SlideShare ist ein Scribd-Unternehmen logo
1 von 2
Downloaden Sie, um offline zu lesen
 E‐mail address (W): Tom.Edwards@ekpc.coop         3660 Gladman Way                             
 Home Phone: (859) 224‐8555     Lexington, KY  40503                  
 Mobile Phone (859) 595‐4618    
Thomas Andrew Edwards, PE 
 
Objective:    
Employment: 
 
May, 2000 – Present    East Kentucky Power Cooperative   Winchester, KY 
July 2011 – 
present 
Moved to the System Protection Group of EKPC.  Duties included the setting and installation 
of Generation Protection Relays, Transmission Line Protection Relays, and Distribution 
Protection Relays.    Major responsibilities: generation protection settings and generation 
relay upgrades, transmission settings, and distribution coordination. 
June, 2007 – 
July 2011 
Due to re‐organization at EKPC moved to the Construction Department.   Protect Manager of 
JK Smith CT Units 9 and 10. 
May, 2000 –  
June, 2007 
The electrical engineer for the Production Department at EKPC.  Duties included resolving 
normal day to day electrical issues inside the power plants, upgrading generation protection, 
and project management for large projects.  The typical role for the project manager at EKPC 
is to assist in the development of all specification for bid documents and for major BOP 
equipment associated with the project.  Plus, the project manager is responsible for managing 
and reporting the budget for the project, performing daily and weekly safety audits; and 
supervising day to day task of contract inspectors, manufacture technical advisories, plant 
personnel and administrative assistants/accountants while construction and commissioning is 
going on.   
Major work completed while at EKPC 
 Produced EKPC’s first Generation Protective Relay Setting Criteria 
 Extensively modified EKPC’s Transmission Line Protective Relay Setting Criteria 
 Initiated the utilization S&C cooling curve method and modified EKPC’s distribution transformer 
protection to improve EKPC’s coordination between EKPC’s highside distribution transformer 
protection and the local coop distribution reclosers. 
 Project Manager for the installation of Units 9 and 10 at JK Smith Power Plant.  This project consisted 
in the installation of two GE LMS100 gas turbines.  Developed the specification and purchased a three 
winding GSU transformer for this project.   The approximate cost for this project was $154 million. 
 Project Manager for the installation of the building over Units 4 and 5 at JK Smith.  The approximate 
cost for this project was $2.5 million. 
  Project Manager for the installation of a 20 inch, high‐pressure natural gas transmission system 
between JK Smith and Texas Eastern (Duke Energy).  This natural gas system included the installation 
of 6.3 miles of gas pipeline, a meter yard, and a regulation yard and resolving outstanding land 
acquisition for the project.  The approximate cost for this project was $8 million. 
 Project Manager for the installation of Units 6 and 7 at JK Smith.  This project entailed the installation 
of two GE 7EA Frame CTGs.  Purchased the two needed GSU transformers for this project.  The 
approximate cost for this project was $52.5 million. 
 Electrical Project Manager for Units 4 & 5 at JK Smith.  This project entailed the installation of two GE 
7EA Frame CTGs.  Purchased the two needed GSU transformers for this project.  The approximate 
budget for this project was $48 million. 
 Electrical Project Manager for a Demin (NOX) water system and the building over this Demin water 
system at JK Smith.  The approximate cost for this project was $5 million. 
 Designed and purchased all components needed for controlling, protecting and housing two CAT 3516 
Diesel generator units; including the foundation for these units.  Supervised the   installation of these 
components, and performed final field inspection on the Two BlackStart Diesel Units and their 
associated equipment at JK Smith.  The approximate budget for this project was $745,000. 
 E‐mail address (W): Tom.Edwards@ekpc.coop         3660 Gladman Way                             
 Home Phone: (859) 224‐8555     Lexington, KY  40503                  
 Mobile Phone (859) 595‐4618    
Thomas Andrew Edwards, PE 
 
Major work completed while at EKPC (cont.) 
 Purchased, supervised the installation, and commissioned several line‐ups of switchgear and 
their associated non‐segregated bus duct. 
 Designed, calculated the settings and supervised the installation of several different 
generator protection relays on several of EKPC’s existing generators.    
 Developed initial standards for SERC/NERC compliance documents for the power plants. 
 Miscellaneous duties inside in the power plants – installation of new relays, calculation of 
settings for relays, consultant with power plant personnel on electrical problems they 
encounter on a day to day basis and developed resolutions to issues that the would improve 
or enhance the power plants operations or performance.  
 
Previous 
Employment: 
Kentucky Utilities,  Lexington, KY 
 
Jan 1986 –  
May, 2000         
Electrical Engineer in the Transmission Substation Department 
Major work completed while at KU 
 Supervised the installation, and performed final field checks on numerous pieces of transmission 
substation equipment to entire substations: relay panels, breakers, transformers, PTs, RTUs, etc. 
 Performed all transmission and generation relay calculations for KU 
 Maintained the fault study for KU 
 Maintained the ECAR fault models for KU and EKPC combined 
 Developed KU’s EKPC's System Protection philosophy from the guidelines of the ECAR relaying 
philosophy 
 1991 to 2000 wrote a report for every transmission failure or undesirable breaker operation on KU’s 
transmission system 
 Commissioned the relaying on the first four gas turbine generators at Brown CT 
 Commissioned the 5kV switchgear and other electrical equipment associated with installation of 
scrubber on Ghent Unit 2. 
 Developed a maintenance procedure for the inspection of transformer temperature gauges.  
 Created a combined KU, EKPC, and LGE fault utilizing GE’s PSLF software.  GE’s PSLF software is a PC 
based load flow package, which at that time could not accurately by itself calculate currents without 
some major finagling by utilizing sub routines. 
Programs
Proficient with
ASPEN Oneliner, AutoCad, Microstation, and most Microsoft Office programs
Education 1980 – 1985 University of Kentucky Lexington, KY
Receiving a BSEE in Dec of 1985
 A member of Eta Kappa Nau
Professional
memberships
 A registered Professional Engineer in the Commonwealth of Kentucky
 National Society of Professional Engineer
References:  Upon Request 
 

Weitere ähnliche Inhalte

Ähnlich wie Resume of Tom Edwards PE

Ähnlich wie Resume of Tom Edwards PE (20)

Neil Todd CV
Neil Todd CVNeil Todd CV
Neil Todd CV
 
Resume 02 13 11 2pg
Resume 02 13 11 2pgResume 02 13 11 2pg
Resume 02 13 11 2pg
 
November Cv
November CvNovember Cv
November Cv
 
Tom's Resume 9-1-16
Tom's Resume 9-1-16Tom's Resume 9-1-16
Tom's Resume 9-1-16
 
Devin Howell's Resume December 1, 2015
Devin Howell's Resume December 1, 2015Devin Howell's Resume December 1, 2015
Devin Howell's Resume December 1, 2015
 
Dane A. Scott Resume(1)
Dane A. Scott Resume(1)Dane A. Scott Resume(1)
Dane A. Scott Resume(1)
 
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - ManagerCraig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
 
Most current resume
Most current resumeMost current resume
Most current resume
 
Electrical17OCT
Electrical17OCTElectrical17OCT
Electrical17OCT
 
John Hopwood Resume
John Hopwood ResumeJohn Hopwood Resume
John Hopwood Resume
 
Dans Resume_2015
Dans  Resume_2015Dans  Resume_2015
Dans Resume_2015
 
Josh Resume 11_18_2016
Josh Resume 11_18_2016Josh Resume 11_18_2016
Josh Resume 11_18_2016
 
C Ebeling Resume.pdf
C Ebeling Resume.pdfC Ebeling Resume.pdf
C Ebeling Resume.pdf
 
EJP CV_January2016
EJP CV_January2016EJP CV_January2016
EJP CV_January2016
 
Rita Thakur Resume
Rita Thakur ResumeRita Thakur Resume
Rita Thakur Resume
 
Mark Wendt Resume 2015
Mark Wendt Resume 2015Mark Wendt Resume 2015
Mark Wendt Resume 2015
 
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - ManagerCraig Sparks. Resume April 2016 Electrician - Supervisor - Manager
Craig Sparks. Resume April 2016 Electrician - Supervisor - Manager
 
GARRY RESUME Red Seal industrial Electrician.
GARRY RESUME Red Seal industrial Electrician.GARRY RESUME Red Seal industrial Electrician.
GARRY RESUME Red Seal industrial Electrician.
 
Resume_for_Kendall_Holland1
Resume_for_Kendall_Holland1Resume_for_Kendall_Holland1
Resume_for_Kendall_Holland1
 
Cameron dipple resume
Cameron dipple resumeCameron dipple resume
Cameron dipple resume
 

Resume of Tom Edwards PE

  • 1.  E‐mail address (W): Tom.Edwards@ekpc.coop         3660 Gladman Way                               Home Phone: (859) 224‐8555     Lexington, KY  40503                    Mobile Phone (859) 595‐4618     Thomas Andrew Edwards, PE    Objective:     Employment:    May, 2000 – Present    East Kentucky Power Cooperative   Winchester, KY  July 2011 –  present  Moved to the System Protection Group of EKPC.  Duties included the setting and installation  of Generation Protection Relays, Transmission Line Protection Relays, and Distribution  Protection Relays.    Major responsibilities: generation protection settings and generation  relay upgrades, transmission settings, and distribution coordination.  June, 2007 –  July 2011  Due to re‐organization at EKPC moved to the Construction Department.   Protect Manager of  JK Smith CT Units 9 and 10.  May, 2000 –   June, 2007  The electrical engineer for the Production Department at EKPC.  Duties included resolving  normal day to day electrical issues inside the power plants, upgrading generation protection,  and project management for large projects.  The typical role for the project manager at EKPC  is to assist in the development of all specification for bid documents and for major BOP  equipment associated with the project.  Plus, the project manager is responsible for managing  and reporting the budget for the project, performing daily and weekly safety audits; and  supervising day to day task of contract inspectors, manufacture technical advisories, plant  personnel and administrative assistants/accountants while construction and commissioning is  going on.    Major work completed while at EKPC   Produced EKPC’s first Generation Protective Relay Setting Criteria   Extensively modified EKPC’s Transmission Line Protective Relay Setting Criteria   Initiated the utilization S&C cooling curve method and modified EKPC’s distribution transformer  protection to improve EKPC’s coordination between EKPC’s highside distribution transformer  protection and the local coop distribution reclosers.   Project Manager for the installation of Units 9 and 10 at JK Smith Power Plant.  This project consisted  in the installation of two GE LMS100 gas turbines.  Developed the specification and purchased a three  winding GSU transformer for this project.   The approximate cost for this project was $154 million.   Project Manager for the installation of the building over Units 4 and 5 at JK Smith.  The approximate  cost for this project was $2.5 million.    Project Manager for the installation of a 20 inch, high‐pressure natural gas transmission system  between JK Smith and Texas Eastern (Duke Energy).  This natural gas system included the installation  of 6.3 miles of gas pipeline, a meter yard, and a regulation yard and resolving outstanding land  acquisition for the project.  The approximate cost for this project was $8 million.   Project Manager for the installation of Units 6 and 7 at JK Smith.  This project entailed the installation  of two GE 7EA Frame CTGs.  Purchased the two needed GSU transformers for this project.  The  approximate cost for this project was $52.5 million.   Electrical Project Manager for Units 4 & 5 at JK Smith.  This project entailed the installation of two GE  7EA Frame CTGs.  Purchased the two needed GSU transformers for this project.  The approximate  budget for this project was $48 million.   Electrical Project Manager for a Demin (NOX) water system and the building over this Demin water  system at JK Smith.  The approximate cost for this project was $5 million.   Designed and purchased all components needed for controlling, protecting and housing two CAT 3516  Diesel generator units; including the foundation for these units.  Supervised the   installation of these  components, and performed final field inspection on the Two BlackStart Diesel Units and their  associated equipment at JK Smith.  The approximate budget for this project was $745,000. 
  • 2.  E‐mail address (W): Tom.Edwards@ekpc.coop         3660 Gladman Way                               Home Phone: (859) 224‐8555     Lexington, KY  40503                    Mobile Phone (859) 595‐4618     Thomas Andrew Edwards, PE    Major work completed while at EKPC (cont.)   Purchased, supervised the installation, and commissioned several line‐ups of switchgear and  their associated non‐segregated bus duct.   Designed, calculated the settings and supervised the installation of several different  generator protection relays on several of EKPC’s existing generators.      Developed initial standards for SERC/NERC compliance documents for the power plants.   Miscellaneous duties inside in the power plants – installation of new relays, calculation of  settings for relays, consultant with power plant personnel on electrical problems they  encounter on a day to day basis and developed resolutions to issues that the would improve  or enhance the power plants operations or performance.     Previous  Employment:  Kentucky Utilities,  Lexington, KY    Jan 1986 –   May, 2000          Electrical Engineer in the Transmission Substation Department  Major work completed while at KU   Supervised the installation, and performed final field checks on numerous pieces of transmission  substation equipment to entire substations: relay panels, breakers, transformers, PTs, RTUs, etc.   Performed all transmission and generation relay calculations for KU   Maintained the fault study for KU   Maintained the ECAR fault models for KU and EKPC combined   Developed KU’s EKPC's System Protection philosophy from the guidelines of the ECAR relaying  philosophy   1991 to 2000 wrote a report for every transmission failure or undesirable breaker operation on KU’s  transmission system   Commissioned the relaying on the first four gas turbine generators at Brown CT   Commissioned the 5kV switchgear and other electrical equipment associated with installation of  scrubber on Ghent Unit 2.   Developed a maintenance procedure for the inspection of transformer temperature gauges.    Created a combined KU, EKPC, and LGE fault utilizing GE’s PSLF software.  GE’s PSLF software is a PC  based load flow package, which at that time could not accurately by itself calculate currents without  some major finagling by utilizing sub routines.  Programs Proficient with ASPEN Oneliner, AutoCad, Microstation, and most Microsoft Office programs Education 1980 – 1985 University of Kentucky Lexington, KY Receiving a BSEE in Dec of 1985  A member of Eta Kappa Nau Professional memberships  A registered Professional Engineer in the Commonwealth of Kentucky  National Society of Professional Engineer References:  Upon Request