1
Software Project
Management
4th Edition
Step Wise: An
approach to
planning software
projects
Chapter 2
©The McGraw-Hill Companies, 2005
2
‘Step Wise’ - aspirations
• Practicality
– tries to answer the question ‘what do I do
now?’
• Scalability
– useful for small project as well as large
• Range of application
• Accepted techniques
– e.g. borrowed from PRINCE etc
©The McGraw-Hill Companies, 2005
3
‘Step Wise’ - an overview
0.Select
project1. Identify
project objectives
2. Identify project
infrastructure
3. Analyse
project
characteristics
4. Identify products
and activities
5. Estimate effort
for activity
8. Review/ publicize
plan
6. Identify activity
risks
7. Allocate
resources
9. Execute plan
10. Lower level
planning
Review
Lower
level
detail
For each
activity
©The McGraw-Hill Companies, 2005
4
A project scenario
• Hardware/software engineering
company (C++ language of choice)
• teams are selected for individual
projects - some friction has been found
between team members
• HR manager suggests psychometric
testing to select team
©The McGraw-Hill Companies, 2005
5
Project scenario - continued
• Software package to be used to test
staff
• Visual basic suggested as a vehicle for
implementation
• usability is important - decision to carry
out usability tests
©The McGraw-Hill Companies, 2005
6
Step 1 establish project
scope and objectives
• 1.1 Identify objectives and measures of
effectiveness
– ‘how do we know if we have succeeded?’
• 1.2 Establish a project authority
– ‘who is the boss?’
• 1.3 Identify all stakeholders in the project and
their interests
– ‘who will be affected/involved in the project?’
©The McGraw-Hill Companies, 2005
7
Step 1 continued
• 1.4 Modify objectives in the light of
stakeholder analysis
– ‘do we need to do things to win over
stakeholders?’
• 1.5 Establish methods of
communication with all parties
– ‘how do we keep in contact?’
©The McGraw-Hill Companies, 2005
8
Back to the scenario
• Project authority
– should be a project manager rather than
HR manager?
• Stakeholders
– project team members to complete on-
line questionnaires: concern about
results?
• Revision to objectives
– provide feedback to team members on
results
©The McGraw-Hill Companies, 2005
9
Step 2 Establish project
infrastructure
• 2.1 Establish link between project and
any strategic plan
– ‘why did they want the project?’
• 2.2 Identify installation standards and
procedures
– ‘what standards do we have to follow?’
• 2.3. Identify project team organization
– ‘where do I fit in?’
©The McGraw-Hill Companies, 2005
10
Step 3 Analysis of project
characteristics
• 3.1 Distinguish the project as either
objective or product-based.
• 3.2 Analyse other project characteristics
(including quality based ones)
– what is different about this project?
©The McGraw-Hill Companies, 2005
11
Step 3 continued
• Identify high level project risks
– ‘what could go wrong?’
– ‘what can we do to stop it?’
• Take into account user requirements
concerning implementation
• Select general life cycle approach
– waterfall? Increments? Prototypes?
• Review overall resource estimates
– ‘does all this increase the cost?’
©The McGraw-Hill Companies, 2005
12
Back to the scenario
• Objectives vs. products
• Some risks
– team members worried about implications
and do no co-operate
– project managers unwilling to try out
application
– Developer not familiar with features of VB
• Answer? - evolutionary prototype?
©The McGraw-Hill Companies, 2005
13
Step 4 Identify project
products and activities
4.1 Identify and describe project
products - ‘what do we have to
produce?’
Usability
testing
Change
requests
Test results
Testing
arrangements
Selected
subjects
Completed
questionnaire
Questionnaire
design
Booked
PC
Analysis
report
A product breakdown structure
(PBS)
©The McGraw-Hill Companies, 2005
14
Products
• The result of an activity
• Could be (among other things)
– physical thing (‘installed pc’),
– a document (‘logical data structure’)
– a person (‘trained user’)
– a new version of an old product (‘updated
software’)
©The McGraw-Hill Companies, 2005
15
Products
• The following are NOT normally
products:
– activities (e.g. ‘training’)
– events (e.g. ‘interviews completed’)
– resources and actors (e.g. ‘software
developer’) - may be exceptions to this
• Products CAN BE deliverable or
intermediate
©The McGraw-Hill Companies, 2005
16
Product description (PD)
• Product identity
• Description - what
is it?
• Derivation - what is
it based on?
• Composition - what
does it contain?
• Format
• Relevant standards
• Quality criteria
Create a PD for ‘test
data’
©The McGraw-Hill Companies, 2005
17
Step 4 continued
4.2 document
Generic
product
flows
Testing plan
Selected
subjects
Questionnaire
design
Booked
machine
Completed
questionnaire
Analysis report
Test results
Change
requests
©The McGraw-Hill Companies, 2005
18
Step 4.3 Recognize product
instances
• The PBS and PFD will probably have
identified generic products e.g.
‘software modules’
• It might be possible to identify specific
instances e.g. ‘module A’, ‘module B’ …
• But in many cases this will have to be
left to later, more detailed, planning
©The McGraw-Hill Companies, 2005
19
4.4. Produce ideal activity
network
• Identify the activities needed to create
each product in the PFD
• More than one activity might be needed
to create a single product
• Hint: Identify activities by verb + noun
but avoid ‘produce…’ (too vague)
• Draw up activity network
©The McGraw-Hill Companies, 2005
20
An ‘ideal’ activity
Plan
testing
Design
questionnaire
Select
subjects
Book
machine
Conduct
tests
Analyse
results
Draft change
requests
©The McGraw-Hill Companies, 2005
21
Step 4.5 Add check-points if needed
Design
module A
Design
module B
Design
system
Design
module C
Code
module A
Code
module B
Code
module C
Test
system
Design
module A
Design
module B
Design
system
Design
module C
Code
module A
Code
module B
Code
module C
Test
system
Check-point
put in a
check point
©The McGraw-Hill Companies, 2005
22
Step 5:Estimate effort for
each activity
• 5.1 Carry out bottom-up estimates
– distinguish carefully between effort and
elapsed time
• 5.2. Revise plan to create controllable
activities
– break up very long activities into a series
of smaller ones
– bundle up very short activities (create
check lists?)
©The McGraw-Hill Companies, 2005
23
Step 6: Identify activity risks
• 6.1.Identify and quantify risks for
activities
– damage if risk occurs (measure in time lost
or money)
– likelihood if risk occurring
• 6.2. Plan risk reduction and contingency
measures
– risk reduction: activity to stop risk
occurring
– contingency: action if risk does occur
©The McGraw-Hill Companies, 2005
24
• 6.3 Adjust overall plans and estimates
to take account of risks
– e.g. add new activities which reduce risks
associated with other activities e.g.
training, pilot trials, information gathering
©The McGraw-Hill Companies, 2005
25
Step 7: Allocate resources
• 7.1 Identify and allocate resources to
activities
• 7.2 Revise plans and estimates to take
into account resource constraints
– e.g. staff not being available until a later
date
– non-project activities
©The McGraw-Hill Companies, 2005
26
Gantt charts
Select subjects
Design
questionnaire
Book machine
Conduct tests
Analyse results
Week
commencing
5 12 19 26
MARCH
APRIL
9 16
Plan testing
2
Draft changes
LT
TA
LT
TA
LT
LT
TA
LT = lead tester
TA = testing assistant
©The McGraw-Hill Companies, 2005
27
Step 8: Review/publicise
plan
• 8.1 Review quality aspects of project
plan
• 8.2 Document plan and obtain
agreement
Step 9 and 10: Execute plan
and create lower level plans

Weitere ähnliche Inhalte

Was ist angesagt?

Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project ManagementSaadi Jadoon
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTKathirvel Ayyaswamy
 
Lect4 software economics
Lect4 software economicsLect4 software economics
Lect4 software economicsmeena466141
 
History of software engineering
History of software engineeringHistory of software engineering
History of software engineeringFarazChohan2
 
Spm project planning
Spm project planning Spm project planning
Spm project planning Kanchana Devi
 
Software estimation
Software estimationSoftware estimation
Software estimationMd Shakir
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software EngineeringFáber D. Giraldo
 
Fundamentals of software development
Fundamentals of software developmentFundamentals of software development
Fundamentals of software developmentPratik Devmurari
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project ManagementReetesh Gupta
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project ManagementDeepak Kumar
 
Software Project Management (SPM)
Software Project Management (SPM)Software Project Management (SPM)
Software Project Management (SPM)Shahid Riaz
 
Software Process Improvement
Software Process ImprovementSoftware Process Improvement
Software Process ImprovementBilal Shah
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software EngineeringMuhammad Yousuf Abdul Qadir
 
Software Quality Attributes
Software Quality AttributesSoftware Quality Attributes
Software Quality AttributesHayim Makabee
 
Use Case Diagram
Use Case DiagramUse Case Diagram
Use Case DiagramKumar
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTKathirvel Ayyaswamy
 

Was ist angesagt? (20)

Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Lect4 software economics
Lect4 software economicsLect4 software economics
Lect4 software economics
 
History of software engineering
History of software engineeringHistory of software engineering
History of software engineering
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
Software estimation
Software estimationSoftware estimation
Software estimation
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
Software quality
Software qualitySoftware quality
Software quality
 
Fundamentals of software development
Fundamentals of software developmentFundamentals of software development
Fundamentals of software development
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
Introduction to Software Engineering
Introduction to Software EngineeringIntroduction to Software Engineering
Introduction to Software Engineering
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Management
 
Software Project Management (SPM)
Software Project Management (SPM)Software Project Management (SPM)
Software Project Management (SPM)
 
Ooad unit – 1 introduction
Ooad unit – 1 introductionOoad unit – 1 introduction
Ooad unit – 1 introduction
 
Software Process Improvement
Software Process ImprovementSoftware Process Improvement
Software Process Improvement
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software Engineering
 
Software Quality Attributes
Software Quality AttributesSoftware Quality Attributes
Software Quality Attributes
 
Use Case Diagram
Use Case DiagramUse Case Diagram
Use Case Diagram
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Spm unit 4
Spm unit 4Spm unit 4
Spm unit 4
 

Ähnlich wie Spm

Lecture 2
Lecture 2Lecture 2
Lecture 29anm12
 
An approach-to-planning-software-projects
An approach-to-planning-software-projectsAn approach-to-planning-software-projects
An approach-to-planning-software-projectstumetr
 
Chapter 03 overview-of project planning Step Wise
Chapter 03 overview-of project planning Step WiseChapter 03 overview-of project planning Step Wise
Chapter 03 overview-of project planning Step WiseRohanMistry15
 
SPM-Lecture 2.pptx
SPM-Lecture 2.pptxSPM-Lecture 2.pptx
SPM-Lecture 2.pptxssuser92282c
 
1 2. project management
1 2. project management1 2. project management
1 2. project managementakashsaini8
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
Chapter 1_Introduction sunorganisedASE_finalised.pptx
Chapter 1_Introduction sunorganisedASE_finalised.pptxChapter 1_Introduction sunorganisedASE_finalised.pptx
Chapter 1_Introduction sunorganisedASE_finalised.pptxBule Hora University
 
Software Project management
Software Project managementSoftware Project management
Software Project managementsameer farooq
 
project planning components.pdf
project planning components.pdfproject planning components.pdf
project planning components.pdfsaman Iftikhar
 
Software Project Management chapter-1
Software Project Management chapter-1Software Project Management chapter-1
Software Project Management chapter-1Computing Cage
 
Lecture 3
Lecture 3Lecture 3
Lecture 39anm12
 
Chapter 04 project approach
Chapter 04 project approachChapter 04 project approach
Chapter 04 project approachRohanMistry15
 

Ähnlich wie Spm (20)

Lecture 2
Lecture 2Lecture 2
Lecture 2
 
An approach-to-planning-software-projects
An approach-to-planning-software-projectsAn approach-to-planning-software-projects
An approach-to-planning-software-projects
 
Chapter 03 overview-of project planning Step Wise
Chapter 03 overview-of project planning Step WiseChapter 03 overview-of project planning Step Wise
Chapter 03 overview-of project planning Step Wise
 
Spm chapter 1
Spm chapter 1Spm chapter 1
Spm chapter 1
 
SPM-Lecture 2.pptx
SPM-Lecture 2.pptxSPM-Lecture 2.pptx
SPM-Lecture 2.pptx
 
1 2. project management
1 2. project management1 2. project management
1 2. project management
 
Spm unit 1
Spm unit 1Spm unit 1
Spm unit 1
 
Spm
Spm Spm
Spm
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Mg6088 spm unit-2
Mg6088 spm unit-2Mg6088 spm unit-2
Mg6088 spm unit-2
 
Spm
Spm Spm
Spm
 
SPM 3.pdf
SPM 3.pdfSPM 3.pdf
SPM 3.pdf
 
Chapter 1_Introduction sunorganisedASE_finalised.pptx
Chapter 1_Introduction sunorganisedASE_finalised.pptxChapter 1_Introduction sunorganisedASE_finalised.pptx
Chapter 1_Introduction sunorganisedASE_finalised.pptx
 
Software Project management
Software Project managementSoftware Project management
Software Project management
 
project planning components.pdf
project planning components.pdfproject planning components.pdf
project planning components.pdf
 
Proj Mgmt.ppt
Proj Mgmt.pptProj Mgmt.ppt
Proj Mgmt.ppt
 
Software Project Management chapter-1
Software Project Management chapter-1Software Project Management chapter-1
Software Project Management chapter-1
 
Lecture1
Lecture1Lecture1
Lecture1
 
Lecture 3
Lecture 3Lecture 3
Lecture 3
 
Chapter 04 project approach
Chapter 04 project approachChapter 04 project approach
Chapter 04 project approach
 

Kürzlich hochgeladen

Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxAmanpreet Kaur
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxcallscotland1987
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxAmita Gupta
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 

Kürzlich hochgeladen (20)

Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 

Spm

  • 1. ©The McGraw-Hill Companies, 2005 1 Software Project Management 4th Edition Step Wise: An approach to planning software projects Chapter 2
  • 2. ©The McGraw-Hill Companies, 2005 2 ‘Step Wise’ - aspirations • Practicality – tries to answer the question ‘what do I do now?’ • Scalability – useful for small project as well as large • Range of application • Accepted techniques – e.g. borrowed from PRINCE etc
  • 3. ©The McGraw-Hill Companies, 2005 3 ‘Step Wise’ - an overview 0.Select project1. Identify project objectives 2. Identify project infrastructure 3. Analyse project characteristics 4. Identify products and activities 5. Estimate effort for activity 8. Review/ publicize plan 6. Identify activity risks 7. Allocate resources 9. Execute plan 10. Lower level planning Review Lower level detail For each activity
  • 4. ©The McGraw-Hill Companies, 2005 4 A project scenario • Hardware/software engineering company (C++ language of choice) • teams are selected for individual projects - some friction has been found between team members • HR manager suggests psychometric testing to select team
  • 5. ©The McGraw-Hill Companies, 2005 5 Project scenario - continued • Software package to be used to test staff • Visual basic suggested as a vehicle for implementation • usability is important - decision to carry out usability tests
  • 6. ©The McGraw-Hill Companies, 2005 6 Step 1 establish project scope and objectives • 1.1 Identify objectives and measures of effectiveness – ‘how do we know if we have succeeded?’ • 1.2 Establish a project authority – ‘who is the boss?’ • 1.3 Identify all stakeholders in the project and their interests – ‘who will be affected/involved in the project?’
  • 7. ©The McGraw-Hill Companies, 2005 7 Step 1 continued • 1.4 Modify objectives in the light of stakeholder analysis – ‘do we need to do things to win over stakeholders?’ • 1.5 Establish methods of communication with all parties – ‘how do we keep in contact?’
  • 8. ©The McGraw-Hill Companies, 2005 8 Back to the scenario • Project authority – should be a project manager rather than HR manager? • Stakeholders – project team members to complete on- line questionnaires: concern about results? • Revision to objectives – provide feedback to team members on results
  • 9. ©The McGraw-Hill Companies, 2005 9 Step 2 Establish project infrastructure • 2.1 Establish link between project and any strategic plan – ‘why did they want the project?’ • 2.2 Identify installation standards and procedures – ‘what standards do we have to follow?’ • 2.3. Identify project team organization – ‘where do I fit in?’
  • 10. ©The McGraw-Hill Companies, 2005 10 Step 3 Analysis of project characteristics • 3.1 Distinguish the project as either objective or product-based. • 3.2 Analyse other project characteristics (including quality based ones) – what is different about this project?
  • 11. ©The McGraw-Hill Companies, 2005 11 Step 3 continued • Identify high level project risks – ‘what could go wrong?’ – ‘what can we do to stop it?’ • Take into account user requirements concerning implementation • Select general life cycle approach – waterfall? Increments? Prototypes? • Review overall resource estimates – ‘does all this increase the cost?’
  • 12. ©The McGraw-Hill Companies, 2005 12 Back to the scenario • Objectives vs. products • Some risks – team members worried about implications and do no co-operate – project managers unwilling to try out application – Developer not familiar with features of VB • Answer? - evolutionary prototype?
  • 13. ©The McGraw-Hill Companies, 2005 13 Step 4 Identify project products and activities 4.1 Identify and describe project products - ‘what do we have to produce?’ Usability testing Change requests Test results Testing arrangements Selected subjects Completed questionnaire Questionnaire design Booked PC Analysis report A product breakdown structure (PBS)
  • 14. ©The McGraw-Hill Companies, 2005 14 Products • The result of an activity • Could be (among other things) – physical thing (‘installed pc’), – a document (‘logical data structure’) – a person (‘trained user’) – a new version of an old product (‘updated software’)
  • 15. ©The McGraw-Hill Companies, 2005 15 Products • The following are NOT normally products: – activities (e.g. ‘training’) – events (e.g. ‘interviews completed’) – resources and actors (e.g. ‘software developer’) - may be exceptions to this • Products CAN BE deliverable or intermediate
  • 16. ©The McGraw-Hill Companies, 2005 16 Product description (PD) • Product identity • Description - what is it? • Derivation - what is it based on? • Composition - what does it contain? • Format • Relevant standards • Quality criteria Create a PD for ‘test data’
  • 17. ©The McGraw-Hill Companies, 2005 17 Step 4 continued 4.2 document Generic product flows Testing plan Selected subjects Questionnaire design Booked machine Completed questionnaire Analysis report Test results Change requests
  • 18. ©The McGraw-Hill Companies, 2005 18 Step 4.3 Recognize product instances • The PBS and PFD will probably have identified generic products e.g. ‘software modules’ • It might be possible to identify specific instances e.g. ‘module A’, ‘module B’ … • But in many cases this will have to be left to later, more detailed, planning
  • 19. ©The McGraw-Hill Companies, 2005 19 4.4. Produce ideal activity network • Identify the activities needed to create each product in the PFD • More than one activity might be needed to create a single product • Hint: Identify activities by verb + noun but avoid ‘produce…’ (too vague) • Draw up activity network
  • 20. ©The McGraw-Hill Companies, 2005 20 An ‘ideal’ activity Plan testing Design questionnaire Select subjects Book machine Conduct tests Analyse results Draft change requests
  • 21. ©The McGraw-Hill Companies, 2005 21 Step 4.5 Add check-points if needed Design module A Design module B Design system Design module C Code module A Code module B Code module C Test system Design module A Design module B Design system Design module C Code module A Code module B Code module C Test system Check-point put in a check point
  • 22. ©The McGraw-Hill Companies, 2005 22 Step 5:Estimate effort for each activity • 5.1 Carry out bottom-up estimates – distinguish carefully between effort and elapsed time • 5.2. Revise plan to create controllable activities – break up very long activities into a series of smaller ones – bundle up very short activities (create check lists?)
  • 23. ©The McGraw-Hill Companies, 2005 23 Step 6: Identify activity risks • 6.1.Identify and quantify risks for activities – damage if risk occurs (measure in time lost or money) – likelihood if risk occurring • 6.2. Plan risk reduction and contingency measures – risk reduction: activity to stop risk occurring – contingency: action if risk does occur
  • 24. ©The McGraw-Hill Companies, 2005 24 • 6.3 Adjust overall plans and estimates to take account of risks – e.g. add new activities which reduce risks associated with other activities e.g. training, pilot trials, information gathering
  • 25. ©The McGraw-Hill Companies, 2005 25 Step 7: Allocate resources • 7.1 Identify and allocate resources to activities • 7.2 Revise plans and estimates to take into account resource constraints – e.g. staff not being available until a later date – non-project activities
  • 26. ©The McGraw-Hill Companies, 2005 26 Gantt charts Select subjects Design questionnaire Book machine Conduct tests Analyse results Week commencing 5 12 19 26 MARCH APRIL 9 16 Plan testing 2 Draft changes LT TA LT TA LT LT TA LT = lead tester TA = testing assistant
  • 27. ©The McGraw-Hill Companies, 2005 27 Step 8: Review/publicise plan • 8.1 Review quality aspects of project plan • 8.2 Document plan and obtain agreement Step 9 and 10: Execute plan and create lower level plans