PENETRATION
TEST
Shweta Sagar & Juhita
M.Tech. CTM
1st sem
PENETRATION TEST OF BITUMEN
AIM
(i) To determine the consistency of the bituminous
material.
(ii)To assess the suitability of bitumen for use under
different climatic conditions and various types of
construction.
PENETRATION TEST OF BITUMEN
APPARATUS
(i) Container: A flat bottomed cylindrical metallic
dish 55mm in diameter and 35 mm in depth is
required. If the penetration is of the order of 225
or more, dish of 70mm diameter and 45mm depth
is required.
(ii)Transfer dish or tray: Should provide support to
the container & should not rock it. It should be of
such capacity as to completely immerse container
during test.
PENETRATION TEST OF BITUMEN
(iii) Water bath: Water bath maintained at 25 ± 0.1 °C,
containing not less than 10 litres of water, the
sample being immersed to a depth not less than
100 mm from top and supported on perforated
shelf not less than 50 mm from bottom of the bath.
(iv) Needle: A straight, highly polished, cylindrical
hard steel rod.
(v) Thermometer: Range 0°C - 44°C and in readable
up to 0.20°C.
PENETRATION TEST OF BITUMEN
(vi) Penetration apparatus: Should be such that it
allows needle to penetrate without much
friction & is accurately calibrated to give
results in one tenth of a millimeter.
(vii) Time measuring device: With an accuracy of
a second.
PENETRATION TEST OF BITUMEN
THEORY
Penetration value is a measure of hardness or
consistency of bituminous material. It is the vertical
distance traversed or penetrated by the point of a
standard needle in to the bituminous material under
specific conditions of load, time and temperature. This
distance is measured in one tenths of a millimeter.
This test is used for evaluating consistency of
bitumen. It is not regarded as suitable for use in
connection with the testing of road tar because of the
high surface tension exhibited by these materials.
PENETRATION TEST OF BITUMEN
PROCEDURE
(i) Preparation of test sample: Soften the material to a
pouring consistency at a temperature not more than
60°C for tars and 90°C for bitumen above the
approximate softening point and stir it thoroughly until
it is homogeneous and is free from air bubbles and
water. Pour the melt into the container to a depth at
least 10mm in excess of the expected penetration.
Protect the sample from dust and allow it to cool in an
atmosphere at a temperature between 15°C to 30°C for
one hour. Then place it along with the transfer dish in
the water bath at 25°C ± 0.1°C, unless otherwise
stated.
PENETRATION TEST OF BITUMEN
(ii) Fill the transfer dish with water from the water bath to
depth sufficient to cover the container completely,
place the sample in it and put it upon the stand of the
penetration apparatus.
(iii) Clean the needle with benzene, dry it and load with
the weight. The total moving load required is 100 ±
0.25 grams, including the weight of the needle, carrier
and super-imposed weights.
(iv) Adjust the needle to make contact with the surface of
the sample. This may be done by placing the
needlepoint in contact with its image reflected by the
surface of the bituminous material.
PENETRATION TEST OF BITUMEN
(v) Make the pointer of the dial to read zero or note the
initial dial reading.
(vi) Release the needle for exactly five seconds.
(vii) Adjust the penetration machine to measure the
distance penetrated.
PENETRATION TEST OF BITUMEN
(viii) Make at least 3 readings at points on the
surface of the sample not less than 10 mm apart
and not less than l0mm from the side of the dish.
After each test return the sample and transfer
dish to the water bath and wash the needle clean
with benzene and dry it. In case of material of
penetration greater than 225, three
determinations on each of the two identical test
specimens using a separate needle for each
determination should be made, leaving the
needle in the sample on completion of each
determination to avoid disturbance of the
specimen.
PENETRATION TEST OF BITUMEN
PENETRATION TEST OF BITUMEN
RECORD OF OBSERVATION
PENETRATION TEST OF BITUMEN
PENETROMETER DIAL READING TEST 1 TEST 2 TEST 3
(A) Initial 200 264 333
(B) Final 264 333 407
PENETRATION VALUE 64 69 74
Actual Test Temperature(°C) = 25°C
Mean Penetration Value = 69
RECOMMENDED VALUE AS
PER IS CODE 73:2006
PENETRATION TEST OF BITUMEN
BITUMEN GRADE PENETRATION VALUE
A-35 30-40
A-45 40-50
A-55 50-60
A-65 60-70
A-90 80-100
A-200 175-225
PENETRATION TEST OF BITUMEN
Download@notescvil.blogspot.in
PENETRATION TEST OF BITUMEN
PRECAUTION
(i) There should be no movement of the container
while needle penetrates into sample.
(ii) The sample should be free from any extraneous
matter.
(iii) The needle should be cleaned with benzene and
dried before penetration.
PENETRATION TEST OF BITUMEN
PENETRATION TEST OF BITUMEN
Thank You

Weitere ähnliche Inhalte

Was ist angesagt?

PENETRATION TEST ON BITUMINOUS MATERIALS.
PENETRATION TEST ON BITUMINOUS MATERIALS.PENETRATION TEST ON BITUMINOUS MATERIALS.
PENETRATION TEST ON BITUMINOUS MATERIALS.Sayed Sajid H.Zidani
 
Presentation on Determination of Penetration & Specific Gravity Test of Bitumen
Presentation on Determination of Penetration & Specific Gravity Test of BitumenPresentation on Determination of Penetration & Specific Gravity Test of Bitumen
Presentation on Determination of Penetration & Specific Gravity Test of BitumenAbu Taher
 
Aggregate impact and crushing test
Aggregate impact and crushing testAggregate impact and crushing test
Aggregate impact and crushing testsudeepmahapatro
 
Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 03 Determination of the flakiness and the elongation index for ...Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 03 Determination of the flakiness and the elongation index for ...Sayed Sajid H.Zidani
 
Unconfined compression test
Unconfined compression testUnconfined compression test
Unconfined compression testNatalie Ulza
 
Marshall Mix Design: Lab Report
Marshall Mix Design: Lab ReportMarshall Mix Design: Lab Report
Marshall Mix Design: Lab ReportPriyansh Singh
 
Permeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head MethodPermeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head MethodJameel Academy
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test pptsayan sarkar
 
Test On Bitumen
Test On BitumenTest On Bitumen
Test On BitumenUjas Patel
 
Shape tests of aggregate
Shape tests of aggregateShape tests of aggregate
Shape tests of aggregateJacob shah
 
Proktor compaction
Proktor compactionProktor compaction
Proktor compactionNatalie Ulza
 
Sieve analysis of coarse and fine aggregate - Report
Sieve analysis of coarse and fine aggregate - ReportSieve analysis of coarse and fine aggregate - Report
Sieve analysis of coarse and fine aggregate - ReportSarchia Khursheed
 
Design mix method of bitumenous materials by Marshall stability method
Design mix method of bitumenous materials by Marshall stability methodDesign mix method of bitumenous materials by Marshall stability method
Design mix method of bitumenous materials by Marshall stability methodAmardeep Singh
 
Laboratory soil compaction test
Laboratory soil compaction testLaboratory soil compaction test
Laboratory soil compaction testAtul Hajong
 

Was ist angesagt? (20)

PENETRATION TEST ON BITUMINOUS MATERIALS.
PENETRATION TEST ON BITUMINOUS MATERIALS.PENETRATION TEST ON BITUMINOUS MATERIALS.
PENETRATION TEST ON BITUMINOUS MATERIALS.
 
Standard Penetration Test
Standard Penetration TestStandard Penetration Test
Standard Penetration Test
 
Presentation on Determination of Penetration & Specific Gravity Test of Bitumen
Presentation on Determination of Penetration & Specific Gravity Test of BitumenPresentation on Determination of Penetration & Specific Gravity Test of Bitumen
Presentation on Determination of Penetration & Specific Gravity Test of Bitumen
 
Aggregate impact and crushing test
Aggregate impact and crushing testAggregate impact and crushing test
Aggregate impact and crushing test
 
Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 03 Determination of the flakiness and the elongation index for ...Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 03 Determination of the flakiness and the elongation index for ...
 
Unconfined compression test
Unconfined compression testUnconfined compression test
Unconfined compression test
 
Standard penetration test
Standard penetration testStandard penetration test
Standard penetration test
 
Tri axial test
Tri axial testTri axial test
Tri axial test
 
Marshall Mix Design: Lab Report
Marshall Mix Design: Lab ReportMarshall Mix Design: Lab Report
Marshall Mix Design: Lab Report
 
Permeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head MethodPermeability Test of soil Using Constant and Falling Head Method
Permeability Test of soil Using Constant and Falling Head Method
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test ppt
 
CBR Test
CBR TestCBR Test
CBR Test
 
Hand auger
Hand augerHand auger
Hand auger
 
Test On Bitumen
Test On BitumenTest On Bitumen
Test On Bitumen
 
Shape tests of aggregate
Shape tests of aggregateShape tests of aggregate
Shape tests of aggregate
 
Wash boring
Wash boringWash boring
Wash boring
 
Proktor compaction
Proktor compactionProktor compaction
Proktor compaction
 
Sieve analysis of coarse and fine aggregate - Report
Sieve analysis of coarse and fine aggregate - ReportSieve analysis of coarse and fine aggregate - Report
Sieve analysis of coarse and fine aggregate - Report
 
Design mix method of bitumenous materials by Marshall stability method
Design mix method of bitumenous materials by Marshall stability methodDesign mix method of bitumenous materials by Marshall stability method
Design mix method of bitumenous materials by Marshall stability method
 
Laboratory soil compaction test
Laboratory soil compaction testLaboratory soil compaction test
Laboratory soil compaction test
 

Ähnlich wie Penetration Test for Bitumen

PENETRATION TEST OF BITUMEN Download@notescvil.blogspot.in
PENETRATION TEST OF BITUMEN  Download@notescvil.blogspot.in PENETRATION TEST OF BITUMEN  Download@notescvil.blogspot.in
PENETRATION TEST OF BITUMEN Download@notescvil.blogspot.in SAURABH GUPTA
 
Quality control lab
Quality control labQuality control lab
Quality control labRaja Katoch
 
Transportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdfTransportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdfRESHMAFEGADE
 
production tests aging of bitumen and modified Bitumen
production tests aging of bitumen and modified Bitumen production tests aging of bitumen and modified Bitumen
production tests aging of bitumen and modified Bitumen Abhijeet Bhosale
 
Penetration of bitumious
Penetration of bitumiousPenetration of bitumious
Penetration of bitumiousTaha Samir
 
Tests of cement in concrete technology
Tests of cement in concrete technologyTests of cement in concrete technology
Tests of cement in concrete technologySunny Saha
 
Practical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptxPractical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptxLaxmiNarayanGurung
 
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Vijay Patidar
 
Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Vijay Patidar
 
Building materials lab_manual lab 01
Building materials lab_manual  lab 01Building materials lab_manual  lab 01
Building materials lab_manual lab 01Engr. Umair Razzaq
 
Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its testsKundan Sanap
 
Fineness air permeability final (1)
Fineness air permeability final (1)Fineness air permeability final (1)
Fineness air permeability final (1)Dave Madhav
 
Water Absorption of Bricks
Water Absorption of BricksWater Absorption of Bricks
Water Absorption of BricksMayur Rahangdale
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Mayur Rahangdale
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixturesTarun kumar
 
Determining the ductility of bitumen
Determining the ductility of bitumenDetermining the ductility of bitumen
Determining the ductility of bitumenpradeep tiwari
 

Ähnlich wie Penetration Test for Bitumen (20)

PENETRATION TEST OF BITUMEN Download@notescvil.blogspot.in
PENETRATION TEST OF BITUMEN  Download@notescvil.blogspot.in PENETRATION TEST OF BITUMEN  Download@notescvil.blogspot.in
PENETRATION TEST OF BITUMEN Download@notescvil.blogspot.in
 
Ii cycle
Ii cycleIi cycle
Ii cycle
 
Quality control lab
Quality control labQuality control lab
Quality control lab
 
Job 3
Job 3Job 3
Job 3
 
Cement test
Cement testCement test
Cement test
 
Transportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdfTransportation-Engg.-LABORATORY_MANUAL.pdf
Transportation-Engg.-LABORATORY_MANUAL.pdf
 
Summer training ppt
Summer training pptSummer training ppt
Summer training ppt
 
production tests aging of bitumen and modified Bitumen
production tests aging of bitumen and modified Bitumen production tests aging of bitumen and modified Bitumen
production tests aging of bitumen and modified Bitumen
 
Penetration of bitumious
Penetration of bitumiousPenetration of bitumious
Penetration of bitumious
 
Tests of cement in concrete technology
Tests of cement in concrete technologyTests of cement in concrete technology
Tests of cement in concrete technology
 
Practical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptxPractical-of-Construction-Material.pptx
Practical-of-Construction-Material.pptx
 
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012
 
Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)Buildingmaterialslabmanuallab01 161125043012 (1)
Buildingmaterialslabmanuallab01 161125043012 (1)
 
Building materials lab_manual lab 01
Building materials lab_manual  lab 01Building materials lab_manual  lab 01
Building materials lab_manual lab 01
 
Sampling of cement & its tests
Sampling of cement & its testsSampling of cement & its tests
Sampling of cement & its tests
 
Fineness air permeability final (1)
Fineness air permeability final (1)Fineness air permeability final (1)
Fineness air permeability final (1)
 
Water Absorption of Bricks
Water Absorption of BricksWater Absorption of Bricks
Water Absorption of Bricks
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
 
Determining the ductility of bitumen
Determining the ductility of bitumenDetermining the ductility of bitumen
Determining the ductility of bitumen
 

Kürzlich hochgeladen

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 

Kürzlich hochgeladen (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 

Penetration Test for Bitumen

  • 1. PENETRATION TEST Shweta Sagar & Juhita M.Tech. CTM 1st sem PENETRATION TEST OF BITUMEN
  • 2. AIM (i) To determine the consistency of the bituminous material. (ii)To assess the suitability of bitumen for use under different climatic conditions and various types of construction. PENETRATION TEST OF BITUMEN
  • 3. APPARATUS (i) Container: A flat bottomed cylindrical metallic dish 55mm in diameter and 35 mm in depth is required. If the penetration is of the order of 225 or more, dish of 70mm diameter and 45mm depth is required. (ii)Transfer dish or tray: Should provide support to the container & should not rock it. It should be of such capacity as to completely immerse container during test. PENETRATION TEST OF BITUMEN
  • 4. (iii) Water bath: Water bath maintained at 25 ± 0.1 °C, containing not less than 10 litres of water, the sample being immersed to a depth not less than 100 mm from top and supported on perforated shelf not less than 50 mm from bottom of the bath. (iv) Needle: A straight, highly polished, cylindrical hard steel rod. (v) Thermometer: Range 0°C - 44°C and in readable up to 0.20°C. PENETRATION TEST OF BITUMEN
  • 5. (vi) Penetration apparatus: Should be such that it allows needle to penetrate without much friction & is accurately calibrated to give results in one tenth of a millimeter. (vii) Time measuring device: With an accuracy of a second. PENETRATION TEST OF BITUMEN
  • 6. THEORY Penetration value is a measure of hardness or consistency of bituminous material. It is the vertical distance traversed or penetrated by the point of a standard needle in to the bituminous material under specific conditions of load, time and temperature. This distance is measured in one tenths of a millimeter. This test is used for evaluating consistency of bitumen. It is not regarded as suitable for use in connection with the testing of road tar because of the high surface tension exhibited by these materials. PENETRATION TEST OF BITUMEN
  • 7. PROCEDURE (i) Preparation of test sample: Soften the material to a pouring consistency at a temperature not more than 60°C for tars and 90°C for bitumen above the approximate softening point and stir it thoroughly until it is homogeneous and is free from air bubbles and water. Pour the melt into the container to a depth at least 10mm in excess of the expected penetration. Protect the sample from dust and allow it to cool in an atmosphere at a temperature between 15°C to 30°C for one hour. Then place it along with the transfer dish in the water bath at 25°C ± 0.1°C, unless otherwise stated. PENETRATION TEST OF BITUMEN
  • 8. (ii) Fill the transfer dish with water from the water bath to depth sufficient to cover the container completely, place the sample in it and put it upon the stand of the penetration apparatus. (iii) Clean the needle with benzene, dry it and load with the weight. The total moving load required is 100 ± 0.25 grams, including the weight of the needle, carrier and super-imposed weights. (iv) Adjust the needle to make contact with the surface of the sample. This may be done by placing the needlepoint in contact with its image reflected by the surface of the bituminous material. PENETRATION TEST OF BITUMEN
  • 9. (v) Make the pointer of the dial to read zero or note the initial dial reading. (vi) Release the needle for exactly five seconds. (vii) Adjust the penetration machine to measure the distance penetrated. PENETRATION TEST OF BITUMEN
  • 10. (viii) Make at least 3 readings at points on the surface of the sample not less than 10 mm apart and not less than l0mm from the side of the dish. After each test return the sample and transfer dish to the water bath and wash the needle clean with benzene and dry it. In case of material of penetration greater than 225, three determinations on each of the two identical test specimens using a separate needle for each determination should be made, leaving the needle in the sample on completion of each determination to avoid disturbance of the specimen. PENETRATION TEST OF BITUMEN
  • 12. RECORD OF OBSERVATION PENETRATION TEST OF BITUMEN PENETROMETER DIAL READING TEST 1 TEST 2 TEST 3 (A) Initial 200 264 333 (B) Final 264 333 407 PENETRATION VALUE 64 69 74 Actual Test Temperature(°C) = 25°C Mean Penetration Value = 69
  • 13. RECOMMENDED VALUE AS PER IS CODE 73:2006 PENETRATION TEST OF BITUMEN BITUMEN GRADE PENETRATION VALUE A-35 30-40 A-45 40-50 A-55 50-60 A-65 60-70 A-90 80-100 A-200 175-225
  • 14. PENETRATION TEST OF BITUMEN Download@notescvil.blogspot.in PENETRATION TEST OF BITUMEN
  • 15. PRECAUTION (i) There should be no movement of the container while needle penetrates into sample. (ii) The sample should be free from any extraneous matter. (iii) The needle should be cleaned with benzene and dried before penetration. PENETRATION TEST OF BITUMEN
  • 16. PENETRATION TEST OF BITUMEN Thank You