Propietario :
Fecha :
Hecho por :
l a h l a (h) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
02.02.00 OBRAS DE CONCRETO SIMPLE
02.02.01 SOLADO P/ZAPATAS E=4" MEZCLA1:12 0.58
4 1.2 1.2 0.1 0.58
02.02.02 CIMIENTOS CORRIDOS F'c=100 KG/CM2 + 30% PG 42.37
LONGITUDINALES EJE A - A DEL 1 - 5 1 15.45 0.5 0.9 6.95
LONGITUDINALES EJE A - A DEL 5 - 7 1 2.15 0.5 0.9 0.97
LONGITUDINALES ENTRE A - C DEL 1 - 2 1 4.49 0.5 0.9 2.02
LONGITUDINALES ENTRE A - C DEL 4 - 5 1 1.75 0.5 0.9 0.79
LONGITUDINALES EJE C - C DEL 1 - 2 1 3.59 0.5 0.9 1.62
LONGITUDINALES EJE C - C DEL 2 - 4 1 5.64 0.5 0.9 2.54
LONGITUDINALES EJE C - C DEL 4 - 6 1 4.31 0.5 0.9 1.94
LONGITUDINALES EJE C - C DEL 4 - 7 1 3.35 0.5 0.9 1.51
LONGITUDINALES ENTRE C - D DEL 1 - 2 1 1.25 0.5 0.9 0.56
LONGITUDINALES EJE D - D DEL 1 - 5 1 15.45 0.5 0.9 6.95
LONGITUDINALES EJE D - D DEL 5 - 7 1 3.35 0.5 0.9 1.51
TRANSVERSALES EJE 1 - 1 DE A - C 1 3.08 0.5 0.9 1.39
TRANSVERSALES EJE 1 - 1 DE C - D 1 2.93 0.5 0.9 1.32
TRANSVERSALES ENTRE 1 - 2 DE A - C 1 0.85 0.5 0.9 0.38
TRANSVERSALES ENTRE 1 - 2 DE C - D 1 1.73 0.5 0.9 0.78
TRANSVERSALES EJE 2 - 2 DE A - C 1 2.81 0.5 0.9 1.26
TRANSVERSALES EJE 2 - 2 DE C - D 1 2 0.5 0.9 0.9
TRANSVERSALES EJE 3 - 3 DE A - C 1 3.7 0.5 0.9 1.67
TRANSVERSALES EJE 3 - 3 DE C - D 1 2.9 0.5 0.9 1.31
TRANSVERSALES EJE 4 - 4 DE A - C 1 3.3 0.5 0.9 1.49
TRANSVERSALES ENTRE 4 - 5 DE A - C 1 2.64 0.5 0.9 1.19
TRANSVERSALES ENTRE 6 - 7 DE A - B 1 2.24 0.5 0.9 1.01
TRANSVERSALES EJE 7 - 7 DE B - C 1 2.34 0.5 0.9 1.05
TRANSVERSALES EJE 7 - 7 DE C - D 1 2.8 0.5 0.9 1.26
02.02.03 CONCRETO EN SOBRECIMIENTO F'c=100 KG/CM2 + 25% PM 5.97 64.81
LONGITUDINALES EJE A - A DEL 1 - 2 1 4.31 0.15 0.4 0.26 8.62 0.4 3.448
LONGITUDINALES EJE A - A DEL 3 - 4 1 3.36 0.15 0.4 0.2 6.72 0.4 2.688
LONGITUDINALES EJE A - A DEL 4 - 5 1 1.95 0.25 0.4 0.2 3.9 0.4 1.56
LONGITUDINALES EJE A - A DEL 5 - 6 1 2.13 0.25 0.4 0.21 4.26 0.4 1.704
LONGITUDINALES EJE A - A DEL 6 - 7 1 2.12 0.25 0.4 0.21 4.24 0.4 1.696
LONGITUDINALES ENTRE A - C DEL 1 - 2 1 3.02 0.15 0.4 0.18 6.04 0.4 2.416
LONGITUDINALES ENTRE A - C DEL 4 - 5 1 1.05 0.15 0.4 0.06 2.1 0.4 0.84
LONGITUDINALES EJE C - C DEL 1 - 2 1 2.81 0.15 0.4 0.17 5.62 0.4 2.248
LONGITUDINALES EJE C - C DEL 3 - 4 1 2.46 0.15 0.4 0.15 4.92 0.4 1.968
LONGITUDINALES EJE C - C DEL 4 - 5 1 1.2 0.15 0.4 0.07 2.4 0.4 0.96
LONGITUDINALES EJE C - C DEL 4 - 5 1 0.88 0.25 0.4 0.09 1.76 0.4 0.704
LONGITUDINALES EJE C - C DEL 5 - 6 1 2.13 0.15 0.4 0.13 4.26 0.4 1.704
LONGITUDINALES EJE C - C DEL 5 - 7 1 3.57 0.15 0.4 0.21 7.14 0.4 2.856
LONGITUDINALES ENTRE C - D DEL 1 - 2 1 0.45 0.15 0.4 0.03 0.9 0.4 0.36
LONGITUDINALES EJE D - D DEL 1 - 2 1 3.81 0.15 0.4 0.23 7.62 0.4 3.048
LONGITUDINALES EJE D - D DEL 2 - 3 1 2.23 0.15 0.4 0.13 4.46 0.4 1.784
LONGITUDINALES EJE D - D DEL 3 - 4 1 3.19 0.15 0.4 0.19 6.38 0.4 2.552
LONGITUDINALES EJE D - D DEL 4 - 5 1 2.88 0.25 0.4 0.29 5.76 0.4 2.304
LONGITUDINALES EJE D - D DEL 5 - 6 1 2.13 0.25 0.4 0.21 4.26 0.4 1.704
LONGITUDINALES EJE D - D DEL 6 - 7 1 3.57 0.25 0.4 0.36 7.14 0.4 2.856
TRANSVERSALES EJE 1 - 1 DE A - C 1 4.03 0.25 0.4 0.4 8.06 0.4 3.224
TRANSVERSALES EJE 1 - 1 DE C - D 1 2.23 0.25 0.4 0.22 4.46 0.4 1.784
TRANSVERSALES ENTRE 1 - 2 DE A - C 1 0.5 0.15 0.4 0.03 1 0.4 0.4
TRANSVERSALES ENTRE 1 - 2 DE C - D 1 0.6 0.15 0.4 0.04 1.2 0.4 0.48
TRANSVERSALES ENTRE 1 - 2 DE C - D 1 1.25 0.15 0.4 0.08 2.5 0.4 1
TRANSVERSALES EJE 2 - 2 DE A - C 1 2.68 0.15 0.4 0.16 5.36 0.4 2.144
TRANSVERSALES EJE 2 - 2 DE A - C 1 1.35 0.15 0.4 0.08 2.7 0.4 1.08
TRANSVERSALES EJE 2 - 2 DE C - D 1 2.25 0.15 0.4 0.14 4.5 0.4 1.8
TRANSVERSALES EJE 3 - 3 DE A - C 1 3.13 0.15 0.4 0.19 6.26 0.4 2.504
TRANSVERSALES EJE 3 - 3 DE C - D 1 2.23 0.15 0.4 0.13 4.46 0.4 1.784
TRANSVERSALES EJE 4 - 4 DE A - C 1 4.03 0.25 0.4 0.4 8.06 0.4 3.224
TRANSVERSALES ENTRE 4 - 5 DE A - C 1 3.33 0.15 0.4 0.2 6.66 0.4 2.664
TRANSVERSALES EJE 7 - 7 DE B - C 1 1.92 0.25 0.4 0.19 3.84 0.4 1.536
TRANSVERSALES EJE 7 - 7 DE C - D 1 2.23 0.15 0.4 0.13 4.46 0.4 1.784
02.03.00 OBRAS DE CONCRETO ARMADO
02.03.01 ZAPATAS
02.03.01.01 CONCRETO F'C=210 KG/CM2 EN ZAPATAS 5.04
ZAPATA1 (1.20 X 1.20 M) 5 1.2 1.2 0.7 5.04
02.03.01.02 ACERO F'y=4,200 KG/CM2 EN ZAPATAS
ZAPATA1 (1.20 X 1.20 M) 61.20
LONGITUDINALES 1/2 5 5 1.2 30.60 30.60
TRANSVERSALES 1/2 5 5 1.2 30.60 30.60
02.03.01 COLUMNAS
02.03.01.01 CONCRETO F'C=210 KG/CM2 EN COLUMNAS
PRIMER NIVEL
C1
19 0.25 0.25 3 3.56 1 3 57
5/8 19 4 3.5 426 425.60
3/8 19 21 1 231.42 231.42
C2
3 0.25 0.15 3 0.34 0.8 3 7.2
LONGITUDINAL 3/8 3 4 3.5 24.36 24.36
TRANSVERSAL 1/4 3 21 0.6 9.45 9.45
C3
2 1.35 3 8.1 0.09 3 0.54
LONGITUDINAL 5/8 2 5 3.5 56 56.00
TRANSVERSAL 3/8 2 21 0.6 14.62 14.62
SEGUDO NIVEL
C1
19 0.25 0.25 3 3.56 1 3 57
5/8 19 4 3.5 426 425.60
3/8 19 21 1 231.42 231.42
C2
3 0.25 0.15 3 0.34 0.8 3 7.2
LONGITUDINAL 3/8 3 4 3.5 24.36 24.36
TRANSVERSAL 1/4 3 21 0.6 9.45 9.45
C3
2 1.35 3 8.1 0.09 3 0.54
LONGITUDINAL 5/8 2 5 3.5 56 56.00
TRANSVERSAL 3/8 2 21 0.6 14.62 14.62
02.03.02 VIGAS
PRIMER NIVEL
V-A1 (25 X 20) 6 13 0.25 0.2 3.9 13 0.65 50.7
LONGITUDINAL 1/2 6 4 12.95 317.02 317.02
LONGITUDINAL 3/8 6 1 12.95 45.07 45.07
TRANSVERSAL 1/4 1 102 1 25.5 25.50
V-A2 (25 X 20) 1 8.7 0.25 0.2 0.44 8.7 0.65 5.66
LONGITUDINAL 1/2 6 1 11.75 71.91 71.91
LONGITUDINAL 3/8 6 1 11.75 40.89 40.89
TRANSVERSAL 1/4 1 86 1 21.5 21.50
V-S1 (25 X 20) 2 20.7 0.25 0.2 2.07 20.7 0.65 26.91
LONGITUDINAL 1/2 2 1 25.6 52.22 52.22
TOTAL
N° de Veces
Longitud
c/ø
P,S - 001-2015
Medidas
N° de Piezas
..de..
Diámetro
ESTRUCTURA
Parcial (kg)
ELEMENTO
Cantidad
elementos
Descripción
Concreto
Medidas Total
(m3)
Partida
N°
Longitud por ø
Total
(m2)
Encofrado
HOJA DE METRADOS DE CONCRETO ARMADO
Obra :
Ing. Omar QUISPE
SETIEMBRE DEL 2015
PIO RIVERA YURICO, SAENZ ROSALES NILTON VLADIMIR
Hoja :
Plano :
Revisado :
Versión :
Fierro
Preparado por Omar 02/10/2015 Página 1
Propietario :
Fecha :
Hecho por :
l a h l a (h) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
TOTAL
N° de Veces
Longitud
c/ø
P,S - 001-2015
Medidas
N° de Piezas
..de..
Diámetro
ESTRUCTURA
Parcial (kg)
ELEMENTO
Cantidad
elementos
Descripción
Concreto
Medidas Total
(m3)
Partida
N°
Longitud por ø
Total
(m2)
Encofrado
HOJA DE METRADOS DE CONCRETO ARMADO
Obra :
Ing. Omar QUISPE
SETIEMBRE DEL 2015
PIO RIVERA YURICO, SAENZ ROSALES NILTON VLADIMIR
Hoja :
Plano :
Revisado :
Versión :
Fierro
LONGITUDINAL 3/8 2 1 25.6 29.70 29.70
TRANSVERSAL 1/4 1 276 1 69 69.00
V-S1´ (25 X 20) 1 16.28 0.25 0.2 0.81 16.28 0.65 10.58
LONGITUDINAL 1/2 1 1 23.5 23.97 23.97
LONGITUDINAL 3/8 1 1 23.5 13.63 13.63
TRANSVERSAL 1/4 1 250 1 62.5 62.50
V-B (15 X 20) 1 20.7 0.15 0.2 0.62 20.7 0.55 11.39
LONGITUDINAL 1/2 1 1 28 28.56 28.56
LONGITUDINAL 3/8 1 1 28 16.24 16.24
TRANSVERSAL 1/4 1 305 0.5 38.1 38.13
V-B ´ (15 X 20) 1 8.7 0.15 0.2 0.26 8.7 0.55 4.79
LONGITUDINAL 1/2 1 1 11.75 11.99 11.99
LONGITUDINAL 3/8 1 1 11.75 6.82 6.82
TRANSVERSAL 1/4 1 86 0.5 10.8 10.75
SEGUNDO NIVEL
V-A1 (25 X 20) 6 13 0.25 0.2 3.9 13 0.65 50.7
LONGITUDINAL 1/2 6 4 12.95 317.02 317.02
LONGITUDINAL 3/8 6 1 12.95 45.07 45.07
TRANSVERSAL 1/4 1 102 1 25.5 25.50
V-A2 (25 X 20) 1 8.7 0.25 0.2 0.44 8.7 0.65 5.66
LONGITUDINAL 1/2 6 1 11.75 71.91 71.91
LONGITUDINAL 3/8 6 1 11.75 40.89 40.89
TRANSVERSAL 1/4 1 86 1 21.5 21.50
V-S1 (25 X 20) 2 20.7 0.25 0.2 2.07 20.7 0.65 26.91
LONGITUDINAL 1/2 2 1 25.6 52.22 52.22
LONGITUDINAL 3/8 2 1 25.6 29.70 29.70
TRANSVERSAL 1/4 1 276 1 69 69.00
V-S1´ (25 X 20) 1 16.28 0.25 0.2 0.81 16.28 0.65 10.58
LONGITUDINAL 1/2 1 1 23.5 23.97 23.97
LONGITUDINAL 3/8 1 1 23.5 13.63 13.63
TRANSVERSAL 1/4 1 250 1 62.5 62.50
V-B (15 X 20) 1 20.7 0.15 0.2 0.62 20.7 0.55 11.39
LONGITUDINAL 1/2 1 1 28 28.56 28.56
LONGITUDINAL 3/8 1 1 28 16.24 16.24
TRANSVERSAL 1/4 1 305 0.5 38.1 38.13
V-B ´ (15 X 20) 1 8.7 0.15 0.2 0.26 8.7 0.55 4.79
LONGITUDINAL 1/2 1 1 11.75 11.99 11.99
LONGITUDINAL 3/8 1 1 11.75 6.82 6.82
TRANSVERSAL 1/4 1 86 0.5 10.8 10.75
1/4" 3/8" 1/2" 5/8" 3/4" 1"
6.35 9.53 12.7 15.9 19.1 25.4
474 845.466 1072.5 963 0 0
0.21 0.56 0.994 1.55 2.24 3.97
98 473.461 1066.1 1495 0 0
52.6 93.9407 119.17 107 0 0
TOTAL de ACERO (kgs) 3132.49
N° de BARRAS
RESUMEN DEL METRADO DE ACERO
Diámetro (ø)
mm
Longitud Total x ø
Peso Kg/ml
TOTAL (kgs)
Preparado por Omar 02/10/2015 Página 2

Weitere ähnliche Inhalte

Andere mochten auch (8)

Dbh 2ko matrikula orri berria zuzenduta
Dbh 2ko matrikula orri berria zuzendutaDbh 2ko matrikula orri berria zuzenduta
Dbh 2ko matrikula orri berria zuzenduta
 
Certficado - VKI
Certficado - VKICertficado - VKI
Certficado - VKI
 
Avaliações 4º bimestre
Avaliações  4º bimestreAvaliações  4º bimestre
Avaliações 4º bimestre
 
Presentazione
PresentazionePresentazione
Presentazione
 
Vientos solares
Vientos solaresVientos solares
Vientos solares
 
Andrew 540-EZSNS
Andrew 540-EZSNSAndrew 540-EZSNS
Andrew 540-EZSNS
 
Practice of Credit Management
Practice of Credit ManagementPractice of Credit Management
Practice of Credit Management
 
ECI 238009-7535
ECI 238009-7535ECI 238009-7535
ECI 238009-7535
 

Ähnlich wie Metrados estructuras y arquitectura

Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
fhjsekkemm
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
fhjsekkemm
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
fikdkksmmd
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
fikdkksmmd
 
219651800 viga-metodo-de-cross
219651800 viga-metodo-de-cross219651800 viga-metodo-de-cross
219651800 viga-metodo-de-cross
Michel Rodriguez
 
Arquitectura final beatriz martinez
Arquitectura final beatriz martinezArquitectura final beatriz martinez
Arquitectura final beatriz martinez
ROXANABRAEZ
 

Ähnlich wie Metrados estructuras y arquitectura (19)

Ir2110 ucd
Ir2110 ucdIr2110 ucd
Ir2110 ucd
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
 
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
Kawasaki 60 z7 wheel loader equipment components parts catalogue manual (seri...
 
0
00
0
 
219651800 viga-metodo-de-cross
219651800 viga-metodo-de-cross219651800 viga-metodo-de-cross
219651800 viga-metodo-de-cross
 
97131896 diseno-de-una-viga-x-metodo-de-cross
97131896 diseno-de-una-viga-x-metodo-de-cross97131896 diseno-de-una-viga-x-metodo-de-cross
97131896 diseno-de-una-viga-x-metodo-de-cross
 
TE2-PE-2014-2S
TE2-PE-2014-2STE2-PE-2014-2S
TE2-PE-2014-2S
 
エシカル消費の基礎知識
エシカル消費の基礎知識エシカル消費の基礎知識
エシカル消費の基礎知識
 
Diagrama Electrónico y de Conexiones Analizador de Química Automatizado Wiene...
Diagrama Electrónico y de Conexiones Analizador de Química Automatizado Wiene...Diagrama Electrónico y de Conexiones Analizador de Química Automatizado Wiene...
Diagrama Electrónico y de Conexiones Analizador de Química Automatizado Wiene...
 
Máy cắt cỏ chạy xăng, đeo vai ebh340 r part list
Máy cắt cỏ chạy xăng, đeo vai ebh340 r part listMáy cắt cỏ chạy xăng, đeo vai ebh340 r part list
Máy cắt cỏ chạy xăng, đeo vai ebh340 r part list
 
TE2-PE-2013-2S
TE2-PE-2013-2STE2-PE-2013-2S
TE2-PE-2013-2S
 
A001
A001A001
A001
 
Arquitectura final beatriz martinez
Arquitectura final beatriz martinezArquitectura final beatriz martinez
Arquitectura final beatriz martinez
 
GSX-R750L4-021.pdf
GSX-R750L4-021.pdfGSX-R750L4-021.pdf
GSX-R750L4-021.pdf
 
85度C 品牌稽核 Marketing Audit
85度C 品牌稽核 Marketing Audit85度C 品牌稽核 Marketing Audit
85度C 品牌稽核 Marketing Audit
 

Metrados estructuras y arquitectura

  • 1. Propietario : Fecha : Hecho por : l a h l a (h) 1/4" 3/8" 1/2" 5/8" 3/4" 1" 02.02.00 OBRAS DE CONCRETO SIMPLE 02.02.01 SOLADO P/ZAPATAS E=4" MEZCLA1:12 0.58 4 1.2 1.2 0.1 0.58 02.02.02 CIMIENTOS CORRIDOS F'c=100 KG/CM2 + 30% PG 42.37 LONGITUDINALES EJE A - A DEL 1 - 5 1 15.45 0.5 0.9 6.95 LONGITUDINALES EJE A - A DEL 5 - 7 1 2.15 0.5 0.9 0.97 LONGITUDINALES ENTRE A - C DEL 1 - 2 1 4.49 0.5 0.9 2.02 LONGITUDINALES ENTRE A - C DEL 4 - 5 1 1.75 0.5 0.9 0.79 LONGITUDINALES EJE C - C DEL 1 - 2 1 3.59 0.5 0.9 1.62 LONGITUDINALES EJE C - C DEL 2 - 4 1 5.64 0.5 0.9 2.54 LONGITUDINALES EJE C - C DEL 4 - 6 1 4.31 0.5 0.9 1.94 LONGITUDINALES EJE C - C DEL 4 - 7 1 3.35 0.5 0.9 1.51 LONGITUDINALES ENTRE C - D DEL 1 - 2 1 1.25 0.5 0.9 0.56 LONGITUDINALES EJE D - D DEL 1 - 5 1 15.45 0.5 0.9 6.95 LONGITUDINALES EJE D - D DEL 5 - 7 1 3.35 0.5 0.9 1.51 TRANSVERSALES EJE 1 - 1 DE A - C 1 3.08 0.5 0.9 1.39 TRANSVERSALES EJE 1 - 1 DE C - D 1 2.93 0.5 0.9 1.32 TRANSVERSALES ENTRE 1 - 2 DE A - C 1 0.85 0.5 0.9 0.38 TRANSVERSALES ENTRE 1 - 2 DE C - D 1 1.73 0.5 0.9 0.78 TRANSVERSALES EJE 2 - 2 DE A - C 1 2.81 0.5 0.9 1.26 TRANSVERSALES EJE 2 - 2 DE C - D 1 2 0.5 0.9 0.9 TRANSVERSALES EJE 3 - 3 DE A - C 1 3.7 0.5 0.9 1.67 TRANSVERSALES EJE 3 - 3 DE C - D 1 2.9 0.5 0.9 1.31 TRANSVERSALES EJE 4 - 4 DE A - C 1 3.3 0.5 0.9 1.49 TRANSVERSALES ENTRE 4 - 5 DE A - C 1 2.64 0.5 0.9 1.19 TRANSVERSALES ENTRE 6 - 7 DE A - B 1 2.24 0.5 0.9 1.01 TRANSVERSALES EJE 7 - 7 DE B - C 1 2.34 0.5 0.9 1.05 TRANSVERSALES EJE 7 - 7 DE C - D 1 2.8 0.5 0.9 1.26 02.02.03 CONCRETO EN SOBRECIMIENTO F'c=100 KG/CM2 + 25% PM 5.97 64.81 LONGITUDINALES EJE A - A DEL 1 - 2 1 4.31 0.15 0.4 0.26 8.62 0.4 3.448 LONGITUDINALES EJE A - A DEL 3 - 4 1 3.36 0.15 0.4 0.2 6.72 0.4 2.688 LONGITUDINALES EJE A - A DEL 4 - 5 1 1.95 0.25 0.4 0.2 3.9 0.4 1.56 LONGITUDINALES EJE A - A DEL 5 - 6 1 2.13 0.25 0.4 0.21 4.26 0.4 1.704 LONGITUDINALES EJE A - A DEL 6 - 7 1 2.12 0.25 0.4 0.21 4.24 0.4 1.696 LONGITUDINALES ENTRE A - C DEL 1 - 2 1 3.02 0.15 0.4 0.18 6.04 0.4 2.416 LONGITUDINALES ENTRE A - C DEL 4 - 5 1 1.05 0.15 0.4 0.06 2.1 0.4 0.84 LONGITUDINALES EJE C - C DEL 1 - 2 1 2.81 0.15 0.4 0.17 5.62 0.4 2.248 LONGITUDINALES EJE C - C DEL 3 - 4 1 2.46 0.15 0.4 0.15 4.92 0.4 1.968 LONGITUDINALES EJE C - C DEL 4 - 5 1 1.2 0.15 0.4 0.07 2.4 0.4 0.96 LONGITUDINALES EJE C - C DEL 4 - 5 1 0.88 0.25 0.4 0.09 1.76 0.4 0.704 LONGITUDINALES EJE C - C DEL 5 - 6 1 2.13 0.15 0.4 0.13 4.26 0.4 1.704 LONGITUDINALES EJE C - C DEL 5 - 7 1 3.57 0.15 0.4 0.21 7.14 0.4 2.856 LONGITUDINALES ENTRE C - D DEL 1 - 2 1 0.45 0.15 0.4 0.03 0.9 0.4 0.36 LONGITUDINALES EJE D - D DEL 1 - 2 1 3.81 0.15 0.4 0.23 7.62 0.4 3.048 LONGITUDINALES EJE D - D DEL 2 - 3 1 2.23 0.15 0.4 0.13 4.46 0.4 1.784 LONGITUDINALES EJE D - D DEL 3 - 4 1 3.19 0.15 0.4 0.19 6.38 0.4 2.552 LONGITUDINALES EJE D - D DEL 4 - 5 1 2.88 0.25 0.4 0.29 5.76 0.4 2.304 LONGITUDINALES EJE D - D DEL 5 - 6 1 2.13 0.25 0.4 0.21 4.26 0.4 1.704 LONGITUDINALES EJE D - D DEL 6 - 7 1 3.57 0.25 0.4 0.36 7.14 0.4 2.856 TRANSVERSALES EJE 1 - 1 DE A - C 1 4.03 0.25 0.4 0.4 8.06 0.4 3.224 TRANSVERSALES EJE 1 - 1 DE C - D 1 2.23 0.25 0.4 0.22 4.46 0.4 1.784 TRANSVERSALES ENTRE 1 - 2 DE A - C 1 0.5 0.15 0.4 0.03 1 0.4 0.4 TRANSVERSALES ENTRE 1 - 2 DE C - D 1 0.6 0.15 0.4 0.04 1.2 0.4 0.48 TRANSVERSALES ENTRE 1 - 2 DE C - D 1 1.25 0.15 0.4 0.08 2.5 0.4 1 TRANSVERSALES EJE 2 - 2 DE A - C 1 2.68 0.15 0.4 0.16 5.36 0.4 2.144 TRANSVERSALES EJE 2 - 2 DE A - C 1 1.35 0.15 0.4 0.08 2.7 0.4 1.08 TRANSVERSALES EJE 2 - 2 DE C - D 1 2.25 0.15 0.4 0.14 4.5 0.4 1.8 TRANSVERSALES EJE 3 - 3 DE A - C 1 3.13 0.15 0.4 0.19 6.26 0.4 2.504 TRANSVERSALES EJE 3 - 3 DE C - D 1 2.23 0.15 0.4 0.13 4.46 0.4 1.784 TRANSVERSALES EJE 4 - 4 DE A - C 1 4.03 0.25 0.4 0.4 8.06 0.4 3.224 TRANSVERSALES ENTRE 4 - 5 DE A - C 1 3.33 0.15 0.4 0.2 6.66 0.4 2.664 TRANSVERSALES EJE 7 - 7 DE B - C 1 1.92 0.25 0.4 0.19 3.84 0.4 1.536 TRANSVERSALES EJE 7 - 7 DE C - D 1 2.23 0.15 0.4 0.13 4.46 0.4 1.784 02.03.00 OBRAS DE CONCRETO ARMADO 02.03.01 ZAPATAS 02.03.01.01 CONCRETO F'C=210 KG/CM2 EN ZAPATAS 5.04 ZAPATA1 (1.20 X 1.20 M) 5 1.2 1.2 0.7 5.04 02.03.01.02 ACERO F'y=4,200 KG/CM2 EN ZAPATAS ZAPATA1 (1.20 X 1.20 M) 61.20 LONGITUDINALES 1/2 5 5 1.2 30.60 30.60 TRANSVERSALES 1/2 5 5 1.2 30.60 30.60 02.03.01 COLUMNAS 02.03.01.01 CONCRETO F'C=210 KG/CM2 EN COLUMNAS PRIMER NIVEL C1 19 0.25 0.25 3 3.56 1 3 57 5/8 19 4 3.5 426 425.60 3/8 19 21 1 231.42 231.42 C2 3 0.25 0.15 3 0.34 0.8 3 7.2 LONGITUDINAL 3/8 3 4 3.5 24.36 24.36 TRANSVERSAL 1/4 3 21 0.6 9.45 9.45 C3 2 1.35 3 8.1 0.09 3 0.54 LONGITUDINAL 5/8 2 5 3.5 56 56.00 TRANSVERSAL 3/8 2 21 0.6 14.62 14.62 SEGUDO NIVEL C1 19 0.25 0.25 3 3.56 1 3 57 5/8 19 4 3.5 426 425.60 3/8 19 21 1 231.42 231.42 C2 3 0.25 0.15 3 0.34 0.8 3 7.2 LONGITUDINAL 3/8 3 4 3.5 24.36 24.36 TRANSVERSAL 1/4 3 21 0.6 9.45 9.45 C3 2 1.35 3 8.1 0.09 3 0.54 LONGITUDINAL 5/8 2 5 3.5 56 56.00 TRANSVERSAL 3/8 2 21 0.6 14.62 14.62 02.03.02 VIGAS PRIMER NIVEL V-A1 (25 X 20) 6 13 0.25 0.2 3.9 13 0.65 50.7 LONGITUDINAL 1/2 6 4 12.95 317.02 317.02 LONGITUDINAL 3/8 6 1 12.95 45.07 45.07 TRANSVERSAL 1/4 1 102 1 25.5 25.50 V-A2 (25 X 20) 1 8.7 0.25 0.2 0.44 8.7 0.65 5.66 LONGITUDINAL 1/2 6 1 11.75 71.91 71.91 LONGITUDINAL 3/8 6 1 11.75 40.89 40.89 TRANSVERSAL 1/4 1 86 1 21.5 21.50 V-S1 (25 X 20) 2 20.7 0.25 0.2 2.07 20.7 0.65 26.91 LONGITUDINAL 1/2 2 1 25.6 52.22 52.22 TOTAL N° de Veces Longitud c/ø P,S - 001-2015 Medidas N° de Piezas ..de.. Diámetro ESTRUCTURA Parcial (kg) ELEMENTO Cantidad elementos Descripción Concreto Medidas Total (m3) Partida N° Longitud por ø Total (m2) Encofrado HOJA DE METRADOS DE CONCRETO ARMADO Obra : Ing. Omar QUISPE SETIEMBRE DEL 2015 PIO RIVERA YURICO, SAENZ ROSALES NILTON VLADIMIR Hoja : Plano : Revisado : Versión : Fierro Preparado por Omar 02/10/2015 Página 1
  • 2. Propietario : Fecha : Hecho por : l a h l a (h) 1/4" 3/8" 1/2" 5/8" 3/4" 1" TOTAL N° de Veces Longitud c/ø P,S - 001-2015 Medidas N° de Piezas ..de.. Diámetro ESTRUCTURA Parcial (kg) ELEMENTO Cantidad elementos Descripción Concreto Medidas Total (m3) Partida N° Longitud por ø Total (m2) Encofrado HOJA DE METRADOS DE CONCRETO ARMADO Obra : Ing. Omar QUISPE SETIEMBRE DEL 2015 PIO RIVERA YURICO, SAENZ ROSALES NILTON VLADIMIR Hoja : Plano : Revisado : Versión : Fierro LONGITUDINAL 3/8 2 1 25.6 29.70 29.70 TRANSVERSAL 1/4 1 276 1 69 69.00 V-S1´ (25 X 20) 1 16.28 0.25 0.2 0.81 16.28 0.65 10.58 LONGITUDINAL 1/2 1 1 23.5 23.97 23.97 LONGITUDINAL 3/8 1 1 23.5 13.63 13.63 TRANSVERSAL 1/4 1 250 1 62.5 62.50 V-B (15 X 20) 1 20.7 0.15 0.2 0.62 20.7 0.55 11.39 LONGITUDINAL 1/2 1 1 28 28.56 28.56 LONGITUDINAL 3/8 1 1 28 16.24 16.24 TRANSVERSAL 1/4 1 305 0.5 38.1 38.13 V-B ´ (15 X 20) 1 8.7 0.15 0.2 0.26 8.7 0.55 4.79 LONGITUDINAL 1/2 1 1 11.75 11.99 11.99 LONGITUDINAL 3/8 1 1 11.75 6.82 6.82 TRANSVERSAL 1/4 1 86 0.5 10.8 10.75 SEGUNDO NIVEL V-A1 (25 X 20) 6 13 0.25 0.2 3.9 13 0.65 50.7 LONGITUDINAL 1/2 6 4 12.95 317.02 317.02 LONGITUDINAL 3/8 6 1 12.95 45.07 45.07 TRANSVERSAL 1/4 1 102 1 25.5 25.50 V-A2 (25 X 20) 1 8.7 0.25 0.2 0.44 8.7 0.65 5.66 LONGITUDINAL 1/2 6 1 11.75 71.91 71.91 LONGITUDINAL 3/8 6 1 11.75 40.89 40.89 TRANSVERSAL 1/4 1 86 1 21.5 21.50 V-S1 (25 X 20) 2 20.7 0.25 0.2 2.07 20.7 0.65 26.91 LONGITUDINAL 1/2 2 1 25.6 52.22 52.22 LONGITUDINAL 3/8 2 1 25.6 29.70 29.70 TRANSVERSAL 1/4 1 276 1 69 69.00 V-S1´ (25 X 20) 1 16.28 0.25 0.2 0.81 16.28 0.65 10.58 LONGITUDINAL 1/2 1 1 23.5 23.97 23.97 LONGITUDINAL 3/8 1 1 23.5 13.63 13.63 TRANSVERSAL 1/4 1 250 1 62.5 62.50 V-B (15 X 20) 1 20.7 0.15 0.2 0.62 20.7 0.55 11.39 LONGITUDINAL 1/2 1 1 28 28.56 28.56 LONGITUDINAL 3/8 1 1 28 16.24 16.24 TRANSVERSAL 1/4 1 305 0.5 38.1 38.13 V-B ´ (15 X 20) 1 8.7 0.15 0.2 0.26 8.7 0.55 4.79 LONGITUDINAL 1/2 1 1 11.75 11.99 11.99 LONGITUDINAL 3/8 1 1 11.75 6.82 6.82 TRANSVERSAL 1/4 1 86 0.5 10.8 10.75 1/4" 3/8" 1/2" 5/8" 3/4" 1" 6.35 9.53 12.7 15.9 19.1 25.4 474 845.466 1072.5 963 0 0 0.21 0.56 0.994 1.55 2.24 3.97 98 473.461 1066.1 1495 0 0 52.6 93.9407 119.17 107 0 0 TOTAL de ACERO (kgs) 3132.49 N° de BARRAS RESUMEN DEL METRADO DE ACERO Diámetro (ø) mm Longitud Total x ø Peso Kg/ml TOTAL (kgs) Preparado por Omar 02/10/2015 Página 2