SlideShare ist ein Scribd-Unternehmen logo
1 von 43
PROJECT SCHEDULING
Prepared by
Shahrukh Vahora (160113105009)
Subject: Plant Design & Project Engineering
Department of chemical engineering
G H Patel College of Engineering & Technology
V.V.Nagar
1
CONTENT
• Introduction
• Task Designate
• Identifying the Activities of a Project
• Exmaple
• The PERT/CPM Approach for
Project Scheduling
2
Introduction
• A project is a collection of tasks that must be
completed in minimum time or at minimal cost.
• Objectives of Project Scheduling
• Completing the project as early as possible by determining
the earliest start and finish of each activity.
• Calculating the likelihood a project will be completed
within a certain time period.
• Finding the minimum cost schedule needed to complete
the project by a certain date.
3
• A project is a collection of tasks that must be
completed in minimum time or at minimal cost.
• Objectives of Project Scheduling
4
– Investigating the results of possible delays in activity’sInvestigating the results of possible delays in activity’s
completion time.completion time.
– Progress control.Progress control.
– Smoothing out resource allocation over the duration ofSmoothing out resource allocation over the duration of
the project.the project.
Task Designate
• Tasks are called “activities.”
• Estimated completion time (and sometimes costs)
are associated with each activity.
• Activity completion time is related to the amount of
resources committed to it.
• The degree of activity details depends on the
application and the level of specificity of data.
5
Identifying the Activities of a
Project
• To determine optimal schedules we need to
• Identify all the project’s activities.
• Determine the precedence relations among activities.
• Based on this information we can develop managerial
tools for project control.
6
Identifying Activities, Example
KLONE COMPUTERS, INC.
• KLONE Computers manufactures personal computers.
• It is about to design, manufacture, and market the
Klonepalm 2000 palmbook computer.
7
EXMAPLE OF KLONE COMPUTERS
8
• There are three major tasks to perform:There are three major tasks to perform:
– Manufacture the new computer.Manufacture the new computer.
– Train staff and vendor representatives.Train staff and vendor representatives.
– Advertise the new computer.Advertise the new computer.
• KLONE needs to develop a precedence relationsKLONE needs to develop a precedence relations
chart.chart.
• The chart gives a concise set of tasks and theirThe chart gives a concise set of tasks and their
immediate predecessors.immediate predecessors.
KLONE COMPUTERS, INC
9
Activity Description
A Prototype model design
B Purchase of materials
Manufacturing C Manufacture of prototype model
activities D Revision of design
E Initial production run
Activity Description
A Prototype model design
B Purchase of materials
Manufacturing C Manufacture of prototype model
activities D Revision of design
E Initial production run
F Staff training
Training activities G Staff input on prototype models
H Sales training
F Staff training
Training activities G Staff input on prototype models
H Sales training
Advertising activities I Pre-production advertising
campaign
J Post-redesign advertising campaign
Advertising activities I Pre-production advertising
campaign
J Post-redesign advertising campaign
KLONE COMPUTERS, INC
From the activity description chart,
we can determine immediate
predecessors for each activity.
10
Activity A is an immediate predecessor
of activity B, because it must be competed
just prior to the commencement of B.
A B
KLONE COMPUTERS, INC
11
Immediate Estimated
Activity Predecessor Completion Time
A None 90
B A 15
C B 5
D G 20
E D 21
F A 25
G C,F 14
H D 28
I A 30
J D,I 45
Precedence Relationships Chart
The PERT/CPM Approach for
Project Scheduling
• The PERT/CPM approach to project scheduling
uses network presentation of the project to
• Reflect activity precedence relations
• Activity completion time
• PERT/CPM is used for scheduling activities such
that the project’s completion time is minimized.
12
KLONE COMPUTERS, INC. - Continued
• Management at KLONE would like to schedule the
activities so that the project is completed in minimal time.
• Management wishes to know:
• The earliest and latest start times for each activity which will not
alter the earliest completion time of the project.
• The earliest finish times for each activity which will not alter this
date.
• Activities with rigid schedule and activities that have slack in their
schedules.
13
Earliest Start Time / Earliest Finish
Time
• Make a forward pass through the network as follows:
• Evaluate all the activities which have no immediate
predecessors.
• The earliest start for such an activity is zero ES = 0.
• The earliest finish is the activity duration EF = Activity duration.
• Evaluate the ES of all the nodes for which EF of all the
immediate predecessor has been determined.
• ES = Max EF of all its immediate predecessors.
• EF = ES + Activity duration.
• Repeat this process until all nodes have been evaluated
• EF of the finish node is the earliest finish time of the project.
14
Earliest Start / Earliest Finish –
Forward Pass
15
A
90
B
15
C
5
F
25
I
30
G
14
D
20
E
21
H
28
J
45
90,105
90,115
90,120
105,110
110,124
115,129 129,149
149,170
149,177
120,165
149,194
170
194
A
0,90
B
I
F
C
G D
E
H
J
177
194
EARLIEST FINISH
Latest start time / Latest finish
time
• Make a backward pass through the network as
follows:
• Evaluate all the activities that immediately precede the
finish node.
• The latest finish for such an activity is LF = minimal project
completion time.
• The latest start for such an activity is LS = LF - activity duration.
• Evaluate the LF of all the nodes for which LS of all the
immediate successors has been determined.
• LF = Min LS of all its immediate successors.
• LS = LF - Activity duration.
• Repeat this process backward until all nodes have been
evaluated.
16
Latest Start / Latest Finish –
Backward Pass
17
B
F
C
A
I
E
DG H
H
28
166,194
J
J
45
149,194
E
21
173,194
90,105
90,115
90,120
105,110
115,129 129,149
149,170
149,177
149,194
153,173
146,166
194
129,149
0,90
129,149
D
20
129,149
129,149
129,149
129,149
129,149
129,149
129,149
G
14
115,129
I
30
119,149
29,119
C
5
110,115B
1595,110
5,95
F
25
90, 115
0,90A
90
Slack Times
• Activity start time and completion time may be delayed
by planned reasons as well as by unforeseen reasons.
• Some of these delays may affect the overall completion
date.
• To learn about the effects of these delays, we calculate
the slack time, and form the critical path.
18
Slack Times
• Slack time is the amount of time an activity can be delayed
without delaying the project completion date, assuming no
other delays are taking place in the project.
19
Slack Time = LS - ES = LF - EF
20
Critical activities
must be rigidly
scheduled
Critical activities
must be rigidly
scheduled
Activity LS - ES Slack
A 0 -0 0
B 95 - 90 5
C 110 - 105 5
D 119 - 119 0
E 173 - 149 24
F 90 - 90 0
G 115 - 115 0
H 166 - 149 17
I 119 - 90 29
J 149 - 149 0
Slack time in the Klonepalm 2000 Project
The Critical Path
• The critical path is a set of activities that have no slack,
connecting the START node with the FINISH node.
• The critical activities (activities with 0 slack) form
at least one critical path in the network.
• A critical path is the longest path in the network.
• The sum of the completion times for the activities
on the critical path is the minimal completion time
of the project.
21
The Critical Path
22
B
F
C
A
I
E
DG H
H
28
166,194
J
J
45
149,194
E
21
173,194
90,105
90,115
90,120
105,110
115,129 129,149
149,170
149,177
149,194
D
20
0,90
129,149
G
14
115,129
I
30
119,149
A
90
C
5
110,115B
15
95,110
F
25
90, 1150,90
Possible Delays
• We observe two different types of delays:
• Single delays.
• Multiple delays.
• Under certain conditions the overall project completion
time will be delayed.
• The conditions that specify each case are presented
next.
23
Single delays
• A delay of a certain amount in a critical activity, causes
the entire project to be delayed by the same amount.
• A delay of a certain amount in a non-critical activity will
delay the project by the amount the delay exceeds the
slack time. When the delay is less than the slack, the
entire project is not delayed.
24
Gantt Charts
• Gantt charts are used as a tool to monitor and control the
project progress.
• A Gantt Chart is a graphical presentation that displays
activities as follows:
• Time is measured on the horizontal axis. A horizontal bar is
drawn proportionately to an activity’ s expected completion time.
• Each activity is listed on the vertical axis.
• In an earliest time Gantt chart each bar begins and ends at
the earliest start/finish the activity can take place.
25
Gantt Charts-
Monitoring Project Progress
• Gantt chart can be used as a visual aid for tracking the
progress of project activities.
• Appropriate percentage of a bar is shaded to document
the completed work.
• The manager can easily see if the project is progressing on
schedule (with respect to the earliest possible completion
times).
26
Gantt Charts –
Advantages and Disadvantages
• Advantages.
• Easy to construct
• Gives earliest completion date.
• Provides a schedule of earliest possible start and finish times
of activities.
• Disadvantages
• Gives only one possible schedule (earliest).
• Does not show whether the project is behind schedule.
• Does not demonstrate the effects of delays in any one activity
on the
start of another activity, thus on the project completion time.
27
The Probability Approach to
Project Scheduling
• Activity completion times are seldom known with
100% accuracy.
• PERT is a technique that treats activity completion
times as random variables.
• Completion time estimates are obtained by the
Three Time Estimate approach
28
The Probability Approach –
Three Time Estimates
29
• The TThe Three Time Estimatehree Time Estimate approachapproach providesprovides
completion time estimate for each activity.completion time estimate for each activity.
• We use the notation:We use the notation:
a = an optimistic time to perform the activity.a = an optimistic time to perform the activity.
m = the most likely time to perform the activity.m = the most likely time to perform the activity.
b = a pessimistic time to perform the activity.b = a pessimistic time to perform the activity.
30
Âľ
σ
= the mean completion time =
a + 4m+ b
6
= the standard deviation =
b -a
6
Approximations for the mean and the standardApproximations for the mean and the standard
deviation of activity completion time are based on thedeviation of activity completion time are based on the
BetaBeta distribution.distribution.
The Distribution, Mean, and StandardThe Distribution, Mean, and Standard
Deviation of an ActivityDeviation of an Activity
The Project Completion Time
Distribution - Assumptions
31
To calculate the mean and standard
deviation of the project completion time
we make some simplifying assumptions.
The Project Completion Time
Distribution - Assumptions
• Assumption 2
• The time to complete one activity is independent of the
time to complete any other activity.
• Assumption 3
• There are enough activities on the critical path so that
the distribution of the overall project completion time
can be approximated by the normal distribution.
32
• Assumption 1Assumption 1
– A critical path can be determined by using the meanA critical path can be determined by using the mean
completion times for the activities.completion times for the activities.
– The project mean completion time is determined solely by theThe project mean completion time is determined solely by the
completion time of the activities on the critical path.completion time of the activities on the critical path.
The Project Completion Time
Distribution
The three assumptions imply that the overall project
completion time is normally distributed, the
following parameters:
33
Mean = Sum of mean completion times along
the critical path.
Variance = Sum of completion time variances
along the critical path.
Standard deviation = √Variance
The Probability Approach –
KLONE COMPUTERS
34
Activity Optimistic Most Likely Pessimistic
A 76 86 120
B 12 15 18
C 4 5 6
D 15 18 33
E 18 21 24
F 16 26 30
G 10 13 22
H 24 18 32
I 22 27 50
J 38 43 60
The Probability Approach –
KLONE COMPUTERS
• Management at KLONE is interested in information
regarding the completion time of the project.
• The probabilistic nature of the completion time
must be considered.
35
KLONE COMPUTERS –
Finding activities’ mean and variance
ÂľA =[76+4(86)+120]/6 = 90
σΑ = (120 - 76)/6 = 7.33 σA
2
= (7.33)2
= 53.78
36
Activity ¾ σ
A 90 7.33 53.78
B 15 1.00 1.00
C 5 0.33 0.11
D 20 3.00 9.00
E 21 1.00 1.00
F 25 2.33 5.44
G 14 2.00 4.00
H 28 1.33 1.78
I 30 4.67 21.78
J 45 3.67 13.44
σ2
KLONE COMPUTERS –
Finding mean and variance for the critical
path
• The mean times are the same as in the CPM problem,
previously solved for KLONE.
• Thus, the critical path is A - F- G - D – J.
• Expected completion time =µA +µF +µG +µD +µJ=194.
• The project variance =σA
2
+σF
2
+σG
2
+σD
2
+σJ
2
= 85.66
• The standard deviation = = 9.255
37
σ2
The Probability Approach –
Critical path spreadsheet
38
MEAN 194
STANDARD DEVIATION* 9.255629 * Assumes all critical activities are on one critical path
VARIANCE* 85.66667 If not, enter in gold box, the variance on one critical path of interest.
PROBABILITY COMPLETE BEFORE 180 = 0.065192
Acitivty Node Critical ¾ σ σ2
ES EF LS LF Slack
Design A * 90 7.333333 53.77778 0 90 0 90 0
Materials B 15 1 1 90 105 95 110 5
Manufacture C 5 0.333333 0.111111 105 110 110 115 5
Design Revision D * 20 3 9 129 149 129 149 0
Production Run E 21 1 1 149 170 173 194 24
Staff Training F * 25 2.333333 5.444444 90 115 90 115 0
Staff Input G * 14 2 4 115 129 115 129 0
Sales Training H 28 1.333333 1.777778 149 177 166 194 17
Preprod. Advertise I 30 4.666667 21.77778 90 120 119 149 29
Post. Advertise J * 45 3.666667 13.44444 149 194 149 194 0
CRITICAL PATH ANALYSIS
Cost Analyses Using
The Critical Path Method (CPM)
• The critical path method (CPM) is a deterministic
approach to project planning.
• Completion time depends only on the amount of
money allocated to activities.
• Reducing an activity’s completion time is called
“crashing.”
39
Crash time/Crash cost
• There are two crucial completion times to consider
for each activity.
• Normal completion time (TN).
• Crash completion time (TC), the minimum possible
completion time.
40
• The cost spent on an activity varies between
– Normal cost (CN). The activity is completed in TN.
– Crash cost (CC). The activity is completed in TC.
Crash time/Crash cost –
The Linearity Assumption
• The maximum crashing of activity completion time
is TC– TN.
• This can be achieved when spending CN – CC.
• Any percentage of the maximum extra cost
(CN – CC)spent to crash an activity, yields the same
percentage reduction of the maximum time savings
(TC– TN).
41
REFERENCES
• PLANT DESIGN AND ECONOMICS FOR CHEMICAL ENGINEER- 4TH
EDITION ,
CHAPTER-11,
BY- MAX S PETER, KLAUS D TIMMERHAUS
42
•THANK YOU
43

Weitere ähnliche Inhalte

Was ist angesagt?

Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and TechniquesMaRS Discovery District
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
Project Scheduling
Project SchedulingProject Scheduling
Project SchedulingCiprian Rusen
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Managementdyaksa hanindito
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Pert
PertPert
Pertcorvinno
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTÚng Trần Thanh
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoringharoldtaylor1113
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project schedulingHarSimaranSinghBhamr
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
 

Was ist angesagt? (20)

Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Pert
PertPert
Pert
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 

Ähnlich wie PROJECT SCHEDULING

Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chaintanishkagupta907
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingSyed Hamza
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptxSougata Das
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdfJerryHung19
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
project network
project networkproject network
project networkSougata Das
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.pptUtkarshDwivedi74
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptxssuserbc5970
 
Project management techniques
Project management techniquesProject management techniques
Project management techniquesRagjni Govindaraju
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 

Ähnlich wie PROJECT SCHEDULING (20)

Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
 
Project Scheduling.ppt
Project Scheduling.pptProject Scheduling.ppt
Project Scheduling.ppt
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project scheduling
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
project network
project networkproject network
project network
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.ppt
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 

KĂźrzlich hochgeladen

Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSrknatarajan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 

KĂźrzlich hochgeladen (20)

Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICSUNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
UNIT-IFLUID PROPERTIES & FLOW CHARACTERISTICS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 

PROJECT SCHEDULING

  • 1. PROJECT SCHEDULING Prepared by Shahrukh Vahora (160113105009) Subject: Plant Design & Project Engineering Department of chemical engineering G H Patel College of Engineering & Technology V.V.Nagar 1
  • 2. CONTENT • Introduction • Task Designate • Identifying the Activities of a Project • Exmaple • The PERT/CPM Approach for Project Scheduling 2
  • 3. Introduction • A project is a collection of tasks that must be completed in minimum time or at minimal cost. • Objectives of Project Scheduling • Completing the project as early as possible by determining the earliest start and finish of each activity. • Calculating the likelihood a project will be completed within a certain time period. • Finding the minimum cost schedule needed to complete the project by a certain date. 3
  • 4. • A project is a collection of tasks that must be completed in minimum time or at minimal cost. • Objectives of Project Scheduling 4 – Investigating the results of possible delays in activity’sInvestigating the results of possible delays in activity’s completion time.completion time. – Progress control.Progress control. – Smoothing out resource allocation over the duration ofSmoothing out resource allocation over the duration of the project.the project.
  • 5. Task Designate • Tasks are called “activities.” • Estimated completion time (and sometimes costs) are associated with each activity. • Activity completion time is related to the amount of resources committed to it. • The degree of activity details depends on the application and the level of specificity of data. 5
  • 6. Identifying the Activities of a Project • To determine optimal schedules we need to • Identify all the project’s activities. • Determine the precedence relations among activities. • Based on this information we can develop managerial tools for project control. 6
  • 7. Identifying Activities, Example KLONE COMPUTERS, INC. • KLONE Computers manufactures personal computers. • It is about to design, manufacture, and market the Klonepalm 2000 palmbook computer. 7
  • 8. EXMAPLE OF KLONE COMPUTERS 8 • There are three major tasks to perform:There are three major tasks to perform: – Manufacture the new computer.Manufacture the new computer. – Train staff and vendor representatives.Train staff and vendor representatives. – Advertise the new computer.Advertise the new computer. • KLONE needs to develop a precedence relationsKLONE needs to develop a precedence relations chart.chart. • The chart gives a concise set of tasks and theirThe chart gives a concise set of tasks and their immediate predecessors.immediate predecessors.
  • 9. KLONE COMPUTERS, INC 9 Activity Description A Prototype model design B Purchase of materials Manufacturing C Manufacture of prototype model activities D Revision of design E Initial production run Activity Description A Prototype model design B Purchase of materials Manufacturing C Manufacture of prototype model activities D Revision of design E Initial production run F Staff training Training activities G Staff input on prototype models H Sales training F Staff training Training activities G Staff input on prototype models H Sales training Advertising activities I Pre-production advertising campaign J Post-redesign advertising campaign Advertising activities I Pre-production advertising campaign J Post-redesign advertising campaign
  • 10. KLONE COMPUTERS, INC From the activity description chart, we can determine immediate predecessors for each activity. 10 Activity A is an immediate predecessor of activity B, because it must be competed just prior to the commencement of B. A B
  • 11. KLONE COMPUTERS, INC 11 Immediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E D 21 F A 25 G C,F 14 H D 28 I A 30 J D,I 45 Precedence Relationships Chart
  • 12. The PERT/CPM Approach for Project Scheduling • The PERT/CPM approach to project scheduling uses network presentation of the project to • Reflect activity precedence relations • Activity completion time • PERT/CPM is used for scheduling activities such that the project’s completion time is minimized. 12
  • 13. KLONE COMPUTERS, INC. - Continued • Management at KLONE would like to schedule the activities so that the project is completed in minimal time. • Management wishes to know: • The earliest and latest start times for each activity which will not alter the earliest completion time of the project. • The earliest finish times for each activity which will not alter this date. • Activities with rigid schedule and activities that have slack in their schedules. 13
  • 14. Earliest Start Time / Earliest Finish Time • Make a forward pass through the network as follows: • Evaluate all the activities which have no immediate predecessors. • The earliest start for such an activity is zero ES = 0. • The earliest finish is the activity duration EF = Activity duration. • Evaluate the ES of all the nodes for which EF of all the immediate predecessor has been determined. • ES = Max EF of all its immediate predecessors. • EF = ES + Activity duration. • Repeat this process until all nodes have been evaluated • EF of the finish node is the earliest finish time of the project. 14
  • 15. Earliest Start / Earliest Finish – Forward Pass 15 A 90 B 15 C 5 F 25 I 30 G 14 D 20 E 21 H 28 J 45 90,105 90,115 90,120 105,110 110,124 115,129 129,149 149,170 149,177 120,165 149,194 170 194 A 0,90 B I F C G D E H J 177 194 EARLIEST FINISH
  • 16. Latest start time / Latest finish time • Make a backward pass through the network as follows: • Evaluate all the activities that immediately precede the finish node. • The latest finish for such an activity is LF = minimal project completion time. • The latest start for such an activity is LS = LF - activity duration. • Evaluate the LF of all the nodes for which LS of all the immediate successors has been determined. • LF = Min LS of all its immediate successors. • LS = LF - Activity duration. • Repeat this process backward until all nodes have been evaluated. 16
  • 17. Latest Start / Latest Finish – Backward Pass 17 B F C A I E DG H H 28 166,194 J J 45 149,194 E 21 173,194 90,105 90,115 90,120 105,110 115,129 129,149 149,170 149,177 149,194 153,173 146,166 194 129,149 0,90 129,149 D 20 129,149 129,149 129,149 129,149 129,149 129,149 129,149 G 14 115,129 I 30 119,149 29,119 C 5 110,115B 1595,110 5,95 F 25 90, 115 0,90A 90
  • 18. Slack Times • Activity start time and completion time may be delayed by planned reasons as well as by unforeseen reasons. • Some of these delays may affect the overall completion date. • To learn about the effects of these delays, we calculate the slack time, and form the critical path. 18
  • 19. Slack Times • Slack time is the amount of time an activity can be delayed without delaying the project completion date, assuming no other delays are taking place in the project. 19 Slack Time = LS - ES = LF - EF
  • 20. 20 Critical activities must be rigidly scheduled Critical activities must be rigidly scheduled Activity LS - ES Slack A 0 -0 0 B 95 - 90 5 C 110 - 105 5 D 119 - 119 0 E 173 - 149 24 F 90 - 90 0 G 115 - 115 0 H 166 - 149 17 I 119 - 90 29 J 149 - 149 0 Slack time in the Klonepalm 2000 Project
  • 21. The Critical Path • The critical path is a set of activities that have no slack, connecting the START node with the FINISH node. • The critical activities (activities with 0 slack) form at least one critical path in the network. • A critical path is the longest path in the network. • The sum of the completion times for the activities on the critical path is the minimal completion time of the project. 21
  • 22. The Critical Path 22 B F C A I E DG H H 28 166,194 J J 45 149,194 E 21 173,194 90,105 90,115 90,120 105,110 115,129 129,149 149,170 149,177 149,194 D 20 0,90 129,149 G 14 115,129 I 30 119,149 A 90 C 5 110,115B 15 95,110 F 25 90, 1150,90
  • 23. Possible Delays • We observe two different types of delays: • Single delays. • Multiple delays. • Under certain conditions the overall project completion time will be delayed. • The conditions that specify each case are presented next. 23
  • 24. Single delays • A delay of a certain amount in a critical activity, causes the entire project to be delayed by the same amount. • A delay of a certain amount in a non-critical activity will delay the project by the amount the delay exceeds the slack time. When the delay is less than the slack, the entire project is not delayed. 24
  • 25. Gantt Charts • Gantt charts are used as a tool to monitor and control the project progress. • A Gantt Chart is a graphical presentation that displays activities as follows: • Time is measured on the horizontal axis. A horizontal bar is drawn proportionately to an activity’ s expected completion time. • Each activity is listed on the vertical axis. • In an earliest time Gantt chart each bar begins and ends at the earliest start/finish the activity can take place. 25
  • 26. Gantt Charts- Monitoring Project Progress • Gantt chart can be used as a visual aid for tracking the progress of project activities. • Appropriate percentage of a bar is shaded to document the completed work. • The manager can easily see if the project is progressing on schedule (with respect to the earliest possible completion times). 26
  • 27. Gantt Charts – Advantages and Disadvantages • Advantages. • Easy to construct • Gives earliest completion date. • Provides a schedule of earliest possible start and finish times of activities. • Disadvantages • Gives only one possible schedule (earliest). • Does not show whether the project is behind schedule. • Does not demonstrate the effects of delays in any one activity on the start of another activity, thus on the project completion time. 27
  • 28. The Probability Approach to Project Scheduling • Activity completion times are seldom known with 100% accuracy. • PERT is a technique that treats activity completion times as random variables. • Completion time estimates are obtained by the Three Time Estimate approach 28
  • 29. The Probability Approach – Three Time Estimates 29 • The TThe Three Time Estimatehree Time Estimate approachapproach providesprovides completion time estimate for each activity.completion time estimate for each activity. • We use the notation:We use the notation: a = an optimistic time to perform the activity.a = an optimistic time to perform the activity. m = the most likely time to perform the activity.m = the most likely time to perform the activity. b = a pessimistic time to perform the activity.b = a pessimistic time to perform the activity.
  • 30. 30 Âľ σ = the mean completion time = a + 4m+ b 6 = the standard deviation = b -a 6 Approximations for the mean and the standardApproximations for the mean and the standard deviation of activity completion time are based on thedeviation of activity completion time are based on the BetaBeta distribution.distribution. The Distribution, Mean, and StandardThe Distribution, Mean, and Standard Deviation of an ActivityDeviation of an Activity
  • 31. The Project Completion Time Distribution - Assumptions 31 To calculate the mean and standard deviation of the project completion time we make some simplifying assumptions.
  • 32. The Project Completion Time Distribution - Assumptions • Assumption 2 • The time to complete one activity is independent of the time to complete any other activity. • Assumption 3 • There are enough activities on the critical path so that the distribution of the overall project completion time can be approximated by the normal distribution. 32 • Assumption 1Assumption 1 – A critical path can be determined by using the meanA critical path can be determined by using the mean completion times for the activities.completion times for the activities. – The project mean completion time is determined solely by theThe project mean completion time is determined solely by the completion time of the activities on the critical path.completion time of the activities on the critical path.
  • 33. The Project Completion Time Distribution The three assumptions imply that the overall project completion time is normally distributed, the following parameters: 33 Mean = Sum of mean completion times along the critical path. Variance = Sum of completion time variances along the critical path. Standard deviation = √Variance
  • 34. The Probability Approach – KLONE COMPUTERS 34 Activity Optimistic Most Likely Pessimistic A 76 86 120 B 12 15 18 C 4 5 6 D 15 18 33 E 18 21 24 F 16 26 30 G 10 13 22 H 24 18 32 I 22 27 50 J 38 43 60
  • 35. The Probability Approach – KLONE COMPUTERS • Management at KLONE is interested in information regarding the completion time of the project. • The probabilistic nature of the completion time must be considered. 35
  • 36. KLONE COMPUTERS – Finding activities’ mean and variance ÂľA =[76+4(86)+120]/6 = 90 σΑ = (120 - 76)/6 = 7.33 σA 2 = (7.33)2 = 53.78 36 Activity Âľ σ A 90 7.33 53.78 B 15 1.00 1.00 C 5 0.33 0.11 D 20 3.00 9.00 E 21 1.00 1.00 F 25 2.33 5.44 G 14 2.00 4.00 H 28 1.33 1.78 I 30 4.67 21.78 J 45 3.67 13.44 σ2
  • 37. KLONE COMPUTERS – Finding mean and variance for the critical path • The mean times are the same as in the CPM problem, previously solved for KLONE. • Thus, the critical path is A - F- G - D – J. • Expected completion time =ÂľA +ÂľF +ÂľG +ÂľD +ÂľJ=194. • The project variance =σA 2 +σF 2 +σG 2 +σD 2 +σJ 2 = 85.66 • The standard deviation = = 9.255 37 σ2
  • 38. The Probability Approach – Critical path spreadsheet 38 MEAN 194 STANDARD DEVIATION* 9.255629 * Assumes all critical activities are on one critical path VARIANCE* 85.66667 If not, enter in gold box, the variance on one critical path of interest. PROBABILITY COMPLETE BEFORE 180 = 0.065192 Acitivty Node Critical Âľ σ σ2 ES EF LS LF Slack Design A * 90 7.333333 53.77778 0 90 0 90 0 Materials B 15 1 1 90 105 95 110 5 Manufacture C 5 0.333333 0.111111 105 110 110 115 5 Design Revision D * 20 3 9 129 149 129 149 0 Production Run E 21 1 1 149 170 173 194 24 Staff Training F * 25 2.333333 5.444444 90 115 90 115 0 Staff Input G * 14 2 4 115 129 115 129 0 Sales Training H 28 1.333333 1.777778 149 177 166 194 17 Preprod. Advertise I 30 4.666667 21.77778 90 120 119 149 29 Post. Advertise J * 45 3.666667 13.44444 149 194 149 194 0 CRITICAL PATH ANALYSIS
  • 39. Cost Analyses Using The Critical Path Method (CPM) • The critical path method (CPM) is a deterministic approach to project planning. • Completion time depends only on the amount of money allocated to activities. • Reducing an activity’s completion time is called “crashing.” 39
  • 40. Crash time/Crash cost • There are two crucial completion times to consider for each activity. • Normal completion time (TN). • Crash completion time (TC), the minimum possible completion time. 40 • The cost spent on an activity varies between – Normal cost (CN). The activity is completed in TN. – Crash cost (CC). The activity is completed in TC.
  • 41. Crash time/Crash cost – The Linearity Assumption • The maximum crashing of activity completion time is TC– TN. • This can be achieved when spending CN – CC. • Any percentage of the maximum extra cost (CN – CC)spent to crash an activity, yields the same percentage reduction of the maximum time savings (TC– TN). 41
  • 42. REFERENCES • PLANT DESIGN AND ECONOMICS FOR CHEMICAL ENGINEER- 4TH EDITION , CHAPTER-11, BY- MAX S PETER, KLAUS D TIMMERHAUS 42