ID Title Dur. Start Finish Assigned To Pred |||
1 Rough Framing 10 9-27-2016 10-10-2016 N/A -
2 Cabinetry Measurement 2 9-30-2016 10-3-2016 N/A -
3 Waterproofing 11 9-30-2016 10-14-2016 N/A -
4 Blocking 5 10-4-2016 10-10-2016 N/A 1
5 Rough: Electrical 15 10-4-2016 10-24-2016 N/A 1
6 Drywall and Cement Board Installation15 10-11-2016 10-31-2016 N/A 1
7 Floor Installation 5 10-18-2016 10-24-2016 N/A -
8 Finalized 1 10-24-2016 10-24-2016 N/A -
9 Installation of electical 17 10-24-2016 11-15-2016 N/A -
10 Tile and Stone Installation 10 10-25-2016 11-7-2016 N/A 3
11 Skim Coat 10 11-1-2016 11-14-2016 N/A 6
12 Case and Base Molding 8 11-8-2016 11-17-2016 N/A 11
13 Door and Hardware 3 11-15-2016 11-17-2016 N/A 11
14 Painting 12 11-15-2016 11-30-2016 N/A 11
15 Garbage Disposal 1 11-18-2016 11-18-2016 N/A -
16 Cabinetry Installation 6 11-21-2016 11-28-2016 N/A -
17 Glass and Stone Measurement 9 11-23-2016 12-5-2016 N/A -
18 Cleaning 16 11-28-2016 12-19-2016 N/A -
19 Millwork revision 5 11-28-2016 12-2-2016 N/A 16
20 Glass and Stone Installation 3 12-5-2016 12-7-2016 N/A 17
21 Touch up 4 12-8-2016 12-13-2016 N/A 14
22 Final Walk Through 1 12-20-2016 12-20-2016 N/A 18, 21
20-Sep-2016 25-Sep-2016 02-Oct-2016 09-Oct-2016 16-Oct-2016 23-Oct-2016 30-Oct-2016 06-Nov-2016 13-Nov-2016 20-Nov-2016 27-Nov-2016 04-Dec-2016 11-Dec-2016 18-Dec-2016 25-Dec-2016 01-Jan-2017
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
Rough Framing
Cabinetry Measurement
Waterproofing
Blocking
Rough: Electrical
Drywall and Cement Board Installation
Floor Installation
Finalized
Installation of electical
Tile and Stone Installation
Skim Coat
Case and Base Molding
Door and Hardware
Painting
Garbage Disposal
Cabinetry Installation
Glass and Stone Measurement
Cleaning
Millwork revision
Glass and Stone Installation
Touch up
Final Walk Through
Demolition and framing phase Construction phase Finishing phase
01 | Minimalism Residential
A. Project Schedule
PROPOSED ELECTRICAL PLANEXISTING PROPOSED
01 | Minimalism Residential
B. Project Blueprint
02 | Untouctable
A. Design Progress
02 | Untouctable
B. Prototype
03 | Tri County Water Treatment Plant Improvement
A. Soil Profile Analysis
03 | Tri County Water Treatment Plant Improvement
B. Excavation Plan
03 | Tri County Water Treatment Plant Improvement
C. New Buildings Construction Site

Weitere ähnliche Inhalte

Ähnlich wie Portfolio Dec 22-min

Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
Nixzalis Bourdier
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
Ahmed Khaled
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
Rodger McKinley
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
Benoit Latapie
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
Ahmed Mehrem
 
Final year Revit project
Final year Revit projectFinal year Revit project
Final year Revit project
Mark Thornton
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
MUHAMMAD SALEEM
 

Ähnlich wie Portfolio Dec 22-min (20)

IHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdfIHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdf
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
MS project Sample gantt chart
MS project Sample  gantt chartMS project Sample  gantt chart
MS project Sample gantt chart
 
Meeting of the brossard good neighbourly relations committee september 21 2016
Meeting of the brossard good neighbourly relations committee   september 21 2016Meeting of the brossard good neighbourly relations committee   september 21 2016
Meeting of the brossard good neighbourly relations committee september 21 2016
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
12FS-18WP ABTP - Bldg P Upgrades and Odour Control Project - 6 Week Look Ahea...
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
 
Public Information Meeting - Verdu - May 25, 2016
Public Information Meeting - Verdu - May 25, 2016Public Information Meeting - Verdu - May 25, 2016
Public Information Meeting - Verdu - May 25, 2016
 
T2_Programación de obras_Grupo7_ValdiviesoAntonFrancoJhayro.pdf
T2_Programación de obras_Grupo7_ValdiviesoAntonFrancoJhayro.pdfT2_Programación de obras_Grupo7_ValdiviesoAntonFrancoJhayro.pdf
T2_Programación de obras_Grupo7_ValdiviesoAntonFrancoJhayro.pdf
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Final year Revit project
Final year Revit projectFinal year Revit project
Final year Revit project
 
QA QC.pptx
QA QC.pptxQA QC.pptx
QA QC.pptx
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
 
Building Technology 2
Building Technology 2Building Technology 2
Building Technology 2
 
Presentation
PresentationPresentation
Presentation
 
2016 Contech Calendar
2016 Contech Calendar2016 Contech Calendar
2016 Contech Calendar
 

Portfolio Dec 22-min

  • 1.
  • 2. Table of Content 01 | Minimalism Residential A. Project Schedule B. Project Blueprint 02 | Untouctable A. Design Progress B. Prototype 03 | Tri County Water Treatment Plant Improvement A. Soil Profile Analysis B. Excavation Plan C. New Buildings Construction Site
  • 3. Michael & Paul ID Title Dur. Start Finish Assigned To Pred ||| 1 Rough Framing 10 9-27-2016 10-10-2016 N/A - 2 Cabinetry Measurement 2 9-30-2016 10-3-2016 N/A - 3 Waterproofing 11 9-30-2016 10-14-2016 N/A - 4 Blocking 5 10-4-2016 10-10-2016 N/A 1 5 Rough: Electrical 15 10-4-2016 10-24-2016 N/A 1 6 Drywall and Cement Board Installation15 10-11-2016 10-31-2016 N/A 1 7 Floor Installation 5 10-18-2016 10-24-2016 N/A - 8 Finalized 1 10-24-2016 10-24-2016 N/A - 9 Installation of electical 17 10-24-2016 11-15-2016 N/A - 10 Tile and Stone Installation 10 10-25-2016 11-7-2016 N/A 3 11 Skim Coat 10 11-1-2016 11-14-2016 N/A 6 12 Case and Base Molding 8 11-8-2016 11-17-2016 N/A 11 13 Door and Hardware 3 11-15-2016 11-17-2016 N/A 11 14 Painting 12 11-15-2016 11-30-2016 N/A 11 15 Garbage Disposal 1 11-18-2016 11-18-2016 N/A - 16 Cabinetry Installation 6 11-21-2016 11-28-2016 N/A - 17 Glass and Stone Measurement 9 11-23-2016 12-5-2016 N/A - 18 Cleaning 16 11-28-2016 12-19-2016 N/A - 19 Millwork revision 5 11-28-2016 12-2-2016 N/A 16 20 Glass and Stone Installation 3 12-5-2016 12-7-2016 N/A 17 21 Touch up 4 12-8-2016 12-13-2016 N/A 14 22 Final Walk Through 1 12-20-2016 12-20-2016 N/A 18, 21 20-Sep-2016 25-Sep-2016 02-Oct-2016 09-Oct-2016 16-Oct-2016 23-Oct-2016 30-Oct-2016 06-Nov-2016 13-Nov-2016 20-Nov-2016 27-Nov-2016 04-Dec-2016 11-Dec-2016 18-Dec-2016 25-Dec-2016 01-Jan-2017 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M Rough Framing Cabinetry Measurement Waterproofing Blocking Rough: Electrical Drywall and Cement Board Installation Floor Installation Finalized Installation of electical Tile and Stone Installation Skim Coat Case and Base Molding Door and Hardware Painting Garbage Disposal Cabinetry Installation Glass and Stone Measurement Cleaning Millwork revision Glass and Stone Installation Touch up Final Walk Through Demolition and framing phase Construction phase Finishing phase 01 | Minimalism Residential A. Project Schedule
  • 4. PROPOSED ELECTRICAL PLANEXISTING PROPOSED 01 | Minimalism Residential B. Project Blueprint
  • 5. 02 | Untouctable A. Design Progress
  • 7. 03 | Tri County Water Treatment Plant Improvement A. Soil Profile Analysis
  • 8. 03 | Tri County Water Treatment Plant Improvement B. Excavation Plan
  • 9. 03 | Tri County Water Treatment Plant Improvement C. New Buildings Construction Site