Supply Chain Program Management
& Process Controls
This presentation will explore the role of Supply Chain Liaison in order to facilitate the qualifying of a Supplier of
manufactured goods. Traditionally, the Customer, or provider of devices to the marketplace, have directly dealt
with the Supplier through the in-house Purchasing group; with less than adequate support in fulfilling the orders
on-time with quality initiatives met. This is due in large part to in-house responsibilities taking precedence with
the Manufacturing & Quality Engineers. The Supply Chain Liaison will work in this role while bridging the gap
between the Supplier & Customer in meeting the product launch requirements, followed by sustaining cost saving
initiatives thereafter.
2
Contents
 Overview 3
 Step 1: Identify 6
 Step 2: Document 13
 Step 3: Measure 20
 Step 4: Administer 28
 Step 5: Improve 33
 Summary 40
3
Contents
 Overview
 Step 1: Identify
 Step 2: Document
 Step 3: Measure
 Step 4: Administer
 Step 5: Improve
 Summary
4
In tracking with the five steps toward establishing the integrity of the manufacturing process, we’ll
examine the team contributions based on:
 Project Team Deliverables to include the collaborative effort of the Liaison & Customer in
identifying & ultimately qualifying the Supplier
 Project Liaison Deliverables based on the above inputs
This document defines and explains the 5-step process to Supply Chain
Management and establishing process controls
Supply Chain Management & Process Controls – Overview
5
The diagram below lays out the 5 step approach to our supply chain
management and process control framework
5-Step Approach
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
 Step 1: Identify project team and project
liaison deliverables in assessing the supplier
in terms of their core competencies.
 Step 2: Document project team and project
liaison deliverables with the objective of
securing proper work instructions at the cell.
 Step 3: Measure project team and project
liaison deliverables in determining what
features are to be measure at what frequency.
 Step 4: Administer project team and project
liaison deliverables in correlating on
measurement accuracy between both parties.
 Step 5: Improve project team project liaison
deliverables toward continuous improvement.
6
Contents
 Overview
 Step 1: Identify
 Step 2: Document
 Step 3: Measure
 Step 4: Administer
 Step 5: Improve
 Summary
7
Step 1: Identify Project Team Deliverables
Project Team Decision (1 of 4)
PROJECT TEAM DECISION
•Determine supplier, based on primary & secondary processes
1. How vertically integrated are they?
a.In other words, are they equipped to capture all of the processes required to produce your
product internally?
2. If not, what processes would have to be outsourced?
a.This is important as the likelihood of controlling lead times is diminished with outsourcing
on the part of your supplier.
b.This determination also will contribute significantly toward the line item costs and should be
vetted out before the actual quote requests are issued.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
8
Step 1: Identify Project Team Deliverables
Project Team Decision (2 of 4)
PROJECT TEAM DECISION
•Identify applicable core competencies exist
1. Is there a strategic fit for this supplier with respect to the product to be
manufactured in question?
a.Ensure that the Supplier is an “Expert” in the processing of parts similar to your product
targeted for outsourcing
2. What is their track record in the industry as it pertains to similar product produced
for other OEM’s?
a.Research in determining not only whether or not the capability is there, but to what level of
success.
3. Finally, if not already an established supplier with your company, how much
opportunity is there elsewhere in your portfolio?
a.When assessing the value a new supplier would bring to your new product, be certain that
there’s an opportunity to help consolidate your supplier list in allowing for the occasion to
bring them in on other legacy product.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
9
Step 1: Identify Project Team Deliverables
Project Team Decision (3 of 4)
PROJECT TEAM DECISION
•Confirm project team resources are available
1.On the part of the Supplier there should be Manufacturing, Procurement, and
Quality represented.
a.Ensure that the identified resources also have the sufficient % of their time
appropriately allocated to the new product line.
2.On the Customer front, as typical with most OEM new project teams, there
should be Manufacturing, Quality, Procurement, Regulatory, and Marketing.
a.Must also ensure that the individuals have the appropriate % of their day
dedicated to the activities surrounding this new product line.
3.Meet with Supplier management to confirm team buy-in & resource allocation
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
10
Step 1: Identify Project Team Deliverables
Project Team Decision (4 of 4)
PROJECT TEAM DECISION
•Ensure the ability of the supplier in having met Quality CFR Title 21, Part 820
requirements
1. Design Control phase gates are honored as per the above Section 820.30 that
speaks to the FDA’s Subpart on Quality System Regulation
a.In this collaborative effort on the part of the Customer & Supplier, ensure that all phase
gates allow for design for manufacturing & allow for inputs on the part of the Supplier.
b.As per the required documentation, evidence on the part of the Supplier will be provided to
ensure the translation of the design to manufacture is consistently held leading up to and
including the eventual production lots.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
11
Step 1: Identify Project Liaison Deliverables
Project Liaison Deliverables (1 of 2)
PROJECT LIAISON DELIVERABLE
•Perform on-site analysis of supplier quality management system
1. In tandem with the Customer’s own quality representative, assess the quality
system.
2. In addition, along with Manufacturing Engineer representative on behalf of the
Customer, assess the manufacturing equipment responsible for the product.
3. Finally, complete the appropriate checklists & assessment forms in determining the
eligibility and certification on the part of the supplier.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
12
Step 1: Identify Project Liaison Deliverables
Project Liaison Deliverables (2 of 2)
PROJECT LIAISON DELIVERABLE
•Establish Project Charter to ensure buy-in from both the supplier & the
customer team members
1. As the primary with respect to authoring the Charter, document the project with
respect to the project objectives, timeline, and deliverables in scoping the work.
2. Engage both teams to establish the buy-in necessary in relaying the message of
the charter.
3. Assign roles & responsibilities moving forward in meeting the project initiatives and
kick-off the project deliverables while signing off on the charter documentation.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
13
Contents
 Overview
 Step 1: Identify
 Step 2: Document
 Step 3: Measure
 Step 4: Administer
 Step 5: Improve
 Summary
14
Step 2: Document Project Team Deliverables
Project Team Decision (1 of 2)
PROJECT TEAM DECISION
•Introduce the equipment to be utilized for all processes required
1. Computer Numerical Controlled, (CNC), equipment identified for all processes
related to the manufacture of targeted product.
2. All CNC software to be verified as part of the equipment identified above.
3. All Fixtures & Gages already in place that speak to the manufacture of the product
in question.
4. Coordinate Measuring Machines, or CMM equipment identified as part of the
inspection process for targeted manufactured product.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
15
Step 2: Document Project Team Deliverables
Project Team Decision (2 of 2)
PROJECT TEAM DECISION
•Develop Action Plan from which new process specific parameters will be
driven, (Master Validation Plan)
1. Master Validation Plan, (MVP), will identify the necessary protocols for all
equipment and processes as required.
2. May include, (if not already performed), Installation Qualification Protocols for any
automated equipment.
3. Any Process Operational Qualifications related to equipment connected to the
processes required for manufacture.
4. All Process Performance Qualifications related to equipment also tied to the
processes defined for manufacture of product.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
16
Step 2: Document Project Liaison Deliverables
Project Liaison Deliverables (1 of 4)
PROJECT LIAISON DELIVERABLE
•Perform on-site analysis at the source of supplier processes and equipment
1. Assess the equipment to be validated in a production environment with obviously
no exposure to the specifics of the parts being produced.
2. Verify that the previously identified SOP’s & WI’s are present and accounted for at
the machining cell.
3. Visually account for the appropriate line clearances in both the set-up as well as
the closing out of an operation.
4. Determine that all training and maintenance manuals & logs are present and
accounted for at the equipment cell.
5. Visit the Quality inspection cell for Final and In-Process inspection in reviewing the
applicable gages & inspection logs consistent with your product requirements.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
17
Step 2: Document Project Team Deliverables
Project Liaison Deliverables (2 of 4)
PROJECT LIAISON DELIVERABLE
•Draft Process Operational Protocols, POQ’s, in defining existing supplier
process documentation & equipment
1. Intent here is to capture the necessary outputs in determining that the equipment
will produce acceptable results in a production setting.
a.This would include outputs based on anticipated operating conditions to include
upper/lower worst case conditions
b.Once proved successful, will demonstrate that the system through all operating ranges
allows for the desired requirements as outlined in the Master Validation Protocol.
c.Will include all identified documentation that address the set-up, in-process inspection, and
handling of line clearance at the machine cell.
2. Route the completed protocols for approval on the part of both the Customer and
the Supplier.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
18
Step 2: Document Project Liaison Deliverables
Project Liaison Deliverables (3 of 4)
PROJECT LIAISON DELIVERABLE
•Execute on all POQ’s & capture data
1. Once protocol has been approved, execute as per the protocol equipment
repeatability and record.
a.CNC Machine Axis Repeatability
b.Spindle Speed, or RPM’s as gaged at both the maximum and low extremes as well as the
mean rate.
c.Spindle Run out at taper falls within previously determined range.
d.Contour or profile of a surface is falling within an acceptable range.
e.CNC Software controls are verified by bringing about the necessary alarms in determining
over travel and improper coding in the programs.
f.Examine the designated product features as to the statistical variation when equipment is
running at the extreme & mean rates of speed.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
19
Step 2: Document Project Liaison Deliverables
Project Liaison Deliverables (4 of 4)
PROJECT LIAISON DELIVERABLE
•Route all POQ’s for approval
1. Route the completed reports for approval on the part of both the Customer and the
Supplier.
a.Include all data record tables as addendums with report.
2. Capture final electronically signed off documentation and place card this material
within the Master Validation Plan for safekeeping.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
20
Contents
 Overview
 Step 1: Identify
 Step 2: Document
 Step 3: Measure
 Step 4: Administer
 Step 5: Improve
 Summary
21
Step 3: Measure Project Team Deliverables
Project Team Decision (1 of 3)
PROJECT TEAM DECISION
•Ascertain the applicable processes parameters from which to take
measurements
1. Make note of dimensional characteristics deemed critical for design integrity.
2. Prioritize those measureable features that present challenges to the process.
3. Assess the minimal metal removal processes for their impact on the variability of
the manufactured component, i.e., polishing, blasting, anodizing, etc.
4. Additionally, consider challenges to certain features where there’s ability to
negotiate from a design perspective, if challenges in maintaining manufacturability
are deemed likely.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
22
Step 3: Measure Project Team Deliverables
Project Team Decision (2 of 3)
PROJECT TEAM DECISION
•Determine sample size & statistical reliability
1. With a minimum sample size of 30 pieces to be considered, based on the Central
Limit Theorem where a distribution stabilizes after approximately 30 pieces,
determine your desired minimum target requirement, or Cpk of perhaps 1.33, with
probability of less than 1 piece per million non-conforming.
2. To demonstrate repeatability across lots, two additional lots of 30 are required.
3. Based on a percentile, agree upon a Reliability & Confidence level percentage for
statistical reliability.
4. Based on these figures, determine the actual number of pieces to be run from the
calculation, where c = Confidence level, and q = Reliability, and n = Sample Size
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
23
Step 3: Measure Project Team Deliverables
Project Team Decision (3 of 3)
PROJECT TEAM DECISION
•Develop the quality inspection methods to be included in the process
parameters qualification
1. Now that the process features & controls to be measured have been defined, for
each, determine the method of inspection, i.e.,
2. Determine which are Variable, discreet measurement or Attribute, as in Pass/Fail
a.Calipers?
b.Micrometers?
c.Overlays? (Attribute only)
d.CMM?
e.Thread/Ring/Pin, or Custom Gages
3. If Custom gages are required, cut down lead time with non-production material
specifications if long lead times in Gage manufacturing is an issue.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
24
Step 3: Measure Project Liaison Deliverables
Project Liaison Deliverables (1 of 4)
PROJECT LIAISON DELIVERABLE
•Draft Process Performance Protocols, PPQ’s, in determining supplier
capability
1. Intent here is to capture the necessary outputs in determining that the process
critical features will produce acceptable results in a production setting.
a.This would include the aforementioned 3 production setting piece runs, while centering the
process and performing a 6 sigma assessment on the results.
b.Once proved successful, will demonstrate the statistical evidence that will allow for the
desired requirements as outlined in the Master Validation Protocol.
2. Route the completed protocols for approval on the part of both the Customer and
the Supplier.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
25
Step 3: Measure Project Liaison Deliverables
Project Liaison Deliverables (2 of 4)
PROJECT LIAISON DELIVERABLE
•Execute on all PPQ’s & capture data
1. Once protocol has been approved, execute as per the protocol and record.
a.Will include all captured variable features in a spreadsheet addendum to provide statistical
evidence of a process in control.
b.Provide 6 Sigma graphs to illustrate the findings of the data captured in the spreadsheet
addendum.
2. Record any deviations or Non-Conformances that may have occurred during the
validation runs for review.
a.If deemed acceptable, the non-conforming features to the protocol may be flagged for a
higher level of inspection later, whereby allowing for all other process variables and
therefore the validation, to move forward.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
26
Step 3: Measure Project Liaison Deliverables
Project Liaison Deliverables (3 of 4)
PROJECT LIAISON DELIVERABLE
•Capture costs associated with processes in establishing baseline for ROI
1. With the help of an inspection plan based on the process validation, determine
costs to manufacture and inspect, based on the pre-determined optimum lot size.
2. Assess material costs associated with each component
3. Calculate labor as part of the exercise and an overhead rate for in process
inspection & auditing.
4. Finally, if assembly costs are to be included, roll all components into inventory and
assess the cost of assembly work on it’s own merit.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
27
Step 3: Measure Project Liaison Deliverables
Project Liaison Deliverables (4 of 4)
PROJECT LIAISON DELIVERABLE
•Route all PPQ’s for approval
1. Route the completed reports for approval on the part of both the Customer and the
Supplier.
a.Include all data record tables as addendums with report.
2. Capture final electronically signed off documentation and place card this material
within the Master Validation Plan for safekeeping.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
28
Contents
 Overview
 Step 1: Identify
 Step 2: Document
 Step 3: Measure
 Step 4: Administer
 Step 5: Improve
 Summary
29
Step 4: Administer Project Team Deliverables
Project Team Decision (1 of 2)
PROJECT TEAM DECISION
•Correlate inspection measurements between the Supplier & Customer Teams
1. With the Quality representatives on both sides at a minimum, perform a gage R&R
with pieces already ran during the PPQ in order to establish accuracy between
measuring systems on both sides.
2. Collaborate on a draft of the Gage R&R protocol for approval.
3. Once approved, initiate the inspection activities on the part of the Customer,
followed by the Supplier, and return to the Liaison for an overall committee review.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
30
Step 4: Administer Project Team Deliverables
Project Team Decision (2 of 2)
PROJECT TEAM DECISION
•Determine the new frequency of measurement & confirm methods of
inspection
1. Based on the results of the PPQ’s, determine which features should be measured
with an increased sampling rate.
2. Once the inspection plan is complete in addressing the rate of inspection, begin
draft of a Control Plan.
3. Finalize the methods of inspection for sake of the Control Plan and compile the
required quality inspection records for capturing the data.
4. Provide all documentation to both teams in addressing both in-process and final
inspection quality departments.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
31
Step 4: Administer Project Liaison Deliverables
Project Liaison Deliverables (1 of 2)
PROJECT LIAISON DELIVERABLE
•Route MVP Report in qualifying supplier
1. At this point, once all documentation has been rolled in to the MVP by the Liaison,
he or she must then meet with both the Supplier & Customer teams in
communicating the results.
2. Review overall performance and approve the MVP for sake of compiling the results
into the subsequent Master Validation Report, (MVR), for approval.
3. In approving the report, committee featuring both teams then agree to initiate the
defining of the process improvement activities in the interest of process sustaining
efforts.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
32
Step 4: Administer Project Liaison Deliverables
Project Liaison Deliverables (2 of 2)
PROJECT LIAISON DELIVERABLE
•Capture inspection cost savings and adjust baseline for ROI
1. Adjust for reduced incoming inspection on the part of the Customer’s final
inspection team, based on the results of the Gage R&R & Process Validation
results.
2. Refresh the numbers from the prior exercise in establishing baseline costs
associated with the overall manufacturing process.
3. Calculate new ROI based on these results in leading to the final step in working
further to streamline our operating costs.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
33
Contents
 Overview
 Step 1: Identify
 Step 2: Document
 Step 3: Measure
 Step 4: Administer
 Step 5: Improve
 Summary
34
Step 5: Improve Project Team Deliverables
Project Team Decision (1 of 2)
PROJECT TEAM DECISION
•Determine scope & resources for future state of process
1. Often with less representation, two teams, once again representing the Supplier &
Customer sites, are to be formed for sustaining activities moving forward.
2. Representatives from both teams meet with Customer Executive Management in
determining the scope of the project agenda.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
35
Step 5: Improve Project Team Deliverables
Project Team Decision (2 of 2)
PROJECT TEAM DECISION
•Plan follow-up strategic planning sessions for continued sustaining activities
1. From there, draft a charter and schedule for the two teams to meet in addressing
the previously agreed to agenda items for continuous improvement.
2. Route the Project Charter for approval and initiate activities with a joint meeting
between the two project teams to kick off the effort.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
36
Step 5: Improve Project Liaison Deliverables
Project Liaison Deliverables (1 of 3)
PROJECT LIAISON DELIVERABLES
•Establish Floor feedback in providing support to sustaining teams
1. The best source for sustaining efforts is at the operator level. Ensure that the
information and interviews are taking place in describing the nuances behind the
operation for increased visibility of the process.
2. Examples include the cost savings realized on the operating floor by way of
enhanced technology and/or time saving innovations provided by way of operator
feedback.
3. Establish the data stream from which the statistical process controls are captured
in the interest of process improvements moving forward.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
37
Step 5: Improve Project Liaison Deliverables
Project Liaison Deliverables (2 of 3)
PROJECT LIAISON DELIVERABLES
•Draft & approve a Dock to Stock or Inspection instruction for incoming
inspection
1. With enough statistical data and inspection reports to support it, a Dock to Stock
plan in all but eliminating incoming inspection should be initiated.
2. Draft of protocol would include a provision for audited inspection on a random
basis, but the objective would be leverage a robust validated process to include the
extensive cost savings that would result from this.
3. Route protocol for subsequent approval and implementation within the
organization.
4. Revisit the baseline costs associated with the manufacturing process to realize the
reduction in operating costs toward the product ROI.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
38
Step 5: Improve Project Liaison Deliverables
Project Liaison Deliverables (3 of 3)
PROJECT LIAISON DELIVERABLES
•Establish Kanban system of supplier managed inventory
1. Once having implemented the cost saving initiatives provided by reduced
inspection and sustaining activities in manufacturing, consideration must be given
to supplier managed inventory.
2. By now the trust has risen to include correlation on the inspection front, and
process costs can be further reduced with controlled inventory.
3. Once inventory loads can be estimated with the proper level of confidence, further
cost savings are realized with the just in time delivery of product to the customer
for the build out of sets.
4. Over time, with enough trending data on the demand for product, these costs will
again transfer to the bottom line for enhanced cost savings.
TextSTEP 1
Identify
STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
39
Contents
 Overview
 Step 1: Identify
 Step 2: Document
 Step 3: Measure
 Step 4: Administer
 Step 5: Improve
 Summary
40
The Supply Chain Liaison will continue to manage the sustaining effort
Summary
With the Supply Chain Liaison leading the effort, we will continue to decrease costs with an
emphasis on process improvements in coordinating the effort with the Customer Executive Team.
time
MEASURE
Continuous
Improvement
Breakthrough!
STEP 1
Identify STEP 2
Document
STEP 3
Measure
STEP 4
Administer
STEP 5
Improve
41
About the Author, Stephen O’Neil
You can connect with Stephen O’Neil on LinkedIn here:
https://www.linkedin.com/in/stephengoneil
Stephen O’Neil
P.O. Box 4753, Wilmington, NC 28406
Phone: 248-388-7071 • Email: stephen.g.oneil@gmail.com
Over the course of my career I've had the pleasure to have worked in several capacities. All of which
has led me to the point where I see myself blending that background into a multi-faceted Supply Chain
Liaison role, as defined in detail with this 5 Step Plan. I look forward to sharing with you all that I’ve
gained in the way of experience, (certainly in part with lessons learned), but also with the excitement in
sharing the journey!
1. As an entrepreneur in my business partnership, I was able to help build on a business plan in
presenting engineering solutions that would include scanning & database documentation along
with design engineering contract placement. This included marketing two facilities out of both
the UK & US while traversing these diverse markets in growing the business.
2. In the role of a contract manufacturer representative, as both a Project Engineer in developing
prototype manufacturing cells, and as Project Manager representing our customer’s needs;
delivered on new product based on the orthopedic customer’s design intent.
3. And finally, over the past several years in representing MIS Spine new project teams in the role of
a Manufacturing Engineer, led the manufacturing effort to bring about product launches, through
both internal & external supply chain resources, in expediting new product to market in support of
the Thoracic Lumbar, Anterior Cervical, and Posterior Lumbar regions.

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (11)

Fight club film analysis1
Fight club film analysis1Fight club film analysis1
Fight club film analysis1
 
Intro to media studies
Intro to media studiesIntro to media studies
Intro to media studies
 
Film Noir
Film NoirFilm Noir
Film Noir
 
Wide Sargasso Sea/The Yellow Wallpaper Oppression of Women
Wide Sargasso Sea/The Yellow Wallpaper Oppression of WomenWide Sargasso Sea/The Yellow Wallpaper Oppression of Women
Wide Sargasso Sea/The Yellow Wallpaper Oppression of Women
 
To what extend do postmodern text challenge...
To what extend do postmodern text challenge...To what extend do postmodern text challenge...
To what extend do postmodern text challenge...
 
Agile Values, Principles and Practices
Agile Values, Principles and PracticesAgile Values, Principles and Practices
Agile Values, Principles and Practices
 
The male gaze in videogames
The male gaze in videogamesThe male gaze in videogames
The male gaze in videogames
 
The Scrum Model
The Scrum ModelThe Scrum Model
The Scrum Model
 
Scrum and JIRA
Scrum and JIRAScrum and JIRA
Scrum and JIRA
 
Camera angles in fight club
Camera angles in fight clubCamera angles in fight club
Camera angles in fight club
 
Executive Presentation on Agile Project Management by Boardroom Metrics Inc.
Executive Presentation on Agile Project Management by Boardroom Metrics Inc.Executive Presentation on Agile Project Management by Boardroom Metrics Inc.
Executive Presentation on Agile Project Management by Boardroom Metrics Inc.
 

Andere mochten auch

The Supply Chain Index - Improving Strength, Balance and Resiliency - 13 MAY ...
The Supply Chain Index - Improving Strength, Balance and Resiliency - 13 MAY ...The Supply Chain Index - Improving Strength, Balance and Resiliency - 13 MAY ...
The Supply Chain Index - Improving Strength, Balance and Resiliency - 13 MAY ...
Lora Cecere
 
Procurement & supply chain kpi benchmark 2010
Procurement & supply chain kpi benchmark 2010Procurement & supply chain kpi benchmark 2010
Procurement & supply chain kpi benchmark 2010
FGB
 
Mapping supply chains
Mapping supply chainsMapping supply chains
Mapping supply chains
Arkkkky
 
Supply chain diagram 8 stages powerpoint templates 0712
Supply chain diagram 8 stages powerpoint templates 0712Supply chain diagram 8 stages powerpoint templates 0712
Supply chain diagram 8 stages powerpoint templates 0712
SlideTeam.net
 

Andere mochten auch (11)

Improving Supply Chain-Management based on Semantically Enriched Risk Descrip...
Improving Supply Chain-Management based on Semantically Enriched Risk Descrip...Improving Supply Chain-Management based on Semantically Enriched Risk Descrip...
Improving Supply Chain-Management based on Semantically Enriched Risk Descrip...
 
Learn how to reduce costs by improving supply chain efficiency b2 b gateway...
Learn how to reduce costs by improving supply chain efficiency   b2 b gateway...Learn how to reduce costs by improving supply chain efficiency   b2 b gateway...
Learn how to reduce costs by improving supply chain efficiency b2 b gateway...
 
Supply Chain Process Improvement
Supply Chain Process ImprovementSupply Chain Process Improvement
Supply Chain Process Improvement
 
The Supply Chain Index - Improving Strength, Balance and Resiliency - 13 MAY ...
The Supply Chain Index - Improving Strength, Balance and Resiliency - 13 MAY ...The Supply Chain Index - Improving Strength, Balance and Resiliency - 13 MAY ...
The Supply Chain Index - Improving Strength, Balance and Resiliency - 13 MAY ...
 
Strategic sourcing & vendor selection
Strategic sourcing & vendor selectionStrategic sourcing & vendor selection
Strategic sourcing & vendor selection
 
Steps implement better integrated supply chain management. Case study. Logi...
Steps implement better integrated supply chain management.  Case study.  Logi...Steps implement better integrated supply chain management.  Case study.  Logi...
Steps implement better integrated supply chain management. Case study. Logi...
 
Procurement & supply chain kpi benchmark 2010
Procurement & supply chain kpi benchmark 2010Procurement & supply chain kpi benchmark 2010
Procurement & supply chain kpi benchmark 2010
 
Supply Chain Process Improvement Methodology V1
Supply Chain Process Improvement Methodology V1Supply Chain Process Improvement Methodology V1
Supply Chain Process Improvement Methodology V1
 
Mapping supply chains
Mapping supply chainsMapping supply chains
Mapping supply chains
 
Supply chain diagram 8 stages powerpoint templates 0712
Supply chain diagram 8 stages powerpoint templates 0712Supply chain diagram 8 stages powerpoint templates 0712
Supply chain diagram 8 stages powerpoint templates 0712
 
Supply Chain Management of TOYOTA.......case study by sabio bernard.
Supply Chain Management of TOYOTA.......case study by sabio bernard.Supply Chain Management of TOYOTA.......case study by sabio bernard.
Supply Chain Management of TOYOTA.......case study by sabio bernard.
 

Ähnlich wie Supply Chain Liaison 5 Step Management Program

Process and product quality Assurance
Process and product quality AssuranceProcess and product quality Assurance
Process and product quality Assurance
Joydip Bhattacharya
 
Quality Management handout
Quality Management handoutQuality Management handout
Quality Management handout
Prizzl
 
Quality management form
Quality management formQuality management form
Quality management form
jobguide247
 
An analysis incoming quality control of material in manufacturing company l...
An analysis incoming quality control of material in manufacturing company   l...An analysis incoming quality control of material in manufacturing company   l...
An analysis incoming quality control of material in manufacturing company l...
Steve Sapp
 
7.quality management chapter 7
7.quality management chapter 77.quality management chapter 7
7.quality management chapter 7
Warui Maina
 
Quality management review template
Quality management review templateQuality management review template
Quality management review template
selinasimpson2801
 

Ähnlich wie Supply Chain Liaison 5 Step Management Program (20)

Introduction to CMMI-DEV v1.3 - Day 3
Introduction to CMMI-DEV v1.3  - Day 3Introduction to CMMI-DEV v1.3  - Day 3
Introduction to CMMI-DEV v1.3 - Day 3
 
build-for-speed-brochure
build-for-speed-brochurebuild-for-speed-brochure
build-for-speed-brochure
 
Verification process
Verification processVerification process
Verification process
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Process and product quality Assurance
Process and product quality AssuranceProcess and product quality Assurance
Process and product quality Assurance
 
QFD-COVID TEST KIT updated-converted.pdf
QFD-COVID TEST KIT updated-converted.pdfQFD-COVID TEST KIT updated-converted.pdf
QFD-COVID TEST KIT updated-converted.pdf
 
Speech
SpeechSpeech
Speech
 
Quality Management handout
Quality Management handoutQuality Management handout
Quality Management handout
 
asme_product_development_cycle.ppt
asme_product_development_cycle.pptasme_product_development_cycle.ppt
asme_product_development_cycle.ppt
 
Introduction to CMMI-DEV v1.3 - Day 2
Introduction to CMMI-DEV v1.3  - Day 2Introduction to CMMI-DEV v1.3  - Day 2
Introduction to CMMI-DEV v1.3 - Day 2
 
тестовые стратегии
тестовые стратегиитестовые стратегии
тестовые стратегии
 
Quality management form
Quality management formQuality management form
Quality management form
 
Product quality management
Product quality managementProduct quality management
Product quality management
 
Process assessment sample
Process assessment sampleProcess assessment sample
Process assessment sample
 
Quality assurance
Quality assuranceQuality assurance
Quality assurance
 
An analysis incoming quality control of material in manufacturing company l...
An analysis incoming quality control of material in manufacturing company   l...An analysis incoming quality control of material in manufacturing company   l...
An analysis incoming quality control of material in manufacturing company l...
 
On Demand Feedback Analysis for Certification Process
On Demand Feedback Analysis for Certification ProcessOn Demand Feedback Analysis for Certification Process
On Demand Feedback Analysis for Certification Process
 
7.quality management chapter 7
7.quality management chapter 77.quality management chapter 7
7.quality management chapter 7
 
Quality management slides
Quality management slidesQuality management slides
Quality management slides
 
Quality management review template
Quality management review templateQuality management review template
Quality management review template
 

Supply Chain Liaison 5 Step Management Program

  • 1. Supply Chain Program Management & Process Controls This presentation will explore the role of Supply Chain Liaison in order to facilitate the qualifying of a Supplier of manufactured goods. Traditionally, the Customer, or provider of devices to the marketplace, have directly dealt with the Supplier through the in-house Purchasing group; with less than adequate support in fulfilling the orders on-time with quality initiatives met. This is due in large part to in-house responsibilities taking precedence with the Manufacturing & Quality Engineers. The Supply Chain Liaison will work in this role while bridging the gap between the Supplier & Customer in meeting the product launch requirements, followed by sustaining cost saving initiatives thereafter.
  • 2. 2 Contents  Overview 3  Step 1: Identify 6  Step 2: Document 13  Step 3: Measure 20  Step 4: Administer 28  Step 5: Improve 33  Summary 40
  • 3. 3 Contents  Overview  Step 1: Identify  Step 2: Document  Step 3: Measure  Step 4: Administer  Step 5: Improve  Summary
  • 4. 4 In tracking with the five steps toward establishing the integrity of the manufacturing process, we’ll examine the team contributions based on:  Project Team Deliverables to include the collaborative effort of the Liaison & Customer in identifying & ultimately qualifying the Supplier  Project Liaison Deliverables based on the above inputs This document defines and explains the 5-step process to Supply Chain Management and establishing process controls Supply Chain Management & Process Controls – Overview
  • 5. 5 The diagram below lays out the 5 step approach to our supply chain management and process control framework 5-Step Approach TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve  Step 1: Identify project team and project liaison deliverables in assessing the supplier in terms of their core competencies.  Step 2: Document project team and project liaison deliverables with the objective of securing proper work instructions at the cell.  Step 3: Measure project team and project liaison deliverables in determining what features are to be measure at what frequency.  Step 4: Administer project team and project liaison deliverables in correlating on measurement accuracy between both parties.  Step 5: Improve project team project liaison deliverables toward continuous improvement.
  • 6. 6 Contents  Overview  Step 1: Identify  Step 2: Document  Step 3: Measure  Step 4: Administer  Step 5: Improve  Summary
  • 7. 7 Step 1: Identify Project Team Deliverables Project Team Decision (1 of 4) PROJECT TEAM DECISION •Determine supplier, based on primary & secondary processes 1. How vertically integrated are they? a.In other words, are they equipped to capture all of the processes required to produce your product internally? 2. If not, what processes would have to be outsourced? a.This is important as the likelihood of controlling lead times is diminished with outsourcing on the part of your supplier. b.This determination also will contribute significantly toward the line item costs and should be vetted out before the actual quote requests are issued. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 8. 8 Step 1: Identify Project Team Deliverables Project Team Decision (2 of 4) PROJECT TEAM DECISION •Identify applicable core competencies exist 1. Is there a strategic fit for this supplier with respect to the product to be manufactured in question? a.Ensure that the Supplier is an “Expert” in the processing of parts similar to your product targeted for outsourcing 2. What is their track record in the industry as it pertains to similar product produced for other OEM’s? a.Research in determining not only whether or not the capability is there, but to what level of success. 3. Finally, if not already an established supplier with your company, how much opportunity is there elsewhere in your portfolio? a.When assessing the value a new supplier would bring to your new product, be certain that there’s an opportunity to help consolidate your supplier list in allowing for the occasion to bring them in on other legacy product. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 9. 9 Step 1: Identify Project Team Deliverables Project Team Decision (3 of 4) PROJECT TEAM DECISION •Confirm project team resources are available 1.On the part of the Supplier there should be Manufacturing, Procurement, and Quality represented. a.Ensure that the identified resources also have the sufficient % of their time appropriately allocated to the new product line. 2.On the Customer front, as typical with most OEM new project teams, there should be Manufacturing, Quality, Procurement, Regulatory, and Marketing. a.Must also ensure that the individuals have the appropriate % of their day dedicated to the activities surrounding this new product line. 3.Meet with Supplier management to confirm team buy-in & resource allocation TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 10. 10 Step 1: Identify Project Team Deliverables Project Team Decision (4 of 4) PROJECT TEAM DECISION •Ensure the ability of the supplier in having met Quality CFR Title 21, Part 820 requirements 1. Design Control phase gates are honored as per the above Section 820.30 that speaks to the FDA’s Subpart on Quality System Regulation a.In this collaborative effort on the part of the Customer & Supplier, ensure that all phase gates allow for design for manufacturing & allow for inputs on the part of the Supplier. b.As per the required documentation, evidence on the part of the Supplier will be provided to ensure the translation of the design to manufacture is consistently held leading up to and including the eventual production lots. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 11. 11 Step 1: Identify Project Liaison Deliverables Project Liaison Deliverables (1 of 2) PROJECT LIAISON DELIVERABLE •Perform on-site analysis of supplier quality management system 1. In tandem with the Customer’s own quality representative, assess the quality system. 2. In addition, along with Manufacturing Engineer representative on behalf of the Customer, assess the manufacturing equipment responsible for the product. 3. Finally, complete the appropriate checklists & assessment forms in determining the eligibility and certification on the part of the supplier. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 12. 12 Step 1: Identify Project Liaison Deliverables Project Liaison Deliverables (2 of 2) PROJECT LIAISON DELIVERABLE •Establish Project Charter to ensure buy-in from both the supplier & the customer team members 1. As the primary with respect to authoring the Charter, document the project with respect to the project objectives, timeline, and deliverables in scoping the work. 2. Engage both teams to establish the buy-in necessary in relaying the message of the charter. 3. Assign roles & responsibilities moving forward in meeting the project initiatives and kick-off the project deliverables while signing off on the charter documentation. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 13. 13 Contents  Overview  Step 1: Identify  Step 2: Document  Step 3: Measure  Step 4: Administer  Step 5: Improve  Summary
  • 14. 14 Step 2: Document Project Team Deliverables Project Team Decision (1 of 2) PROJECT TEAM DECISION •Introduce the equipment to be utilized for all processes required 1. Computer Numerical Controlled, (CNC), equipment identified for all processes related to the manufacture of targeted product. 2. All CNC software to be verified as part of the equipment identified above. 3. All Fixtures & Gages already in place that speak to the manufacture of the product in question. 4. Coordinate Measuring Machines, or CMM equipment identified as part of the inspection process for targeted manufactured product. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 15. 15 Step 2: Document Project Team Deliverables Project Team Decision (2 of 2) PROJECT TEAM DECISION •Develop Action Plan from which new process specific parameters will be driven, (Master Validation Plan) 1. Master Validation Plan, (MVP), will identify the necessary protocols for all equipment and processes as required. 2. May include, (if not already performed), Installation Qualification Protocols for any automated equipment. 3. Any Process Operational Qualifications related to equipment connected to the processes required for manufacture. 4. All Process Performance Qualifications related to equipment also tied to the processes defined for manufacture of product. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 16. 16 Step 2: Document Project Liaison Deliverables Project Liaison Deliverables (1 of 4) PROJECT LIAISON DELIVERABLE •Perform on-site analysis at the source of supplier processes and equipment 1. Assess the equipment to be validated in a production environment with obviously no exposure to the specifics of the parts being produced. 2. Verify that the previously identified SOP’s & WI’s are present and accounted for at the machining cell. 3. Visually account for the appropriate line clearances in both the set-up as well as the closing out of an operation. 4. Determine that all training and maintenance manuals & logs are present and accounted for at the equipment cell. 5. Visit the Quality inspection cell for Final and In-Process inspection in reviewing the applicable gages & inspection logs consistent with your product requirements. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 17. 17 Step 2: Document Project Team Deliverables Project Liaison Deliverables (2 of 4) PROJECT LIAISON DELIVERABLE •Draft Process Operational Protocols, POQ’s, in defining existing supplier process documentation & equipment 1. Intent here is to capture the necessary outputs in determining that the equipment will produce acceptable results in a production setting. a.This would include outputs based on anticipated operating conditions to include upper/lower worst case conditions b.Once proved successful, will demonstrate that the system through all operating ranges allows for the desired requirements as outlined in the Master Validation Protocol. c.Will include all identified documentation that address the set-up, in-process inspection, and handling of line clearance at the machine cell. 2. Route the completed protocols for approval on the part of both the Customer and the Supplier. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 18. 18 Step 2: Document Project Liaison Deliverables Project Liaison Deliverables (3 of 4) PROJECT LIAISON DELIVERABLE •Execute on all POQ’s & capture data 1. Once protocol has been approved, execute as per the protocol equipment repeatability and record. a.CNC Machine Axis Repeatability b.Spindle Speed, or RPM’s as gaged at both the maximum and low extremes as well as the mean rate. c.Spindle Run out at taper falls within previously determined range. d.Contour or profile of a surface is falling within an acceptable range. e.CNC Software controls are verified by bringing about the necessary alarms in determining over travel and improper coding in the programs. f.Examine the designated product features as to the statistical variation when equipment is running at the extreme & mean rates of speed. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 19. 19 Step 2: Document Project Liaison Deliverables Project Liaison Deliverables (4 of 4) PROJECT LIAISON DELIVERABLE •Route all POQ’s for approval 1. Route the completed reports for approval on the part of both the Customer and the Supplier. a.Include all data record tables as addendums with report. 2. Capture final electronically signed off documentation and place card this material within the Master Validation Plan for safekeeping. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 20. 20 Contents  Overview  Step 1: Identify  Step 2: Document  Step 3: Measure  Step 4: Administer  Step 5: Improve  Summary
  • 21. 21 Step 3: Measure Project Team Deliverables Project Team Decision (1 of 3) PROJECT TEAM DECISION •Ascertain the applicable processes parameters from which to take measurements 1. Make note of dimensional characteristics deemed critical for design integrity. 2. Prioritize those measureable features that present challenges to the process. 3. Assess the minimal metal removal processes for their impact on the variability of the manufactured component, i.e., polishing, blasting, anodizing, etc. 4. Additionally, consider challenges to certain features where there’s ability to negotiate from a design perspective, if challenges in maintaining manufacturability are deemed likely. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 22. 22 Step 3: Measure Project Team Deliverables Project Team Decision (2 of 3) PROJECT TEAM DECISION •Determine sample size & statistical reliability 1. With a minimum sample size of 30 pieces to be considered, based on the Central Limit Theorem where a distribution stabilizes after approximately 30 pieces, determine your desired minimum target requirement, or Cpk of perhaps 1.33, with probability of less than 1 piece per million non-conforming. 2. To demonstrate repeatability across lots, two additional lots of 30 are required. 3. Based on a percentile, agree upon a Reliability & Confidence level percentage for statistical reliability. 4. Based on these figures, determine the actual number of pieces to be run from the calculation, where c = Confidence level, and q = Reliability, and n = Sample Size TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 23. 23 Step 3: Measure Project Team Deliverables Project Team Decision (3 of 3) PROJECT TEAM DECISION •Develop the quality inspection methods to be included in the process parameters qualification 1. Now that the process features & controls to be measured have been defined, for each, determine the method of inspection, i.e., 2. Determine which are Variable, discreet measurement or Attribute, as in Pass/Fail a.Calipers? b.Micrometers? c.Overlays? (Attribute only) d.CMM? e.Thread/Ring/Pin, or Custom Gages 3. If Custom gages are required, cut down lead time with non-production material specifications if long lead times in Gage manufacturing is an issue. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 24. 24 Step 3: Measure Project Liaison Deliverables Project Liaison Deliverables (1 of 4) PROJECT LIAISON DELIVERABLE •Draft Process Performance Protocols, PPQ’s, in determining supplier capability 1. Intent here is to capture the necessary outputs in determining that the process critical features will produce acceptable results in a production setting. a.This would include the aforementioned 3 production setting piece runs, while centering the process and performing a 6 sigma assessment on the results. b.Once proved successful, will demonstrate the statistical evidence that will allow for the desired requirements as outlined in the Master Validation Protocol. 2. Route the completed protocols for approval on the part of both the Customer and the Supplier. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 25. 25 Step 3: Measure Project Liaison Deliverables Project Liaison Deliverables (2 of 4) PROJECT LIAISON DELIVERABLE •Execute on all PPQ’s & capture data 1. Once protocol has been approved, execute as per the protocol and record. a.Will include all captured variable features in a spreadsheet addendum to provide statistical evidence of a process in control. b.Provide 6 Sigma graphs to illustrate the findings of the data captured in the spreadsheet addendum. 2. Record any deviations or Non-Conformances that may have occurred during the validation runs for review. a.If deemed acceptable, the non-conforming features to the protocol may be flagged for a higher level of inspection later, whereby allowing for all other process variables and therefore the validation, to move forward. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 26. 26 Step 3: Measure Project Liaison Deliverables Project Liaison Deliverables (3 of 4) PROJECT LIAISON DELIVERABLE •Capture costs associated with processes in establishing baseline for ROI 1. With the help of an inspection plan based on the process validation, determine costs to manufacture and inspect, based on the pre-determined optimum lot size. 2. Assess material costs associated with each component 3. Calculate labor as part of the exercise and an overhead rate for in process inspection & auditing. 4. Finally, if assembly costs are to be included, roll all components into inventory and assess the cost of assembly work on it’s own merit. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 27. 27 Step 3: Measure Project Liaison Deliverables Project Liaison Deliverables (4 of 4) PROJECT LIAISON DELIVERABLE •Route all PPQ’s for approval 1. Route the completed reports for approval on the part of both the Customer and the Supplier. a.Include all data record tables as addendums with report. 2. Capture final electronically signed off documentation and place card this material within the Master Validation Plan for safekeeping. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 28. 28 Contents  Overview  Step 1: Identify  Step 2: Document  Step 3: Measure  Step 4: Administer  Step 5: Improve  Summary
  • 29. 29 Step 4: Administer Project Team Deliverables Project Team Decision (1 of 2) PROJECT TEAM DECISION •Correlate inspection measurements between the Supplier & Customer Teams 1. With the Quality representatives on both sides at a minimum, perform a gage R&R with pieces already ran during the PPQ in order to establish accuracy between measuring systems on both sides. 2. Collaborate on a draft of the Gage R&R protocol for approval. 3. Once approved, initiate the inspection activities on the part of the Customer, followed by the Supplier, and return to the Liaison for an overall committee review. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 30. 30 Step 4: Administer Project Team Deliverables Project Team Decision (2 of 2) PROJECT TEAM DECISION •Determine the new frequency of measurement & confirm methods of inspection 1. Based on the results of the PPQ’s, determine which features should be measured with an increased sampling rate. 2. Once the inspection plan is complete in addressing the rate of inspection, begin draft of a Control Plan. 3. Finalize the methods of inspection for sake of the Control Plan and compile the required quality inspection records for capturing the data. 4. Provide all documentation to both teams in addressing both in-process and final inspection quality departments. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 31. 31 Step 4: Administer Project Liaison Deliverables Project Liaison Deliverables (1 of 2) PROJECT LIAISON DELIVERABLE •Route MVP Report in qualifying supplier 1. At this point, once all documentation has been rolled in to the MVP by the Liaison, he or she must then meet with both the Supplier & Customer teams in communicating the results. 2. Review overall performance and approve the MVP for sake of compiling the results into the subsequent Master Validation Report, (MVR), for approval. 3. In approving the report, committee featuring both teams then agree to initiate the defining of the process improvement activities in the interest of process sustaining efforts. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 32. 32 Step 4: Administer Project Liaison Deliverables Project Liaison Deliverables (2 of 2) PROJECT LIAISON DELIVERABLE •Capture inspection cost savings and adjust baseline for ROI 1. Adjust for reduced incoming inspection on the part of the Customer’s final inspection team, based on the results of the Gage R&R & Process Validation results. 2. Refresh the numbers from the prior exercise in establishing baseline costs associated with the overall manufacturing process. 3. Calculate new ROI based on these results in leading to the final step in working further to streamline our operating costs. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 33. 33 Contents  Overview  Step 1: Identify  Step 2: Document  Step 3: Measure  Step 4: Administer  Step 5: Improve  Summary
  • 34. 34 Step 5: Improve Project Team Deliverables Project Team Decision (1 of 2) PROJECT TEAM DECISION •Determine scope & resources for future state of process 1. Often with less representation, two teams, once again representing the Supplier & Customer sites, are to be formed for sustaining activities moving forward. 2. Representatives from both teams meet with Customer Executive Management in determining the scope of the project agenda. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 35. 35 Step 5: Improve Project Team Deliverables Project Team Decision (2 of 2) PROJECT TEAM DECISION •Plan follow-up strategic planning sessions for continued sustaining activities 1. From there, draft a charter and schedule for the two teams to meet in addressing the previously agreed to agenda items for continuous improvement. 2. Route the Project Charter for approval and initiate activities with a joint meeting between the two project teams to kick off the effort. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 36. 36 Step 5: Improve Project Liaison Deliverables Project Liaison Deliverables (1 of 3) PROJECT LIAISON DELIVERABLES •Establish Floor feedback in providing support to sustaining teams 1. The best source for sustaining efforts is at the operator level. Ensure that the information and interviews are taking place in describing the nuances behind the operation for increased visibility of the process. 2. Examples include the cost savings realized on the operating floor by way of enhanced technology and/or time saving innovations provided by way of operator feedback. 3. Establish the data stream from which the statistical process controls are captured in the interest of process improvements moving forward. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 37. 37 Step 5: Improve Project Liaison Deliverables Project Liaison Deliverables (2 of 3) PROJECT LIAISON DELIVERABLES •Draft & approve a Dock to Stock or Inspection instruction for incoming inspection 1. With enough statistical data and inspection reports to support it, a Dock to Stock plan in all but eliminating incoming inspection should be initiated. 2. Draft of protocol would include a provision for audited inspection on a random basis, but the objective would be leverage a robust validated process to include the extensive cost savings that would result from this. 3. Route protocol for subsequent approval and implementation within the organization. 4. Revisit the baseline costs associated with the manufacturing process to realize the reduction in operating costs toward the product ROI. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 38. 38 Step 5: Improve Project Liaison Deliverables Project Liaison Deliverables (3 of 3) PROJECT LIAISON DELIVERABLES •Establish Kanban system of supplier managed inventory 1. Once having implemented the cost saving initiatives provided by reduced inspection and sustaining activities in manufacturing, consideration must be given to supplier managed inventory. 2. By now the trust has risen to include correlation on the inspection front, and process costs can be further reduced with controlled inventory. 3. Once inventory loads can be estimated with the proper level of confidence, further cost savings are realized with the just in time delivery of product to the customer for the build out of sets. 4. Over time, with enough trending data on the demand for product, these costs will again transfer to the bottom line for enhanced cost savings. TextSTEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 39. 39 Contents  Overview  Step 1: Identify  Step 2: Document  Step 3: Measure  Step 4: Administer  Step 5: Improve  Summary
  • 40. 40 The Supply Chain Liaison will continue to manage the sustaining effort Summary With the Supply Chain Liaison leading the effort, we will continue to decrease costs with an emphasis on process improvements in coordinating the effort with the Customer Executive Team. time MEASURE Continuous Improvement Breakthrough! STEP 1 Identify STEP 2 Document STEP 3 Measure STEP 4 Administer STEP 5 Improve
  • 41. 41 About the Author, Stephen O’Neil You can connect with Stephen O’Neil on LinkedIn here: https://www.linkedin.com/in/stephengoneil Stephen O’Neil P.O. Box 4753, Wilmington, NC 28406 Phone: 248-388-7071 • Email: stephen.g.oneil@gmail.com Over the course of my career I've had the pleasure to have worked in several capacities. All of which has led me to the point where I see myself blending that background into a multi-faceted Supply Chain Liaison role, as defined in detail with this 5 Step Plan. I look forward to sharing with you all that I’ve gained in the way of experience, (certainly in part with lessons learned), but also with the excitement in sharing the journey! 1. As an entrepreneur in my business partnership, I was able to help build on a business plan in presenting engineering solutions that would include scanning & database documentation along with design engineering contract placement. This included marketing two facilities out of both the UK & US while traversing these diverse markets in growing the business. 2. In the role of a contract manufacturer representative, as both a Project Engineer in developing prototype manufacturing cells, and as Project Manager representing our customer’s needs; delivered on new product based on the orthopedic customer’s design intent. 3. And finally, over the past several years in representing MIS Spine new project teams in the role of a Manufacturing Engineer, led the manufacturing effort to bring about product launches, through both internal & external supply chain resources, in expediting new product to market in support of the Thoracic Lumbar, Anterior Cervical, and Posterior Lumbar regions.