrical energy (a) before and (b) after the installation of capacitors and (c) the saving effected by their use. Allow 8% per annum for interest and depreciation on the capacitors. Ans. (a) Rs 48530 (b) Rs 48270 (c) Rs 260 Q12. A generating station supplies the following loads: 15 MW, 12 MW, 8.5 MW, 6 MW and 0.45 MW. The annual load factor of the power station is 48%. Calculate (i) the number of units supplied annually (ii) diversity factor and (iii) demand factor, if the station has a maximum demand of 22 MW. Ans. (i) 92.5 X 10e6 kWh (ii) 1.907 (iii) 52.5% Q13. A power station has a maximum demand of 200 MW, a plant load factor of 0.6, a plant capacity factor of 0.5 and a plant use factor of 0.8. Find (i) the daily energy consumed (ii) the reserve capacity of the plant and (iii) maximum energy that can be produced daily. Ans. (i) 2880 MWh (ii) 40 MW (iii) 5706 MWh Q14. The maximum demand of a power supply system is 30 MW. The annual factors as follows: Load factor = 60%; Capacity factor = 50%; Use factor = 75%. Determine (i) the annual energy production (ii) reserve capacity and (iii) the hours during which the plant is not in service per year. Ans. (i) 157.68 X 10e6 kWh (ii) 6 MW (iii) 2920 hours. Q15. The maximum demand of a consumer is 1 MW and the units consumed per annum are 500000 kWh. Calculate the reduction in cost if the power factor is raised from 0.5 to 0.8. The tariff is Rs 900 per annum per kW demand plus Rs 1.50 per kWh plus Re 0.30 per kVAh reactive. Calculate the flat rate tariff for a unity power factor load. Ans. Rs 147310.00; Rs 3.30 per kWh Q16. A consumer, whose connected load is 400 kVA, consumes 1 X 10e6 kWh per annum and the maximum demand registered is 250 kVA. He is offered the following two alternative tariffs: Tariff A: Rs 1000 per annum per kVA of connected load + first 150 kWh per KVA of connected load at Rs 3.0/kWh, next 50000 kWh at Rs 2.00 per kWh and the rest at Re 1.0/kWh. Tariff B: Rs 1200 per annum per kVA of maximum demand + first 150 kWh per kVA of maximum demand at Rs 3.0 per kWh; next 50000 kWh at Rs 2.0/kWh and the rest at Re 1.0/kWh. Which tariff is economical and what is the annual gain? Ans. Tariff B is cheaper; Annual gain = Rs 14500000