SlideShare ist ein Scribd-Unternehmen logo
1 von 4
Downloaden Sie, um offline zu lesen
Vermont Power Import Alternatives
Active interconnection requests—A review
Proposed Elective Transmission Upgrades (ETU)
1. NY-VT: Grand Isle Intertie (230kV AC-QP314)
• 400 MW capacity
• 230 KV phase angle regulator-controlled tie at a new Champlain
Substation site
• Plattsburgh Substation upgrade
• Submarine cables (Lake Champlain)/underground or overhead 230kV
• Target in-service date: 6/2017

2. HQ-VT: New England Clean Power Link (320kV DC-QP425)
•
•
•
•
•

1,000 MW capacity
320 kV DC transmission tie
AC/DC converter connecting to HQ 75kV system
AC/DC converter connecting to VT 345kV system
Target in-service date: 12/2018

3. HQ-VT: Highgate Expansion (Back-to-back converter-QP
TBD)
•
•
•
•

425 MW capacity
120/115kV transmission lines
Back-to-back converter station
Target in-service date: 06/2018

2
Current status of the proposed import projects
Grand Isle Intertie
•
•
•
•
•

Partially completed the feasibility study
Started system impact study with NYISO and ISO-NE
Assembling project team and reviewing alternate routes
Met with VELCO to discuss access to rights of way to conduct surveys/studies
Initiating stakeholder outreach

New England Clean Power Link
•
•
•
•
•
•

Started the ISO-NE interconnection process (system impact study agreement not executed yet)
Assembling project team and reviewing preferred routes and corridors
Met with VELCO to discuss access to rights of way to conduct studies
Initiating stakeholder outreach
Drafting legal agreements to establish VELCO’s role in the review of the project
Developer intends to submit permit applications in September 2014

Highgate Expansion
•
•
•
•

No New England studies have started yet
HQ production request of “point-to-point service” to the US/Canada border
Submitted inquiry to VELCO regarding project development, rights of way, etc.
Discussed system limitation in Quebec’s system

3
Current status/next steps
Current status—VELCO’s interaction
• Establishing VELCO teams to interact with developers regarding right-of-way
access/reviews, respond to inquiries, requests, etc.
• Continuing communication with project developers and other stakeholders to evaluate
and mitigate potential impacts
• Participating actively in ISO-NE interconnection process
• Collaborating with VT Public Service Department to aid in addressing critical questions
Current status—import project review
• Obtaining a clearer understanding of VELCO’s legal rights and responsibilities associated
with projects, as well as opportunities for revenue generation and/or investment
–
–

Team is currently gathering input from the PSD based on draft transmission alternative
evaluation document
Evaluating potential risks and projects’ value to Vermont, including distribution utilities
•
•

•

Investigating possible opportunities to offset rising regional transmission costs
Developing summary of projects’ value as well as risk/threats

Initiated legal review to determine necessary steps to allow for VELCO’s involvement

4

Weitere ähnliche Inhalte

Was ist angesagt?

Organics Processing Request for Proposals
Organics Processing Request for ProposalsOrganics Processing Request for Proposals
Organics Processing Request for Proposals
WALK
 
Caltrain hsrmo uletter
Caltrain hsrmo uletterCaltrain hsrmo uletter
Caltrain hsrmo uletter
Adina Levin
 

Was ist angesagt? (20)

WV State Freight Plan
WV State Freight PlanWV State Freight Plan
WV State Freight Plan
 
2040 Metropolitan Transportation Plan and Downtown Huntington Access Study
2040 Metropolitan Transportation Plan and Downtown Huntington Access Study2040 Metropolitan Transportation Plan and Downtown Huntington Access Study
2040 Metropolitan Transportation Plan and Downtown Huntington Access Study
 
Innovation Showcase – Bentley’s AssetWise Optram
Innovation Showcase – Bentley’s AssetWise OptramInnovation Showcase – Bentley’s AssetWise Optram
Innovation Showcase – Bentley’s AssetWise Optram
 
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013Fuel Cell Electric Buses in California Fuel Cell Seminar 2013
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013
 
Survey-Services
Survey-ServicesSurvey-Services
Survey-Services
 
James wright and philbert chan rssb
James wright and philbert chan rssbJames wright and philbert chan rssb
James wright and philbert chan rssb
 
2015 STS - OS/OW Corridor Movement (Mark Berndt portion)
2015 STS - OS/OW Corridor Movement (Mark Berndt portion)2015 STS - OS/OW Corridor Movement (Mark Berndt portion)
2015 STS - OS/OW Corridor Movement (Mark Berndt portion)
 
2015 March 16 ASCE TTG - I-405 Improvement Project
2015 March 16   ASCE TTG - I-405 Improvement Project 2015 March 16   ASCE TTG - I-405 Improvement Project
2015 March 16 ASCE TTG - I-405 Improvement Project
 
Evolving Planning Process Drivers - Steve Herling, PJM Interconnection LLC
Evolving Planning Process Drivers - Steve Herling, PJM Interconnection LLCEvolving Planning Process Drivers - Steve Herling, PJM Interconnection LLC
Evolving Planning Process Drivers - Steve Herling, PJM Interconnection LLC
 
Organics Processing Request for Proposals
Organics Processing Request for ProposalsOrganics Processing Request for Proposals
Organics Processing Request for Proposals
 
Caltrans Independent Assurance Update for stakeholders
Caltrans Independent Assurance Update for stakeholdersCaltrans Independent Assurance Update for stakeholders
Caltrans Independent Assurance Update for stakeholders
 
A Balanced Routing Algorithm for Blockchain Offline Channels using Flocking
A Balanced Routing Algorithm for Blockchain Offline Channels using FlockingA Balanced Routing Algorithm for Blockchain Offline Channels using Flocking
A Balanced Routing Algorithm for Blockchain Offline Channels using Flocking
 
Kyriakos Tyrologos
Kyriakos TyrologosKyriakos Tyrologos
Kyriakos Tyrologos
 
PPRO
PPROPPRO
PPRO
 
Cooperative load balancing and dynamic channel allocation for cluster based m...
Cooperative load balancing and dynamic channel allocation for cluster based m...Cooperative load balancing and dynamic channel allocation for cluster based m...
Cooperative load balancing and dynamic channel allocation for cluster based m...
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Caltrain hsrmo uletter
Caltrain hsrmo uletterCaltrain hsrmo uletter
Caltrain hsrmo uletter
 
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
Boosting Active Transportation at the Regional Level: Setting and Meeting Per...
 
Nov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateNov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule Update
 
Designing Sustainable Supply Chains - Amar Ramudhin, University of Hull
Designing Sustainable Supply Chains - Amar Ramudhin, University of HullDesigning Sustainable Supply Chains - Amar Ramudhin, University of Hull
Designing Sustainable Supply Chains - Amar Ramudhin, University of Hull
 

Andere mochten auch

Mieko Ozeki's Philosophy of Education statement
Mieko Ozeki's Philosophy of Education statementMieko Ozeki's Philosophy of Education statement
Mieko Ozeki's Philosophy of Education statement
Mieko Ozeki
 

Andere mochten auch (6)

Plugging into the Smart Grid: How College and Universities Can Get Involved
Plugging into the Smart Grid: How College and Universities Can Get InvolvedPlugging into the Smart Grid: How College and Universities Can Get Involved
Plugging into the Smart Grid: How College and Universities Can Get Involved
 
Telecom tower carbon footprint IoT Case Study
Telecom tower carbon footprint IoT Case StudyTelecom tower carbon footprint IoT Case Study
Telecom tower carbon footprint IoT Case Study
 
Mieko Ozeki's Philosophy of Education statement
Mieko Ozeki's Philosophy of Education statementMieko Ozeki's Philosophy of Education statement
Mieko Ozeki's Philosophy of Education statement
 
Pass That Exam! Test Prep Strategies & Resources
Pass That Exam! Test Prep Strategies & ResourcesPass That Exam! Test Prep Strategies & Resources
Pass That Exam! Test Prep Strategies & Resources
 
Groovy Grammar! Interesting ways to learn grammar!
Groovy Grammar! Interesting ways to learn grammar!Groovy Grammar! Interesting ways to learn grammar!
Groovy Grammar! Interesting ways to learn grammar!
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of Work
 

Ähnlich wie Vermont Power Import Alternatives

K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
ascemiami-dade
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
Sher Chuhan
 
Bob Smith WEIL 7-10-15
Bob Smith WEIL 7-10-15Bob Smith WEIL 7-10-15
Bob Smith WEIL 7-10-15
Robert Smith
 
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Andrew Gelston
 
Navigating I T
Navigating I  TNavigating I  T
Navigating I T
rpeters
 
Minteer Resume 4.7.16 - Linkedin
Minteer Resume 4.7.16 - LinkedinMinteer Resume 4.7.16 - Linkedin
Minteer Resume 4.7.16 - Linkedin
Zachary Minteer
 
Transbay presentation-2-14-13
Transbay presentation-2-14-13Transbay presentation-2-14-13
Transbay presentation-2-14-13
Adina Levin
 
DEVELOPING AN EV CHARGING STATION: A TECHNICAL AND REGULATORY OVERVIEW
DEVELOPING AN EV CHARGING STATION: A TECHNICAL AND REGULATORY OVERVIEWDEVELOPING AN EV CHARGING STATION: A TECHNICAL AND REGULATORY OVERVIEW
DEVELOPING AN EV CHARGING STATION: A TECHNICAL AND REGULATORY OVERVIEW
DesignTeam8
 

Ähnlich wie Vermont Power Import Alternatives (20)

K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
Update on public utility commission of texas activities
Update on public utility commission of texas activitiesUpdate on public utility commission of texas activities
Update on public utility commission of texas activities
 
Benter, Water Rates
Benter, Water RatesBenter, Water Rates
Benter, Water Rates
 
Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
 
Wp [final]master plan may 16 workshop summary
Wp   [final]master plan may 16 workshop summaryWp   [final]master plan may 16 workshop summary
Wp [final]master plan may 16 workshop summary
 
Planning for the Future: The Changing World of the Electric Transmission System
Planning for the Future: The Changing World of the Electric Transmission SystemPlanning for the Future: The Changing World of the Electric Transmission System
Planning for the Future: The Changing World of the Electric Transmission System
 
Bob Smith WEIL 7-10-15
Bob Smith WEIL 7-10-15Bob Smith WEIL 7-10-15
Bob Smith WEIL 7-10-15
 
2014 Enbridge Day - Major Projects
2014 Enbridge Day - Major Projects2014 Enbridge Day - Major Projects
2014 Enbridge Day - Major Projects
 
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
Turkey Point-6 and Turkey Point-7 Project Overview (May 2013)
 
Planning Principles for Full Fleet Electrification
Planning Principles for Full Fleet ElectrificationPlanning Principles for Full Fleet Electrification
Planning Principles for Full Fleet Electrification
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Navigating Interconnecion and Transmission in the Major US Markets
Navigating Interconnecion and Transmission in the Major US MarketsNavigating Interconnecion and Transmission in the Major US Markets
Navigating Interconnecion and Transmission in the Major US Markets
 
Navigating I T
Navigating I  TNavigating I  T
Navigating I T
 
General Assembly Actions Related to Utility Undergrounding
General Assembly Actions Related to Utility UndergroundingGeneral Assembly Actions Related to Utility Undergrounding
General Assembly Actions Related to Utility Undergrounding
 
Minteer Resume 4.7.16 - Linkedin
Minteer Resume 4.7.16 - LinkedinMinteer Resume 4.7.16 - Linkedin
Minteer Resume 4.7.16 - Linkedin
 
Transbay presentation-2-14-13
Transbay presentation-2-14-13Transbay presentation-2-14-13
Transbay presentation-2-14-13
 
DEVELOPING AN EV CHARGING STATION: A TECHNICAL AND REGULATORY OVERVIEW
DEVELOPING AN EV CHARGING STATION: A TECHNICAL AND REGULATORY OVERVIEWDEVELOPING AN EV CHARGING STATION: A TECHNICAL AND REGULATORY OVERVIEW
DEVELOPING AN EV CHARGING STATION: A TECHNICAL AND REGULATORY OVERVIEW
 
What it all means: solar regulatory world 101
What it all means: solar regulatory world 101What it all means: solar regulatory world 101
What it all means: solar regulatory world 101
 
Wp special master-plan[071113]
Wp special master-plan[071113]Wp special master-plan[071113]
Wp special master-plan[071113]
 
Interconnection Issues at Higher Penetrations
Interconnection Issues at Higher PenetrationsInterconnection Issues at Higher Penetrations
Interconnection Issues at Higher Penetrations
 

KĂźrzlich hochgeladen

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

KĂźrzlich hochgeladen (20)

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Top 10 Most Downloaded Games on Play Store in 2024
Top 10 Most Downloaded Games on Play Store in 2024Top 10 Most Downloaded Games on Play Store in 2024
Top 10 Most Downloaded Games on Play Store in 2024
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
HTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesHTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation Strategies
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 

Vermont Power Import Alternatives

  • 1. Vermont Power Import Alternatives
  • 2. Active interconnection requests—A review Proposed Elective Transmission Upgrades (ETU) 1. NY-VT: Grand Isle Intertie (230kV AC-QP314) • 400 MW capacity • 230 KV phase angle regulator-controlled tie at a new Champlain Substation site • Plattsburgh Substation upgrade • Submarine cables (Lake Champlain)/underground or overhead 230kV • Target in-service date: 6/2017 2. HQ-VT: New England Clean Power Link (320kV DC-QP425) • • • • • 1,000 MW capacity 320 kV DC transmission tie AC/DC converter connecting to HQ 75kV system AC/DC converter connecting to VT 345kV system Target in-service date: 12/2018 3. HQ-VT: Highgate Expansion (Back-to-back converter-QP TBD) • • • • 425 MW capacity 120/115kV transmission lines Back-to-back converter station Target in-service date: 06/2018 2
  • 3. Current status of the proposed import projects Grand Isle Intertie • • • • • Partially completed the feasibility study Started system impact study with NYISO and ISO-NE Assembling project team and reviewing alternate routes Met with VELCO to discuss access to rights of way to conduct surveys/studies Initiating stakeholder outreach New England Clean Power Link • • • • • • Started the ISO-NE interconnection process (system impact study agreement not executed yet) Assembling project team and reviewing preferred routes and corridors Met with VELCO to discuss access to rights of way to conduct studies Initiating stakeholder outreach Drafting legal agreements to establish VELCO’s role in the review of the project Developer intends to submit permit applications in September 2014 Highgate Expansion • • • • No New England studies have started yet HQ production request of “point-to-point service” to the US/Canada border Submitted inquiry to VELCO regarding project development, rights of way, etc. Discussed system limitation in Quebec’s system 3
  • 4. Current status/next steps Current status—VELCO’s interaction • Establishing VELCO teams to interact with developers regarding right-of-way access/reviews, respond to inquiries, requests, etc. • Continuing communication with project developers and other stakeholders to evaluate and mitigate potential impacts • Participating actively in ISO-NE interconnection process • Collaborating with VT Public Service Department to aid in addressing critical questions Current status—import project review • Obtaining a clearer understanding of VELCO’s legal rights and responsibilities associated with projects, as well as opportunities for revenue generation and/or investment – – Team is currently gathering input from the PSD based on draft transmission alternative evaluation document Evaluating potential risks and projects’ value to Vermont, including distribution utilities • • • Investigating possible opportunities to offset rising regional transmission costs Developing summary of projects’ value as well as risk/threats Initiated legal review to determine necessary steps to allow for VELCO’s involvement 4