Improvement group presentation slide for September 2010 progress report by Manufacturing Engineering(B) - Taiyo Yuden(Sarawak), Malaysia.
Prepared by Abdul Qaiyum Alidin
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Improvement Group September Latest(Edited)
1. Improvement Group
Process Development
Malaysia Sarawak, Taiyo Yuden
16th Fiscal Year, August - September
Monthly Presentation
2. Table of Content
Development Summary Air Press Machine
Noise Reduction
Activity Progress
Traverser
1. Activities on August
transparent cover for
MS-24 Installation
Plating(2)
Air Press Machine
RO membrane
Auto Loader for replacement together
item 316 with aquamatic
Air Press Machine valve & inverter
Noise Reduction panel installation
2. Activities on Future activities and
September planning
MS-24 Installation
Plating 1 new line setup
5. Gaiden(m) Development
Activity
Air Press Machine Noise Reduction
Aug 10 Sept 10
Theme Activity PIC Status
WK 2
WK 3
WK 4
WK 2
WK 3
WK 4
WK 1
WK 1
Plan
Modification Improvement Group
Actual
Plan
Testing Improvement Group
Actual
Air Press Machine Noise Reduction
Plan
Monitoring & effectiveness Operation &
confirmation improvement Group
Actual
Plan
Waiting for report 1st appearance
Actual
Plan Done In progress Delay
6. Gaiden(m) Development
Activity
Air Press Machine Noise Reduction
Figure 4
Machine adjustment and test results
Before After
Machine No. Result Item Name
Adjustment Adjustment
(during
(leadscrew) (leadscrew)
testing)
I-23(316) Upper 70mm 70/70 ↑ Line-A
Lower 64mm 70/60 ↑ E316BJ226KL
60/60 NG
65/60 ↓OK
I-21(316) Upper 60mm 60/65 ↓OK Line-A
Lower 70mm E316BJ226KL
R-9(316) Upper 65mm 65/60 ↓OK Line-A
Lower 67mm E316BJ226KL
P-8(316) Upper 63mm 63/60 ↓NG Line-A
Lower 68mm 63/63 ↓OK E316BJ226KL
7. Gaiden(m) Development
Activity
Air Press Machine Noise Reduction
Chip Height Measurement Method using Laser Profile kit
Carrier plate
point number
1 2 3
4 5 6
Total of 9 area
points on carrier
plate are
7 8 9
measured
Remark: Average of 5 chips height value measured from each point for recording purpose
8. Gaiden(m) Development
Activity
Air Press Machine Noise Reduction
Chip Height Laser Profile for item 316 Chip Height Laser Profile for item 212
Before Before
Chip modification modification
Chip
Height(μm) After After
Height(μm)
1.25 modification modification
1.55
1.2 1.5
1.15
1.45
1.1
1.4
1.05
1.35
1
1.3
0.95
1.25
0.9
1.2
one two three four five six seven eight nine Plate Point
one two three four five six seven eight nine Plate Point
A record of chip height or protrusion data pattern in graph
9. Gaiden(m) Development
Activity
Air Press Machine Noise Reduction
Chip Height Laser Profile for item 316 Chip Height Laser Profile for item 212
Before Before
Chip modification modification
Chip
Height(μm) After After
Height(μm)
1.25 modification modification
1.55
1.2 1.5
1.15
1.45
1.1
1.4
1.05
1.35
1
1.3
0.95
1.25
0.9
1.2
one two three four five six seven eight nine Plate Point
one two three four five six seven eight nine Plate Point
A record of chip height or protrusion data pattern in graph
10. Gaiden(m) Development
Activity
Air Press Machine Noise Reduction
Chip Height Laser Profile for item 316 Chip Height Laser Profile for item 212
Before Before
Chip modification modification
Chip
Height(μm) After After
Height(μm)
1.3 modification modification
1.55
1.25
1.5
1.2
1.45
1.15
1.4
1.1
1.05 1.35
1 1.3
0.95 1.25
0.9
1.2
one two three four five six seven eight nine Plate Point
one two three four five six seven eight nine Plate Point
A record of chip height or protrusion data pattern in graph
11. Shousei Development Activity
MS-24 Installation
Aug 10 Sept 10
Theme Activity PIC Status
WK 2
WK 3
WK 4
WK 2
WK 3
WK 4
WK 1
WK 1
Plan
Testing(purging N2, wiring, piping) Improvement Group
Actual
Plan
MS-24 Monitoring(temperature profile) Improvement Group
Actual
Machine running for Plan
MSTY-Tech
production Actual
Plan Done In progress Delay
12. Shousei Development Activity
MS-24 Installation
New feature
Blower 1 to blower 2 controller with relay
Project issues
Exhaust fan, blower & piping to roof resulting to unstable
internal pressure
Off roof blower during maintenance
Burnt sheath heater at zone no. 2 & no.3, cooling zone
Replace sheath heater and covered holes using fiber
Production alarm panel not properly maintain
Tested and working
13. Plating(1) Development
Activity
RO aquamatic valve & inverter panel installation
Sept10
Theme Activity PIC Status
WK 2
WK 3
WK 4
WK 1
Plan
Installation Improvement Group
Actual
Plan
RO aquamatic valve & inverter panel Monitoring Improvement Group
installation Actual
Plan
Effectiveness confirmation Improvement Group
Actual
Remark:
11-Sep-10 RO Plant 1 Change Aquamatic Valve with new. (By KIASUI)
Plan Done In progress Delay
14. Plating(2) Development
Activity
Traverser transparent cover installation
Aug 10 Sept 10
Theme Activity PIC Status
WK 2
WK 3
WK 4
WK 2
WK 3
WK 4
WK 1
WK 1
Plan
Proposal and discussion Improvement Group
Actual
Plan
Modification and installation Improvement Group
Actual
Transparent cover Plan
Downtime Monitoring Improvement Group
For easy inspection and monitoring Actual
Plan
Effectiveness confirmation Improvement Group
Actual
Operation & Plan
Implement all line
improvement group
Actual
Plan Done In progress Delay
15. Plating(2) Development
Activity
After modification
Before modification 170mm
260mm
Objective:
- Easy traverser chain inspection, maintenance and monitoring
- Reduce downtime during doing replacement part(Limit Switch) and they
do not need to open traverser cover
16. Plating(2) Development
Activity
RO membrane replacement together with aquamatic valve &
inverter panel installation
Sept10
Theme Activity PIC Status
WK 2
WK 3
WK 4
WK 1
Plan
Installation Improvement Group
Actual
Plan
RO membrane replacement together with Monitoring Improvement Group
auqamatic valve & inverter panel installation Actual
Plan
Effectiveness confirmation Improvement Group
Actual
Plan Done In progress Delay
19. 16 Fiscal Year th
Future Activity and Planning
Web-based system for spare part purpose integration
with ME-B existing system(ex. Yokogawa Recorder)
MW100 implementation to Shousei for monitoring
purpose
Monitoring heater resistance & exhaust fan inverter
Require further discussion & information
Machine incoming & development process
Plating(1) auto line – On progress.
Datsubai – KIV implementation due to no further confirmation
20. 16 Fiscal Year th
Future Activity and Planning
Web-based system planning
Sept 10 Oct 10
Theme Activity PIC Status
WK 2
WK 3
WK 4
WK 2
WK 3
WK 4
WK 1
WK 1
Outline project requirement Plan
Improvement Group
Prepare activity schedule Actual
Plan
Research on project requirement Improvement Group
Actual
Plan
Web-based system for spare part Web development Improvement Group
Actual
Plan
Testing Improvement Group Future Activity Progress
Actual
Plan
Proposal presentation Improvement group
Actual
Plan Done In progress Delay
21. Improvement Group
Process Development
Machine incoming & development process
CONTENT:
Plating(1) auto line –Facilities planning progress
schedule, Plating 1 Auto line Set-up schedule(no
progress),progress picture(dismantle),new D.I plant
layout.
Datsubai – Confirmed total of 8 machines out, 1st
batch expected 4 machines out on October and later
2nd batch another 4 machines out on November.
22. Plating1(RMW) Development Activity
.Facilities planning progress schedule
Sept-10 Oct-10 Nov-10
Activities P. I .C
w1
w2
w3
w4
w1
w2
w3
w4
w1
w2
w3
w4
Primary Works plan
( Power Supplycompress air and
TAIKISHA
city water. ) actual No information
New R.O tank & D.I tank plan
TAIKISHA
piping. actual
plan
Installation new D.I plant TAIKISHA
actual
Manual line dismantle(Line D PRODUCTION/
plan
& E) ME
actual COMPLETE
Renovation of ceiling(install plan
new ceiling height and re-
TAIKISHA
install new lighting and M&E actual
system
plan actual Delay
23. Plating1(RMW) Development Activity
Plating Auto line Set-up schedule.
Nov 10 Dec 10
Theme Activities
1 wk 2 wk
st nd
3 wk
rd
4 wk
th
1 wk 2 wk 3rd wk 4th wk
st nd
Plan
Machine Move In
Actual
Plan
Structure / Frame Setup
Actual
Plan
EpNi-Sn Auto Machine Setup Schedule Machine Setup
Actual
Plan
Barrel Sensor and Positioning Check
Actual
Plan
Test Run And Monitoring
Actual
Plan
Machine Move In
Actual
Plan
Structure / Frame Setup
Actual
Plan
StCu-EpCu Auto Machine Setup Schedule Machine Setup
Actual
Plan
Barrel Sensor and Positioning Check
Actual
Plan
Test Run And Monitoring
Actual
plan Actual Delay