SlideShare ist ein Scribd-Unternehmen logo
1 von 7
Downloaden Sie, um offline zu lesen
AR50383 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Page 1 of 7
AR50383 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Page 2 of 7 
Contents 
1.0 
Introduction .................................................................................................................................. 3 
1.1 
Purpose of Close out Report ...................................................................................................... 3 
2.0 
Project Closure Notifications ...................................................................................................... 3 
2.1 
Work Accpetance ........................................................................................................................ 3 
2.2 
Outstanding Works ..................................................................................................................... 3 
2.3 
Completion of Contractual Obligations ...................................................................................... 3 
3.0 
Project Evaluation ........................................................................................................................ 4 
3.1 
Time Performance ...................................................................................................................... 4 
3.2 
Cost Performance ....................................................................................................................... 4 
3.3 Quality Performance ................................................................................................................... 5 
3.4 
Scope Performance .................................................................................................................... 6 
4.0 
Lessons Learned ......................................................................................................................... 6 
5.0 
Commentary ................................................................................................................................ 6 
List of Figure 
Figure 1 Quality Trending…...………………………………………………………………………………………………….5 
Close out Report History 
Version Date Author/Editor Reasons 
01 30nd March 2017 CPM Ltd. Close out Report
AR50383 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
1.0 Introduction 
1.1 Purpose of Close out Report 
Concept Project Management Ltd. prepares the project close out report in order to be submitted to the steering 
committee of Copham Hospital to satisfy them that the project is completed successfully to the required conditions and 
functions as per the project design and specifications. This report will ensure, evaluate and identify the followings; 
• Ensure that the client/authorities’ formal acceptance for the executed works has been achieved. 
• Ensure that all the contractual issues have been fulfilled. 
• Evaluate how well the project was performed against the planned objectives including time, cost, quality and 
scope performance. 
• Identify the remedial works (outstanding). 
• Identify the lessons learned. 
2.0 Project Closure Notifications 
2.1 Work Acceptance 
The consultants have inspected the completed work packages and a snagging list was produced for some defects that 
appeared to the consultant during the inspection. The contractor finalized the entire snagging list and handed over 
successfully all the work packages free of defects to the consultant who has formally accepted it. 
Also, the civil defence inspected and accepted the fire fighting system and the electricity/ water authority inspected 
and accepted the electrical and sanitary systems. 
The consultant and different authorities have run integrated test and formally accepted the overall integrated 
performance of all hospital systems when they were all operated together. 
Based on all the above, a Practical Completion Certificate was issued to the contractor confirming the acceptance 
of all the executed works except some remedial works to be done during the defects liability period. 
2.2 Outstanding Works 
There are some remedial works that have to be accomplished by the contractor during the defect liability period, such 
as; 
• Some damages to the floor coating have to be rectified in the plant rooms that were occurred during the 
equipment commissioning. 
• Five fan coil units have to be changed at the main reception in the clinical accommodation building. 
2.3 Completion of Contractual Obligations 
All the contractual aspects between client and contractor have been completed and fulfilled except some obligations to be 
fulfilled during the defects liability period. The completed aspects include; 
• The contractor carried out and completed the work in a proper manner according to the contract document, health 
and safety plan and quality plan. 
• The contractor supplied the proper materials to be used in constructing the hospital. 
• The contractor handed over the project without any delays from his side. 
• The contractor supplied all the required bonds, insurances and permits during the project. 
• The contractor handed over successfully to the consultant/client the followings; 
ü As built drawings, documents and works schedule. 
ü Operation and maintenance manuals. 
ü Training to the operation team. 
ü Operating instructions and procedures. 
• The client has released all the contractor’s payments within the specified time limit mentioned in the contract. 
• The client has released half of retention monies and the second half will be released by the end of defect liability 
period. 
• The client has awarded an extension of time and prolongation cost to the contractor due to excusable delays. 
Page 3 of 7
AR50383 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
3.0 Project Evaluation 
3.1 Time Performance 
The design consultant delayed (-30 days) in developing the concept design, however, these delays were mitigated in 
the stage of developing the detailed design and tender documents. Moreover, (-30 days) resulted from the change 
order and (-5 days) resulted from the inclement weather. 
The contractor was awarded extension of time of 35 days due the excusable delays resulted from the change orders 
and inclement weather. 
Milestones/Deliverables Planned Date Actual Date Variance Behind Schedule Reasons 
Procure Project Management Firm Mar-26-2014 Mar-26-2014 0 days 
Procure Design Consultant May-07-2014 May-07-2014 0 days 
Concept Design Development Aug-07-2014 Sep-07-2014 - 30 days Delays in mobilizing the required professional 
3.2 Cost Performance 
The project original budget was set to be 31 million but by the end of construction the total expenditures became 31.7 
million due to the change orders, which increased the fees that have to be paid to the design consultant, and PM for 
extending their services beside the a one-month prolongation cost that had to be paid to the contractor. 
Page 4 of 7 
staff (Mitigated) 
Detailed Design and Tender Docs. Jan-26-2015 Jan-26-2015 0 days 
Tender and Awarding Apr-30-2015 Apr-30-2015 0 days 
Commencement of Construction Jun-03-2015 Jun-03-2015 0 days 
End of Construction Feb-12-2017 Mar-17-2017 - 35 days Delays resulted from weather and materials 
change orders issued by client. Procuring the 
new materials consumed more time to get it 
delivered to the site. (Time Extension) 
# Item Estimated 
Budget 
Actual 
Budget 
Variance Over Budget Reasons 
1 Professional Fees 2,700,000 £ 2,760,000 £ -60,000 £ The service of PM and design consultant 
was extended 35 days because of the 
time extension that awarded to the 
contractor due to client’s change orders 
and inclement weather. 
2 Land Purchase 1,000,000 £ 1,000,000 £ 00.000 £ 
3 Civil and 
Architectural Works 
10,336,842 £ 10,936,842 £ -600,000 £ Changing the material of acoustic ceiling 
and flooring in hospital corridors and 
plant rooms. 
4 Mechanical Works 5,336,842 £ 5,336,842 £ 00.000 £ 
5 Electrical Works 1,389,474 £ 1,389,474 £ 00.000 £ 
6 Sanitary Works 600,000 £ 600,000 £ 00.000 £ 
7 Fire Fighting/Alarm 336,842 £ 336,842 £ 00.000 £ 
8 Medical Equipment 4,000,000 £ 4,000,000 £ 00.000 £ 
9 Commissioning 2,000,000 £ 2,000,000 £ On-going 
10 Contingency 2,575,000 £ 2,675,000 £ -100,000 £ 1 month of prolongation that was paid to 
the contractor. 
11 Surface Diversion, 
Access Road and 
Decant Cost 
725,000 £ 725,000 £ 00.000 £ 
Total 31,000,000 £ 31,760,000 £ -760,000 £
AR50383 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
3.3 Quality Performance 
During the construction period: 965 work inspections, 370 material inspections and daily quality site walks were 
conducted. Moreover, 18 non-conformance reports (NCR) were raised and closed. 
The project recorded some deviation as per below figure; 
Code Item Cases 
Figure 1 
In general, the project was delivered with a high standard of quality except some remedial works. 
Page 5 of 7 
Number 
A Deviation from specification 1 
B Use if unapproved drawings 1 
C Use of superseded drawings Nil 
D Use of unapproved materials 3 
E Damage to materials 2 
F Not following manufacture’s instruction 1 
G Not working as per method statement 3 
H Inadequate supervision 2 
J Other miscellaneous causes 5
AR50383 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
3.4 Scope Performance 
During the project, two change orders were issued for changing the materials of acoustic ceiling and flooring in 
hospital corridor and plant rooms. 
Changing the aforementioned materials increased the project budget plus the long delivery duration of these materials 
delayed the completion date. 
Topic Lessons Learned Description Method of Circulation of 
Stakeholders It is necessary to get formally all the stakeholders’ 
requirements in order to avoid the changes during 
construction, as the change orders are always have a cost 
and time impact. 
Schedule More time has to be considered to enable the designer to 
Quality During equipment commissioning, floor protection has to 
be fixed to protect the floor from potential damages. 
Risks The risk assessment for civil works ignored the inclement 
weather effect on project completion date. 
Page 6 of 7 
4.0 Lessons Learned 
Lessons 
Ensure that a team has to be 
assigned for understanding 
and collecting formally the 
stakeholder requirements. 
do his staff mobilization. 
Ensure that 30 days for the 
mobilization of design staff 
has to be considered for all 
future projects. 
Ensure that the floor 
protection methods have to 
be considered for all future 
projects. 
Ensure that the weather 
effect has to be considered in 
assessing the project risks 
and thus accurately estimate 
the contingency fund. 
5.0 Commentary 
5.1 To who and why 
This report will be submitted to the steering committee of Copham Hospital and CPCT in order to; 
• Satisfy them that the project is completed successfully to the required conditions and functions as per the 
project design and specifications. 
• To sum up the project performance in terms of scope, time, cost and quality in order to highlight the lessons 
learned and recommendations. Therefore, the report will give a direction for how to plan better for the future 
projects using the lessons learned of the past ones. 
• To draw the attention for the outstanding works that has to be done. 
• To confirm that all the contract mutual obligations were fulfilled. 
• To confirm the project has achieved the project charter’s objectives. 
5.2 When and how 
The close out report has to be submitted by the end of construction period as a revision 1 and then a revision 2 has to 
be submitted after the completion of defects liability period to include the performance and lessons learned for that 
period as well. 
The de-brief will be conducted in form of close out report.
AR50383 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
5.3 How to collect project data 
The project data will be collected through ACONEX (www.aconex.com). Aconex is a platform that has the ability to 
upload, store and share the drawings, reports, schedules, specifications, emails, contracts, invoices, transmittals and 
other documentations among the project participants. All the required data for assessing the schedule performance, 
budget performance, quality performance and scope performance can be downloaded easily from ACONEX. 
5.4 Organizational learning’s evaluation and recording 
All the organizational procedure manuals, always used in the future projects, have to be updated in new revisions 
using the lessons learned and recommendations of the close out report. These manuals are; 
Page 7 of 7 
• Budget and cost management. 
• Procurement management. 
• Contract administration. 
• Communication management. 
• Change management. 
• Schedule management. 
• Quality management. 
• Risk management. 
• Health, safety and environment. 
• Estimating management. 
When all the aforementioned manuals will be updated using the close report outcomes (lessons learned& 
recommendations) then it is guaranteed that all the forthcoming projects will get the benefits of the close out reports 
outcomes.

Weitere ähnliche Inhalte

Was ist angesagt?

Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report SampleElias Ibrahim
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Jamal Nelson, CCM
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...Antonio Coladarce
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
Curriculum Vitae end to start 19-7-2016
Curriculum Vitae end to start 19-7-2016Curriculum Vitae end to start 19-7-2016
Curriculum Vitae end to start 19-7-2016Ayman Issa
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 

Was ist angesagt? (18)

AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Monitoring Programme Review
Monitoring Programme ReviewMonitoring Programme Review
Monitoring Programme Review
 
DAMAC Heights Project
DAMAC Heights ProjectDAMAC Heights Project
DAMAC Heights Project
 
Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report Sample
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...Monthly progress report , Resettlement  ,Rehabilitation , Livelihood and Rest...
Monthly progress report , Resettlement ,Rehabilitation , Livelihood and Rest...
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
Updated Resume.DOC
Updated Resume.DOCUpdated Resume.DOC
Updated Resume.DOC
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Student Project
Student ProjectStudent Project
Student Project
 
Curriculum Vitae end to start 19-7-2016
Curriculum Vitae end to start 19-7-2016Curriculum Vitae end to start 19-7-2016
Curriculum Vitae end to start 19-7-2016
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 

Ähnlich wie Kandil_Sameh_CPMPart 4 _b

C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case studyFreelancelanders
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Contract adminstration and planning
Contract adminstration and planningContract adminstration and planning
Contract adminstration and planningawad suliman
 
Sample wind apartment ins val rep
Sample wind apartment ins val repSample wind apartment ins val rep
Sample wind apartment ins val repIndependentgroup
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTNur Ain Samsudin
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docxhyacinthshackley2629
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
35 days bid procedure for construction project
35 days bid procedure for construction project35 days bid procedure for construction project
35 days bid procedure for construction projectMarvin M Gamboa
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
 
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docx
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docxProject ManagementMGT 402 A02Argosy UniversityProfessor B.docx
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docxbriancrawford30935
 

Ähnlich wie Kandil_Sameh_CPMPart 4 _b (20)

C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Contract adminstration and planning
Contract adminstration and planningContract adminstration and planning
Contract adminstration and planning
 
Sample wind apartment ins val rep
Sample wind apartment ins val repSample wind apartment ins val rep
Sample wind apartment ins val rep
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
contract procedure
contract procedurecontract procedure
contract procedure
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docx
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
35 days bid procedure for construction project
35 days bid procedure for construction project35 days bid procedure for construction project
35 days bid procedure for construction project
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docx
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docxProject ManagementMGT 402 A02Argosy UniversityProfessor B.docx
Project ManagementMGT 402 A02Argosy UniversityProfessor B.docx
 

Mehr von Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

Mehr von Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (19)

Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
N1
N1N1
N1
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
Resources Histograms
Resources HistogramsResources Histograms
Resources Histograms
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
Kandil_Sameh_AR50411_Part 1 to 5
Kandil_Sameh_AR50411_Part 1 to 5Kandil_Sameh_AR50411_Part 1 to 5
Kandil_Sameh_AR50411_Part 1 to 5
 

Kandil_Sameh_CPMPart 4 _b

  • 1. AR50383 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Page 1 of 7
  • 2. AR50383 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Page 2 of 7 Contents 1.0 Introduction .................................................................................................................................. 3 1.1 Purpose of Close out Report ...................................................................................................... 3 2.0 Project Closure Notifications ...................................................................................................... 3 2.1 Work Accpetance ........................................................................................................................ 3 2.2 Outstanding Works ..................................................................................................................... 3 2.3 Completion of Contractual Obligations ...................................................................................... 3 3.0 Project Evaluation ........................................................................................................................ 4 3.1 Time Performance ...................................................................................................................... 4 3.2 Cost Performance ....................................................................................................................... 4 3.3 Quality Performance ................................................................................................................... 5 3.4 Scope Performance .................................................................................................................... 6 4.0 Lessons Learned ......................................................................................................................... 6 5.0 Commentary ................................................................................................................................ 6 List of Figure Figure 1 Quality Trending…...………………………………………………………………………………………………….5 Close out Report History Version Date Author/Editor Reasons 01 30nd March 2017 CPM Ltd. Close out Report
  • 3. AR50383 Assignment Name: (Sameh Kandil Mohammed Ibrahim) 1.0 Introduction 1.1 Purpose of Close out Report Concept Project Management Ltd. prepares the project close out report in order to be submitted to the steering committee of Copham Hospital to satisfy them that the project is completed successfully to the required conditions and functions as per the project design and specifications. This report will ensure, evaluate and identify the followings; • Ensure that the client/authorities’ formal acceptance for the executed works has been achieved. • Ensure that all the contractual issues have been fulfilled. • Evaluate how well the project was performed against the planned objectives including time, cost, quality and scope performance. • Identify the remedial works (outstanding). • Identify the lessons learned. 2.0 Project Closure Notifications 2.1 Work Acceptance The consultants have inspected the completed work packages and a snagging list was produced for some defects that appeared to the consultant during the inspection. The contractor finalized the entire snagging list and handed over successfully all the work packages free of defects to the consultant who has formally accepted it. Also, the civil defence inspected and accepted the fire fighting system and the electricity/ water authority inspected and accepted the electrical and sanitary systems. The consultant and different authorities have run integrated test and formally accepted the overall integrated performance of all hospital systems when they were all operated together. Based on all the above, a Practical Completion Certificate was issued to the contractor confirming the acceptance of all the executed works except some remedial works to be done during the defects liability period. 2.2 Outstanding Works There are some remedial works that have to be accomplished by the contractor during the defect liability period, such as; • Some damages to the floor coating have to be rectified in the plant rooms that were occurred during the equipment commissioning. • Five fan coil units have to be changed at the main reception in the clinical accommodation building. 2.3 Completion of Contractual Obligations All the contractual aspects between client and contractor have been completed and fulfilled except some obligations to be fulfilled during the defects liability period. The completed aspects include; • The contractor carried out and completed the work in a proper manner according to the contract document, health and safety plan and quality plan. • The contractor supplied the proper materials to be used in constructing the hospital. • The contractor handed over the project without any delays from his side. • The contractor supplied all the required bonds, insurances and permits during the project. • The contractor handed over successfully to the consultant/client the followings; ü As built drawings, documents and works schedule. ü Operation and maintenance manuals. ü Training to the operation team. ü Operating instructions and procedures. • The client has released all the contractor’s payments within the specified time limit mentioned in the contract. • The client has released half of retention monies and the second half will be released by the end of defect liability period. • The client has awarded an extension of time and prolongation cost to the contractor due to excusable delays. Page 3 of 7
  • 4. AR50383 Assignment Name: (Sameh Kandil Mohammed Ibrahim) 3.0 Project Evaluation 3.1 Time Performance The design consultant delayed (-30 days) in developing the concept design, however, these delays were mitigated in the stage of developing the detailed design and tender documents. Moreover, (-30 days) resulted from the change order and (-5 days) resulted from the inclement weather. The contractor was awarded extension of time of 35 days due the excusable delays resulted from the change orders and inclement weather. Milestones/Deliverables Planned Date Actual Date Variance Behind Schedule Reasons Procure Project Management Firm Mar-26-2014 Mar-26-2014 0 days Procure Design Consultant May-07-2014 May-07-2014 0 days Concept Design Development Aug-07-2014 Sep-07-2014 - 30 days Delays in mobilizing the required professional 3.2 Cost Performance The project original budget was set to be 31 million but by the end of construction the total expenditures became 31.7 million due to the change orders, which increased the fees that have to be paid to the design consultant, and PM for extending their services beside the a one-month prolongation cost that had to be paid to the contractor. Page 4 of 7 staff (Mitigated) Detailed Design and Tender Docs. Jan-26-2015 Jan-26-2015 0 days Tender and Awarding Apr-30-2015 Apr-30-2015 0 days Commencement of Construction Jun-03-2015 Jun-03-2015 0 days End of Construction Feb-12-2017 Mar-17-2017 - 35 days Delays resulted from weather and materials change orders issued by client. Procuring the new materials consumed more time to get it delivered to the site. (Time Extension) # Item Estimated Budget Actual Budget Variance Over Budget Reasons 1 Professional Fees 2,700,000 £ 2,760,000 £ -60,000 £ The service of PM and design consultant was extended 35 days because of the time extension that awarded to the contractor due to client’s change orders and inclement weather. 2 Land Purchase 1,000,000 £ 1,000,000 £ 00.000 £ 3 Civil and Architectural Works 10,336,842 £ 10,936,842 £ -600,000 £ Changing the material of acoustic ceiling and flooring in hospital corridors and plant rooms. 4 Mechanical Works 5,336,842 £ 5,336,842 £ 00.000 £ 5 Electrical Works 1,389,474 £ 1,389,474 £ 00.000 £ 6 Sanitary Works 600,000 £ 600,000 £ 00.000 £ 7 Fire Fighting/Alarm 336,842 £ 336,842 £ 00.000 £ 8 Medical Equipment 4,000,000 £ 4,000,000 £ 00.000 £ 9 Commissioning 2,000,000 £ 2,000,000 £ On-going 10 Contingency 2,575,000 £ 2,675,000 £ -100,000 £ 1 month of prolongation that was paid to the contractor. 11 Surface Diversion, Access Road and Decant Cost 725,000 £ 725,000 £ 00.000 £ Total 31,000,000 £ 31,760,000 £ -760,000 £
  • 5. AR50383 Assignment Name: (Sameh Kandil Mohammed Ibrahim) 3.3 Quality Performance During the construction period: 965 work inspections, 370 material inspections and daily quality site walks were conducted. Moreover, 18 non-conformance reports (NCR) were raised and closed. The project recorded some deviation as per below figure; Code Item Cases Figure 1 In general, the project was delivered with a high standard of quality except some remedial works. Page 5 of 7 Number A Deviation from specification 1 B Use if unapproved drawings 1 C Use of superseded drawings Nil D Use of unapproved materials 3 E Damage to materials 2 F Not following manufacture’s instruction 1 G Not working as per method statement 3 H Inadequate supervision 2 J Other miscellaneous causes 5
  • 6. AR50383 Assignment Name: (Sameh Kandil Mohammed Ibrahim) 3.4 Scope Performance During the project, two change orders were issued for changing the materials of acoustic ceiling and flooring in hospital corridor and plant rooms. Changing the aforementioned materials increased the project budget plus the long delivery duration of these materials delayed the completion date. Topic Lessons Learned Description Method of Circulation of Stakeholders It is necessary to get formally all the stakeholders’ requirements in order to avoid the changes during construction, as the change orders are always have a cost and time impact. Schedule More time has to be considered to enable the designer to Quality During equipment commissioning, floor protection has to be fixed to protect the floor from potential damages. Risks The risk assessment for civil works ignored the inclement weather effect on project completion date. Page 6 of 7 4.0 Lessons Learned Lessons Ensure that a team has to be assigned for understanding and collecting formally the stakeholder requirements. do his staff mobilization. Ensure that 30 days for the mobilization of design staff has to be considered for all future projects. Ensure that the floor protection methods have to be considered for all future projects. Ensure that the weather effect has to be considered in assessing the project risks and thus accurately estimate the contingency fund. 5.0 Commentary 5.1 To who and why This report will be submitted to the steering committee of Copham Hospital and CPCT in order to; • Satisfy them that the project is completed successfully to the required conditions and functions as per the project design and specifications. • To sum up the project performance in terms of scope, time, cost and quality in order to highlight the lessons learned and recommendations. Therefore, the report will give a direction for how to plan better for the future projects using the lessons learned of the past ones. • To draw the attention for the outstanding works that has to be done. • To confirm that all the contract mutual obligations were fulfilled. • To confirm the project has achieved the project charter’s objectives. 5.2 When and how The close out report has to be submitted by the end of construction period as a revision 1 and then a revision 2 has to be submitted after the completion of defects liability period to include the performance and lessons learned for that period as well. The de-brief will be conducted in form of close out report.
  • 7. AR50383 Assignment Name: (Sameh Kandil Mohammed Ibrahim) 5.3 How to collect project data The project data will be collected through ACONEX (www.aconex.com). Aconex is a platform that has the ability to upload, store and share the drawings, reports, schedules, specifications, emails, contracts, invoices, transmittals and other documentations among the project participants. All the required data for assessing the schedule performance, budget performance, quality performance and scope performance can be downloaded easily from ACONEX. 5.4 Organizational learning’s evaluation and recording All the organizational procedure manuals, always used in the future projects, have to be updated in new revisions using the lessons learned and recommendations of the close out report. These manuals are; Page 7 of 7 • Budget and cost management. • Procurement management. • Contract administration. • Communication management. • Change management. • Schedule management. • Quality management. • Risk management. • Health, safety and environment. • Estimating management. When all the aforementioned manuals will be updated using the close report outcomes (lessons learned& recommendations) then it is guaranteed that all the forthcoming projects will get the benefits of the close out reports outcomes.