The rail over bridge is designed to allow the
road traffic to pass over the railway line.
CONSTRUCTION OF RAILWAY
OVER BRIDGE
GROUP 15: -
DESIGN AND ESTIMATION OF A 4 LANE 90 M RAILWAY
OVER BRIDGE (ROB) IN CHAND SARAI, LUCKNOW
Contents
 Bridge
 Types of Bridges
 Introduction: Railway Over Bridge
 Project Details
 Test carried out before start of construction
 Methodology
 Suggestions
 Bibliography
Bridge
 Bridge is a type of structure that provides passage over obstacles such as valleys, rough terrain or bodies of water by spanning those
obstacles with natural or man made materials even in those areas where traffic volume is really high.
 Components of a Bridge:
a) Deck slab
b) Longitudinal girder
c) Cross beams
d) Bearings
e) Joints
f) Pier / Abutment
g) Pier cap
h) R.E. Wall
Types of Bridges
 Beam Bridge
 Cantilever Bridge
 Suspension bridge
 Arch Bridge
 Truss Bridge
 Cable-stayed Bridge
Introduction: Railway Over Bridge
 The railway over bridge is a result of collaborated working of Bridge Corporation and Indian Railways.
 The Railway over bridge is divided as:
• Rail portion: Its construction is carried out by Indian Railways.
• Viaduct portion: It lies on both sides of railway portion and is constructed by bridge corporation.
Project Details
 Department: Uttar Pradesh Expressway and Industrial Development Authority (UPEIDA)
 Site Name: Chand Sarai, Lucknow
 Total Length of the Bridge: 90m
 Bridge Type: Railway Over Bridge
Test carried out before start of
construction
 Material Test
• Sieve analysis
• Cube Test
• Impact test of aggregates
• Consistency test of Cement
• Setting time of Cement
 Soil Bearing Capacity Test
• Plate-load Test
1. Surveying
2. Traffic Design
3. Engineering Design
4. Foundation
5. Bearings
6. Girders
7. Shuttering
8. Concreting
METHODOLOG
Y
1. Surveying
Surveying or land surveying is the technique, profession, art, and science of determining the terrestrial or
three-dimensional positions of points and the distances and angles between them.
Under Surveying we have:
 Reconnaissance Survey
 Topographic Survey
 Total Station Traverse
 Bench Mark
 Detailed Survey
METHODOLOG
Y
2. Traffic Design
The capacity standards for Bridge have been adopted as per the “Guidelines for Bridge”. Capacity analysis is
fundamental to the planning, design and operation of roads and provides, among other things, the basis for
determining the carriageway width to be provided at any point in a road network with respect to the volume
and composition of traffic. Moreover, it is a valuable tool for evaluation of the investments needed for future
road constructions and improvements.
 Equivalency Factors are calculated.
 Capacity Analysis
METHODOLOG
Y
3. Engineering Design
The Preliminary Design has been carried out on the selected alignment so as to have optimum Construction,
Operation & maintenance cost and Vehicle Operation Cost; minimum Social Impacts and Social Costs and
Environmental Impacts and Environmental Mitigation Costs.
 Geometric Design of the Alignment
 Indicative Design Standards
 Design Speed
METHODOLOG
Y
METHODOLOGY
4. Then Foundation is being laid.
PILE FOUNDATION
Noticed that the soft rock exists after two or three layers of soil which explains the selection of foundation for
transfer of super structural loads coming from the bridge onto the ground safely.
Construct of Pile Foundation
Test On Pile Foundation
 To assess the carrying capacity of the casted piles and to ensure the
homogeneity, various advanced tests have been conducted.
 They are listed below:
I. Initial Pile Load test / Kent Ledge Load Test
II. Dynamic load Test
III. Pile Integrity Test
Initial Pile Load Test/Kent Ledge Load
Test
Loading applied on the pile head was measured by
volumetric method. In this method sand bags were
arranged on top of the platform which is made with
8mm thick MS plate. The plate rests on the
secondary beams of ISMB 300. These 27 No’s
ISMB 300 was resting on 7No’s of ISMB 600 and
supported by solid bed on either of the pile. The total
dead load available for the pile load test was about
1100MT
Dynamic load Test
The basic purpose of high strain dynamic pile testing is to evaluate pile static capacity and its
structural integrity using measurement of both force and velocity.
Strain transducers and accelerometers are attached to the test pile.
Strains induced under the impact of a heavy falling hammer from a pre-determined height are
measured with the help of strain transducers attached to the pile, whereas accelerometers record the
accelerations generated in the pile. The Pile Driving Analyzer(PDA) converts strain to force, and
acceleration records are converted to velocities.
By using measured velocities, they performed trial and error process in CAPWAP Software and
computed forces in order to plot the graph between measured and computed forces.
And subsequent results have been found out and assured by the Chief Engineer or Engineer In
charge.
Pile Integrity Test
 The low strain Integrity testing is a Non-
Destructive Integrity test method for foundation
piles for the assessment of potential problems
like cross sectional changes, honeycombing,
Physical dimensions, continuity of pile and
concrete quality.
 This testing requires the attachment of the
highly sensitive accelerometer to the pile top
with viscous material.
 After hammer impact downward compressive
wave is generated travelling with wave speed
“c”.
Bearings
 The bearing is an element of superstructure which provides
an interface between the superstructure and substructure.
 This interface is vital because superstructure undergoes
dimensional changes and deformations due to various
factors which are as follow:
a. Thermal expansion / contraction
b. Elastic Deformation under live load
c. Seismic forces
d. Creep and shrinkage of concrete
e. Settlement of supports
f. Longitudinal forces – tractive / breaking
g. Wind Loads
Types of Bearings
i. Free Float Bearing of Capacity 248MT
ii. Pin Metallic Guided Bearing of Capacity 18MT
iii. Pin Fixed Bearing of Capacity 93-114MT
iv. Free Float Bearing of Capacity 189MT
v. Slide Guide Bearing of Capacity 178MT
vi. Slide Guide Bearing of Capacity 189MT
Girders
Girders are structural members carry super structural loads and distribute to the substructure,
from then, to the ground safely.
PSC Girders
Composite Steel Girders
Cross Girders/Diaphragms
PSC Girders
Firmly, Precast PSC Girders are casted at the site.
After curing for 15days, stressing has been done and accordingly
evaluated elongation so as to check with the specifications provided.
Arrangement of the reinforcement and Cable profiling are shown in the below figure.
Cross Girders/Diaphragms
Cross Girders/Diaphragms act like tie beams.
Intermediate Diaphragms
End Diaphragms
Below picture is representing reinforcement inside an End Diaphragm.
Composite Steel Girders
Composite girders are manufactured in the
workshop namely PMGStructural’s Limited.
As per the designed drawings, composite girders
are manufactured and shipped to the site.
Before going for the manufacture of composite
girders, activities included like materials’ tests such
as Physical dimensional check, Chemical
analysis, Mechanical testing and etc.
For the erection of composite girders, DTI
Washer was used in the process of tightening the
bolted connection.
5. Shuttering
 Temporary timber, plywood, metal or other material used to provide support to wet concrete mix till it gets
strength for self-support.
 It provides support to horizontal, vertical and inclined surface and also provides support to cast concrete
according to required shape and size.
 Types of shuttering:
a) Steel Shuttering
b) Wooden plank shuttering
c) Temporary brick masonry shuttering
METHODOLOGY
 Material required for shuttering
a) Bottom (casting bed)
b) Beam plate & Cross beam plate
c) Tube anchorage
d) H.T.S wire (12.5 mm), winding wire
e) Nuts & bolts
f) Plastic plate
g) Wooden block
METHODOLOGY
6. Concreting
 Concreting is the process of mixing together the various ingredients – water, cement, aggregate, and any additives – to
produce concrete.
 Concrete production is time-sensitive. Once the ingredients are mixed, workers must put the concrete in place before it
hardens.
 In modern usage, most concrete production takes place in a large type of industrial facility called a concrete plant, or often a
batch plant.
 Machine used in concreting:
a) Batching plant
b) One bag mixer
c) Two bag mixer
d) Four bag mixer
METHODOLOGY
 Bag mixer divided in
3 parts:
a) Hooper
b) Drum
c) Air-bucket
7. After the setting of concrete, the shuttering is removed.
Recommended period for removal of shuttering:
 48 hours-foundations, columns, beams, walls.
 7 days-underside of slab up to 4.5 m span.
 14 days-underside of slab, beam arches above 4.5 m up to 6 m span.
 21 days-6m to 9m span.
 28 days-above 9m span.
METHODOLOGY
Suggestions
 Bridges maintenance consists of combination of structural health monitoring and testing.
 This is regulated in country specific engineer standard.
 A Simple test or inspection every two to three years and a major inspection every six to ten years is done.
 There are several methods used to monitor the stress in large structures like bridges.
a) Use of accelerometer.
b) Use of Doppler vibrometer.
Conclusion
The innovation design of ROB has the potential to save in crores of Rupees in addition to facilitate local
people to cross Railway land with ease and enhanced safety to train operations through closure of level
crossing. The reduced land requirement, reduced length of approaches, improved feasibility of economic
open foundation design, possible immunity from bearing capacity variations and enhance aesthetics are
advantages which are recurring in nature and makes this design attractive and useful. Railway Board’s
appreciation and further advice to other Zones of Indian Railways endorses this innovation as resolute.
REFRENCES
 UTTAR PRADESH EXPRESSWAYS INDUSTRIAL DEVELOPMENT AUTHORITY
(UPEIDA)
 Victor, D. J. Design of Bridges
 IS 800, General Construction in Steel – Code of practice, 2007
 IRC 21, Construction of Bridges, 2000
 Mr Mohit Choubey, Professor of Civil Engineering, BBDITM, Lucknow, India
THANK YOU
Submitted by
Under the guidance of
Mr. Mohit Choubey
(Assistant Professor)
NAME ROLL NO.
SAURABH SINGH 1805400918
SURYA PRAKASH RAWAT 1805400919
TANMAY SINGH CHAUHAN 1805400920
VIKAS SINGH RAJPUT 1805400921
VIKAS SINGHANIYA 1805400922
VIKRAM PRATAP SINGH 1805400923
VISHWAJEET 1805400924

Weitere ähnliche Inhalte

Was ist angesagt?

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
Halcrow
 

Was ist angesagt? (20)

PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
 
road construction
road constructionroad construction
road construction
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Unit 4
Unit 4Unit 4
Unit 4
 
Introduction to bridges
Introduction to bridgesIntroduction to bridges
Introduction to bridges
 
Ppt bridges & types
Ppt bridges & typesPpt bridges & types
Ppt bridges & types
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete road
 
Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit Kumar
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
 
DESIGN AND ANALYSIS OF G+3 RESIDENTIAL BUILDING BY S.MAHAMMAD FROM RAJIV GAND...
DESIGN AND ANALYSIS OF G+3 RESIDENTIAL BUILDING BY S.MAHAMMAD FROM RAJIV GAND...DESIGN AND ANALYSIS OF G+3 RESIDENTIAL BUILDING BY S.MAHAMMAD FROM RAJIV GAND...
DESIGN AND ANALYSIS OF G+3 RESIDENTIAL BUILDING BY S.MAHAMMAD FROM RAJIV GAND...
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Bridge report
Bridge reportBridge report
Bridge report
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
Bearings in bridges
Bearings in bridgesBearings in bridges
Bearings in bridges
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 

Ähnlich wie Railway over bridge

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
toddr4
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training report
Rajendra Jhurawat
 
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch BridgeThe Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
IJERA Editor
 
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch BridgeThe Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
IJERA Editor
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Dr.Subramanian Narayanan
 

Ähnlich wie Railway over bridge (20)

Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Structural Health Monitoring and Strengthening Of BridgesStructural Health Mo...
Structural Health Monitoring and Strengthening Of BridgesStructural Health Mo...Structural Health Monitoring and Strengthening Of BridgesStructural Health Mo...
Structural Health Monitoring and Strengthening Of BridgesStructural Health Mo...
 
Structural Health Monitoring and Strengthening Of Bridges
Structural Health Monitoring and Strengthening Of BridgesStructural Health Monitoring and Strengthening Of Bridges
Structural Health Monitoring and Strengthening Of Bridges
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptx
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training report
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
IRJET-Parametric Study of Bridge Piers
IRJET-Parametric Study of Bridge Piers                                      IRJET-Parametric Study of Bridge Piers
IRJET-Parametric Study of Bridge Piers
 
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch BridgeThe Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
 
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch BridgeThe Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
The Performance Evaluation of Concrete Filled Steel Tubular Arch Bridge
 
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
 
Special structure
Special structureSpecial structure
Special structure
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
 
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
RESTORATION OF EXISTING MAJOR BRIDGE ACROSS RIVER BHADAR ON NATIONAL HIGHWAY ...
 
Sub.ass.2
Sub.ass.2Sub.ass.2
Sub.ass.2
 

Kürzlich hochgeladen

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Kürzlich hochgeladen (20)

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 

Railway over bridge

  • 1. Railway Over Bridge C O N S T R U C T I O N START NOW The rail over bridge is designed to allow the road traffic to pass over the railway line.
  • 2. CONSTRUCTION OF RAILWAY OVER BRIDGE GROUP 15: - DESIGN AND ESTIMATION OF A 4 LANE 90 M RAILWAY OVER BRIDGE (ROB) IN CHAND SARAI, LUCKNOW
  • 3. Contents  Bridge  Types of Bridges  Introduction: Railway Over Bridge  Project Details  Test carried out before start of construction  Methodology  Suggestions  Bibliography
  • 4. Bridge  Bridge is a type of structure that provides passage over obstacles such as valleys, rough terrain or bodies of water by spanning those obstacles with natural or man made materials even in those areas where traffic volume is really high.  Components of a Bridge: a) Deck slab b) Longitudinal girder c) Cross beams d) Bearings e) Joints f) Pier / Abutment g) Pier cap h) R.E. Wall
  • 5. Types of Bridges  Beam Bridge  Cantilever Bridge  Suspension bridge  Arch Bridge  Truss Bridge  Cable-stayed Bridge
  • 6. Introduction: Railway Over Bridge  The railway over bridge is a result of collaborated working of Bridge Corporation and Indian Railways.  The Railway over bridge is divided as: • Rail portion: Its construction is carried out by Indian Railways. • Viaduct portion: It lies on both sides of railway portion and is constructed by bridge corporation.
  • 7. Project Details  Department: Uttar Pradesh Expressway and Industrial Development Authority (UPEIDA)  Site Name: Chand Sarai, Lucknow  Total Length of the Bridge: 90m  Bridge Type: Railway Over Bridge
  • 8. Test carried out before start of construction  Material Test • Sieve analysis • Cube Test • Impact test of aggregates • Consistency test of Cement • Setting time of Cement  Soil Bearing Capacity Test • Plate-load Test
  • 9. 1. Surveying 2. Traffic Design 3. Engineering Design 4. Foundation 5. Bearings 6. Girders 7. Shuttering 8. Concreting METHODOLOG Y
  • 10. 1. Surveying Surveying or land surveying is the technique, profession, art, and science of determining the terrestrial or three-dimensional positions of points and the distances and angles between them. Under Surveying we have:  Reconnaissance Survey  Topographic Survey  Total Station Traverse  Bench Mark  Detailed Survey METHODOLOG Y
  • 11. 2. Traffic Design The capacity standards for Bridge have been adopted as per the “Guidelines for Bridge”. Capacity analysis is fundamental to the planning, design and operation of roads and provides, among other things, the basis for determining the carriageway width to be provided at any point in a road network with respect to the volume and composition of traffic. Moreover, it is a valuable tool for evaluation of the investments needed for future road constructions and improvements.  Equivalency Factors are calculated.  Capacity Analysis METHODOLOG Y
  • 12. 3. Engineering Design The Preliminary Design has been carried out on the selected alignment so as to have optimum Construction, Operation & maintenance cost and Vehicle Operation Cost; minimum Social Impacts and Social Costs and Environmental Impacts and Environmental Mitigation Costs.  Geometric Design of the Alignment  Indicative Design Standards  Design Speed METHODOLOG Y
  • 13. METHODOLOGY 4. Then Foundation is being laid. PILE FOUNDATION Noticed that the soft rock exists after two or three layers of soil which explains the selection of foundation for transfer of super structural loads coming from the bridge onto the ground safely.
  • 14. Construct of Pile Foundation
  • 15. Test On Pile Foundation  To assess the carrying capacity of the casted piles and to ensure the homogeneity, various advanced tests have been conducted.  They are listed below: I. Initial Pile Load test / Kent Ledge Load Test II. Dynamic load Test III. Pile Integrity Test
  • 16. Initial Pile Load Test/Kent Ledge Load Test Loading applied on the pile head was measured by volumetric method. In this method sand bags were arranged on top of the platform which is made with 8mm thick MS plate. The plate rests on the secondary beams of ISMB 300. These 27 No’s ISMB 300 was resting on 7No’s of ISMB 600 and supported by solid bed on either of the pile. The total dead load available for the pile load test was about 1100MT
  • 17. Dynamic load Test The basic purpose of high strain dynamic pile testing is to evaluate pile static capacity and its structural integrity using measurement of both force and velocity. Strain transducers and accelerometers are attached to the test pile. Strains induced under the impact of a heavy falling hammer from a pre-determined height are measured with the help of strain transducers attached to the pile, whereas accelerometers record the accelerations generated in the pile. The Pile Driving Analyzer(PDA) converts strain to force, and acceleration records are converted to velocities. By using measured velocities, they performed trial and error process in CAPWAP Software and computed forces in order to plot the graph between measured and computed forces. And subsequent results have been found out and assured by the Chief Engineer or Engineer In charge.
  • 18. Pile Integrity Test  The low strain Integrity testing is a Non- Destructive Integrity test method for foundation piles for the assessment of potential problems like cross sectional changes, honeycombing, Physical dimensions, continuity of pile and concrete quality.  This testing requires the attachment of the highly sensitive accelerometer to the pile top with viscous material.  After hammer impact downward compressive wave is generated travelling with wave speed “c”.
  • 19. Bearings  The bearing is an element of superstructure which provides an interface between the superstructure and substructure.  This interface is vital because superstructure undergoes dimensional changes and deformations due to various factors which are as follow: a. Thermal expansion / contraction b. Elastic Deformation under live load c. Seismic forces d. Creep and shrinkage of concrete e. Settlement of supports f. Longitudinal forces – tractive / breaking g. Wind Loads
  • 20. Types of Bearings i. Free Float Bearing of Capacity 248MT ii. Pin Metallic Guided Bearing of Capacity 18MT iii. Pin Fixed Bearing of Capacity 93-114MT iv. Free Float Bearing of Capacity 189MT v. Slide Guide Bearing of Capacity 178MT vi. Slide Guide Bearing of Capacity 189MT
  • 21. Girders Girders are structural members carry super structural loads and distribute to the substructure, from then, to the ground safely. PSC Girders Composite Steel Girders Cross Girders/Diaphragms
  • 22. PSC Girders Firmly, Precast PSC Girders are casted at the site. After curing for 15days, stressing has been done and accordingly evaluated elongation so as to check with the specifications provided. Arrangement of the reinforcement and Cable profiling are shown in the below figure.
  • 23. Cross Girders/Diaphragms Cross Girders/Diaphragms act like tie beams. Intermediate Diaphragms End Diaphragms Below picture is representing reinforcement inside an End Diaphragm.
  • 24. Composite Steel Girders Composite girders are manufactured in the workshop namely PMGStructural’s Limited. As per the designed drawings, composite girders are manufactured and shipped to the site. Before going for the manufacture of composite girders, activities included like materials’ tests such as Physical dimensional check, Chemical analysis, Mechanical testing and etc. For the erection of composite girders, DTI Washer was used in the process of tightening the bolted connection.
  • 25. 5. Shuttering  Temporary timber, plywood, metal or other material used to provide support to wet concrete mix till it gets strength for self-support.  It provides support to horizontal, vertical and inclined surface and also provides support to cast concrete according to required shape and size.  Types of shuttering: a) Steel Shuttering b) Wooden plank shuttering c) Temporary brick masonry shuttering METHODOLOGY
  • 26.  Material required for shuttering a) Bottom (casting bed) b) Beam plate & Cross beam plate c) Tube anchorage d) H.T.S wire (12.5 mm), winding wire e) Nuts & bolts f) Plastic plate g) Wooden block METHODOLOGY
  • 27. 6. Concreting  Concreting is the process of mixing together the various ingredients – water, cement, aggregate, and any additives – to produce concrete.  Concrete production is time-sensitive. Once the ingredients are mixed, workers must put the concrete in place before it hardens.  In modern usage, most concrete production takes place in a large type of industrial facility called a concrete plant, or often a batch plant.  Machine used in concreting: a) Batching plant b) One bag mixer c) Two bag mixer d) Four bag mixer METHODOLOGY  Bag mixer divided in 3 parts: a) Hooper b) Drum c) Air-bucket
  • 28. 7. After the setting of concrete, the shuttering is removed. Recommended period for removal of shuttering:  48 hours-foundations, columns, beams, walls.  7 days-underside of slab up to 4.5 m span.  14 days-underside of slab, beam arches above 4.5 m up to 6 m span.  21 days-6m to 9m span.  28 days-above 9m span. METHODOLOGY
  • 29. Suggestions  Bridges maintenance consists of combination of structural health monitoring and testing.  This is regulated in country specific engineer standard.  A Simple test or inspection every two to three years and a major inspection every six to ten years is done.  There are several methods used to monitor the stress in large structures like bridges. a) Use of accelerometer. b) Use of Doppler vibrometer.
  • 30. Conclusion The innovation design of ROB has the potential to save in crores of Rupees in addition to facilitate local people to cross Railway land with ease and enhanced safety to train operations through closure of level crossing. The reduced land requirement, reduced length of approaches, improved feasibility of economic open foundation design, possible immunity from bearing capacity variations and enhance aesthetics are advantages which are recurring in nature and makes this design attractive and useful. Railway Board’s appreciation and further advice to other Zones of Indian Railways endorses this innovation as resolute.
  • 31. REFRENCES  UTTAR PRADESH EXPRESSWAYS INDUSTRIAL DEVELOPMENT AUTHORITY (UPEIDA)  Victor, D. J. Design of Bridges  IS 800, General Construction in Steel – Code of practice, 2007  IRC 21, Construction of Bridges, 2000  Mr Mohit Choubey, Professor of Civil Engineering, BBDITM, Lucknow, India
  • 32. THANK YOU Submitted by Under the guidance of Mr. Mohit Choubey (Assistant Professor) NAME ROLL NO. SAURABH SINGH 1805400918 SURYA PRAKASH RAWAT 1805400919 TANMAY SINGH CHAUHAN 1805400920 VIKAS SINGH RAJPUT 1805400921 VIKAS SINGHANIYA 1805400922 VIKRAM PRATAP SINGH 1805400923 VISHWAJEET 1805400924