Earned Value Management
Getting Started
Kim Koster
Project Management Evangelist, Unanet
Rich Wilkinson
Director of Solution Engineering - Unanet
© Unanet
Project Reality
0
20
40
60
80
100
120
Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19
%Complete
Time Line
Plan Reality
4) Result - late and over budget project
1 – It all starts with a plan
2 – A surprise occurs
3 – Recovery Impossible
© Unanet
EVM For Project Success
• EVM encourages detailed realistic plans to be used from the start of a project.
• EVM requires disciplined and integrated planning that will help achieve early detection of
issues to course correct.
• Provides a common set of guidelines for measuring technical, schedule, and cost
performance throughout the life of a project.
• EV provides objective indicators as to performance during the life of a project.
• EVM implementation can be tailored based on complexity of the project.
• EVM and project management aims to have an achievable program plan.
• EV provides an accurate forecast (EAC) of the total funds required for project completion.
• EVM provides metrics based on actual performance data.
• Provides a signal in time for the project manager to take corrective action.
© Unanet
Benefits of EVM
• All project sizes will benefit
• Measure accomplishments
• Accurately forecast project completion and final cost
• Early warning to delays or overruns
• Provide schedule and cost variances
• Minimize scope creep that can result in overruns
• Improve the control of project performance
• Provides a competitive advantage and delights customers
© Unanet
1 2 3
Tasks “earn”
value as work
is completed.
Earned Value (EV) can then
be compared to actuals and
budget for current status and
to predict the future.
Progress is measured in
dollars and hours, so schedule
and cost performance can be
analyzed in the same units.
EVM is the Answer
Earned Value Management (EVM) is a project management methodology that combines schedule
and cost performance to answer the question, What work was done for the money spent?
© Unanet
The Big 3 – Common for All Types of Projects
Cost
Scope – What is the product (Goods or Services)?
Schedule – When will the products be delivered?
Cost – How much will it cost to deliver the product?
EVM provides a structured process to manage all 3!
© Unanet
Organize
the Work
Define Control
Accounts
Plan
Resources
Scope
Comprehension
Establish an
Org Structure
Schedule
Tasks
Establish a Baseline
(cost and schedule)
EVM Roadmap
It all starts with a
great proposal
© Unanet
It all Starts with a GREAT Proposal
Steps for completing the proposal estimate:
▪ Understand the scope, scope comprehension is the key to accurate estimating
▪ Utilize the project template to clone or populate the project information, the past estimates, and the timelines for the tasks
▪ Establish a work breakdown structure (WBS)
▪ Estimate the resources needed to complete the work
▪ Understand the timing of needed resources
▪ Include all materials, services, and travel required
▪ Time phase the estimates
▪ Ensure that the right skill set is available when you need them
▪ Use To Be Determined (TBDs) if the name of the resource is not yet available
▪ Gain buy-in from the proposal team and the functional departments before submission to the customer
At contract award the proposal is the starting point for the project plans!
© Unanet
Scope Comprehension
IMP
PWS
SOW
The
Project
• Statement of Work (SOW) – description
of what is to be delivered to the
customer.
• Performance Work Statements (PWS) –
summary of the work that needs to be
done for a contract
• Integrated Master Plan – event driven
plan that documents the
accomplishments needed to complete
the scope of work and relates each
accomplishment to a project event.
© Unanet
Establish a Work Breakdown Structure (WBS)
Definition
A WBS is a hierarchical
decomposition of the work to be
accomplished on a project. It is
typically outcome or product based
and should make the management
of scope, schedule, and cost much
easier.
© Unanet
Organizational (Department) Breakdown Structure
Enterprise
Quality Project MgmtEngineering
Mechanical Electrical Inspection Reliability PMO Proj Controls
Responsible Organizations - A functional organization is a common type of
organizational structure in which the organization is divided into smaller groups
based on specialized functional areas, such as Engineering, Quality, or Project
Management.
© Unanet
Engineering
Control
Account
Control
Account
Quality
Control
Account
Control
Account
Control
Account
Control
Account
Project
Management
Control
Account
System
Integration
Control
Account
Management
Casing
Electronics
Monitor
Final
Assembly
Super
Computer
Control
Account
Define Control Accounts
Responsibility Assignment Matrix (RAM) - a graphic representation that reflects the integration of project participants such
as work teams, subcontractors, and internal organizations with individual project Work Breakdown Structure elements to
form Control Accounts (CA).
© Unanet
Schedule Tasks
Task 1
Task 4
Task 3
Task 5
Task 6
Task 7
Task 8
Task 9
Task 10
Task 2
Plan your tasks with start and stop dates
© Unanet
Plan and Manage Your Resources
Look for availability and skills to complete your project
© Unanet
Plan and Manage Your Resources
Resource Management:
1) Skills library
2) Enterprise availability
3) Planning grid
4) Visual notification
5) Available to all
stakeholders
© Unanet
Create a Cost Plan (Budget)
Characteristics of a good budget:
1. All scope is included
2. Time-phased
3. Meets the contract cost and
schedule
4. Includes all the resources
needed
5. Aligns with the WBS
6. Basis for comparison to
actuals and EV
https://www.unanet.com/blog/8-tips-budgeting-project-based-organizations
© Unanet
Execute the Project
Execution:
1. Time charged to tasks
2. Status % complete on
each task
3. Explain schedule and
cost variances
4. Update to go forecast
5. Look at metrics for
current issues and
potential future issues
© Unanet
Tips for Picking the Right KPIs
• Very clear purpose (what matters most)
• Common business language
• Align with your current processes if possible
• Holistic approach (think through the unintended consequences)
• Drive the desired behavior (Encourage and reward)
• Define tolerances (red, yellow, green, blue)
• Have a mechanism to display the KPIs to all stakeholders
(dashboards)
I – Important
P – Potential Improvement
A – Authority
IPA Rule
© Unanet
EV Metrics –
help manage
current
status and
gives you a
window into
the future!
© Unanet
Myth Reality
EVM is only for huge government
projects
EVM is a basic project mgmt discipline –
scope, schedule, and cost regardless of
project size
EVM is expensive to implement
All of the base data is in the system
already…merely status % complete
EVM is looking only in the rearview
mirror
EVM provides metrics based on current
performance to predict the future
EVM is old and outdated
Good project management practices
never go out of date
EVM Myths
© Unanet
Formal EVMS Requirement? EVMS forProject™
• Full-featured EVMS solution from forProject Technology
(www.forproject.com)
• Modern user interface - easy to learn and use
• Integrates with Unanet for comprehensive EVMS and
formal (EIA-748) EVMS compliance and reporting
• Direct schedule integration with Microsoft Project,
Project Server and Primavera P6
• Over 40 EVMS metrics and KPIs
• Built-in EVMS reports and charts, including
government IPMR reports and UN/CEFACT XML exports
• Integration with Empower from Encore Analytics
© Unanet
If you are ready to jump
into the Earned Value Pond
and take control of your
projects please contact us
at:
Unanet.com
Kim Koster
kkoster@Unanet.com
Rich Wilkinson
rwilkinson@Unanet.com

Weitere ähnliche Inhalte

Mehr von Unanet

Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)Unanet
 
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Unanet
 
Control the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastControl the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastUnanet
 
The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionUnanet
 
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Unanet
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of ProjectsUnanet
 
Indirect Rates - What Strategy is Right for your Organization
Indirect Rates - What Strategy is Right for your OrganizationIndirect Rates - What Strategy is Right for your Organization
Indirect Rates - What Strategy is Right for your OrganizationUnanet
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value ManagementUnanet
 
Project Billing and Revenue Recognition
Project Billing and Revenue RecognitionProject Billing and Revenue Recognition
Project Billing and Revenue RecognitionUnanet
 
Top Reasons to Make Managing Your Pipeline a Priority
Top Reasons to Make Managing Your Pipeline a PriorityTop Reasons to Make Managing Your Pipeline a Priority
Top Reasons to Make Managing Your Pipeline a PriorityUnanet
 
Top Signs You May Have Outgrown Your Legacy ERP System
Top Signs You May Have Outgrown Your Legacy ERP SystemTop Signs You May Have Outgrown Your Legacy ERP System
Top Signs You May Have Outgrown Your Legacy ERP SystemUnanet
 
Government Contract Foundations – Understanding Indirect Rates
Government Contract Foundations – Understanding Indirect RatesGovernment Contract Foundations – Understanding Indirect Rates
Government Contract Foundations – Understanding Indirect RatesUnanet
 
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last CallCybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last CallUnanet
 
Improve Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsImprove Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsUnanet
 
NIST Cybersecurity Requirements for Government Contractors
NIST Cybersecurity Requirements for Government ContractorsNIST Cybersecurity Requirements for Government Contractors
NIST Cybersecurity Requirements for Government ContractorsUnanet
 
DCAA Audits Without Tears
DCAA Audits Without TearsDCAA Audits Without Tears
DCAA Audits Without TearsUnanet
 
8 Signs You’ve Outgrown Quickbooks!
8 Signs You’ve Outgrown Quickbooks!8 Signs You’ve Outgrown Quickbooks!
8 Signs You’ve Outgrown Quickbooks!Unanet
 
Managing Indirect Rates Just Got a Lot Easier
Managing Indirect Rates Just Got a Lot EasierManaging Indirect Rates Just Got a Lot Easier
Managing Indirect Rates Just Got a Lot EasierUnanet
 
Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Unanet
 

Mehr von Unanet (19)

Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
 
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
 
Control the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastControl the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & Forecast
 
The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost Submission
 
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of Projects
 
Indirect Rates - What Strategy is Right for your Organization
Indirect Rates - What Strategy is Right for your OrganizationIndirect Rates - What Strategy is Right for your Organization
Indirect Rates - What Strategy is Right for your Organization
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
Project Billing and Revenue Recognition
Project Billing and Revenue RecognitionProject Billing and Revenue Recognition
Project Billing and Revenue Recognition
 
Top Reasons to Make Managing Your Pipeline a Priority
Top Reasons to Make Managing Your Pipeline a PriorityTop Reasons to Make Managing Your Pipeline a Priority
Top Reasons to Make Managing Your Pipeline a Priority
 
Top Signs You May Have Outgrown Your Legacy ERP System
Top Signs You May Have Outgrown Your Legacy ERP SystemTop Signs You May Have Outgrown Your Legacy ERP System
Top Signs You May Have Outgrown Your Legacy ERP System
 
Government Contract Foundations – Understanding Indirect Rates
Government Contract Foundations – Understanding Indirect RatesGovernment Contract Foundations – Understanding Indirect Rates
Government Contract Foundations – Understanding Indirect Rates
 
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last CallCybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
 
Improve Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsImprove Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type Contracts
 
NIST Cybersecurity Requirements for Government Contractors
NIST Cybersecurity Requirements for Government ContractorsNIST Cybersecurity Requirements for Government Contractors
NIST Cybersecurity Requirements for Government Contractors
 
DCAA Audits Without Tears
DCAA Audits Without TearsDCAA Audits Without Tears
DCAA Audits Without Tears
 
8 Signs You’ve Outgrown Quickbooks!
8 Signs You’ve Outgrown Quickbooks!8 Signs You’ve Outgrown Quickbooks!
8 Signs You’ve Outgrown Quickbooks!
 
Managing Indirect Rates Just Got a Lot Easier
Managing Indirect Rates Just Got a Lot EasierManaging Indirect Rates Just Got a Lot Easier
Managing Indirect Rates Just Got a Lot Easier
 
Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types
 

Kürzlich hochgeladen

How To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsHow To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsAndolasoft Inc
 
HR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comHR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comFatema Valibhai
 
The Real-World Challenges of Medical Device Cybersecurity- Mitigating Vulnera...
The Real-World Challenges of Medical Device Cybersecurity- Mitigating Vulnera...The Real-World Challenges of Medical Device Cybersecurity- Mitigating Vulnera...
The Real-World Challenges of Medical Device Cybersecurity- Mitigating Vulnera...ICS
 
How To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerHow To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerThousandEyes
 
Active Directory Penetration Testing, cionsystems.com.pdf
Active Directory Penetration Testing, cionsystems.com.pdfActive Directory Penetration Testing, cionsystems.com.pdf
Active Directory Penetration Testing, cionsystems.com.pdfCionsystems
 
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...gurkirankumar98700
 
Cloud Management Software Platforms: OpenStack
Cloud Management Software Platforms: OpenStackCloud Management Software Platforms: OpenStack
Cloud Management Software Platforms: OpenStackVICTOR MAESTRE RAMIREZ
 
What is Binary Language? Computer Number Systems
What is Binary Language?  Computer Number SystemsWhat is Binary Language?  Computer Number Systems
What is Binary Language? Computer Number SystemsJheuzeDellosa
 
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...MyIntelliSource, Inc.
 
Salesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantSalesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantAxelRicardoTrocheRiq
 
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfThe Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfkalichargn70th171
 
Software Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsSoftware Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsArshad QA
 
A Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxA Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxComplianceQuest1
 
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...stazi3110
 
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...MyIntelliSource, Inc.
 
Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)OPEN KNOWLEDGE GmbH
 
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...OnePlan Solutions
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software DevelopersVinodh Ram
 
Diamond Application Development Crafting Solutions with Precision
Diamond Application Development Crafting Solutions with PrecisionDiamond Application Development Crafting Solutions with Precision
Diamond Application Development Crafting Solutions with PrecisionSolGuruz
 

Kürzlich hochgeladen (20)

How To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsHow To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.js
 
HR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.comHR Software Buyers Guide in 2024 - HRSoftware.com
HR Software Buyers Guide in 2024 - HRSoftware.com
 
The Real-World Challenges of Medical Device Cybersecurity- Mitigating Vulnera...
The Real-World Challenges of Medical Device Cybersecurity- Mitigating Vulnera...The Real-World Challenges of Medical Device Cybersecurity- Mitigating Vulnera...
The Real-World Challenges of Medical Device Cybersecurity- Mitigating Vulnera...
 
How To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerHow To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected Worker
 
Active Directory Penetration Testing, cionsystems.com.pdf
Active Directory Penetration Testing, cionsystems.com.pdfActive Directory Penetration Testing, cionsystems.com.pdf
Active Directory Penetration Testing, cionsystems.com.pdf
 
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
(Genuine) Escort Service Lucknow | Starting ₹,5K To @25k with A/C 🧑🏽‍❤️‍🧑🏻 89...
 
Cloud Management Software Platforms: OpenStack
Cloud Management Software Platforms: OpenStackCloud Management Software Platforms: OpenStack
Cloud Management Software Platforms: OpenStack
 
What is Binary Language? Computer Number Systems
What is Binary Language?  Computer Number SystemsWhat is Binary Language?  Computer Number Systems
What is Binary Language? Computer Number Systems
 
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
Steps To Getting Up And Running Quickly With MyTimeClock Employee Scheduling ...
 
Salesforce Certified Field Service Consultant
Salesforce Certified Field Service ConsultantSalesforce Certified Field Service Consultant
Salesforce Certified Field Service Consultant
 
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfThe Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
 
Software Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsSoftware Quality Assurance Interview Questions
Software Quality Assurance Interview Questions
 
A Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docxA Secure and Reliable Document Management System is Essential.docx
A Secure and Reliable Document Management System is Essential.docx
 
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
Building a General PDE Solving Framework with Symbolic-Numeric Scientific Mac...
 
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
 
Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)Der Spagat zwischen BIAS und FAIRNESS (2024)
Der Spagat zwischen BIAS und FAIRNESS (2024)
 
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
Tech Tuesday-Harness the Power of Effective Resource Planning with OnePlan’s ...
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software Developers
 
Exploring iOS App Development: Simplifying the Process
Exploring iOS App Development: Simplifying the ProcessExploring iOS App Development: Simplifying the Process
Exploring iOS App Development: Simplifying the Process
 
Diamond Application Development Crafting Solutions with Precision
Diamond Application Development Crafting Solutions with PrecisionDiamond Application Development Crafting Solutions with Precision
Diamond Application Development Crafting Solutions with Precision
 

Earned Value Management – How to Get Started

  • 1. © Unanet Earned Value Management Getting Started Kim Koster Project Management Evangelist, Unanet Rich Wilkinson Director of Solution Engineering - Unanet
  • 2. © Unanet Project Reality 0 20 40 60 80 100 120 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 %Complete Time Line Plan Reality 4) Result - late and over budget project 1 – It all starts with a plan 2 – A surprise occurs 3 – Recovery Impossible
  • 3. © Unanet EVM For Project Success • EVM encourages detailed realistic plans to be used from the start of a project. • EVM requires disciplined and integrated planning that will help achieve early detection of issues to course correct. • Provides a common set of guidelines for measuring technical, schedule, and cost performance throughout the life of a project. • EV provides objective indicators as to performance during the life of a project. • EVM implementation can be tailored based on complexity of the project. • EVM and project management aims to have an achievable program plan. • EV provides an accurate forecast (EAC) of the total funds required for project completion. • EVM provides metrics based on actual performance data. • Provides a signal in time for the project manager to take corrective action.
  • 4. © Unanet Benefits of EVM • All project sizes will benefit • Measure accomplishments • Accurately forecast project completion and final cost • Early warning to delays or overruns • Provide schedule and cost variances • Minimize scope creep that can result in overruns • Improve the control of project performance • Provides a competitive advantage and delights customers
  • 5. © Unanet 1 2 3 Tasks “earn” value as work is completed. Earned Value (EV) can then be compared to actuals and budget for current status and to predict the future. Progress is measured in dollars and hours, so schedule and cost performance can be analyzed in the same units. EVM is the Answer Earned Value Management (EVM) is a project management methodology that combines schedule and cost performance to answer the question, What work was done for the money spent?
  • 6. © Unanet The Big 3 – Common for All Types of Projects Cost Scope – What is the product (Goods or Services)? Schedule – When will the products be delivered? Cost – How much will it cost to deliver the product? EVM provides a structured process to manage all 3!
  • 7. © Unanet Organize the Work Define Control Accounts Plan Resources Scope Comprehension Establish an Org Structure Schedule Tasks Establish a Baseline (cost and schedule) EVM Roadmap It all starts with a great proposal
  • 8. © Unanet It all Starts with a GREAT Proposal Steps for completing the proposal estimate: ▪ Understand the scope, scope comprehension is the key to accurate estimating ▪ Utilize the project template to clone or populate the project information, the past estimates, and the timelines for the tasks ▪ Establish a work breakdown structure (WBS) ▪ Estimate the resources needed to complete the work ▪ Understand the timing of needed resources ▪ Include all materials, services, and travel required ▪ Time phase the estimates ▪ Ensure that the right skill set is available when you need them ▪ Use To Be Determined (TBDs) if the name of the resource is not yet available ▪ Gain buy-in from the proposal team and the functional departments before submission to the customer At contract award the proposal is the starting point for the project plans!
  • 9. © Unanet Scope Comprehension IMP PWS SOW The Project • Statement of Work (SOW) – description of what is to be delivered to the customer. • Performance Work Statements (PWS) – summary of the work that needs to be done for a contract • Integrated Master Plan – event driven plan that documents the accomplishments needed to complete the scope of work and relates each accomplishment to a project event.
  • 10. © Unanet Establish a Work Breakdown Structure (WBS) Definition A WBS is a hierarchical decomposition of the work to be accomplished on a project. It is typically outcome or product based and should make the management of scope, schedule, and cost much easier.
  • 11. © Unanet Organizational (Department) Breakdown Structure Enterprise Quality Project MgmtEngineering Mechanical Electrical Inspection Reliability PMO Proj Controls Responsible Organizations - A functional organization is a common type of organizational structure in which the organization is divided into smaller groups based on specialized functional areas, such as Engineering, Quality, or Project Management.
  • 12. © Unanet Engineering Control Account Control Account Quality Control Account Control Account Control Account Control Account Project Management Control Account System Integration Control Account Management Casing Electronics Monitor Final Assembly Super Computer Control Account Define Control Accounts Responsibility Assignment Matrix (RAM) - a graphic representation that reflects the integration of project participants such as work teams, subcontractors, and internal organizations with individual project Work Breakdown Structure elements to form Control Accounts (CA).
  • 13. © Unanet Schedule Tasks Task 1 Task 4 Task 3 Task 5 Task 6 Task 7 Task 8 Task 9 Task 10 Task 2 Plan your tasks with start and stop dates
  • 14. © Unanet Plan and Manage Your Resources Look for availability and skills to complete your project
  • 15. © Unanet Plan and Manage Your Resources Resource Management: 1) Skills library 2) Enterprise availability 3) Planning grid 4) Visual notification 5) Available to all stakeholders
  • 16. © Unanet Create a Cost Plan (Budget) Characteristics of a good budget: 1. All scope is included 2. Time-phased 3. Meets the contract cost and schedule 4. Includes all the resources needed 5. Aligns with the WBS 6. Basis for comparison to actuals and EV https://www.unanet.com/blog/8-tips-budgeting-project-based-organizations
  • 17. © Unanet Execute the Project Execution: 1. Time charged to tasks 2. Status % complete on each task 3. Explain schedule and cost variances 4. Update to go forecast 5. Look at metrics for current issues and potential future issues
  • 18. © Unanet Tips for Picking the Right KPIs • Very clear purpose (what matters most) • Common business language • Align with your current processes if possible • Holistic approach (think through the unintended consequences) • Drive the desired behavior (Encourage and reward) • Define tolerances (red, yellow, green, blue) • Have a mechanism to display the KPIs to all stakeholders (dashboards) I – Important P – Potential Improvement A – Authority IPA Rule
  • 19. © Unanet EV Metrics – help manage current status and gives you a window into the future!
  • 20. © Unanet Myth Reality EVM is only for huge government projects EVM is a basic project mgmt discipline – scope, schedule, and cost regardless of project size EVM is expensive to implement All of the base data is in the system already…merely status % complete EVM is looking only in the rearview mirror EVM provides metrics based on current performance to predict the future EVM is old and outdated Good project management practices never go out of date EVM Myths
  • 21. © Unanet Formal EVMS Requirement? EVMS forProject™ • Full-featured EVMS solution from forProject Technology (www.forproject.com) • Modern user interface - easy to learn and use • Integrates with Unanet for comprehensive EVMS and formal (EIA-748) EVMS compliance and reporting • Direct schedule integration with Microsoft Project, Project Server and Primavera P6 • Over 40 EVMS metrics and KPIs • Built-in EVMS reports and charts, including government IPMR reports and UN/CEFACT XML exports • Integration with Empower from Encore Analytics
  • 22. © Unanet If you are ready to jump into the Earned Value Pond and take control of your projects please contact us at: Unanet.com Kim Koster kkoster@Unanet.com Rich Wilkinson rwilkinson@Unanet.com