SlideShare ist ein Scribd-Unternehmen logo
1 von 29
PERT & CPM
SUBMITTED BY:-
SHASHANK KAPOOR
MECHANICAL , 154169
What isthe PERT&CPM?
It is nothing but the technique used in Network analysis
of project management, such as planning ,
management and control of project.
So, what is project ??
“A project is a series of activities directed
to accomplishment of a desired objective.”
Plan your work first…..then work your plan
Project Evaluation & Review
Techniques
(PERT)
In PERT is basicallyamethod to analyze the tasks involved in
completing agiven project,especially the time neededto completeeachtask,
and to identify the minimum time neededto complete the total project.
– Multiple time estimates
– Probabilistic activity times
USED IN : Project management - for non-repetitive jobs
(research and development work), where the time and cost
estimates tend to be quite uncertain. This technique uses
probabilistic time estimates.
Critical Path Method
(CPM)
In CPM activities are shown as a network of
precedence relationships using activity-on-node network
construction.
– Single estimate of activity time
– Deterministic activity times
USED IN : Production management - for the jobs of
repetitive in nature where the activity time
estimates can be predicted with considerable
certainty due to the existence of past experience.
KEY ELEMENTS
 Arrows:- leading from tail to head directionally Indicate
Activity
 Nodes:- Indicate Event, a point in time where one or more activities start
and/or finish.
 Earliest time:It is categorized in two sub elements.
1. Earliest Starting time (ES):-Time at which the activity can
start
2. Earliest finishing time(EF):-Equals to the earliest start time
for the activity plus the time required to complete the
activity
 Latest time :It is categorized in two sub elements.
1.Latest Starting time (LS):-Time in which the activity can be
completed without delaying
2.Latest Finishing time (LF):-equal to the latest finish time minus the time
required to complete the activity.
 Slack time:-The difference between its earliest and latest start time.
 Critical Path:-The path of activities having zero Slack time.
KEY ELEMENTS
 Optimistic time (a): – It is the shortest time in which the activity
can be completed.
 Most likely time (m) – It is the probable time required to perform
the activity.
 Pessimistic time (b)– It is the longest estimated time required to
perform an activity .
 Expected time (Te) – approximation time taken to complete an
activity.
Te=
𝒂+𝟒𝒎+𝒃
𝟔
 Standard deviation ( ) – Higher the SD is the greater amount of
uncertainty exists
 Variance (𝝈 𝟐
) − Large variance indicates great uncertainty, a small
variance indicates a more accurate estimate
=
𝑏−𝑎
6
ILLUSTRATION ON PERT
SOLUTION
Activity Optimistic
Time (a)
Most
likely
Time(m)
Pessimisti
c Time (b)
Expected
Time (Te)
Standard
Deviation
1-2 1 1 7 2 1
1-3 1 4 7 4 1
1-4 2 2 8 3 1
2-5 1 1 1 1 0
3-5 2 5 14 6 2
4-6 2 5 8 5 1
5-6 3 6 15 7 2
SOLUTION
CRITICAL PATH
 Paths:-
1-2-5-6 = 2+1+7=10
1-3-5-6 = 4+6+7=17
1-4-6 = 3+5=8
 1-3-5-6 is critical path since it take maximum time.
CRITICAL PATH
NODE LC-ES TOTAL
1 0-0 0
2 9-2 7
3 4-4 0
4 12-3 9
5 10-10 0
6 17-17 0
On Analyzing the Node which having total =0 is 1-3-5-6
Hence it is critical path
PROBABILISTIC
DETERMINATION
 What isthe Probability of it taking20 weeks?
CriticalPath=1-3-5-6=17weeks
T =20 weeks C=17 weeks
𝑧 = 𝑇−𝐶
𝜎2
(Variance) 𝜎2 = 1 + 4 + 4 = 9
𝑧 = 20−17
9
= 1
Lookup Zvalue in normal distribution table
Pz=0.8413 or 84.13%
Goingover 20 weeks would be 100 – 84.13 = 15.87%
(Probability of ittaking 20 weeks)
ILLUSTRATION ON CPM
SOLUTION
SOLUTION
SOLUTION
SOLUTION
SOLUTION
SOLUTION
SOLUTION
SOLUTION
SOLUTION
SOLUTION
SOLUTION
CRITICAL PATH
 Paths:-
 1-2-5-7-8=2+1+2+1=6 days
 1-3-5-7-8=3+2+2+1=8 days
 1-3-6-7-8=3+5+3+1=12days
 1-4-6-7-8=4+7+3+1=15 days
1-4-6-7-8 is critical path since it take maximum
time.
CRITICAL PATH
NODE LC-ES TOTAL
1 0-0 0
2 11-2 9
3 6-3 3
4 4-4 0
5 12-5 7
6 11-11 0
7 14-14 0
8 15-15 0
On Analyzing the Node which having total =0 is 1-4-6-7-8
Hence it is critical path
What happen if we have large
number of Network problem??
Conclusion
 For large number of network problem Ford
Fulkerson Max Flow Algorithm is the point
that can give us the optimal critical path
since it is use for finding the maximum flow
in a flow network for single source and single
sink.
THANK YOU

Weitere ähnliche Inhalte

Was ist angesagt?

Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN PanigrahiSN Panigrahi, PMP
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Project management Pert & cpm
Project management Pert & cpm Project management Pert & cpm
Project management Pert & cpm RandhirKumar172
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt chartsVARSHA RUSTAGI
 
Cpm and pert - project management
Cpm and pert - project managementCpm and pert - project management
Cpm and pert - project managementExam Coach
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 

Was ist angesagt? (20)

Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Project management Pert & cpm
Project management Pert & cpm Project management Pert & cpm
Project management Pert & cpm
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Cpm and pert - project management
Cpm and pert - project managementCpm and pert - project management
Cpm and pert - project management
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 

Ähnlich wie Pert and cpm

Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpasyamputra
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii referenceahsanrabbani
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.pptNitin137794
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLSiddanna Balapgol
 
[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path MethodMichele Palumbo
 
ManSciProjMan-CPM.pptx
ManSciProjMan-CPM.pptxManSciProjMan-CPM.pptx
ManSciProjMan-CPM.pptxssuser85ddaa
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptxHimanshuKaklotar1
 
Management science
Management scienceManagement science
Management sciencekamrul islam
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 RevisionJoyce Wong
 

Ähnlich wie Pert and cpm (20)

Cpm pert
Cpm pertCpm pert
Cpm pert
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method
 
PM-Problems.pptx
PM-Problems.pptxPM-Problems.pptx
PM-Problems.pptx
 
ManSciProjMan-CPM.pptx
ManSciProjMan-CPM.pptxManSciProjMan-CPM.pptx
ManSciProjMan-CPM.pptx
 
Pert
PertPert
Pert
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 
Management science
Management scienceManagement science
Management science
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 Revision
 

Mehr von Shashank Kapoor

Rural engineering process : Development of farms by automation
Rural engineering process : Development of  farms by automationRural engineering process : Development of  farms by automation
Rural engineering process : Development of farms by automationShashank Kapoor
 
Design and analysis of polar, cartesian and delta 3d printer
Design and analysis of polar, cartesian and delta 3d printerDesign and analysis of polar, cartesian and delta 3d printer
Design and analysis of polar, cartesian and delta 3d printerShashank Kapoor
 
Multi processor scheduling
Multi  processor schedulingMulti  processor scheduling
Multi processor schedulingShashank Kapoor
 
Nano 3d printing : Two Photon lithography
Nano 3d printing : Two Photon lithographyNano 3d printing : Two Photon lithography
Nano 3d printing : Two Photon lithographyShashank Kapoor
 
MQTT Protocol: IOT Technology
MQTT Protocol: IOT TechnologyMQTT Protocol: IOT Technology
MQTT Protocol: IOT TechnologyShashank Kapoor
 
Real time Canny edge detection
Real time Canny edge detectionReal time Canny edge detection
Real time Canny edge detectionShashank Kapoor
 
Training report of C language
Training report of C languageTraining report of C language
Training report of C languageShashank Kapoor
 
Real time heart monitoring system
Real time heart monitoring systemReal time heart monitoring system
Real time heart monitoring systemShashank Kapoor
 
IFTTT: If This Then That
IFTTT: If This Then ThatIFTTT: If This Then That
IFTTT: If This Then ThatShashank Kapoor
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and CpmShashank Kapoor
 
Bushed pin flange coupling
Bushed pin flange couplingBushed pin flange coupling
Bushed pin flange couplingShashank Kapoor
 
Jigs and there application
Jigs and there applicationJigs and there application
Jigs and there applicationShashank Kapoor
 
Air cooling of electrical equipments
Air cooling of electrical equipmentsAir cooling of electrical equipments
Air cooling of electrical equipmentsShashank Kapoor
 
Mach Number and Shock waves
Mach Number and Shock waves Mach Number and Shock waves
Mach Number and Shock waves Shashank Kapoor
 

Mehr von Shashank Kapoor (15)

Rural engineering process : Development of farms by automation
Rural engineering process : Development of  farms by automationRural engineering process : Development of  farms by automation
Rural engineering process : Development of farms by automation
 
Design and analysis of polar, cartesian and delta 3d printer
Design and analysis of polar, cartesian and delta 3d printerDesign and analysis of polar, cartesian and delta 3d printer
Design and analysis of polar, cartesian and delta 3d printer
 
Cfc’s and hcfc’s
Cfc’s and hcfc’sCfc’s and hcfc’s
Cfc’s and hcfc’s
 
Multi processor scheduling
Multi  processor schedulingMulti  processor scheduling
Multi processor scheduling
 
Nano 3d printing : Two Photon lithography
Nano 3d printing : Two Photon lithographyNano 3d printing : Two Photon lithography
Nano 3d printing : Two Photon lithography
 
MQTT Protocol: IOT Technology
MQTT Protocol: IOT TechnologyMQTT Protocol: IOT Technology
MQTT Protocol: IOT Technology
 
Real time Canny edge detection
Real time Canny edge detectionReal time Canny edge detection
Real time Canny edge detection
 
Training report of C language
Training report of C languageTraining report of C language
Training report of C language
 
Real time heart monitoring system
Real time heart monitoring systemReal time heart monitoring system
Real time heart monitoring system
 
IFTTT: If This Then That
IFTTT: If This Then ThatIFTTT: If This Then That
IFTTT: If This Then That
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and Cpm
 
Bushed pin flange coupling
Bushed pin flange couplingBushed pin flange coupling
Bushed pin flange coupling
 
Jigs and there application
Jigs and there applicationJigs and there application
Jigs and there application
 
Air cooling of electrical equipments
Air cooling of electrical equipmentsAir cooling of electrical equipments
Air cooling of electrical equipments
 
Mach Number and Shock waves
Mach Number and Shock waves Mach Number and Shock waves
Mach Number and Shock waves
 

Kürzlich hochgeladen

Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxPurva Nikam
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 

Kürzlich hochgeladen (20)

Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 

Pert and cpm

  • 1. PERT & CPM SUBMITTED BY:- SHASHANK KAPOOR MECHANICAL , 154169
  • 2. What isthe PERT&CPM? It is nothing but the technique used in Network analysis of project management, such as planning , management and control of project. So, what is project ?? “A project is a series of activities directed to accomplishment of a desired objective.” Plan your work first…..then work your plan
  • 3. Project Evaluation & Review Techniques (PERT) In PERT is basicallyamethod to analyze the tasks involved in completing agiven project,especially the time neededto completeeachtask, and to identify the minimum time neededto complete the total project. – Multiple time estimates – Probabilistic activity times USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
  • 4. Critical Path Method (CPM) In CPM activities are shown as a network of precedence relationships using activity-on-node network construction. – Single estimate of activity time – Deterministic activity times USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.
  • 5. KEY ELEMENTS  Arrows:- leading from tail to head directionally Indicate Activity  Nodes:- Indicate Event, a point in time where one or more activities start and/or finish.  Earliest time:It is categorized in two sub elements. 1. Earliest Starting time (ES):-Time at which the activity can start 2. Earliest finishing time(EF):-Equals to the earliest start time for the activity plus the time required to complete the activity  Latest time :It is categorized in two sub elements. 1.Latest Starting time (LS):-Time in which the activity can be completed without delaying 2.Latest Finishing time (LF):-equal to the latest finish time minus the time required to complete the activity.  Slack time:-The difference between its earliest and latest start time.  Critical Path:-The path of activities having zero Slack time.
  • 6. KEY ELEMENTS  Optimistic time (a): – It is the shortest time in which the activity can be completed.  Most likely time (m) – It is the probable time required to perform the activity.  Pessimistic time (b)– It is the longest estimated time required to perform an activity .  Expected time (Te) – approximation time taken to complete an activity. Te= 𝒂+𝟒𝒎+𝒃 𝟔  Standard deviation ( ) – Higher the SD is the greater amount of uncertainty exists  Variance (𝝈 𝟐 ) − Large variance indicates great uncertainty, a small variance indicates a more accurate estimate = 𝑏−𝑎 6
  • 8. SOLUTION Activity Optimistic Time (a) Most likely Time(m) Pessimisti c Time (b) Expected Time (Te) Standard Deviation 1-2 1 1 7 2 1 1-3 1 4 7 4 1 1-4 2 2 8 3 1 2-5 1 1 1 1 0 3-5 2 5 14 6 2 4-6 2 5 8 5 1 5-6 3 6 15 7 2
  • 10. CRITICAL PATH  Paths:- 1-2-5-6 = 2+1+7=10 1-3-5-6 = 4+6+7=17 1-4-6 = 3+5=8  1-3-5-6 is critical path since it take maximum time.
  • 11. CRITICAL PATH NODE LC-ES TOTAL 1 0-0 0 2 9-2 7 3 4-4 0 4 12-3 9 5 10-10 0 6 17-17 0 On Analyzing the Node which having total =0 is 1-3-5-6 Hence it is critical path
  • 12. PROBABILISTIC DETERMINATION  What isthe Probability of it taking20 weeks? CriticalPath=1-3-5-6=17weeks T =20 weeks C=17 weeks 𝑧 = 𝑇−𝐶 𝜎2 (Variance) 𝜎2 = 1 + 4 + 4 = 9 𝑧 = 20−17 9 = 1 Lookup Zvalue in normal distribution table Pz=0.8413 or 84.13% Goingover 20 weeks would be 100 – 84.13 = 15.87% (Probability of ittaking 20 weeks)
  • 25. CRITICAL PATH  Paths:-  1-2-5-7-8=2+1+2+1=6 days  1-3-5-7-8=3+2+2+1=8 days  1-3-6-7-8=3+5+3+1=12days  1-4-6-7-8=4+7+3+1=15 days 1-4-6-7-8 is critical path since it take maximum time.
  • 26. CRITICAL PATH NODE LC-ES TOTAL 1 0-0 0 2 11-2 9 3 6-3 3 4 4-4 0 5 12-5 7 6 11-11 0 7 14-14 0 8 15-15 0 On Analyzing the Node which having total =0 is 1-4-6-7-8 Hence it is critical path
  • 27. What happen if we have large number of Network problem??
  • 28. Conclusion  For large number of network problem Ford Fulkerson Max Flow Algorithm is the point that can give us the optimal critical path since it is use for finding the maximum flow in a flow network for single source and single sink.