Concepts of Cutover Planning and Management
Sanjay Choubey
2
Agenda
 Introduction to Cutover: What is Cutover?
 Plan for the Plan
 Cutover Planning Process
 Cutover Plan Vs. Business Readiness Plan
 Contingency Planning
 Must Get Right
3
What is Cutover?
Cutover is the process of planning, managing and executing ALL of the tasks and
activities that allow the impacted business/function to ‘cutover’ to the SAP system.
Business Preparation Activities related to Cutover and Legacy Integration/
Shutdown are key components of the Cutover Plan.
Cutover Planning and Execution Activities are organized and managed under the
following categories:
System Build (Technical & Functional)
Data Migration/Verification
Business Preparation
Legacy Integration/Shutdown
Business Startup Activities
These are the primary building blocks of Cutover and success
requires rigorous, detailed and integrated planning.
4
Cutover Activities
 System Build
– Technical / Infrastructure Build
• Build Production environment
• Connectivity to middleware, Bolt-Ons, and legacy environments
• Setup of printers and scanners
– Functional build
• Apply all transports (Configuration, Security and Development)
• Perform manual steps
 Data Migration & Verification
– Data Accuracy Testing
– Extract and transform data
– Load master data into production with end user sign-off
– Load transaction data into production and reconcile with end user sign-off
5
Cutover Activities, cont’d
 Business Preparation
– Business activities and procedures in support of the Cutover process e.g.:
• Last Processing of Business Transactions
• Inventory procedures
 Legacy Integration/Shutdown
– Legacy System freeze schedules
– Shutdown/decommissioning procedures
– Legacy interface re-pointing
 Business Startup Activities
– Restarting the business based on the new solution (processes, data,
technology)
– Focused on key identified areas
6
Plan for the Plan
To prepare a detailed cutover plan leveraging resources from project and various business
units, a Plan for the plan is necessary. Plan of the plan helps in planning & tracking various
milestones and effort. The milestones defined are as follows:
1. Initial Cutover Planning
– Define roles and responsibilities, Cutover meeting cadence
– Establish Cutover Schedule
– Define Scope, approach of Initial cutover planning workshops
– Conduct Initial workshops
1. Detailed Cutover Planning
– Conduct Detailed cutover workshops with Process and Horizontal teams
– Review Communication Plan, Site Readiness plan
– Create and Review Contingency plan
– Facilitate issue based workshops
– Road-show/ Communication of “Draft Cutover Plan”
1. Cutover Rehearsal
– Create rehearsal Plan
– Execute Cutover Rehearsal
– Facilitate Lessons Learned for Cutover rehearsal
1. Release of “Final Cutover Plan”
7
Initial Planning
 Objective
– Kick start planning activity by identifying the key tasks and
planning team members
 Inputs
– Planning Accelerators (Planning workbooks for different teams)
– List of Interfaces and Legacy IT systems
– Prior Release Contingency Plans
– Prior Release Lessons Learned
 Outputs
– Preliminary List of Cutover Tasks (Draft Workbook)
– Planning Team Members
• List of team members (SAP team, Data team, Legacy IT &
Interface Coordinators)
• Business Resources
8
Detailed Planning
 Objective
– Develop a Draft Cutover Plan, aligned
with Business Readiness and
Shutdown plan
– Develop a Draft Business Startup
Plan
 Inputs
– Preliminary Planning Workbook
– Business Readiness Plans (incl.
Shutdown Plans)
 Outputs
– Draft Cutover Plan
– Draft Startup Plan
– Cutover Rehearsal Plan
Key Takeaway: there is much iteration as we go
deeper in each process subteam and then integrate
across processes; it is very likely that business
team members will find some overlap as we look
into detailed Cutover tasks and plan for Shutdown
because the tasks are heavily interdependent
9
Cutover Rehearsal
 Objective
– To practice, to greatest extent possible, Cutover and build
lessons learned into the final Cutover Plan
– To practice Startup (limited to transactional processing, not
operations)
 Inputs
– Draft Cutover Plan
– Draft Startup Plan
 Outputs
– Final Cutover Plan
– Updated Startup Plan
Key Takeaway: not everything is rehearsed; specifically not
every Business Prep task is a candidate for rehearsal;
conversely, some activity will have been rehearsed many times
by this point (e.g., Data Migration)
10
Cutover
 Objective
– To successfully Go Live
– To have a well orchestrated Startup
 Inputs
– Cutover Plan
– Updated Startup Plan
 Outputs
– New SAP Production Capability (this is not just about a system!)
Key Takeaways: (1) Startup activity that needs to be done
within SAP before Go Live must be in the Cutover Plan, (2) the
Cutover Plan is a controlled document with change control – we
need to get it first time right ! (3) Startup planning is not just a
site or division – everything is now integrated !
11
Cutover Plan and Business Readiness Plans
Business
Readiness Plans
(Planning lead by Business
Leads)
Cutover Plan
(planning lead by
SAP Team)
System Build
Data Migration
Legacy System Shutdown
Business Prep
(e.g., Shutdown)
Legacy System Integrations
Prepare SOPs
Business
Continuity Plans
Benefits
Ownership
Start UpPlanned by SAP
team
(planned at the
executable level of
detail)
Planned by the
Business
(planned at the
executable level of
detail)
Planned Collaboratively
(planned a the milestone level and
then the executable level of detail is
carried in the most appropriate plan)
12
Cutover and Business Readiness Plan Milestone Dates
Level 1
Level 2
Level 3
These are the critical Cutover Milestones; these
are fixed dates/times and are in the Cutover Plan
These are the key milestones that form the critical path
for the Level 1 dates (e.g., last 3rd
Party Invoice paid
before A/P closed, close Sales/Inventory); these are also
fixed and shifts need to be approved/negotiated; these
are also in the Cutover Plan
These are the important milestones that the
Business or Legacy IT must achieve in order to
accomplish Level 2 dates (e.g., turn off legacy
system for Requisitioning); these are flexible
only to the extent that Level 2 milestones stay on
track; these are expected to be in Legacy
Business Readiness Plans but higher risk
milestones may also be carried in the Cutover
Plan
13
Contingency Planning
Contingency Planning is needed to ensure that organization can continue to perform
their critical business functions in an acceptable period of time
Two types of Contingency Plan are developed:
1. IT & SAP Contingency Plan
a. One way of SAP Vs. another way – What If Scenarios
b. Interface Vs Manual SAP transaction
c. Hardware (Network, Printers, SSO etc) & Software (Internet explorer
version Vs Mozilla Firefox etc)
Developed by Project Implementation Team during Cutover meetings
2. Business Continuity Plan at Business Unit level
a. Leveraging Manual processes in the event of non SAP
b. Paper based/ Legacy system Based
c. Decision on Procedural Checks and Balances
Developed By Business (reviewed & agreed by Project team)
14
Must Get Right
 Approval from Project sponsors for Key Cutover Strategies, Draft Cutover schedule and Key
Timelines
 Clearly defined and documented roles and responsibilities of Cutover Team
– Cutover Lead
– Data Migration lead
– Interface Coordinator
– Legacy IT Coordinator
– System Build (Functional & Technical) Coordinator
 Clear agreement from Business about their participation and involvement
 Change, Communication and Training Team should be in loop in the entire process and
should help drive communication and change initiatives aligned with Cutover Schedule
 Infrastructure arrangement for Cutover Rehearsal should be similar to Actual Cutover. There
shouldn’t be any compromise during rehearsal in terms of participation of business or effort.
 One should pay very close attention to User provisioning, role definition & testing of roles
 Business Verification transactions during Cutover rehearsal should be detailed enough and
should include security roles too.
15

Weitere ähnliche Inhalte

Was ist angesagt?

SAP HANA Migration Deck.pptx
SAP HANA Migration Deck.pptxSAP HANA Migration Deck.pptx
SAP HANA Migration Deck.pptx
SingbBablu
 

Was ist angesagt? (20)

Sap S/4 HANA New Implementation
Sap S/4 HANA New ImplementationSap S/4 HANA New Implementation
Sap S/4 HANA New Implementation
 
SAP Project Systems with Success Factors
SAP Project Systems with Success FactorsSAP Project Systems with Success Factors
SAP Project Systems with Success Factors
 
Kickoff meeting template
Kickoff meeting templateKickoff meeting template
Kickoff meeting template
 
Cutover plan template Tool
Cutover plan template ToolCutover plan template Tool
Cutover plan template Tool
 
example of SAP Cut over strategy FI CO MM PS module
example of SAP Cut over strategy FI CO MM PS moduleexample of SAP Cut over strategy FI CO MM PS module
example of SAP Cut over strategy FI CO MM PS module
 
Project kick off
Project kick offProject kick off
Project kick off
 
SAP HANA Migration Deck.pptx
SAP HANA Migration Deck.pptxSAP HANA Migration Deck.pptx
SAP HANA Migration Deck.pptx
 
SAP S/4 HANA Technical assessment before migration
SAP S/4 HANA Technical assessment before migrationSAP S/4 HANA Technical assessment before migration
SAP S/4 HANA Technical assessment before migration
 
Cutover activities
Cutover activitiesCutover activities
Cutover activities
 
SAP Activate Methodology for S/4HANA Implementation
SAP Activate Methodology for S/4HANA ImplementationSAP Activate Methodology for S/4HANA Implementation
SAP Activate Methodology for S/4HANA Implementation
 
Selecting SAP S/4 HANA- Digital Core migration strategy - Greenfield vs Brow...
Selecting SAP S/4 HANA- Digital Core migration strategy -  Greenfield vs Brow...Selecting SAP S/4 HANA- Digital Core migration strategy -  Greenfield vs Brow...
Selecting SAP S/4 HANA- Digital Core migration strategy - Greenfield vs Brow...
 
SAP S4HANA Migration Cockpit.pdf
SAP S4HANA Migration Cockpit.pdfSAP S4HANA Migration Cockpit.pdf
SAP S4HANA Migration Cockpit.pdf
 
S4HANA Migration Overview
S4HANA Migration OverviewS4HANA Migration Overview
S4HANA Migration Overview
 
Migration to sap s4 hana
Migration to sap s4 hanaMigration to sap s4 hana
Migration to sap s4 hana
 
Moving to SAP S/4HANA
Moving to SAP S/4HANAMoving to SAP S/4HANA
Moving to SAP S/4HANA
 
Integration with Group Reporting Preparation Ledger.pdf
Integration with Group Reporting Preparation Ledger.pdfIntegration with Group Reporting Preparation Ledger.pdf
Integration with Group Reporting Preparation Ledger.pdf
 
Transition to SAP S/4HANA System Conversion: A step-by-step guide
Transition to SAP S/4HANA System Conversion: A step-by-step guide Transition to SAP S/4HANA System Conversion: A step-by-step guide
Transition to SAP S/4HANA System Conversion: A step-by-step guide
 
L1_RISE_with_SAP_NNN_V3.4.pptx
L1_RISE_with_SAP_NNN_V3.4.pptxL1_RISE_with_SAP_NNN_V3.4.pptx
L1_RISE_with_SAP_NNN_V3.4.pptx
 
BPD Design Template
BPD Design TemplateBPD Design Template
BPD Design Template
 
“Migration to Suite of HANA”
“Migration to Suite of HANA”“Migration to Suite of HANA”
“Migration to Suite of HANA”
 

Andere mochten auch

Competing On Resources Balance Scorecard
Competing On Resources  Balance ScorecardCompeting On Resources  Balance Scorecard
Competing On Resources Balance Scorecard
vinod63
 
Mastergrad final version
Mastergrad final versionMastergrad final version
Mastergrad final version
Marita Myhre
 
The HR scorecard
The HR scorecardThe HR scorecard
The HR scorecard
Jon Ingham
 
Introduction to Kanban
Introduction to KanbanIntroduction to Kanban
Introduction to Kanban
TO THE NEW | Technology
 

Andere mochten auch (19)

Business Process Management - Building The BPM Balanced Scorecard
Business Process Management - Building The BPM Balanced ScorecardBusiness Process Management - Building The BPM Balanced Scorecard
Business Process Management - Building The BPM Balanced Scorecard
 
Strategic HR
Strategic HRStrategic HR
Strategic HR
 
Office365 vs Hosted Exchange: Migrations Made Easy
Office365 vs Hosted Exchange: Migrations Made EasyOffice365 vs Hosted Exchange: Migrations Made Easy
Office365 vs Hosted Exchange: Migrations Made Easy
 
Competing On Resources Balance Scorecard
Competing On Resources  Balance ScorecardCompeting On Resources  Balance Scorecard
Competing On Resources Balance Scorecard
 
Strategy map 16
Strategy map 16Strategy map 16
Strategy map 16
 
Introduction to BPM
Introduction to BPMIntroduction to BPM
Introduction to BPM
 
Hr Balanced scorecard
Hr Balanced  scorecardHr Balanced  scorecard
Hr Balanced scorecard
 
Mastergrad final version
Mastergrad final versionMastergrad final version
Mastergrad final version
 
Strategic Performance Management System
Strategic Performance Management SystemStrategic Performance Management System
Strategic Performance Management System
 
Roger Martin. Playing to Win - How to make strategy work
Roger Martin. Playing to Win - How to make strategy workRoger Martin. Playing to Win - How to make strategy work
Roger Martin. Playing to Win - How to make strategy work
 
Notes on balanced scorecard
Notes on balanced scorecardNotes on balanced scorecard
Notes on balanced scorecard
 
Balanced Scorecard
Balanced Scorecard  Balanced Scorecard
Balanced Scorecard
 
Working with Emotional Intelligence
Working with Emotional IntelligenceWorking with Emotional Intelligence
Working with Emotional Intelligence
 
The HR scorecard
The HR scorecardThe HR scorecard
The HR scorecard
 
Understanding financial statements
Understanding financial statementsUnderstanding financial statements
Understanding financial statements
 
Employee engagement by vinay ravindran (www.vinayravindran.com)
Employee engagement by vinay ravindran (www.vinayravindran.com)Employee engagement by vinay ravindran (www.vinayravindran.com)
Employee engagement by vinay ravindran (www.vinayravindran.com)
 
Introduction to Kanban
Introduction to KanbanIntroduction to Kanban
Introduction to Kanban
 
HR SCORECARD Human Resource Scorecard PPT Slides
HR SCORECARD Human Resource Scorecard PPT SlidesHR SCORECARD Human Resource Scorecard PPT Slides
HR SCORECARD Human Resource Scorecard PPT Slides
 
Balanced scorecard ppt slides
Balanced scorecard ppt slidesBalanced scorecard ppt slides
Balanced scorecard ppt slides
 

Ähnlich wie Concepts of cutover planning and management

Erp Asap implementation 1214825612078403-9
Erp Asap implementation 1214825612078403-9Erp Asap implementation 1214825612078403-9
Erp Asap implementation 1214825612078403-9
Hari Krishna
 
Erpasapimplementation 1214825612078403-9
Erpasapimplementation 1214825612078403-9Erpasapimplementation 1214825612078403-9
Erpasapimplementation 1214825612078403-9
Hari Krishna
 
ASAP Methodology- SAP Project management
ASAP Methodology- SAP Project managementASAP Methodology- SAP Project management
ASAP Methodology- SAP Project management
ArjunPawar29
 
ASAP methodology overview
ASAP methodology overviewASAP methodology overview
ASAP methodology overview
Bogdan Gorka
 
eCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration ProjecteCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration Project
David Niles
 

Ähnlich wie Concepts of cutover planning and management (20)

Asap implementation methodology (2)
Asap implementation methodology (2)Asap implementation methodology (2)
Asap implementation methodology (2)
 
Erp Asap implementation 1214825612078403-9
Erp Asap implementation 1214825612078403-9Erp Asap implementation 1214825612078403-9
Erp Asap implementation 1214825612078403-9
 
Erpasapimplementation 1214825612078403-9
Erpasapimplementation 1214825612078403-9Erpasapimplementation 1214825612078403-9
Erpasapimplementation 1214825612078403-9
 
ASAP Methodology in Implementing ERP
ASAP Methodology in Implementing ERPASAP Methodology in Implementing ERP
ASAP Methodology in Implementing ERP
 
Playbook for Remote Cutover S4H_747 How to Approach Remote Cutover.pptx
Playbook for Remote Cutover S4H_747 How to Approach Remote Cutover.pptxPlaybook for Remote Cutover S4H_747 How to Approach Remote Cutover.pptx
Playbook for Remote Cutover S4H_747 How to Approach Remote Cutover.pptx
 
SAP Implementation Phase!!
SAP Implementation Phase!!SAP Implementation Phase!!
SAP Implementation Phase!!
 
ASAP Methodology- SAP Project management
ASAP Methodology- SAP Project managementASAP Methodology- SAP Project management
ASAP Methodology- SAP Project management
 
Asap methodology sap Anilkumar chowdary
Asap methodology sap Anilkumar chowdaryAsap methodology sap Anilkumar chowdary
Asap methodology sap Anilkumar chowdary
 
Asap overview
Asap overviewAsap overview
Asap overview
 
SharePoint: What You Need to Know Before Upgrading
SharePoint: What You Need to Know Before UpgradingSharePoint: What You Need to Know Before Upgrading
SharePoint: What You Need to Know Before Upgrading
 
ASAP Roadmap Phases.pptx
ASAP Roadmap Phases.pptxASAP Roadmap Phases.pptx
ASAP Roadmap Phases.pptx
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Asap methodoloy
Asap methodoloyAsap methodoloy
Asap methodoloy
 
Business Analyst Role in Hybrid Agile Waterfall
Business Analyst Role in Hybrid Agile WaterfallBusiness Analyst Role in Hybrid Agile Waterfall
Business Analyst Role in Hybrid Agile Waterfall
 
ASAP methodology overview
ASAP methodology overviewASAP methodology overview
ASAP methodology overview
 
eCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration ProjecteCIO PPT Roles for a SAP and Systems Integration Project
eCIO PPT Roles for a SAP and Systems Integration Project
 
Intelaphase PLM methodology
Intelaphase PLM methodologyIntelaphase PLM methodology
Intelaphase PLM methodology
 
Resume arvind -csm
Resume arvind -csmResume arvind -csm
Resume arvind -csm
 
ASAP Methodology Roadmaps and Phases.pdf
ASAP Methodology Roadmaps and Phases.pdfASAP Methodology Roadmaps and Phases.pdf
ASAP Methodology Roadmaps and Phases.pdf
 
S4H_747 How to Approach Remote Cutover (2).pptx
S4H_747 How to Approach Remote Cutover (2).pptxS4H_747 How to Approach Remote Cutover (2).pptx
S4H_747 How to Approach Remote Cutover (2).pptx
 

Kürzlich hochgeladen

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 

Kürzlich hochgeladen (20)

Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 

Concepts of cutover planning and management

  • 1. Concepts of Cutover Planning and Management Sanjay Choubey
  • 2. 2 Agenda  Introduction to Cutover: What is Cutover?  Plan for the Plan  Cutover Planning Process  Cutover Plan Vs. Business Readiness Plan  Contingency Planning  Must Get Right
  • 3. 3 What is Cutover? Cutover is the process of planning, managing and executing ALL of the tasks and activities that allow the impacted business/function to ‘cutover’ to the SAP system. Business Preparation Activities related to Cutover and Legacy Integration/ Shutdown are key components of the Cutover Plan. Cutover Planning and Execution Activities are organized and managed under the following categories: System Build (Technical & Functional) Data Migration/Verification Business Preparation Legacy Integration/Shutdown Business Startup Activities These are the primary building blocks of Cutover and success requires rigorous, detailed and integrated planning.
  • 4. 4 Cutover Activities  System Build – Technical / Infrastructure Build • Build Production environment • Connectivity to middleware, Bolt-Ons, and legacy environments • Setup of printers and scanners – Functional build • Apply all transports (Configuration, Security and Development) • Perform manual steps  Data Migration & Verification – Data Accuracy Testing – Extract and transform data – Load master data into production with end user sign-off – Load transaction data into production and reconcile with end user sign-off
  • 5. 5 Cutover Activities, cont’d  Business Preparation – Business activities and procedures in support of the Cutover process e.g.: • Last Processing of Business Transactions • Inventory procedures  Legacy Integration/Shutdown – Legacy System freeze schedules – Shutdown/decommissioning procedures – Legacy interface re-pointing  Business Startup Activities – Restarting the business based on the new solution (processes, data, technology) – Focused on key identified areas
  • 6. 6 Plan for the Plan To prepare a detailed cutover plan leveraging resources from project and various business units, a Plan for the plan is necessary. Plan of the plan helps in planning & tracking various milestones and effort. The milestones defined are as follows: 1. Initial Cutover Planning – Define roles and responsibilities, Cutover meeting cadence – Establish Cutover Schedule – Define Scope, approach of Initial cutover planning workshops – Conduct Initial workshops 1. Detailed Cutover Planning – Conduct Detailed cutover workshops with Process and Horizontal teams – Review Communication Plan, Site Readiness plan – Create and Review Contingency plan – Facilitate issue based workshops – Road-show/ Communication of “Draft Cutover Plan” 1. Cutover Rehearsal – Create rehearsal Plan – Execute Cutover Rehearsal – Facilitate Lessons Learned for Cutover rehearsal 1. Release of “Final Cutover Plan”
  • 7. 7 Initial Planning  Objective – Kick start planning activity by identifying the key tasks and planning team members  Inputs – Planning Accelerators (Planning workbooks for different teams) – List of Interfaces and Legacy IT systems – Prior Release Contingency Plans – Prior Release Lessons Learned  Outputs – Preliminary List of Cutover Tasks (Draft Workbook) – Planning Team Members • List of team members (SAP team, Data team, Legacy IT & Interface Coordinators) • Business Resources
  • 8. 8 Detailed Planning  Objective – Develop a Draft Cutover Plan, aligned with Business Readiness and Shutdown plan – Develop a Draft Business Startup Plan  Inputs – Preliminary Planning Workbook – Business Readiness Plans (incl. Shutdown Plans)  Outputs – Draft Cutover Plan – Draft Startup Plan – Cutover Rehearsal Plan Key Takeaway: there is much iteration as we go deeper in each process subteam and then integrate across processes; it is very likely that business team members will find some overlap as we look into detailed Cutover tasks and plan for Shutdown because the tasks are heavily interdependent
  • 9. 9 Cutover Rehearsal  Objective – To practice, to greatest extent possible, Cutover and build lessons learned into the final Cutover Plan – To practice Startup (limited to transactional processing, not operations)  Inputs – Draft Cutover Plan – Draft Startup Plan  Outputs – Final Cutover Plan – Updated Startup Plan Key Takeaway: not everything is rehearsed; specifically not every Business Prep task is a candidate for rehearsal; conversely, some activity will have been rehearsed many times by this point (e.g., Data Migration)
  • 10. 10 Cutover  Objective – To successfully Go Live – To have a well orchestrated Startup  Inputs – Cutover Plan – Updated Startup Plan  Outputs – New SAP Production Capability (this is not just about a system!) Key Takeaways: (1) Startup activity that needs to be done within SAP before Go Live must be in the Cutover Plan, (2) the Cutover Plan is a controlled document with change control – we need to get it first time right ! (3) Startup planning is not just a site or division – everything is now integrated !
  • 11. 11 Cutover Plan and Business Readiness Plans Business Readiness Plans (Planning lead by Business Leads) Cutover Plan (planning lead by SAP Team) System Build Data Migration Legacy System Shutdown Business Prep (e.g., Shutdown) Legacy System Integrations Prepare SOPs Business Continuity Plans Benefits Ownership Start UpPlanned by SAP team (planned at the executable level of detail) Planned by the Business (planned at the executable level of detail) Planned Collaboratively (planned a the milestone level and then the executable level of detail is carried in the most appropriate plan)
  • 12. 12 Cutover and Business Readiness Plan Milestone Dates Level 1 Level 2 Level 3 These are the critical Cutover Milestones; these are fixed dates/times and are in the Cutover Plan These are the key milestones that form the critical path for the Level 1 dates (e.g., last 3rd Party Invoice paid before A/P closed, close Sales/Inventory); these are also fixed and shifts need to be approved/negotiated; these are also in the Cutover Plan These are the important milestones that the Business or Legacy IT must achieve in order to accomplish Level 2 dates (e.g., turn off legacy system for Requisitioning); these are flexible only to the extent that Level 2 milestones stay on track; these are expected to be in Legacy Business Readiness Plans but higher risk milestones may also be carried in the Cutover Plan
  • 13. 13 Contingency Planning Contingency Planning is needed to ensure that organization can continue to perform their critical business functions in an acceptable period of time Two types of Contingency Plan are developed: 1. IT & SAP Contingency Plan a. One way of SAP Vs. another way – What If Scenarios b. Interface Vs Manual SAP transaction c. Hardware (Network, Printers, SSO etc) & Software (Internet explorer version Vs Mozilla Firefox etc) Developed by Project Implementation Team during Cutover meetings 2. Business Continuity Plan at Business Unit level a. Leveraging Manual processes in the event of non SAP b. Paper based/ Legacy system Based c. Decision on Procedural Checks and Balances Developed By Business (reviewed & agreed by Project team)
  • 14. 14 Must Get Right  Approval from Project sponsors for Key Cutover Strategies, Draft Cutover schedule and Key Timelines  Clearly defined and documented roles and responsibilities of Cutover Team – Cutover Lead – Data Migration lead – Interface Coordinator – Legacy IT Coordinator – System Build (Functional & Technical) Coordinator  Clear agreement from Business about their participation and involvement  Change, Communication and Training Team should be in loop in the entire process and should help drive communication and change initiatives aligned with Cutover Schedule  Infrastructure arrangement for Cutover Rehearsal should be similar to Actual Cutover. There shouldn’t be any compromise during rehearsal in terms of participation of business or effort.  One should pay very close attention to User provisioning, role definition & testing of roles  Business Verification transactions during Cutover rehearsal should be detailed enough and should include security roles too.
  • 15. 15

Hinweis der Redaktion

  1. Although most of you are already aware about the Concept of Cutover, however, I would to start with Introduction to Cutover Time: 1 Min
  2. Cutover Definition The definition of the categories are explained in more detail in coming slides Time: 1-2 minutes
  3. In this slide, I would talk about details of System Build: Technical system build: Build of Prod environment Pre-transport manual activities by process teams Application of transports Post Transport manual configuration activities by process teams -- Data Migration and verification activities Data Verification activities differ from business to business i.e. a. Validated business Vs Non validated business b. Strategy of data migration & Testing (Target testing, Load testing etc) c. Sensitiveness of client about the data quality Post data migration, manual activities by process teams Time: 3-4 min
  4. - Business Prep activities i.e. Business Cutover activities: Detail process and procedure about Business cutover tasks in different areas and their dependencies Last processing of business transactions and their exact timings Dependencies of the business tasks Ascertaining the timing, responsible and accountable person for the tasks Agreement with Business for the tasks Legacy Integration and Shutdown Agreement about the system freezing schedule Legacy system readiness for shutdown/ decommissioning Schedule Interface start timing – Last file send & Receive date and time Agreement about the timing of interface readiness date and time Time: 4-5 min
  5. To be able to manage a Big cutover of more than 300 project resources, one needs to have a very well defined planning approach for Cutover Planning: To effectively plan a big cutover with optimum utilization of project resources, it is extremely essential to have a Plan for the Cutover Planning Mention about the Definition of Roles and Responsibilities for Cutover: Full time Resources Cutover Lead & support Data Migration Lead & team Interface coordinator Legacy System Coordinator Infrastructure Coordinator On Need basis Process teams and Horizontal teams Business leads Time: 4-5 min
  6. Planning Workbook to capture cutover tasks per team List of interfaces and legacy systems Contingency Plan – template - Full time Resources Cutover Lead & support Data Migration Lead & team Interface coordinator Legacy System Coordinator Infrastructure Coordinator On Need basis Process teams and Horizontal teams Business leads Time: 2-3 min
  7. Conducting detailed cutover meeting Aligning business tasks and IT (Interfaces, Legacy extraction) Agree about the date, time, Volume of business etc Alignment with Business readiness Plan Start up Planning Time: 5 min
  8. Time: 1-2 min
  9. Time: 1 min
  10. Distinction of Business Role Vs. Role of Cutover team Time: 1-2 min
  11. Time: 3-4 Min
  12. Time: 2-3 min A Contingency plan template will be available in download form for reference
  13. Time: 3-4 min