PowerPoint presentation to accompany
Chopra and Meindl Supply Chain Management, 5e
1-1
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
1-1
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
1-1
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
8-1
Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
8
Aggregate
Planning in a
Supply Chain
8-2Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Learning Objectives
1. Identify the decisions that are best solved by
aggregate planning.
2. Understand the importance of aggregate
planning as a supply chain activity.
3. Describe the information needed to produce
an aggregate plan.
4. Explain the basic trade-offs to consider
when creating an aggregate plan.
5. Formulate and solve basic aggregate
planning problems using Microsoft Excel.
8-3Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Role of Aggregate Planning
in a Supply Chain
• Capacity has a cost and lead times are often long
• Aggregate planning:
– process by which a company determines levels of
capacity, production, subcontracting, inventory,
stockouts, and pricing over a specified time horizon
– goal is to maximize profit
– decisions made at a product family (not SKU) level
– time frame of 3 to 18 months
– how can a firm best use the facilities it has?
8-4Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Role of Aggregate Planning
in a Supply Chain
• Specify operational parameters over the time
horizon
– Production rate – Subcontracting
– Workforce – Backlog
– Overtime – Inventory on hand
– Machine capacity level
• All supply chain stages should work together on
an aggregate plan that will optimize supply chain
performance
8-5Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
The Aggregate Planning Problem
• Given the demand forecast for each period in the
planning horizon, determine the production level,
inventory level, and the capacity level for each period
that maximizes the firm’s (supply chain’s) profit over the
planning horizon
• Specify the planning horizon (typically 3-18 months)
• Specify the duration of each period
• Specify key information required to develop an
aggregate plan
8-6Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Information Needed for
an Aggregate Plan
• Aggregate demand forecast Ft for each Period t over T
periods
• Production costs
– Labor costs, regular time ($/hr) and overtime ($/hr)
– Subcontracting costs ($/hr or $/unit)
– Cost of changing capacity – hiring or layoff ($/worker), adding or
reducing machine capacity ($/machine)
• Labor/machine hours required per unit
• Inventory holding cost ($/unit/period)
• Stockout or backlog cost ($/unit/period)
• Constraints – overtime, layoffs, capital available,
stockouts, backlogs, from suppliers
8-7Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Outputs of Aggregate Plan
• Production quantity from regular time, overtime,
and subcontracted time
• Inventory held
• Backlog/stockout quantity
• Machine capacity increase/decrease
• A poor aggregate plan can result in lost sales,
lost profits, excess inventory, or excess capacity
8-8Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Identifying Aggregate Units of
Production
• Aggregate unit should be identified in a
way that the resulting production schedule
can be accomplished in practice
• Focus on the bottlenecks when selecting
the aggregate unit and identifying capacity
and production times
• Account for activities such as setups and
maintenance
8-9Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Family
Material
Cost/
Unit ($)
Revenue/
Unit ($)
Setup
Time/B
atch
(hour)
Average
Batch
Size
Production
Time/ Unit
(hour)
Net
Production
Time/Unit
(hour)
Percentage
Share of
Units Sold
A 15 54 8 50 5.60 5.76 10
B 7 30 6 150 3.00 3.04 25
C 9 39 8 100 3.80 3.88 20
D 12 49 10 50 4.80 5.00 10
E 9 36 6 100 3.60 3.66 20
F 13 48 5 75 4.30 4.37 15
Table 8-1
8-10Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
• Weighted average approach
Material cost per aggregate unit
= 15 x 0.10 + 7 x 0.25 + 9 x 0.20
+ 12 x 0.10 + 9 x 0.20 + 13 x 0.15
= $10
• Similarly
Revenue per aggregate unit = $40
Net production time per aggregate unit = 4.00 hours
8-11Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Aggregate Planning Strategies
• Trade-off between capacity, inventory,
backlog/lost sales
• Chase strategy – using capacity as the
lever
• Time flexibility from workforce or capacity
strategy – using utilization as the lever
• Level strategy – using inventory as the
lever
• Tailored or hybrid strategy – a
combination of strategies
8-12Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Chase Strategy
• Vary machine capacity or hire and lay off
workers as demand varies
• Often difficult to vary capacity and workforce
on short notice
• Expensive if cost of varying capacity is high
• Negative effect on workforce morale
• Results in low levels of inventory
• Used when inventory holding costs are high
and costs of changing capacity are low
8-13Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Time Flexibility Strategy
• Use excess machine capacity
• Workforce stable, number of hours worked
varies
• Use overtime or a flexible work schedule
• Flexible workforce, avoids morale problems
• Low levels of inventory, lower utilization
• Used when inventory holding costs are high
and capacity is relatively inexpensive
8-14Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Level Strategy
• Stable machine capacity and workforce
levels, constant output rate
• Inventory levels fluctuate over time
• Inventories carried over from high to low
demand periods
• Better for worker morale
• Large inventories and backlogs may
accumulate
• Used when inventory holding and backlog
costs are relatively low
8-15Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Aggregate Planning Using
Linear Programming
• Red Tomato Tools
– Highly seasonal demand
– Develop a forecast
Month Demand Forecast
January 1,600
February 3,000
March 3,200
April 3,800
May 2,200
June 2,200
Table 8-2
8-16Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Item Cost
Material cost $10/unit
Inventory holding cost $2/unit/month
Marginal cost of stockout/backlog $5/unit/month
Hiring and training costs $300/worker
Layoff cost $500/worker
Labor hours required 4/unit
Regular time cost $4/hour
Overtime cost $6/hour
Cost of subcontracting $30/unit
Table 8-3
8-17Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Decision Variables
For t = 1, ..., 6
Wt = Workforce size for month t
Ht = Number of employees hired at the beginning of
month t
Lt = Number of employees laid off at the beginning of
month t
Pt = Production in month t
It = Inventory at the end of month t
St = Number of units stocked out at the end of month t
Ct = Number of units subcontracted for month t
Ot = Number of overtime hours worked in month t
8-18Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Objective Function
• Minimize
(Regular-time labor cost + Overtime labor cost + Cost of
hiring and layoffs + Cost of holding inventory + Cost of
stocking out + Cost of subcontracting + Material cost)
Min 640Wt
t=1
6
å + 6Ot
t=1
6
å + 300Ht
t=1
6
å + 500Lt
t=1
6
å
+ 2It
t=1
6
å + 5St
t=1
6
å + 10Pt
t=1
6
å + 30Ct
t=1
6
å
8-19Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Constraints
1. Workforce, hiring, and layoff constraints
All for t = 1,..., 6
Wt
=W t–1
+Ht
– Lt
2. Capacity constraints
Pt
£ 40Wt
+
Ot
4
3. Inventory balance constraints
It–1
+ Pt
+Ct
= Dt
+ St–1
+ It
– St
4. Overtime limit constraints
Ot
£10Wt
8-20Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Average inventory =
(I0
+ IT
) / 2+ Itt=1
T –1
å( )
T
=
(I0
+ IT
) / 2+ Itt=1
T –1
å( )
T
é
ë
ê
ê
ê
ù
û
ú
ú
ú
Dtt=1
T –1
å( )
T
é
ë
ê
ê
ê
ù
û
ú
ú
ú
Average time
in inventory
8-21Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Total cost over planning horizon = $422,275
Revenue over planning horizon = 40 x 16,000 = $640,000
Period,
t
No.
Hired,
Ht
No.
Laid
Off,
Lt
Workforce
Size, Wt
Overtime,
Ot
Inventory,
It
Stockout,
St
Subcontract
, Ct
Total
Production,
Pt
0 0 0 80 0 1,000 0 0
1 0 15 65 0 1,983 0 0 2,583
2 0 0 65 0 1,567 0 0 2,583
3 0 0 65 0 950 0 0 2,583
4 0 0 65 0 0 267 0 2,583
5 0 0 65 0 117 0 0 2,583
6 0 0 65 0 500 0 0 2,583
Table 8-4
8-22Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
=
(I0
+ I6
) / 2+ Itt=1
5
å( )
T
=
5,367
6
= 895
Average
seasonal
inventory
Average flow time =
895
2,667
= 0.34 = 0.34 months
8-23Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
• Higher demand variability
Month Demand Forecast
January 1,000
February 3,000
March 3,800
April 4,800
May 2,000
June 1,400
Table 8-5
=
(I0
+ IT
) / 2+ Itt=1
T –1
å( )
T
=
6,450
6
=1,075
Average
seasonal
inventory
8-24Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Total cost over planning horizon = $432,858
Period,
t
No.
Hired,
Ht
No.
Laid
Off,
Lt
Workforce
Size, Wt
Overtime,
Ot
Inventory,
It
Stockout,
St
Subcontract
, Ct
Total
Production,
Pt
0 0 0 80 0 1,000 0 0
1 0 15 65 0 2,583 0 0 2,583
2 0 0 65 0 2,167 0 0 2,583
3 0 0 65 0 950 0 0 2,583
4 0 0 65 0 0 1,267 0 2,583
5 0 0 65 0 0 683 0 2,583
6 0 0 65 0 500 0 0 2,583
Table 8-6
Average flow time =
1,075
2,667
= 0.40 months
8-25Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
• Lower hiring and layoff costs
=
(I0
+ IT
) / 2+ Itt=1
T –1
å( )
T
=
2,500
6
= 417
Average
seasonal
inventory
Average flow time =
417
2,667
= 0.16 months
Total cost over planning horizon = $412,688
8-26Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Red Tomato Tools
Period,
t
No.
Hired,
Ht
No.
Laid
Off,
Lt
Workforce
Size, Wt
Overtime,
Ot
Inventory,
It
Stockout,
St
Subcontract
, Ct
Total
Production,
Pt
0 0 0 80 0 1,000 0 0
1 0 35 45 0 1,200 0 0 2,267
2 0 0 45 0 0 0 0 2,267
3 42 0 87 0 300 0 0 2,267
4 0 0 87 0 0 1,267 0 2,267
5 0 26 61 0 250 683 0 2,267
6 0 0 61 0 500 0 0 2,267
Table 8-7
8-27Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Forecast Error in Aggregate Plans
• Forecast errors must be considered
• Safety inventory
• Safety capacity
– Use overtime as a form of safety capacity
– Carry extra workforce permanently as a form of
safety capacity
– Use subcontractors as a form of safety capacity
– Build and carry extra inventories as a form of safety
inventory
– Purchase capacity or product from an open or spot
market as a form of safety capacity
8-28Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Aggregate Planning In Excel
For t = 1, ..., 6
Wt = Workforce size for Month t
Ht = Number of employees hired at the beginning
of Month t
Lt = Number of employees laid off at the
beginning of Month t
Pt = Production in Month t
It = Inventory at the end of Month t
St = Number of units stocked out at the end of
Month t
Ct = Number of units subcontracted for Month t
Ot = Number of overtime hours worked in Month t
8-29Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Aggregate Planning In Excel
Figure 8-1
8-30Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Aggregate Planning In Excel
Figure 8-2
8-31Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Aggregate Planning In Excel
Figure 8-3
8-32Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Aggregate Planning In Excel
Figure 8-4
8-33Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Building a Rough Master
Production Schedule
• Disaggregate an aggregate plan
Family
Setup
Time/B
atch
(hour)
Average
Batch
Size
Production
Time/Unit
(hour)
Production
Quantity
Number
of
Setups
Setup
Time
(hours)
Production
Time
(hours)
A 8 50 5.60 258 5 40 1,445
B 6 150 3.00 646 4 24 1,938
C 8 100 3.80 517 5 40 1,965
D 10 50 4.80 258 5 50 1,238
E 6 100 3.60 517 5 30 1,861
F 5 75 4.30 387 5 25 1,664
Table 8-8
8-34Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
The Role of IT in
Aggregate Planning
• The ability to handle large problems
• The ability to handle complex problems
(through either nonlinear optimization or
linear approximations)
• The ability to interact with other core IT
systems such as inventory management
and sourcing
8-35Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Implementing Aggregate Planning
in Practice
1. Think beyond the enterprise to the
entire supply chain
2. Make plans flexible because forecasts
are always inaccurate
3. Rerun the aggregate plan as new data
emerge
4. Use aggregate planning as capacity
utilization increases
8-36Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
Summary of Learning Objectives
1. Identify the decisions that are best solved by
aggregate planning
2. Understand the importance of aggregate
planning as a supply chain activity
3. Describe the information needed to produce
an aggregate plan
4. Explain the basic trade-offs to consider when
creating an aggregate plan
5. Formulate and solve aggregate planning
problems using Microsoft Excel
8-37Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical, photocopying,
recording, or otherwise, without the prior written permission of the publisher.
Printed in the United States of America.

Weitere ähnliche Inhalte

Was ist angesagt?

Supply Chain Management chap 7
Supply Chain Management chap 7Supply Chain Management chap 7
Supply Chain Management chap 7Umair Arain
 
Supply Chain Management chap 17
Supply Chain Management chap 17Supply Chain Management chap 17
Supply Chain Management chap 17Umair Arain
 
Supply Chain Management chap 9
Supply Chain Management chap 9Supply Chain Management chap 9
Supply Chain Management chap 9Umair Arain
 
Supply Chain Management chap 12
Supply Chain Management chap 12Supply Chain Management chap 12
Supply Chain Management chap 12Umair Arain
 
Supply Chain Management chap 2
Supply Chain Management chap 2Supply Chain Management chap 2
Supply Chain Management chap 2Umair Arain
 
Supply Chain Management chap 13
Supply Chain Management chap 13Supply Chain Management chap 13
Supply Chain Management chap 13Umair Arain
 
Supply Chain Management chap 14
Supply Chain Management chap 14Supply Chain Management chap 14
Supply Chain Management chap 14Umair Arain
 
Supply Chain Management chap 10
Supply Chain Management chap 10Supply Chain Management chap 10
Supply Chain Management chap 10Umair Arain
 
Supply Chain Management chap 5
Supply Chain Management chap 5Supply Chain Management chap 5
Supply Chain Management chap 5Umair Arain
 
Supply Chain Management chap 18
Supply Chain Management chap 18Supply Chain Management chap 18
Supply Chain Management chap 18Umair Arain
 
Supply chain management ch03 chopra
Supply chain management ch03 chopraSupply chain management ch03 chopra
Supply chain management ch03 chopraJamil Ahmed AKASH
 

Was ist angesagt? (20)

Supply Chain Management chap 7
Supply Chain Management chap 7Supply Chain Management chap 7
Supply Chain Management chap 7
 
Supply Chain Management chap 17
Supply Chain Management chap 17Supply Chain Management chap 17
Supply Chain Management chap 17
 
Supply Chain Management chap 9
Supply Chain Management chap 9Supply Chain Management chap 9
Supply Chain Management chap 9
 
Supply Chain Management chap 12
Supply Chain Management chap 12Supply Chain Management chap 12
Supply Chain Management chap 12
 
Chopra Meindl Chapter 4
Chopra Meindl Chapter 4Chopra Meindl Chapter 4
Chopra Meindl Chapter 4
 
Supply Chain Management chap 2
Supply Chain Management chap 2Supply Chain Management chap 2
Supply Chain Management chap 2
 
Supply Chain Management chap 13
Supply Chain Management chap 13Supply Chain Management chap 13
Supply Chain Management chap 13
 
Supply Chain Management chap 14
Supply Chain Management chap 14Supply Chain Management chap 14
Supply Chain Management chap 14
 
Supply Chain Management chap 10
Supply Chain Management chap 10Supply Chain Management chap 10
Supply Chain Management chap 10
 
Supply Chain Management chap 5
Supply Chain Management chap 5Supply Chain Management chap 5
Supply Chain Management chap 5
 
Chopra Meindl Chapter 7
Chopra Meindl Chapter 7Chopra Meindl Chapter 7
Chopra Meindl Chapter 7
 
Chopra scm5 ch04_ge
Chopra scm5 ch04_geChopra scm5 ch04_ge
Chopra scm5 ch04_ge
 
Chopra scm5 ch02_ge
Chopra scm5 ch02_geChopra scm5 ch02_ge
Chopra scm5 ch02_ge
 
Chopra Meindl Chapter 5
Chopra Meindl Chapter 5Chopra Meindl Chapter 5
Chopra Meindl Chapter 5
 
Supply Chain Management chap 18
Supply Chain Management chap 18Supply Chain Management chap 18
Supply Chain Management chap 18
 
Supply chain management ch03 chopra
Supply chain management ch03 chopraSupply chain management ch03 chopra
Supply chain management ch03 chopra
 
Chopra Meindl Chapter 9
Chopra Meindl Chapter 9Chopra Meindl Chapter 9
Chopra Meindl Chapter 9
 
Chopra Meindl Chapter 1
Chopra Meindl Chapter 1Chopra Meindl Chapter 1
Chopra Meindl Chapter 1
 
Chopra Meindl Chapter 10
Chopra Meindl Chapter 10Chopra Meindl Chapter 10
Chopra Meindl Chapter 10
 
Chopra scm5 ch03_ge
Chopra scm5 ch03_geChopra scm5 ch03_ge
Chopra scm5 ch03_ge
 

Ähnlich wie Optimize Supply Chain Performance with Aggregate Planning

08.1 Aggregate Planning in SC. and scope pptx
08.1 Aggregate Planning in SC. and scope pptx08.1 Aggregate Planning in SC. and scope pptx
08.1 Aggregate Planning in SC. and scope pptxassadullahdm1
 
Supply Chain Management Strategy, Planning, and OperationSeve
Supply Chain Management Strategy, Planning, and OperationSeveSupply Chain Management Strategy, Planning, and OperationSeve
Supply Chain Management Strategy, Planning, and OperationSeveVannaJoy20
 
mid Chapter 4- capacity planning.ppt
mid Chapter 4- capacity planning.pptmid Chapter 4- capacity planning.ppt
mid Chapter 4- capacity planning.pptAzwadHabib
 
Heizer om10 ch13
Heizer om10 ch13Heizer om10 ch13
Heizer om10 ch13ryaekle
 
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyAggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyIRJET Journal
 
aggregate planning in the supply chain
aggregate planning in the supply chainaggregate planning in the supply chain
aggregate planning in the supply chainManish Kaushik
 
aggregate planning in the supply chain
aggregate planning in the supply chain aggregate planning in the supply chain
aggregate planning in the supply chain Manish Kaushik
 
Chapter 4_Aggregate Planning (2).pptx
Chapter 4_Aggregate Planning (2).pptxChapter 4_Aggregate Planning (2).pptx
Chapter 4_Aggregate Planning (2).pptxhongthao6
 
CLO31(1).pptx
CLO31(1).pptxCLO31(1).pptx
CLO31(1).pptxshaikha65
 
How to Measure Capacity, Three Definitions of Capacity,
How to Measure Capacity, Three Definitions of Capacity,How to Measure Capacity, Three Definitions of Capacity,
How to Measure Capacity, Three Definitions of Capacity,Junaid Amjad
 
Inventory & store management m
Inventory & store management mInventory & store management m
Inventory & store management mMohit Mendiratta
 
Supply Chain Management -- Case Studies
Supply Chain Management -- Case StudiesSupply Chain Management -- Case Studies
Supply Chain Management -- Case StudiesGuennoun Wajih
 
week 1 operation & productivity.ppt
week 1 operation & productivity.pptweek 1 operation & productivity.ppt
week 1 operation & productivity.pptdevina81
 
basic of eco 7
basic of eco 7basic of eco 7
basic of eco 7Doukan10
 
15-sourcing-desisions-in-a-supply-chain.pdf
15-sourcing-desisions-in-a-supply-chain.pdf15-sourcing-desisions-in-a-supply-chain.pdf
15-sourcing-desisions-in-a-supply-chain.pdfBishoyRomani
 

Ähnlich wie Optimize Supply Chain Performance with Aggregate Planning (20)

08.1 Aggregate Planning in SC. and scope pptx
08.1 Aggregate Planning in SC. and scope pptx08.1 Aggregate Planning in SC. and scope pptx
08.1 Aggregate Planning in SC. and scope pptx
 
Supply Chain Management Strategy, Planning, and OperationSeve
Supply Chain Management Strategy, Planning, and OperationSeveSupply Chain Management Strategy, Planning, and OperationSeve
Supply Chain Management Strategy, Planning, and OperationSeve
 
Chopra Meindl Chapter 8
Chopra Meindl Chapter 8Chopra Meindl Chapter 8
Chopra Meindl Chapter 8
 
chapter-8
chapter-8chapter-8
chapter-8
 
mid Chapter 4- capacity planning.ppt
mid Chapter 4- capacity planning.pptmid Chapter 4- capacity planning.ppt
mid Chapter 4- capacity planning.ppt
 
Sales Operations
Sales OperationsSales Operations
Sales Operations
 
Heizer om10 ch13
Heizer om10 ch13Heizer om10 ch13
Heizer om10 ch13
 
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase StrategyAggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
Aggregate Production Planning for a Pump Manufacturing Company: Chase Strategy
 
aggregate planning in the supply chain
aggregate planning in the supply chainaggregate planning in the supply chain
aggregate planning in the supply chain
 
aggregate planning in the supply chain
aggregate planning in the supply chain aggregate planning in the supply chain
aggregate planning in the supply chain
 
Chapter 4_Aggregate Planning (2).pptx
Chapter 4_Aggregate Planning (2).pptxChapter 4_Aggregate Planning (2).pptx
Chapter 4_Aggregate Planning (2).pptx
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
aggregate.ppt
aggregate.pptaggregate.ppt
aggregate.ppt
 
CLO31(1).pptx
CLO31(1).pptxCLO31(1).pptx
CLO31(1).pptx
 
How to Measure Capacity, Three Definitions of Capacity,
How to Measure Capacity, Three Definitions of Capacity,How to Measure Capacity, Three Definitions of Capacity,
How to Measure Capacity, Three Definitions of Capacity,
 
Inventory & store management m
Inventory & store management mInventory & store management m
Inventory & store management m
 
Supply Chain Management -- Case Studies
Supply Chain Management -- Case StudiesSupply Chain Management -- Case Studies
Supply Chain Management -- Case Studies
 
week 1 operation & productivity.ppt
week 1 operation & productivity.pptweek 1 operation & productivity.ppt
week 1 operation & productivity.ppt
 
basic of eco 7
basic of eco 7basic of eco 7
basic of eco 7
 
15-sourcing-desisions-in-a-supply-chain.pdf
15-sourcing-desisions-in-a-supply-chain.pdf15-sourcing-desisions-in-a-supply-chain.pdf
15-sourcing-desisions-in-a-supply-chain.pdf
 

Mehr von Umair Arain

How the gps system works
How the gps system worksHow the gps system works
How the gps system worksUmair Arain
 
Entrepreneurship Chap 14
Entrepreneurship Chap 14Entrepreneurship Chap 14
Entrepreneurship Chap 14Umair Arain
 
Entrepreneurship Chap 15
Entrepreneurship Chap 15Entrepreneurship Chap 15
Entrepreneurship Chap 15Umair Arain
 
Entrepreneurship Chap 13
Entrepreneurship Chap 13Entrepreneurship Chap 13
Entrepreneurship Chap 13Umair Arain
 
Entrepreneurship Chap 12
Entrepreneurship Chap 12Entrepreneurship Chap 12
Entrepreneurship Chap 12Umair Arain
 
Entrepreneurship Chap 11
Entrepreneurship Chap 11Entrepreneurship Chap 11
Entrepreneurship Chap 11Umair Arain
 
Entrepreneurship Chap 10
Entrepreneurship Chap 10Entrepreneurship Chap 10
Entrepreneurship Chap 10Umair Arain
 
Entrepreneurship Chap 9
Entrepreneurship Chap 9Entrepreneurship Chap 9
Entrepreneurship Chap 9Umair Arain
 
Entrepreneurship Chap 8
Entrepreneurship Chap 8Entrepreneurship Chap 8
Entrepreneurship Chap 8Umair Arain
 
Entrepreneurship Chap 7
Entrepreneurship Chap 7Entrepreneurship Chap 7
Entrepreneurship Chap 7Umair Arain
 
Entrepreneurship Chap 6
Entrepreneurship Chap 6Entrepreneurship Chap 6
Entrepreneurship Chap 6Umair Arain
 
Entrepreneurship Chap 5
Entrepreneurship Chap 5Entrepreneurship Chap 5
Entrepreneurship Chap 5Umair Arain
 
Entrepreneurship Chap 4
Entrepreneurship Chap 4Entrepreneurship Chap 4
Entrepreneurship Chap 4Umair Arain
 

Mehr von Umair Arain (13)

How the gps system works
How the gps system worksHow the gps system works
How the gps system works
 
Entrepreneurship Chap 14
Entrepreneurship Chap 14Entrepreneurship Chap 14
Entrepreneurship Chap 14
 
Entrepreneurship Chap 15
Entrepreneurship Chap 15Entrepreneurship Chap 15
Entrepreneurship Chap 15
 
Entrepreneurship Chap 13
Entrepreneurship Chap 13Entrepreneurship Chap 13
Entrepreneurship Chap 13
 
Entrepreneurship Chap 12
Entrepreneurship Chap 12Entrepreneurship Chap 12
Entrepreneurship Chap 12
 
Entrepreneurship Chap 11
Entrepreneurship Chap 11Entrepreneurship Chap 11
Entrepreneurship Chap 11
 
Entrepreneurship Chap 10
Entrepreneurship Chap 10Entrepreneurship Chap 10
Entrepreneurship Chap 10
 
Entrepreneurship Chap 9
Entrepreneurship Chap 9Entrepreneurship Chap 9
Entrepreneurship Chap 9
 
Entrepreneurship Chap 8
Entrepreneurship Chap 8Entrepreneurship Chap 8
Entrepreneurship Chap 8
 
Entrepreneurship Chap 7
Entrepreneurship Chap 7Entrepreneurship Chap 7
Entrepreneurship Chap 7
 
Entrepreneurship Chap 6
Entrepreneurship Chap 6Entrepreneurship Chap 6
Entrepreneurship Chap 6
 
Entrepreneurship Chap 5
Entrepreneurship Chap 5Entrepreneurship Chap 5
Entrepreneurship Chap 5
 
Entrepreneurship Chap 4
Entrepreneurship Chap 4Entrepreneurship Chap 4
Entrepreneurship Chap 4
 

Kürzlich hochgeladen

Sales Pitch Structure Digital Marketing as a Service.pdf
Sales Pitch Structure Digital Marketing as a Service.pdfSales Pitch Structure Digital Marketing as a Service.pdf
Sales Pitch Structure Digital Marketing as a Service.pdfsystreatwork
 
Call girls in Jaipur 9358660226 escort service in Jaipur
Call girls in Jaipur 9358660226 escort service in JaipurCall girls in Jaipur 9358660226 escort service in Jaipur
Call girls in Jaipur 9358660226 escort service in Jaipurrahul222jai
 
Maya❤️Call girls in Mohali ☎️7435815124☎️ Call Girl service in Mohali☎️ Mohal...
Maya❤️Call girls in Mohali ☎️7435815124☎️ Call Girl service in Mohali☎️ Mohal...Maya❤️Call girls in Mohali ☎️7435815124☎️ Call Girl service in Mohali☎️ Mohal...
Maya❤️Call girls in Mohali ☎️7435815124☎️ Call Girl service in Mohali☎️ Mohal...Sheetaleventcompany
 
Best VIP Call Girls Noida Sector 62 Call Me: 8448380779
Best VIP Call Girls Noida Sector 62 Call Me: 8448380779Best VIP Call Girls Noida Sector 62 Call Me: 8448380779
Best VIP Call Girls Noida Sector 62 Call Me: 8448380779Delhi Call girls
 
CALL ON ➥8923113531 🔝Call Girls Kakori Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Kakori Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Kakori Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Kakori Lucknow best sexual serviceanilsa9823
 
BEST ✨Call Girls In Park Plaza Gurugram ✔️9773824855✔️ Escorts Service In Del...
BEST ✨Call Girls In Park Plaza Gurugram ✔️9773824855✔️ Escorts Service In Del...BEST ✨Call Girls In Park Plaza Gurugram ✔️9773824855✔️ Escorts Service In Del...
BEST ✨Call Girls In Park Plaza Gurugram ✔️9773824855✔️ Escorts Service In Del...noida100girls
 
Russian ​❤️ Call Girls In Radisson Blu MBD Hotel, Noida ✔️ 9871031762 ✔️ Esco...
Russian ​❤️ Call Girls In Radisson Blu MBD Hotel, Noida ✔️ 9871031762 ✔️ Esco...Russian ​❤️ Call Girls In Radisson Blu MBD Hotel, Noida ✔️ 9871031762 ✔️ Esco...
Russian ​❤️ Call Girls In Radisson Blu MBD Hotel, Noida ✔️ 9871031762 ✔️ Esco...noida100girls
 
Best VIP Call Girls Noida Sector 49 Call Me: 8448380779
Best VIP Call Girls Noida Sector 49 Call Me: 8448380779Best VIP Call Girls Noida Sector 49 Call Me: 8448380779
Best VIP Call Girls Noida Sector 49 Call Me: 8448380779Delhi Call girls
 
Call Girls In Hauz Khas Delhi 9654467111 Independent Escorts Service
Call Girls In Hauz Khas Delhi 9654467111 Independent Escorts ServiceCall Girls In Hauz Khas Delhi 9654467111 Independent Escorts Service
Call Girls In Hauz Khas Delhi 9654467111 Independent Escorts ServiceSapana Sha
 
BEST ✨ Call Girls In Greater Noida ✔️ 9871031762 ✔️ Escorts Service In Delhi ...
BEST ✨ Call Girls In Greater Noida ✔️ 9871031762 ✔️ Escorts Service In Delhi ...BEST ✨ Call Girls In Greater Noida ✔️ 9871031762 ✔️ Escorts Service In Delhi ...
BEST ✨ Call Girls In Greater Noida ✔️ 9871031762 ✔️ Escorts Service In Delhi ...noida100girls
 
BEST ✨ Call Girls In Noida Electronic City ✔️ 9871031762 ✔️ Escorts Service I...
BEST ✨ Call Girls In Noida Electronic City ✔️ 9871031762 ✔️ Escorts Service I...BEST ✨ Call Girls In Noida Electronic City ✔️ 9871031762 ✔️ Escorts Service I...
BEST ✨ Call Girls In Noida Electronic City ✔️ 9871031762 ✔️ Escorts Service I...noida100girls
 
Best VIP Call Girls Noida Sector 63 Call Me: 8448380779
Best VIP Call Girls Noida Sector 63 Call Me: 8448380779Best VIP Call Girls Noida Sector 63 Call Me: 8448380779
Best VIP Call Girls Noida Sector 63 Call Me: 8448380779Delhi Call girls
 
Russian ​❤️ Call Girls In The Grand New Delhi Near By Vasant Kunj ✔️ 9871031...
Russian ​❤️ Call Girls In The Grand New Delhi Near By Vasant Kunj  ✔️ 9871031...Russian ​❤️ Call Girls In The Grand New Delhi Near By Vasant Kunj  ✔️ 9871031...
Russian ​❤️ Call Girls In The Grand New Delhi Near By Vasant Kunj ✔️ 9871031...noida100girls
 
Call Girls in Calangute Beach 8588052666 Goa Escorts
Call Girls in Calangute Beach 8588052666 Goa EscortsCall Girls in Calangute Beach 8588052666 Goa Escorts
Call Girls in Calangute Beach 8588052666 Goa Escortsnishakur201
 
BEST ✨ Call Girls In Park Plaza Faridabad ✔️ 9871031762 ✔️ Escorts Service In...
BEST ✨ Call Girls In Park Plaza Faridabad ✔️ 9871031762 ✔️ Escorts Service In...BEST ✨ Call Girls In Park Plaza Faridabad ✔️ 9871031762 ✔️ Escorts Service In...
BEST ✨ Call Girls In Park Plaza Faridabad ✔️ 9871031762 ✔️ Escorts Service In...noida100girls
 
CALL ON ➥8923113531 🔝Call Girls Vikas Nagar Lucknow best Female service 🧥
CALL ON ➥8923113531 🔝Call Girls Vikas Nagar Lucknow best Female service  🧥CALL ON ➥8923113531 🔝Call Girls Vikas Nagar Lucknow best Female service  🧥
CALL ON ➥8923113531 🔝Call Girls Vikas Nagar Lucknow best Female service 🧥anilsa9823
 
BEST ✨ Call Girls In Gaur City 2 [ Noida ] ✔️ 9871031762 ✔️ Escorts Service I...
BEST ✨ Call Girls In Gaur City 2 [ Noida ] ✔️ 9871031762 ✔️ Escorts Service I...BEST ✨ Call Girls In Gaur City 2 [ Noida ] ✔️ 9871031762 ✔️ Escorts Service I...
BEST ✨ Call Girls In Gaur City 2 [ Noida ] ✔️ 9871031762 ✔️ Escorts Service I...noida100girls
 
BEST ✨ Call Girls In Shangri-La Eros New Delhi✔️ 9871031762 ✔️ Escorts Servic...
BEST ✨ Call Girls In Shangri-La Eros New Delhi✔️ 9871031762 ✔️ Escorts Servic...BEST ✨ Call Girls In Shangri-La Eros New Delhi✔️ 9871031762 ✔️ Escorts Servic...
BEST ✨ Call Girls In Shangri-La Eros New Delhi✔️ 9871031762 ✔️ Escorts Servic...noida100girls
 
Russian ​❤️ Call Girls In Malviya Nagar ✔️9773824855✔️ Escorts Service In Del...
Russian ​❤️ Call Girls In Malviya Nagar ✔️9773824855✔️ Escorts Service In Del...Russian ​❤️ Call Girls In Malviya Nagar ✔️9773824855✔️ Escorts Service In Del...
Russian ​❤️ Call Girls In Malviya Nagar ✔️9773824855✔️ Escorts Service In Del...noida100girls
 
Cheap Rate ➥8448380779 ▻Call Girls In Sector 57 Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Sector 57 GurgaonCheap Rate ➥8448380779 ▻Call Girls In Sector 57 Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Sector 57 GurgaonDelhi Call girls
 

Kürzlich hochgeladen (20)

Sales Pitch Structure Digital Marketing as a Service.pdf
Sales Pitch Structure Digital Marketing as a Service.pdfSales Pitch Structure Digital Marketing as a Service.pdf
Sales Pitch Structure Digital Marketing as a Service.pdf
 
Call girls in Jaipur 9358660226 escort service in Jaipur
Call girls in Jaipur 9358660226 escort service in JaipurCall girls in Jaipur 9358660226 escort service in Jaipur
Call girls in Jaipur 9358660226 escort service in Jaipur
 
Maya❤️Call girls in Mohali ☎️7435815124☎️ Call Girl service in Mohali☎️ Mohal...
Maya❤️Call girls in Mohali ☎️7435815124☎️ Call Girl service in Mohali☎️ Mohal...Maya❤️Call girls in Mohali ☎️7435815124☎️ Call Girl service in Mohali☎️ Mohal...
Maya❤️Call girls in Mohali ☎️7435815124☎️ Call Girl service in Mohali☎️ Mohal...
 
Best VIP Call Girls Noida Sector 62 Call Me: 8448380779
Best VIP Call Girls Noida Sector 62 Call Me: 8448380779Best VIP Call Girls Noida Sector 62 Call Me: 8448380779
Best VIP Call Girls Noida Sector 62 Call Me: 8448380779
 
CALL ON ➥8923113531 🔝Call Girls Kakori Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Kakori Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Kakori Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Kakori Lucknow best sexual service
 
BEST ✨Call Girls In Park Plaza Gurugram ✔️9773824855✔️ Escorts Service In Del...
BEST ✨Call Girls In Park Plaza Gurugram ✔️9773824855✔️ Escorts Service In Del...BEST ✨Call Girls In Park Plaza Gurugram ✔️9773824855✔️ Escorts Service In Del...
BEST ✨Call Girls In Park Plaza Gurugram ✔️9773824855✔️ Escorts Service In Del...
 
Russian ​❤️ Call Girls In Radisson Blu MBD Hotel, Noida ✔️ 9871031762 ✔️ Esco...
Russian ​❤️ Call Girls In Radisson Blu MBD Hotel, Noida ✔️ 9871031762 ✔️ Esco...Russian ​❤️ Call Girls In Radisson Blu MBD Hotel, Noida ✔️ 9871031762 ✔️ Esco...
Russian ​❤️ Call Girls In Radisson Blu MBD Hotel, Noida ✔️ 9871031762 ✔️ Esco...
 
Best VIP Call Girls Noida Sector 49 Call Me: 8448380779
Best VIP Call Girls Noida Sector 49 Call Me: 8448380779Best VIP Call Girls Noida Sector 49 Call Me: 8448380779
Best VIP Call Girls Noida Sector 49 Call Me: 8448380779
 
Call Girls In Hauz Khas Delhi 9654467111 Independent Escorts Service
Call Girls In Hauz Khas Delhi 9654467111 Independent Escorts ServiceCall Girls In Hauz Khas Delhi 9654467111 Independent Escorts Service
Call Girls In Hauz Khas Delhi 9654467111 Independent Escorts Service
 
BEST ✨ Call Girls In Greater Noida ✔️ 9871031762 ✔️ Escorts Service In Delhi ...
BEST ✨ Call Girls In Greater Noida ✔️ 9871031762 ✔️ Escorts Service In Delhi ...BEST ✨ Call Girls In Greater Noida ✔️ 9871031762 ✔️ Escorts Service In Delhi ...
BEST ✨ Call Girls In Greater Noida ✔️ 9871031762 ✔️ Escorts Service In Delhi ...
 
BEST ✨ Call Girls In Noida Electronic City ✔️ 9871031762 ✔️ Escorts Service I...
BEST ✨ Call Girls In Noida Electronic City ✔️ 9871031762 ✔️ Escorts Service I...BEST ✨ Call Girls In Noida Electronic City ✔️ 9871031762 ✔️ Escorts Service I...
BEST ✨ Call Girls In Noida Electronic City ✔️ 9871031762 ✔️ Escorts Service I...
 
Best VIP Call Girls Noida Sector 63 Call Me: 8448380779
Best VIP Call Girls Noida Sector 63 Call Me: 8448380779Best VIP Call Girls Noida Sector 63 Call Me: 8448380779
Best VIP Call Girls Noida Sector 63 Call Me: 8448380779
 
Russian ​❤️ Call Girls In The Grand New Delhi Near By Vasant Kunj ✔️ 9871031...
Russian ​❤️ Call Girls In The Grand New Delhi Near By Vasant Kunj  ✔️ 9871031...Russian ​❤️ Call Girls In The Grand New Delhi Near By Vasant Kunj  ✔️ 9871031...
Russian ​❤️ Call Girls In The Grand New Delhi Near By Vasant Kunj ✔️ 9871031...
 
Call Girls in Calangute Beach 8588052666 Goa Escorts
Call Girls in Calangute Beach 8588052666 Goa EscortsCall Girls in Calangute Beach 8588052666 Goa Escorts
Call Girls in Calangute Beach 8588052666 Goa Escorts
 
BEST ✨ Call Girls In Park Plaza Faridabad ✔️ 9871031762 ✔️ Escorts Service In...
BEST ✨ Call Girls In Park Plaza Faridabad ✔️ 9871031762 ✔️ Escorts Service In...BEST ✨ Call Girls In Park Plaza Faridabad ✔️ 9871031762 ✔️ Escorts Service In...
BEST ✨ Call Girls In Park Plaza Faridabad ✔️ 9871031762 ✔️ Escorts Service In...
 
CALL ON ➥8923113531 🔝Call Girls Vikas Nagar Lucknow best Female service 🧥
CALL ON ➥8923113531 🔝Call Girls Vikas Nagar Lucknow best Female service  🧥CALL ON ➥8923113531 🔝Call Girls Vikas Nagar Lucknow best Female service  🧥
CALL ON ➥8923113531 🔝Call Girls Vikas Nagar Lucknow best Female service 🧥
 
BEST ✨ Call Girls In Gaur City 2 [ Noida ] ✔️ 9871031762 ✔️ Escorts Service I...
BEST ✨ Call Girls In Gaur City 2 [ Noida ] ✔️ 9871031762 ✔️ Escorts Service I...BEST ✨ Call Girls In Gaur City 2 [ Noida ] ✔️ 9871031762 ✔️ Escorts Service I...
BEST ✨ Call Girls In Gaur City 2 [ Noida ] ✔️ 9871031762 ✔️ Escorts Service I...
 
BEST ✨ Call Girls In Shangri-La Eros New Delhi✔️ 9871031762 ✔️ Escorts Servic...
BEST ✨ Call Girls In Shangri-La Eros New Delhi✔️ 9871031762 ✔️ Escorts Servic...BEST ✨ Call Girls In Shangri-La Eros New Delhi✔️ 9871031762 ✔️ Escorts Servic...
BEST ✨ Call Girls In Shangri-La Eros New Delhi✔️ 9871031762 ✔️ Escorts Servic...
 
Russian ​❤️ Call Girls In Malviya Nagar ✔️9773824855✔️ Escorts Service In Del...
Russian ​❤️ Call Girls In Malviya Nagar ✔️9773824855✔️ Escorts Service In Del...Russian ​❤️ Call Girls In Malviya Nagar ✔️9773824855✔️ Escorts Service In Del...
Russian ​❤️ Call Girls In Malviya Nagar ✔️9773824855✔️ Escorts Service In Del...
 
Cheap Rate ➥8448380779 ▻Call Girls In Sector 57 Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Sector 57 GurgaonCheap Rate ➥8448380779 ▻Call Girls In Sector 57 Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Sector 57 Gurgaon
 

Optimize Supply Chain Performance with Aggregate Planning

  • 1. PowerPoint presentation to accompany Chopra and Meindl Supply Chain Management, 5e 1-1 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall.Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. 1-1 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. 1-1 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. 8-1 Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. 8 Aggregate Planning in a Supply Chain
  • 2. 8-2Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Learning Objectives 1. Identify the decisions that are best solved by aggregate planning. 2. Understand the importance of aggregate planning as a supply chain activity. 3. Describe the information needed to produce an aggregate plan. 4. Explain the basic trade-offs to consider when creating an aggregate plan. 5. Formulate and solve basic aggregate planning problems using Microsoft Excel.
  • 3. 8-3Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Role of Aggregate Planning in a Supply Chain • Capacity has a cost and lead times are often long • Aggregate planning: – process by which a company determines levels of capacity, production, subcontracting, inventory, stockouts, and pricing over a specified time horizon – goal is to maximize profit – decisions made at a product family (not SKU) level – time frame of 3 to 18 months – how can a firm best use the facilities it has?
  • 4. 8-4Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Role of Aggregate Planning in a Supply Chain • Specify operational parameters over the time horizon – Production rate – Subcontracting – Workforce – Backlog – Overtime – Inventory on hand – Machine capacity level • All supply chain stages should work together on an aggregate plan that will optimize supply chain performance
  • 5. 8-5Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. The Aggregate Planning Problem • Given the demand forecast for each period in the planning horizon, determine the production level, inventory level, and the capacity level for each period that maximizes the firm’s (supply chain’s) profit over the planning horizon • Specify the planning horizon (typically 3-18 months) • Specify the duration of each period • Specify key information required to develop an aggregate plan
  • 6. 8-6Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Information Needed for an Aggregate Plan • Aggregate demand forecast Ft for each Period t over T periods • Production costs – Labor costs, regular time ($/hr) and overtime ($/hr) – Subcontracting costs ($/hr or $/unit) – Cost of changing capacity – hiring or layoff ($/worker), adding or reducing machine capacity ($/machine) • Labor/machine hours required per unit • Inventory holding cost ($/unit/period) • Stockout or backlog cost ($/unit/period) • Constraints – overtime, layoffs, capital available, stockouts, backlogs, from suppliers
  • 7. 8-7Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Outputs of Aggregate Plan • Production quantity from regular time, overtime, and subcontracted time • Inventory held • Backlog/stockout quantity • Machine capacity increase/decrease • A poor aggregate plan can result in lost sales, lost profits, excess inventory, or excess capacity
  • 8. 8-8Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Identifying Aggregate Units of Production • Aggregate unit should be identified in a way that the resulting production schedule can be accomplished in practice • Focus on the bottlenecks when selecting the aggregate unit and identifying capacity and production times • Account for activities such as setups and maintenance
  • 9. 8-9Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Family Material Cost/ Unit ($) Revenue/ Unit ($) Setup Time/B atch (hour) Average Batch Size Production Time/ Unit (hour) Net Production Time/Unit (hour) Percentage Share of Units Sold A 15 54 8 50 5.60 5.76 10 B 7 30 6 150 3.00 3.04 25 C 9 39 8 100 3.80 3.88 20 D 12 49 10 50 4.80 5.00 10 E 9 36 6 100 3.60 3.66 20 F 13 48 5 75 4.30 4.37 15 Table 8-1
  • 10. 8-10Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools • Weighted average approach Material cost per aggregate unit = 15 x 0.10 + 7 x 0.25 + 9 x 0.20 + 12 x 0.10 + 9 x 0.20 + 13 x 0.15 = $10 • Similarly Revenue per aggregate unit = $40 Net production time per aggregate unit = 4.00 hours
  • 11. 8-11Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Aggregate Planning Strategies • Trade-off between capacity, inventory, backlog/lost sales • Chase strategy – using capacity as the lever • Time flexibility from workforce or capacity strategy – using utilization as the lever • Level strategy – using inventory as the lever • Tailored or hybrid strategy – a combination of strategies
  • 12. 8-12Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Chase Strategy • Vary machine capacity or hire and lay off workers as demand varies • Often difficult to vary capacity and workforce on short notice • Expensive if cost of varying capacity is high • Negative effect on workforce morale • Results in low levels of inventory • Used when inventory holding costs are high and costs of changing capacity are low
  • 13. 8-13Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Time Flexibility Strategy • Use excess machine capacity • Workforce stable, number of hours worked varies • Use overtime or a flexible work schedule • Flexible workforce, avoids morale problems • Low levels of inventory, lower utilization • Used when inventory holding costs are high and capacity is relatively inexpensive
  • 14. 8-14Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Level Strategy • Stable machine capacity and workforce levels, constant output rate • Inventory levels fluctuate over time • Inventories carried over from high to low demand periods • Better for worker morale • Large inventories and backlogs may accumulate • Used when inventory holding and backlog costs are relatively low
  • 15. 8-15Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Aggregate Planning Using Linear Programming • Red Tomato Tools – Highly seasonal demand – Develop a forecast Month Demand Forecast January 1,600 February 3,000 March 3,200 April 3,800 May 2,200 June 2,200 Table 8-2
  • 16. 8-16Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Item Cost Material cost $10/unit Inventory holding cost $2/unit/month Marginal cost of stockout/backlog $5/unit/month Hiring and training costs $300/worker Layoff cost $500/worker Labor hours required 4/unit Regular time cost $4/hour Overtime cost $6/hour Cost of subcontracting $30/unit Table 8-3
  • 17. 8-17Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Decision Variables For t = 1, ..., 6 Wt = Workforce size for month t Ht = Number of employees hired at the beginning of month t Lt = Number of employees laid off at the beginning of month t Pt = Production in month t It = Inventory at the end of month t St = Number of units stocked out at the end of month t Ct = Number of units subcontracted for month t Ot = Number of overtime hours worked in month t
  • 18. 8-18Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Objective Function • Minimize (Regular-time labor cost + Overtime labor cost + Cost of hiring and layoffs + Cost of holding inventory + Cost of stocking out + Cost of subcontracting + Material cost) Min 640Wt t=1 6 å + 6Ot t=1 6 å + 300Ht t=1 6 å + 500Lt t=1 6 å + 2It t=1 6 å + 5St t=1 6 å + 10Pt t=1 6 å + 30Ct t=1 6 å
  • 19. 8-19Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Constraints 1. Workforce, hiring, and layoff constraints All for t = 1,..., 6 Wt =W t–1 +Ht – Lt 2. Capacity constraints Pt £ 40Wt + Ot 4 3. Inventory balance constraints It–1 + Pt +Ct = Dt + St–1 + It – St 4. Overtime limit constraints Ot £10Wt
  • 20. 8-20Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Average inventory = (I0 + IT ) / 2+ Itt=1 T –1 å( ) T = (I0 + IT ) / 2+ Itt=1 T –1 å( ) T é ë ê ê ê ù û ú ú ú Dtt=1 T –1 å( ) T é ë ê ê ê ù û ú ú ú Average time in inventory
  • 21. 8-21Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Total cost over planning horizon = $422,275 Revenue over planning horizon = 40 x 16,000 = $640,000 Period, t No. Hired, Ht No. Laid Off, Lt Workforce Size, Wt Overtime, Ot Inventory, It Stockout, St Subcontract , Ct Total Production, Pt 0 0 0 80 0 1,000 0 0 1 0 15 65 0 1,983 0 0 2,583 2 0 0 65 0 1,567 0 0 2,583 3 0 0 65 0 950 0 0 2,583 4 0 0 65 0 0 267 0 2,583 5 0 0 65 0 117 0 0 2,583 6 0 0 65 0 500 0 0 2,583 Table 8-4
  • 22. 8-22Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools = (I0 + I6 ) / 2+ Itt=1 5 å( ) T = 5,367 6 = 895 Average seasonal inventory Average flow time = 895 2,667 = 0.34 = 0.34 months
  • 23. 8-23Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools • Higher demand variability Month Demand Forecast January 1,000 February 3,000 March 3,800 April 4,800 May 2,000 June 1,400 Table 8-5 = (I0 + IT ) / 2+ Itt=1 T –1 å( ) T = 6,450 6 =1,075 Average seasonal inventory
  • 24. 8-24Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Total cost over planning horizon = $432,858 Period, t No. Hired, Ht No. Laid Off, Lt Workforce Size, Wt Overtime, Ot Inventory, It Stockout, St Subcontract , Ct Total Production, Pt 0 0 0 80 0 1,000 0 0 1 0 15 65 0 2,583 0 0 2,583 2 0 0 65 0 2,167 0 0 2,583 3 0 0 65 0 950 0 0 2,583 4 0 0 65 0 0 1,267 0 2,583 5 0 0 65 0 0 683 0 2,583 6 0 0 65 0 500 0 0 2,583 Table 8-6 Average flow time = 1,075 2,667 = 0.40 months
  • 25. 8-25Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools • Lower hiring and layoff costs = (I0 + IT ) / 2+ Itt=1 T –1 å( ) T = 2,500 6 = 417 Average seasonal inventory Average flow time = 417 2,667 = 0.16 months Total cost over planning horizon = $412,688
  • 26. 8-26Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Red Tomato Tools Period, t No. Hired, Ht No. Laid Off, Lt Workforce Size, Wt Overtime, Ot Inventory, It Stockout, St Subcontract , Ct Total Production, Pt 0 0 0 80 0 1,000 0 0 1 0 35 45 0 1,200 0 0 2,267 2 0 0 45 0 0 0 0 2,267 3 42 0 87 0 300 0 0 2,267 4 0 0 87 0 0 1,267 0 2,267 5 0 26 61 0 250 683 0 2,267 6 0 0 61 0 500 0 0 2,267 Table 8-7
  • 27. 8-27Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Forecast Error in Aggregate Plans • Forecast errors must be considered • Safety inventory • Safety capacity – Use overtime as a form of safety capacity – Carry extra workforce permanently as a form of safety capacity – Use subcontractors as a form of safety capacity – Build and carry extra inventories as a form of safety inventory – Purchase capacity or product from an open or spot market as a form of safety capacity
  • 28. 8-28Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Aggregate Planning In Excel For t = 1, ..., 6 Wt = Workforce size for Month t Ht = Number of employees hired at the beginning of Month t Lt = Number of employees laid off at the beginning of Month t Pt = Production in Month t It = Inventory at the end of Month t St = Number of units stocked out at the end of Month t Ct = Number of units subcontracted for Month t Ot = Number of overtime hours worked in Month t
  • 29. 8-29Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Aggregate Planning In Excel Figure 8-1
  • 30. 8-30Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Aggregate Planning In Excel Figure 8-2
  • 31. 8-31Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Aggregate Planning In Excel Figure 8-3
  • 32. 8-32Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Aggregate Planning In Excel Figure 8-4
  • 33. 8-33Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Building a Rough Master Production Schedule • Disaggregate an aggregate plan Family Setup Time/B atch (hour) Average Batch Size Production Time/Unit (hour) Production Quantity Number of Setups Setup Time (hours) Production Time (hours) A 8 50 5.60 258 5 40 1,445 B 6 150 3.00 646 4 24 1,938 C 8 100 3.80 517 5 40 1,965 D 10 50 4.80 258 5 50 1,238 E 6 100 3.60 517 5 30 1,861 F 5 75 4.30 387 5 25 1,664 Table 8-8
  • 34. 8-34Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. The Role of IT in Aggregate Planning • The ability to handle large problems • The ability to handle complex problems (through either nonlinear optimization or linear approximations) • The ability to interact with other core IT systems such as inventory management and sourcing
  • 35. 8-35Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Implementing Aggregate Planning in Practice 1. Think beyond the enterprise to the entire supply chain 2. Make plans flexible because forecasts are always inaccurate 3. Rerun the aggregate plan as new data emerge 4. Use aggregate planning as capacity utilization increases
  • 36. 8-36Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. Summary of Learning Objectives 1. Identify the decisions that are best solved by aggregate planning 2. Understand the importance of aggregate planning as a supply chain activity 3. Describe the information needed to produce an aggregate plan 4. Explain the basic trade-offs to consider when creating an aggregate plan 5. Formulate and solve aggregate planning problems using Microsoft Excel
  • 37. 8-37Copyright ©2013 Pearson Education, Inc. publishing as Prentice Hall. All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without the prior written permission of the publisher. Printed in the United States of America.