Introduction:
    Sambhavna offers many flats ranging from 520 sq ft
    to 1520 sq ft in 9 & 12-storey towers.

   Luxuriously planned with the most amicable
    amenities, boasts of 60% open green spaces with
    most apartments facing the central garden.
Project Snapshot :
   The project is located off the Lucknow Rae
    Bareilly road and is 10 kilometres (km)
    away from Amausi Airport and 11 km from
    Hazratganj. The project has good road
    connectivity. The project is targeted to the
    service class in the region.
   A wide range of lifestyle amenities such as a
    club, a swimming pool, indoor and outdoor sport
    facilities, central park and shopping complex are
    available.
   There are in all 17 towers with 14 towers having
    12 floors and remaining 3 towers having 11
    floors each, internal roads were 12 m wide.
   Completion Date:2013
Equipments used:
    Transit mixer:
    It is device that homogeneously combines
     cement, aggregate such as sand or gravel, and
     water to form concrete.
    Transit mixer is truck mounted by a revolving
     drum to mix the components. For smaller
     volume works portable concrete mixers are
     often used so that the concrete can be made at
     the construction site.
Back hoe:
   A backhoe, is a piece of excavating
    equipment or digger consisting of a digging
    bucket on the end of a two-part articulated
    arm.

   They are typically mounted on the back of
    a tractor or front loader. The section of the
    arm closest to the vehicle is known as the
    boom, and the section which carries the
    bucket is known as the dipper or dipper stick.
Concrete Pump:
 The main type of concrete pump is either
  mounted on a truck and known as a truck-
  mounted concrete pump or placed on a
  trailer, and it is commonly referred to as a
  line pump or trailer-mounted concrete pump.
 This pump requires steel or rubber concrete
  placing hoses to be manually attached to the
  outlet of the machine.
BATCHING PLANT
FLY ASH
FLY ASH BRICKS
BRICK WORK
Procedure
 Excavation:
 Excavation was carried out both
  manually as well as mechanically.

   Adequate precautions are taken to see
    that the excavation operations do not
    effect the adjoining structures.
P.C.C:
 After the process of excavation, laying of plain
  cement concrete that is PCC is done. A layer of
  75 mm was made in such a manner that it was
  not mixed with the soil.

   It provides a solid base for the raft foundation
    and a mix of 1:3:6 that is, 1 part of cement to 3
    parts of fine aggregates and 6 parts of coarse
    aggregates by volume were used in it.
LAYING OF FOUNDATION

   At the site, Raft foundations was used to spread
    the load from a structure over a large area,
    normally the entire area of the structure.
      Normally raft foundation is used when large
    load is to be distributed and it is not possible to
    provide individual footings.
        Raft foundations have the advantage of
    reducing differential settlements as the concrete
    slab resists differential movements between
    loading positions.
   They are often needed on soft or loose soils
    with low bearing capacity.
   Raft Foundation had a thickness of 750 mm.
   Bars of 25 mm to 16 mm were used and chairs
    were used.
FORM WORK
   Forms or moulds or shutters are the
    receptacles in which concrete is placed,
    so that it will have the desired shape or
    outline when hardened.
   Once the concrete develops adequate
    strength, the forms are removed. Forms
    are generally made of the materials like
    timber, plywood, steel, etc.
Scaffolding/props used:
   Scaffolding is a temporary structure used to
    support people and material in the construction
    or repair of buildings and other large structures.
    It is usually a modular system of metal pipes or
    tubes, although it can be from other materials.
   The key elements of a scaffold are standards,
    ledgers and transoms.
CONCRETING

   Type of Cement Used :P.P.C (A.C.C)
   Grade of concrete in slabs and beams :M-20
   Grade of concrete in coloumns:M-30
   Grade of concrete in P.C.C work:M-10
   Grade of concrete in Raft foundation:M-25
   Concrete was made at the site only at
    the batching plant.
   From there it was carried upto the site
    with the transit mixer.
   Capacity of a transit mixer :6m3
   Aggregates sizes :20 mm ,10mm
   Fine aggregate (sand):zone 2
REINFORCEMENT


 Fe-500 grade of steel was used.
 High strength deformed bars conforming to
  IS: 1786 ,grade Fe 500, indicate yield
  stresses 500 N/mm2 are commonly used.
Column

   Total no. of columns in a floor was 69 , in
    which 64 have dimension 750*250 and
    remaining 5 columns having dimension
    600*250.
   There were 10 bars used in the columns in
    which the corner bars were of dia. 25
    mm ,and the remaining were 20 mm dia. till
    5 th floor.
   6 th to 9 th floor bars of dia. 20 mm and 16
    mm were provided respectively in the
    corner and in the middle.
   From 9 th onwards till the end the bars of
    dia. 16 mm and 12 mm were provided.
Ring/Tie bars:
   8 mm dia. bars were used as ring.
   The larger ring was of dimension 650*150 mm
    which holds the corner bars and the smaller ring
    was of dimension 350*150 which holds the inner
    bars.

 Spacing between the rings:
 The spacing between the top and the next ring
  was 80 mm and also the same spacing was
  provided for the bottommost and the ring above
  it.
 Rest all the spacing between the rings was
  120mm.
Beams:
   Beams were of sizes 230*400,small beams of
    size 230*160 was also provided.
    Main Reinforcement: Mostly bars of dia 25,20
    and 16 mm were provided.
    Shear Reinforcement:
   Stirrup was of dia. 8mm.
   Stirrups were provided for the shear
    reinforcement ,1 st stirrup is at 40 mm from face
    of the supporting member.
   Spacing of the stirrup was upto 2*(dia of the
    main bar)
Slab:
   Main bars used were of 12 mm at the top and
    also at the bottom.
    Chairs were provided at different locations to
    provide the spacing required between the top
    and bottom reinforcement.
   Thickness of the slab was 100 mm.
   Note: No shear reinforcement is provided in the
    slab.
Cover block:
   Cover blocks are placed to prevent the steel
    rods from touching the shuttering plates and
    there by providing a minimum cover and fix the
    reinforcements as per the design drawings.
   Covers should be made of cement sand mortar
    (1:3). Ideally, cover should have strength similar
    to the surrounding concrete, with the least
    perimeter so that chances of water to penetrate
    through periphery will be minimized.
SAFETY NETS
CONCLUSION
   This training is comprehensive in filling the gap
    between the theoretical & practical studies
   At the site there was a good management
    system between the contractor, the consultant,
    and the client.
   I found that there was good understanding
    between the supervisor and the workers,
    though works are interdependent but there
    were no contradiction between them.
ppt on training civil report on shuttering

Weitere ähnliche Inhalte

Was ist angesagt?

Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building Self-employed
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques GAURAV. H .TANDON
 
Concrete Road
Concrete RoadConcrete Road
Concrete RoadKp Ahm
 
Building construction
Building constructionBuilding construction
Building constructionnhmurad
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanAnis Rahman Khokan
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING Vikas Sukhwal
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential buildingSumit Singh
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONROHITASH ROJ
 
Pavement construction methods
Pavement construction methodsPavement construction methods
Pavement construction methodsshrikanth16
 
Summer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman NigamSummer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman NigamRaju kumar Gautam
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportAman Gupta
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential buildingsuraj jha
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteRAVI KUMAR
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Make Mannan
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshulAnshul Shakya
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Pile cap
Pile cap Pile cap
Pile cap Lam Yu
 

Was ist angesagt? (20)

Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Concrete Road
Concrete RoadConcrete Road
Concrete Road
 
Building construction
Building constructionBuilding construction
Building construction
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential building
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Pavement construction methods
Pavement construction methodsPavement construction methods
Pavement construction methods
 
Summer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman NigamSummer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman Nigam
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training report
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential building
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Pile cap
Pile cap Pile cap
Pile cap
 

Andere mochten auch

Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
 
Industrial training ppt.
Industrial training ppt.Industrial training ppt.
Industrial training ppt.Tarun Sharma
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineeringalok0025
 
Internship Report on Building Construction
Internship Report on Building ConstructionInternship Report on Building Construction
Internship Report on Building ConstructionEsmael Aragaw
 
Real estate marketing plan ppt (Surat Residency Vrindavan yojana Lucknow)
Real estate marketing plan ppt (Surat Residency Vrindavan yojana Lucknow)Real estate marketing plan ppt (Surat Residency Vrindavan yojana Lucknow)
Real estate marketing plan ppt (Surat Residency Vrindavan yojana Lucknow)Surat Construction PVT LTD
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineeringFazal-E- Jalal
 
Multi storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial buildingMulti storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial buildingRazes Dhakal
 
Analysis and design of a multi storey reinforced concrete
Analysis and design of a multi storey reinforced concreteAnalysis and design of a multi storey reinforced concrete
Analysis and design of a multi storey reinforced concreteSurat Construction PVT LTD
 
Summer internship report L&T
Summer internship report L&TSummer internship report L&T
Summer internship report L&TUmed Paliwal
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)mbrsalman
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Safety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulSafety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulAnshul Shakya
 

Andere mochten auch (20)

Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD
 
Industrial training ppt.
Industrial training ppt.Industrial training ppt.
Industrial training ppt.
 
Vivek Mishra
Vivek MishraVivek Mishra
Vivek Mishra
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineering
 
Internship Report on Building Construction
Internship Report on Building ConstructionInternship Report on Building Construction
Internship Report on Building Construction
 
Industrial Training Report-1
Industrial Training Report-1Industrial Training Report-1
Industrial Training Report-1
 
Industrial training report
Industrial training report Industrial training report
Industrial training report
 
Real estate marketing plan ppt (Surat Residency Vrindavan yojana Lucknow)
Real estate marketing plan ppt (Surat Residency Vrindavan yojana Lucknow)Real estate marketing plan ppt (Surat Residency Vrindavan yojana Lucknow)
Real estate marketing plan ppt (Surat Residency Vrindavan yojana Lucknow)
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
Multi storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial buildingMulti storey building design of 7 storey commercial building
Multi storey building design of 7 storey commercial building
 
Analysis and design of a multi storey reinforced concrete
Analysis and design of a multi storey reinforced concreteAnalysis and design of a multi storey reinforced concrete
Analysis and design of a multi storey reinforced concrete
 
Summer internship report L&T
Summer internship report L&TSummer internship report L&T
Summer internship report L&T
 
Formwork
FormworkFormwork
Formwork
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Yeronga 1992
Yeronga 1992Yeronga 1992
Yeronga 1992
 
Concreting operation
Concreting operationConcreting operation
Concreting operation
 
Hot Mix Plant
Hot Mix PlantHot Mix Plant
Hot Mix Plant
 
Vivek Mishra
Vivek MishraVivek Mishra
Vivek Mishra
 
Safety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area AnshulSafety aspects on construction site in noida area Anshul
Safety aspects on construction site in noida area Anshul
 

Ähnlich wie ppt on training civil report on shuttering

Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptxPranavKd
 
Plastic cell filled concretepavement .pptx
Plastic cell filled concretepavement .pptxPlastic cell filled concretepavement .pptx
Plastic cell filled concretepavement .pptxPranavKd
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxRajeshKumar25548
 
report-on-emmar.docx13
report-on-emmar.docx13report-on-emmar.docx13
report-on-emmar.docx13Minhal Haider
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxJaySinghchib1
 
Building Construction 2 Project 1
Building Construction 2 Project 1Building Construction 2 Project 1
Building Construction 2 Project 1Carlson Ko
 

Ähnlich wie ppt on training civil report on shuttering (20)

Field work
Field workField work
Field work
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptx
 
Plastic cell filled concretepavement .pptx
Plastic cell filled concretepavement .pptxPlastic cell filled concretepavement .pptx
Plastic cell filled concretepavement .pptx
 
Form Work
Form Work Form Work
Form Work
 
road drainage
road drainageroad drainage
road drainage
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Formwork
FormworkFormwork
Formwork
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
report-on-emmar.docx13
report-on-emmar.docx13report-on-emmar.docx13
report-on-emmar.docx13
 
Concrete
ConcreteConcrete
Concrete
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Piles
PilesPiles
Piles
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Building Construction 2 Project 1
Building Construction 2 Project 1Building Construction 2 Project 1
Building Construction 2 Project 1
 

Kürzlich hochgeladen

On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxPooja Bhuva
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxDr. Ravikiran H M Gowda
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024Elizabeth Walsh
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Amil baba
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxDr. Sarita Anand
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxannathomasp01
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 

Kürzlich hochgeladen (20)

On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 

ppt on training civil report on shuttering

  • 1.
  • 2. Introduction:  Sambhavna offers many flats ranging from 520 sq ft to 1520 sq ft in 9 & 12-storey towers.  Luxuriously planned with the most amicable amenities, boasts of 60% open green spaces with most apartments facing the central garden.
  • 3. Project Snapshot :  The project is located off the Lucknow Rae Bareilly road and is 10 kilometres (km) away from Amausi Airport and 11 km from Hazratganj. The project has good road connectivity. The project is targeted to the service class in the region.
  • 4. A wide range of lifestyle amenities such as a club, a swimming pool, indoor and outdoor sport facilities, central park and shopping complex are available.  There are in all 17 towers with 14 towers having 12 floors and remaining 3 towers having 11 floors each, internal roads were 12 m wide.  Completion Date:2013
  • 5.
  • 6. Equipments used: Transit mixer:  It is device that homogeneously combines cement, aggregate such as sand or gravel, and water to form concrete.  Transit mixer is truck mounted by a revolving drum to mix the components. For smaller volume works portable concrete mixers are often used so that the concrete can be made at the construction site.
  • 7.
  • 8. Back hoe:  A backhoe, is a piece of excavating equipment or digger consisting of a digging bucket on the end of a two-part articulated arm.  They are typically mounted on the back of a tractor or front loader. The section of the arm closest to the vehicle is known as the boom, and the section which carries the bucket is known as the dipper or dipper stick.
  • 9.
  • 10. Concrete Pump:  The main type of concrete pump is either mounted on a truck and known as a truck- mounted concrete pump or placed on a trailer, and it is commonly referred to as a line pump or trailer-mounted concrete pump.  This pump requires steel or rubber concrete placing hoses to be manually attached to the outlet of the machine.
  • 11.
  • 16. Procedure Excavation:  Excavation was carried out both manually as well as mechanically.  Adequate precautions are taken to see that the excavation operations do not effect the adjoining structures.
  • 17. P.C.C:  After the process of excavation, laying of plain cement concrete that is PCC is done. A layer of 75 mm was made in such a manner that it was not mixed with the soil.  It provides a solid base for the raft foundation and a mix of 1:3:6 that is, 1 part of cement to 3 parts of fine aggregates and 6 parts of coarse aggregates by volume were used in it.
  • 18. LAYING OF FOUNDATION  At the site, Raft foundations was used to spread the load from a structure over a large area, normally the entire area of the structure. Normally raft foundation is used when large load is to be distributed and it is not possible to provide individual footings. Raft foundations have the advantage of reducing differential settlements as the concrete slab resists differential movements between loading positions.
  • 19. They are often needed on soft or loose soils with low bearing capacity.  Raft Foundation had a thickness of 750 mm.  Bars of 25 mm to 16 mm were used and chairs were used.
  • 20.
  • 21. FORM WORK  Forms or moulds or shutters are the receptacles in which concrete is placed, so that it will have the desired shape or outline when hardened.  Once the concrete develops adequate strength, the forms are removed. Forms are generally made of the materials like timber, plywood, steel, etc.
  • 22.
  • 23. Scaffolding/props used:  Scaffolding is a temporary structure used to support people and material in the construction or repair of buildings and other large structures.  It is usually a modular system of metal pipes or tubes, although it can be from other materials.  The key elements of a scaffold are standards, ledgers and transoms.
  • 24.
  • 25. CONCRETING  Type of Cement Used :P.P.C (A.C.C)  Grade of concrete in slabs and beams :M-20  Grade of concrete in coloumns:M-30  Grade of concrete in P.C.C work:M-10  Grade of concrete in Raft foundation:M-25
  • 26. Concrete was made at the site only at the batching plant.  From there it was carried upto the site with the transit mixer.  Capacity of a transit mixer :6m3  Aggregates sizes :20 mm ,10mm  Fine aggregate (sand):zone 2
  • 27. REINFORCEMENT  Fe-500 grade of steel was used.  High strength deformed bars conforming to IS: 1786 ,grade Fe 500, indicate yield stresses 500 N/mm2 are commonly used.
  • 28.
  • 29. Column  Total no. of columns in a floor was 69 , in which 64 have dimension 750*250 and remaining 5 columns having dimension 600*250.  There were 10 bars used in the columns in which the corner bars were of dia. 25 mm ,and the remaining were 20 mm dia. till 5 th floor.  6 th to 9 th floor bars of dia. 20 mm and 16 mm were provided respectively in the corner and in the middle.  From 9 th onwards till the end the bars of dia. 16 mm and 12 mm were provided.
  • 30.
  • 31. Ring/Tie bars:  8 mm dia. bars were used as ring.  The larger ring was of dimension 650*150 mm which holds the corner bars and the smaller ring was of dimension 350*150 which holds the inner bars. Spacing between the rings:  The spacing between the top and the next ring was 80 mm and also the same spacing was provided for the bottommost and the ring above it.  Rest all the spacing between the rings was 120mm.
  • 32.
  • 33. Beams:  Beams were of sizes 230*400,small beams of size 230*160 was also provided.  Main Reinforcement: Mostly bars of dia 25,20 and 16 mm were provided. Shear Reinforcement:  Stirrup was of dia. 8mm.  Stirrups were provided for the shear reinforcement ,1 st stirrup is at 40 mm from face of the supporting member.  Spacing of the stirrup was upto 2*(dia of the main bar)
  • 34.
  • 35. Slab:  Main bars used were of 12 mm at the top and also at the bottom.  Chairs were provided at different locations to provide the spacing required between the top and bottom reinforcement.  Thickness of the slab was 100 mm.  Note: No shear reinforcement is provided in the slab.
  • 36.
  • 37. Cover block:  Cover blocks are placed to prevent the steel rods from touching the shuttering plates and there by providing a minimum cover and fix the reinforcements as per the design drawings.  Covers should be made of cement sand mortar (1:3). Ideally, cover should have strength similar to the surrounding concrete, with the least perimeter so that chances of water to penetrate through periphery will be minimized.
  • 38.
  • 39.
  • 41. CONCLUSION  This training is comprehensive in filling the gap between the theoretical & practical studies  At the site there was a good management system between the contractor, the consultant, and the client.  I found that there was good understanding between the supervisor and the workers, though works are interdependent but there were no contradiction between them.