Contract 2-Projects Progress Status 
October 2013
Contract 2 
Local Roads and Drainage Programme 
 Planned Dates 
 Actual Dates 
 Planned Dates 
 Actual Dates 
 % Complete 
 High Level Schedule 
 Payment Schedule 
Current Approved 
Baselines 
Schedules 
Dashboard 
Updated Schedules 
 Gateway 4 History QATAR 
ACCOUNT 
MANAGEMENT 
PROGRAM 
 SPI 
 Days till Completion
Current Approved Baselines 
Public Works Authority ASHGHAL 
Local Roads and Drainage Programme 
Master Programme Milestones 
Approved Baselines 
G1 G2 G3 G5 G6 
Baseline 15-May-13 20-Nov-13 13-Feb-14 17-Sep-14 4-Nov-14 21-Jun-17 18-Jul-18 
Actual 15-May-13 20-Nov-13 13-Feb-14 17-Sep-14 4-Nov-14 21-Jun-17 1-Aug-18 
Baseline 19-Dec-12 17-Apr-13 30-Jul-13 18-Dec-13 3-Mar-14 18-Nov-15 16-Nov-16 
Actual 19-Dec-12 3-Jul-13 26-Aug-13 17-Dec-13 3-Mar-14 18-Nov-15 4-Jan-17 
Baseline 22-Oct-12 20-Feb-13 20-Jun-13 18-Dec-13 4-Mar-14 16-Sep-15 21-Sep-16 
Actual 22-Oct-12 3-Jul-13 12-Nov-13 17-Dec-13 4-Mar-14 16-Sep-15 2-Nov-16 
QS016 Access Road to Rashid Village Prelim. Design 
Baseline 17-Apr-13 21-Aug-13 17-Dec-13 18-Jun-14 7-Sep-14 20-Jul-16 20-Sep-17 
Actual 1-May-13 2-Oct-13 17-Dec-13 18-Jun-14 7-Sep-14 20-Jul-16 6-Sep-17 
Baseline 21-Nov-12 3-Jul-13 23-Sep-13 19-Feb-14 6-May-14 19-Aug-15 21-Sep-16 
QS017 Roads and Infrastructure in Al Karanna Village 
Concept 
Design 
QS004 Roads and Infrastructure in Wadi Aba Seleel 
Concept 
Design 
QS015 Roads and Infrastructure in Rawdat Rashed Village Prelim. Design 
Construction 
Detailed Design/ 
Tender Documents 
Tendering 
Project 
Code 
Project Name Current Stage Initiation Concept Design Preliminary Design Maintenance P eriod 
QS028 Roads  Infrastructure in Birkat Al Awamer Industrial Area Prelim. Design 
Actual 21-Nov-12 3-Jul-13 18-Nov-13 19-Feb-14 6-May-14 19-Aug-15 5-Oct-16 
Baseline 15-May-13 20-Nov-13 7-May-14 15-Oct-14 31-Dec-14 15-Feb-17 18-Apr-18 
Actual 6-Nov-13 21-May-14 9-Nov-14 6-May-15 23-Jul-15 20-Sep-17 7-Nov-18 
Baseline 22-Oct-12 27-Feb-13 25-Jun-13 17-Dec-13 18-Feb-14 15-Apr-15 18-May-16 
Actual 22-Oct-12 27-Feb-13 25-Jun-13 17-Dec-13 18-Feb-14 15-Apr-15 1-Jun-16 
Baseline 22-Oct-12 1-Aug-13 27-Oct-13 19-Mar-14 19-May-14 16-Mar-16 15-Mar-17 
Actual 22-Oct-12 1-Aug-13 18-Nov-13 19-Mar-14 19-May-14 16-Mar-16 3-May-17 
QS032 Link Road to Masyabiah Farm 
QS034 Salwa International Highway - Landscaping  Irrigation Prelim. Design 
Baseline Concept/ On 
21-Feb-13 19-Jun-13 21-Oct-13 19-Mar-14 3-Jun-14 16-Mar-16 15-Mar-17 
Actual Hold 
20-Feb-13 2-Oct-13 13-Jan-14 4-Jun-14 24-Aug-14 1-Jun-16 7-Jun-17 
Concept 
Design 
Baseline 27-Feb-13 18-Sep-13 19-Feb-14 21-May-14 5-Aug-14 19-Aug-15 17-Aug-16 
Actual 27-Feb-13 20-Nov-13 19-Mar-14 18-Jun-14 2-Sep-14 7-Oct-15 16-Nov-16 
QS035 Al Kharrara/AlWakra Road Tareenah/Al Kharrara Road 
Roads and Infrastructure for Government Residential 
Division Project 
Gateway 4 History 
Project No. Gateway 4 Date Status 
QS004- Roads and Infrastructure in Wadi Aba Seleel 3-Jul-13 
Approved 
QS034- Salwa International Highway - Landscaping  Irrigation 1-Aug-13 Approved 
QS036 
Detailed 
Design 
QS029 
Roads and Infrastructure in Umm Al Zubar East  West 
Village 
Initiation/ On 
Hold 
QS035- Al Kharrara/AlWakra Road Tareenah/Al Kharrara Road 4-Sep-13 Approved 
QS032- Link Road to Masyabiah Farm 2-Oct-13 Approved 
QS016- Access Road to Rashid Village 6-Nov-13 Not Approved 
File:- Current Approved Baseline Page 1 of 1 Printed On :- 11/11/2013 at 16:01
Contract 2 
Local Roads and Drainage Programme 
QS004 – Roads and Infrastructure in Wadi Aba Saleel 
QATAR 
ACCOUNT 
MANAGEMENT 
PROGRAM
1 
Schedule Dashboard 
Projects Milestones 
QS004 - Roads and Infrastructure QQQSSS000000444 --- RRRoooaaadddsss aaannnddd IIInnnfffrrraaassstttrrruuuccctttuuurrreee iiiinnnn WWWWaaaaddddiiii AAAAbbbbaaaa SSSSeeeelllleeeeeeeellll Plan. Act. 
Initiation G1 15-May-13 15-May-13 0 100% 100% 0 
Concept Design G2 20-Nov-13 20-Nov-13 0 90.0% 73.7% 0 
Preliminary Design 13-Feb-14 13-Feb-14 0 0% 0% 0 
Detailed DesignTender Documents G3 17-Sep-14 17-Sep-14 0 0% 0% 0 
Tendering 04-Nov-14 04-Nov-14 0 0% 0% 0 
Construction G5 21-Jun-17 21-Jun-17 0 0% 0% 0 
Maintenance Period G6 18-Jul-18 01-Aug-18 -14 0% 0% -14 
Monthly Progress Report No. 13 ­Oct 
2013 
Milestones Gateway Planned 
Actual / 
Forecast 
Total 
Variance 
% Progress Trend 
Initiation 
Concept Design 
Preliminary Design 
Detailed DesignTender 
Documents 
Tendering 
Construction 
Maintenance Period 
Planned 
Actual/Forecast 
G1 
G2 
G3 
G5 
G6 
Behind Schedule No Change 
Downward Trend 
On Schedule 
Concept 
Design 
Current Segment 
20 
Days Until Completion 
(Starting from 1st Nov) 
73.7 0.82 
Progress % Complete SPI 
Upward Trend 
File :- Schedule Management - Oct 13 Printed On :- 11/11/2013 at 16:06
Activity ID Activity Name Planned 
Duration 
Current 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
Project Wide - High Level Schedule 1325 1335 11-Apr-13 18-Jul-18 11-Apr-13 A 01-Aug-18 0 0% 
Programme Wide -High Level Schedule 1325 1335 11-Apr-13 18-Jul-18 11-Apr-13 A 01-Aug-18 0 0% 
Programme Wide High Level Schedule 1325 1335 11-Apr-13 18-Jul-18 11-Apr-13 A 01-Aug-18 0 0% 
Initiation 25 25 11-Apr-13 15-May-13 11-Apr-13 A 15-May-13 A 0% 
Initiation 11 11 11-Apr-13 25-Apr-13 11-Apr-13 A 25-Apr-13 A 0% 
QS004 020000 Formal Confirmation Letter from PMC 0 0 11-Apr-13 11-Apr-13 A 100% 
QS004 020330 Initiation 11 11 11-Apr-13 25-Apr-13 11-Apr-13 A 25-Apr-13 A 100% 
QS004 020340 Initiation Slides Submission 0 0 25-Apr-13 25-Apr-13 A 100% 
18 Day Review 19 19 27-Apr-13 15-May-13 27-Apr-13 A 15-May-13 A 0% 
QS004 212101 PMC/PWA Initiation Review 18 18 27-Apr-13 14-May-13 27-Apr-13 A 14-May-13 A 100% 
QS004 020061 Gateway 1 Review Meeting 0 0 15-May-13 15-May-13 A 100% 
Concept Design 129 129 16-May-13 20-Nov-13 16-May-13 A 20-Nov-13 0 0% 
Concept Design 103 103 16-May-13 10-Oct-13 16-May-13 A 10-Oct-13 A 0% 
QS004 020070 Concept Design 103 103 16-May-13 10-Oct-13 16-May-13 A 10-Oct-13 A 100% 
QS004 212411 Concept Design Submission 0 0 10-Oct-13 10-Oct-13 A 100% 
35 Day Review 41 41 11-Oct-13 20-Nov-13 11-Oct-13 A 20-Nov-13 0 0% 
QS004 212421 PMC Concept Design Review 10 10 11-Oct-13 20-Oct-13 11-Oct-13 A 01-Nov-13 0 60% 
QS004 212431 GEC Response to PMC Comments 7 7 21-Oct-13 27-Oct-13 21-Oct-13 A 01-Nov-13 0 34.03% 
QS004 212441 PMC Review of GEC Response 4 4 28-Oct-13 31-Oct-13 02-Nov-13 05-Nov-13 0 0% 
QS004 212451 PWA Review 14 14 01-Nov-13 14-Nov-13 06-Nov-13 19-Nov-13 0 0% 
QS004 212461 Gateway 2 Review Meeting 0 0 20-Nov-13 20-Nov-13 0 0% 
Preliminary Design 82 82 21-Nov-13 20-Mar-14 21-Nov-13 20-Mar-14 90 0% 
Preliminary Design 57 57 21-Nov-13 13-Feb-14 21-Nov-13 13-Feb-14 0 0% 
QS004 020130 Preliminary Design 57 57 21-Nov-13 13-Feb-14 21-Nov-13 13-Feb-14 0 0% 
QS004 212471 Preliminary Design Submission 0 0 13-Feb-14 13-Feb-14 0 0% 
35 Day Review 35 35 14-Feb-14 20-Mar-14 14-Feb-14 20-Mar-14 126 0% 
QS004 212481 PMC Preliminary Design Review 10 10 14-Feb-14 23-Feb-14 14-Feb-14 23-Feb-14 126 0% 
QS004 212491 GEC Response to PMC Comments 7 7 24-Feb-14 02-Mar-14 24-Feb-14 02-Mar-14 126 0% 
QS004 212501 PMC Review of GEC Response 4 4 03-Mar-14 06-Mar-14 03-Mar-14 06-Mar-14 126 0% 
QS004 212511 PWA Review 14 14 07-Mar-14 20-Mar-14 07-Mar-14 20-Mar-14 126 0% 
Detailed Design  Tender Documents 151 151 16-Feb-14 17-Sep-14 16-Feb-14 17-Sep-14 0 0% 
Detailed Design  Tender Documents 125 125 16-Feb-14 12-Aug-14 16-Feb-14 12-Aug-14 0 0% 
QS004 020140 Detailed Design 115 115 16-Feb-14 24-Jul-14 16-Feb-14 24-Jul-14 0 0% 
QS004 020150 Tender Documents 31 31 26-Jun-14 12-Aug-14 26-Jun-14 12-Aug-14 0 0% 
QS004 212521 Detailed DesignTender Documents Submission 0 0 12-Aug-14 12-Aug-14 0 0% 
35 Day Review 36 36 13-Aug-14 17-Sep-14 13-Aug-14 17-Sep-14 0 0% 
QS004 212531 PMC Detailed DesignTender Documents Review 10 10 13-Aug-14 22-Aug-14 13-Aug-14 22-Aug-14 0 0% 
QS004 212541 GEC Response to PMC Comments 7 7 23-Aug-14 29-Aug-14 23-Aug-14 29-Aug-14 0 0% 
QS004 212551 PMC Review of GEC Response 4 4 30-Aug-14 02-Sep-14 30-Aug-14 02-Sep-14 0 0% 
QS004 212561 PWA Review 14 14 03-Sep-14 16-Sep-14 03-Sep-14 16-Sep-14 0 0% 
QS004 020180 Gateway 3 Review Meeting 0 0 17-Sep-14 17-Sep-14 0 0% 
Tendering 42 42 18-Sep-14 19-Nov-14 18-Sep-14 19-Nov-14 12 0% 
Tendering and Awarding 42 42 18-Sep-14 19-Nov-14 18-Sep-14 19-Nov-14 12 0% 
QS004 020210 Tendering of the Project 14 14 18-Sep-14 12-Oct-14 18-Sep-14 12-Oct-14 0 0% 
2013 2014 2015 2016 2017 2018 2019 
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 
Formal Confirmation Letter from PMC 
Initiation 
Initiation Slides Submission 
PMC/PWA Initiation Review 
Gateway 1 Review Meeting 
Concept Design 
Concept Design Submission 
PMC Concept Design Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 2 Review Meeting 
Preliminary Design 
Preliminary Design Submission 
PMC Preliminary Design Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Detailed Design 
Tender Documents 
Detailed DesignTender Documents Submission 
PMC Detailed DesignTender Documents Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 3 Review Meeting 
Tendering of the Project 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 1 of 4 
Printed On : 07-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS004 - Roads and Infrastrucutre in Wadi Aba Seleel 
Update as of 31-Oct-2013 
Date Revision Ch... Appro... 
31-Aug-13 Schedule Update - Aug-13 MN 
30-Sep-13 Schedule Update - Sep-13 MN 
31-Oct-13 Schedule Update - Oct-13 MN
Activity ID Activity Name Planned 
Duration 
Current 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
QS004 020250 Tender AssessmentRecommendations 7 7 13-Oct-14 21-Oct-14 13-Oct-14 21-Oct-14 0 0% 
QS004 020220 Award of the Construction Contract (Work Order) 0 0 04-Nov-14 04-Nov-14 0 0% 
QS004 020270 PMC/PWA Approval 10 10 22-Oct-14 04-Nov-14 22-Oct-14 04-Nov-14 0 0% 
QS004 020360 Prepare and Issue Notice to Proceed 1 1 05-Nov-14 05-Nov-14 05-Nov-14 05-Nov-14 0 0% 
QS004 020280 Prepare Contract Documents for Work Order 5 5 06-Nov-14 12-Nov-14 06-Nov-14 12-Nov-14 12 0% 
QS004 020300 Contract Signed off by ContractorPWA 4 4 13-Nov-14 18-Nov-14 13-Nov-14 18-Nov-14 12 0% 
QS004 020380 Exchange of Contract 1 1 19-Nov-14 19-Nov-14 19-Nov-14 19-Nov-14 12 0% 
Construction 664 664 06-Nov-14 21-Jun-17 06-Nov-14 21-Jun-17 0 0% 
Construction Period 638 638 06-Nov-14 16-May-17 06-Nov-14 16-May-17 0 0% 
QS004 020310 Contractor Mobilization Period 22 22 06-Nov-14 07-Dec-14 06-Nov-14 07-Dec-14 0 0% 
QS004 020230 Construction of the Project 616 616 08-Dec-14 16-May-17 08-Dec-14 16-May-17 0 0% 
QS004 212611 Construction Documents Submission 0 0 16-May-17 16-May-17 0 0% 
35 Day Review 36 36 17-May-17 21-Jun-17 17-May-17 21-Jun-17 0 0% 
QS004 212571 PMC Construction Documents Review 10 10 17-May-17 26-May-17 17-May-17 26-May-17 0 0% 
QS004 212581 GEC Response to PMC Comments 7 7 27-May-17 02-Jun-17 27-May-17 02-Jun-17 0 0% 
QS004 212591 PMC Review of GEC Response 4 4 03-Jun-17 06-Jun-17 03-Jun-17 06-Jun-17 0 0% 
QS004 212601 PWA Review 14 14 07-Jun-17 20-Jun-17 07-Jun-17 20-Jun-17 0 0% 
QS004 020260 Gateway 5 Review Meeting 0 0 21-Jun-17 21-Jun-17 0 0% 
Maintenance Period 392 406 22-Jun-17 18-Jul-18 22-Jun-17 01-Aug-18 0 0% 
Maintenance Period 356 365 22-Jun-17 12-Jun-18 22-Jun-17 21-Jun-18 0 0% 
QS004 020290 Maintenance Period 244 365 22-Jun-17 12-Jun-18 22-Jun-17 21-Jun-18 0 0% 
QS004 212621 Maintenance Documents Submission 0 0 12-Jun-18 21-Jun-18 0 0% 
35 Day Review 36 41 13-Jun-18 18-Jul-18 22-Jun-18 01-Aug-18 0 0% 
QS004 212631 PMC Maintenance Documents Review 10 10 13-Jun-18 22-Jun-18 22-Jun-18 01-Jul-18 0 0% 
QS004 212641 GEC Response to PMC Comments 7 7 23-Jun-18 29-Jun-18 02-Jul-18 08-Jul-18 0 0% 
QS004 212651 PMC Review of GEC Response 4 4 30-Jun-18 03-Jul-18 09-Jul-18 12-Jul-18 0 0% 
QS004 212661 PWA Review 14 14 04-Jul-18 17-Jul-18 13-Jul-18 26-Jul-18 0 0% 
QS004 020320 Gateway 6 Review Meeting 0 0 18-Jul-18 01-Aug-18 0 0% 
QS004 020350 Project Completion 0 0 18-Jul-18 01-Aug-18 0 0% 
MMUP and MOE 267 275 13-Oct-13 06-Nov-14 11-Apr-13 A 06-Nov-14 21 0% 
Ministry of Environment 267 275 13-Oct-13 06-Nov-14 11-Apr-13 A 06-Nov-14 21 0% 
Ministry of Environment 267 275 13-Oct-13 06-Nov-14 11-Apr-13 A 06-Nov-14 21 0% 
QS004 440000 PMC/MOE Review 30 30 25-Dec-13 23-Jan-14 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440010 Enviromental Scoping 30 30 26-Jan-14 09-Mar-14 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440020 PMC/MOE Review 30 30 11-Mar-14 09-Apr-14 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440030 Environmental Impact Assessment (EIA) 61 61 10-Apr-14 03-Jul-14 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440040 PMC/MOE Review 30 30 07-Jul-14 05-Aug-14 11-Apr-13 A 11-Apr-13 A 100% 
QS004 440050 Enviromental Permit Issued 0 0 06-Aug-14 11-Apr-13 A 0% 
QS004 440080 Permit Application Submission 0 0 24-Dec-13 11-Apr-13 A 0% Escaped 
QS004 440090 Enviromental Scoping Submission 0 0 10-Mar-14 11-Apr-13 A 0% Escaped 
QS004 440100 EIA Submission 0 0 06-Jul-14 11-Apr-13 A 0% Escaped 
QS004 440060 Preparation of Enviromental Permit Application 48 48 13-Oct-13 23-Dec-13 15-May-13 A 26-May-13 A 100% 
QS004 440070 Review Contractor CEMP 6 6 15-Oct-14 22-Oct-14 15-Oct-14 22-Oct-14 31 0% 
QS004 440110 CEMP Submission to MOE 0 0 06-Nov-14 06-Nov-14 21 0% 
2013 2014 2015 2016 2017 2018 2019 
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 
Tender AssessmentRecommendations 
Award of the Construction Contract (Work Order) 
PMC/PWA Approval 
Prepare and Issue Notice to Proceed 
Prepare Contract Documents for Work Order 
Contract Signed off by ContractorPWA 
Exchange of Contract 
Contractor Mobilization Period 
Construction of the Project 
Construction Documents Subm 
PMC Construction Documents 
GEC Response to PMC Comm 
PMC Review of GEC Respon 
PWA Review 
Gateway 5 Review Meeting 
Maintenance P 
Maintenance D 
PMC Mainten 
GEC Respon 
PMC Review 
PWA Review 
Gateway 6 R 
Project Com 
PMC/MOE Review 
Enviromental Scoping 
PMC/MOE Review 
Environmental Impact Assessment (EIA) 
PMC/MOE Review 
Enviromental Permit Issued 
Permit Application Submission 
Enviromental Scoping Submission 
EIA Submission 
Preparation of Enviromental Permit Application 
Review Contractor CEMP 
CEMP Submission to MOE 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 2 of 4 
Printed On : 07-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS004 - Roads and Infrastrucutre in Wadi Aba Seleel 
Update as of 31-Oct-2013 
Date Revision Ch... Appro... 
31-Aug-13 Schedule Update - Aug-13 MN 
30-Sep-13 Schedule Update - Sep-13 MN 
31-Oct-13 Schedule Update - Oct-13 MN
Activity ID Activity Name Planned 
Duration 
Current 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
Stakeholders Engagement 1258 1268 15-Jul-13 18-Jul-18 11-Apr-13 A 01-Aug-18 0 0% 
Concept Design 87 87 15-Jul-13 20-Nov-13 16-May-13 A 20-Nov-13 0 0% 
Concept Design 87 87 15-Jul-13 20-Nov-13 16-May-13 A 20-Nov-13 0 0% 
QS004 021020 Liaison with Stakeholders - Concept Design 87 87 15-Jul-13 20-Nov-13 16-May-13 A 20-Nov-13 0 88.89% 
Preliminary Design 60 60 18-Nov-13 13-Feb-14 18-Nov-13 13-Feb-14 0 0% 
Preliminary Design 60 60 18-Nov-13 13-Feb-14 18-Nov-13 13-Feb-14 0 0% 
QS004 212671 Liaison with Stakeholders - Preliminary Design 60 60 18-Nov-13 13-Feb-14 18-Nov-13 13-Feb-14 0 0% 
Detailed Design  Tendering 180 180 19-Feb-14 05-Nov-14 19-Feb-14 05-Nov-14 0 0% 
Detailed Design  Tendering 180 180 19-Feb-14 05-Nov-14 19-Feb-14 05-Nov-14 0 0% 
QS004 212681 Liaison with Stakeholders - Detailed Design  Tendering 180 180 19-Feb-14 05-Nov-14 19-Feb-14 05-Nov-14 0 0% 
Construction 664 664 06-Nov-14 21-Jun-17 06-Nov-14 21-Jun-17 0 0% 
Construction 664 664 06-Nov-14 21-Jun-17 06-Nov-14 21-Jun-17 0 0% 
QS004 212701 Liaison with Stakeholders - Construction 664 664 06-Nov-14 21-Jun-17 06-Nov-14 21-Jun-17 0 0% 
Maintenance Period 267 267 22-Jun-17 18-Jul-18 11-Jul-17 01-Aug-18 0 0% 
Maintenance Period 267 267 22-Jun-17 18-Jul-18 11-Jul-17 01-Aug-18 0 0% 
QS004 212711 Liaison with Stakeholders - Maintenance Period 267 267 22-Jun-17 18-Jul-18 11-Jul-17 01-Aug-18 0 0% 
MMUP Utility Investigation 90 104 15-Jul-13 25-Nov-13 11-Apr-13 A 15-Dec-13 40 0% 
QS004 440240 Superimpose Data on Proposed Road Layout 10 10 05-Sep-13 18-Sep-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440260 Agencies Approval 15 15 19-Sep-13 09-Oct-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440210 Utility Investigation by Owner/Consultant/Client 10 10 15-Jul-13 28-Jul-13 15-Jul-13 A 28-Jul-13 A 100% 
QS004 440220 Collect Data (Existing  Proposed Utilties) 10 10 29-Jul-13 14-Aug-13 29-Jul-13 A 14-Aug-13 A 100% 
QS004 440230 Topo Survey,Trial Pits and Radio Detection 15 15 15-Aug-13 04-Sep-13 15-Aug-13 A 24-Nov-13 40 10% 
QS004 440290 MMUP Approval 15 15 10-Oct-13 04-Nov-13 04-Nov-13 24-Nov-13 40 0% 
QS004 440300 Final Report to MMUP 15 15 05-Nov-13 25-Nov-13 25-Nov-13 15-Dec-13 40 0% 
KAHRAMA 75 114 15-Jul-13 04-Nov-13 15-Jul-13 A 31-Dec-13 30 0% 
QS004 440310 Send an Introductory Letters to KAHRAMA 10 10 15-Jul-13 28-Jul-13 15-Jul-13 A 28-Jul-13 A 100% 
QS004 440320 Request for Information about KAHRAMA's Current/Futu 10 10 29-Jul-13 14-Aug-13 29-Jul-13 A 14-Aug-13 A 100% 
QS004 440340 Superimpose the Plans on Proposed Project to Identify C 10 10 05-Sep-13 18-Sep-13 05-Sep-13 A 17-Nov-13 30 50% 
QS004 440330 Receive Information about KAHRAMA's Current/Future P 15 15 15-Aug-13 04-Sep-13 15-Aug-13 A 24-Nov-13 30 50% 
QS004 440350 Report the Conflicts to KAHRAMA 10 10 19-Sep-13 02-Oct-13 18-Nov-13 01-Dec-13 30 0% 
QS004 440360 Amend the Drawings 10 10 03-Oct-13 21-Oct-13 02-Dec-13 15-Dec-13 30 0% 
QS004 440370 Drawings Submission to KAHRAMA for Approval 10 10 22-Oct-13 04-Nov-13 16-Dec-13 31-Dec-13 30 0% 
Communication (Oredoo/Vodafone) 75 114 15-Jul-13 04-Nov-13 15-Jul-13 A 31-Dec-13 30 0% 
QS004 440380 Send an Introductory Letters to Oredoo/Vodafone 10 10 15-Jul-13 28-Jul-13 15-Jul-13 A 28-Jul-13 A 100% 
QS004 440390 Request for Information about Oredo/Vodafone's Curren 10 10 29-Jul-13 14-Aug-13 29-Jul-13 A 14-Aug-13 A 100% 
QS004 440400 Receive Information about Oredo/Vodafone's Current/Fu 15 15 15-Aug-13 04-Sep-13 15-Aug-13 A 04-Sep-13 A 100% 
QS004 440410 Superimpose the Plans on Proposed Project to Identify C 10 10 05-Sep-13 18-Sep-13 05-Sep-13 A 17-Nov-13 30 25% 
QS004 440420 Report the Conflicts to Oredoo/Vodafone 10 10 19-Sep-13 02-Oct-13 18-Nov-13 01-Dec-13 30 0% 
QS004 440430 Amend the Drawings 10 10 03-Oct-13 21-Oct-13 02-Dec-13 15-Dec-13 30 0% 
QS004 440440 Drawings Submission to Oredoo/Vodafone for Approval 10 10 22-Oct-13 04-Nov-13 16-Dec-13 31-Dec-13 30 0% 
Natural Reserves (NR) 75 75 15-Jul-13 04-Nov-13 11-Apr-13 A 11-Apr-13 A 0% 
QS004 440450 Send an Introductory Letters to NR 10 10 15-Jul-13 28-Jul-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440460 Request for Information about NR's Current/Future Proje 10 10 29-Jul-13 14-Aug-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440470 Receive Information about NR's Current/Future Projects 15 15 15-Aug-13 04-Sep-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
2013 2014 2015 2016 2017 2018 2019 
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 
Liaison with Stakeholders - Concept Design 
Liaison with Stakeholders - Preliminary Design 
Liaison with Stakeholders - Detailed Design  Tendering 
Liaison with Stakeholders - C 
Liaison with 
Superimpose Data on Proposed Road Layout 
Agencies Approval 
Utility Investigation by Owner/Consultant/Client 
Collect Data (Existing  Proposed Utilties) 
Topo Survey,Trial Pits and Radio Detection 
MMUP Approval 
Final Report to MMUP 
Send an Introductory Letters to KAHRAMA 
Request for Information about KAHRAMA's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Receive Information about KAHRAMA's Current/Future Projects 
Report the Conflicts to KAHRAMA 
Amend the Drawings 
Drawings Submission to KAHRAMA for Approval 
Send an Introductory Letters to Oredoo/Vodafone 
Request for Information about Oredo/Vodafone's Current/Future Projects 
Receive Information about Oredo/Vodafone's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Report the Conflicts to Oredoo/Vodafone 
Amend the Drawings 
Drawings Submission to Oredoo/Vodafone for Approval 
Send an Introductory Letters to NR 
Request for Information about NR's Current/Future Projects 
Receive Information about NR's Current/Future Projects 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 3 of 4 
Printed On : 07-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS004 - Roads and Infrastrucutre in Wadi Aba Seleel 
Update as of 31-Oct-2013 
Date Revision Ch... Appro... 
31-Aug-13 Schedule Update - Aug-13 MN 
30-Sep-13 Schedule Update - Sep-13 MN 
31-Oct-13 Schedule Update - Oct-13 MN
Activity ID Activity Name Planned 
Duration 
Current 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
QS004 440480 Superimpose the Plans on Proposed Project to Identify C 10 10 05-Sep-13 18-Sep-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440490 Report the Conflicts to NR 10 10 19-Sep-13 02-Oct-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440500 Amend the Drawings 10 10 03-Oct-13 21-Oct-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440510 Drawings Submission to NR for Approval 10 10 22-Oct-13 04-Nov-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
Private Engineer Office (PEO) 75 94 15-Jul-13 04-Nov-13 11-Apr-13 A 01-Dec-13 50 0% 
QS004 440570 Amend the Drawings 10 10 03-Oct-13 21-Oct-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 
QS004 440520 Send an Introductory Letters to PEO 10 10 15-Jul-13 28-Jul-13 15-Jul-13 A 28-Jul-13 A 100% 
QS004 440530 Request for Information about PEO's Current/Future Pro 10 10 29-Jul-13 14-Aug-13 29-Jul-13 A 14-Aug-13 A 100% 
QS004 440540 Receive Information about PEO's Current/Future Projects 15 15 15-Aug-13 04-Sep-13 15-Aug-13 A 04-Sep-13 A 100% 
QS004 440550 Superimpose the Plans on Proposed Project to Identify C 10 10 05-Sep-13 18-Sep-13 05-Sep-13 A 18-Sep-13 A 100% 
QS004 440560 Report the Conflicts to PEO 10 10 19-Sep-13 02-Oct-13 19-Sep-13 A 17-Nov-13 50 5% 
QS004 440580 Drawings Submission to PEO for Approval 10 10 22-Oct-13 04-Nov-13 18-Nov-13 01-Dec-13 50 0% 
2013 2014 2015 2016 2017 2018 2019 
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 
Superimpose the Plans on Proposed Project to Identify Conflict 
Report the Conflicts to NR 
Amend the Drawings 
Drawings Submission to NR for Approval 
Amend the Drawings 
Send an Introductory Letters to PEO 
Request for Information about PEO's Current/Future Projects 
Receive Information about PEO's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Report the Conflicts to PEO 
Drawings Submission to PEO for Approval 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 4 of 4 
Printed On : 07-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS004 - Roads and Infrastrucutre in Wadi Aba Seleel 
Update as of 31-Oct-2013 
Date Revision Ch... Appro... 
31-Aug-13 Schedule Update - Aug-13 MN 
30-Sep-13 Schedule Update - Sep-13 MN 
31-Oct-13 Schedule Update - Oct-13 MN
Activity ID Activity Name Planned Start Planned Finish Budgeted Payment 
(QAR) 
Actual Payment 
(QAR) 
Remaining Payment 
(QAR) 
Payment % 
Complete 
Earned Value Cost 
Total 16-May-13 19-Nov-14 QR18,219,504 QR3,702,675 QR14,516,831 20.32% QR3,702,673 
Concept Design 16-May-13 14-Nov-13 QR5,877,259 QR3,702,675 QR2,174,587 63% QR3,702,673 
Submission of Concept Design (60%) 16-May-13 07-Oct-13 QR3,526,356 QR3,526,357 QR1 100% QR3,526,356 
QS0041088 Project Schedule 16-May-13 12-Jun-13 QR528,953 QR528,953 QR0 100% QR528,953 
QS0041098 Main Report (Volume 1) 27-Aug-13 03-Oct-13 QR528,953 QR528,953 QR0 100% QR528,953 
QS0041108 Geotechnical Report (Volume 2) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 
QS0041118 Traffic Analysis Report (Volume 3) 05-Sep-13 02-Oct-13 QR352,636 QR352,636 QR0 100% QR352,636 
QS0041128 Drainage Part A (SW  GW) (Volume 4A) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 
QS0041138 Drainage Part B (FS) (Volume 4B) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 
QS0041148 Drainage Part C (TSE) (Volume 4C) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 
QS0041158 Environmental and Sustainablity (Volume 5) 11-Sep-13 01-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 
QS0041168 Drawings (Volume 6) 05-Sep-13 02-Oct-13 QR528,953 QR528,953 QR0 100% QR528,953 
QS0041178 Stakeholders (Volume 7) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 
QS0041188 Commercial Report (Volume 8) 10-Sep-13 07-Oct-13 QR352,636 QR352,636 QR0 100% QR352,636 
QS0041198 RSA - Review (Volume 9A) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 
PMC Acceptance with Comments (20%) 13-Oct-13 20-Oct-13 QR1,175,452 QR117,545 QR1,057,907 10% QR117,545 
QS0041199 PMC Accpetance with Comments 13-Oct-13 20-Oct-13 QR1,175,452 QR117,545 QR1,057,907 10% QR117,545 
PMC Acceptance (10%) 28-Oct-13 31-Oct-13 QR587,726 QR58,773 QR528,953 10% QR58,773 
QS0041200 PMC Accpetance 28-Oct-13 31-Oct-13 QR587,726 QR58,773 QR528,953 10% QR58,773 
PWA Approval (10%) 03-Nov-13 14-Nov-13 QR587,726 QR0 QR587,726 0% QR0 
QS0041201 PWA Approval 03-Nov-13 14-Nov-13 QR587,726 QR0 QR587,726 0% QR0 
Preliminiary Design 21-Nov-13 20-Mar-14 QR2,468,449 QR0 QR2,468,449 0% QR0 
Submission of Preliminary Design (60%) 21-Nov-13 13-Feb-14 QR1,481,069 QR0 QR1,481,069 0% QR0 
QS0041000 Updated Project Schedule 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 
QS0041001 Volume 1 - Main Report 21-Nov-13 13-Feb-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041002 Volume 2 - Geotechnical Investigation Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 
QS0041003 Volume 3 - Traffic Analysis Report 21-Nov-13 13-Feb-14 QR185,134 QR0 QR185,134 0% QR0 
QS0041004 Volume 4A - Surface and Ground Water Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 
QS0041005 Volume 4B - Foul Water Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 
QS0041006 Volume 4C - Treated Sewage Effluent Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 
QS0041007 Volume 5 - Environmental and Sustainability 21-Nov-13 13-Feb-14 QR185,134 QR0 QR185,134 0% QR0 
QS0041008 Volume 6 - Drawings 21-Nov-13 13-Feb-14 QR259,187 QR0 QR259,187 0% QR0 
QS0041009 Volume 7 - Stakeholders Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 
QS0041019 Volume 8 - Commercial Report 21-Nov-13 13-Feb-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041029 Volume 9B - Road Safety Audit - Brief 21-Nov-13 13-Feb-14 QR37,027 QR0 QR37,027 0% QR0 
QS0041039 Volume 9C - Road Safety Audit - Report 21-Nov-13 13-Feb-14 QR37,027 QR0 QR37,027 0% QR0 
QS0041049 Volume 9D - Road Safety Audit - Designer's Res 21-Nov-13 13-Feb-14 QR37,027 QR0 QR37,027 0% QR0 
PMC Acceptance with Comments (20%) 16-Feb-14 23-Feb-14 QR493,690 QR0 QR493,690 0% QR0 
QS0041059 PMC Accpetance with Comments 16-Feb-14 23-Feb-14 QR493,690 QR0 QR493,690 0% QR0 
PMC Acceptance (10%) 03-Mar-14 06-Mar-14 QR246,845 QR0 QR246,845 0% QR0 
QS0041069 PMC Accpetance 03-Mar-14 06-Mar-14 QR246,845 QR0 QR246,845 0% QR0 
PWA Approval (10%) 09-Mar-14 20-Mar-14 QR246,845 QR0 QR246,845 0% QR0 
QS0041079 PWA Approval 09-Mar-14 20-Mar-14 QR246,845 QR0 QR246,845 0% QR0 
2013 2014 2015 
D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D J F 
Project Schedule 
Main Report (Volume 1) 
Geotechnical Report (Volume 2) 
Traffic Analysis Report (Volume 3) 
Drainage Part A (SW  GW) (Volume 4A) 
Drainage Part B (FS) (Volume 4B) 
Drainage Part C (TSE) (Volume 4C) 
Environmental and Sustainablity (Volume 5) 
Drawings (Volume 6) 
Stakeholders (Volume 7) 
Commercial Report (Volume 8) 
RSA - Review (Volume 9A) 
PMC Accpetance with Comments, PMC Accpe 
PMC Accpetance 
PWA Approval 
Updated Project Schedule 
Volume 1 - Main Report 
Volume 2 - Geotechnical Investigatio 
Volume 3 - Traffic Analysis Report 
Volume 4A - Surface and Ground Wa 
Volume 4B - Foul Water Report 
Volume 4C - Treated Sewage Effluen 
Volume 5 - Environmental and Susta 
Volume 6 - Drawings 
Volume 7 - Stakeholders Report 
Volume 8 - Commercial Report 
Volume 9B - Road Safety Audit - Brie 
Volume 9C - Road Safety Audit - Rep 
Volume 9D - Road Safety Audit - Des 
PMC Accpetance with Comments 
PMC Accpetance 
PWA Approval 
Public Works Authority 
Local Roads and Drainage Programme 
Earned Value as of 31-Oct-13 
Remaining Level of Effort 
Actual Level of Effort 
Baseline 
Project Start:- 11-Apr-13 
Project Finish:- 02-Aug-18 
Layout:- A4 - QS004 - Monthly EVM 
Report 
Data Date : 31-Oct-13 
Page : 1 of 3 
Printed On : 07-Nov-13 
Date Revision Checked Approved 
30-Sep-13 Payment Schedule Update MN 
31-Oct-13 Payment Schedule Update MN
Activity ID Activity Name Planned Start Planned Finish Budgeted Payment 
(QAR) 
Actual Payment 
(QAR) 
Remaining Payment 
(QAR) 
Payment % 
Complete 
Earned Value Cost 
Detailed Design 16-Feb-14 16-Sep-14 QR4,936,898 QR0 QR4,936,898 0% QR0 
Submission of Detailed Design (60%) 16-Feb-14 24-Jul-14 QR2,962,139 QR0 QR2,962,139 0% QR0 
QS0041167 Updated Project Schedule 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041168 Volume 1 - Main Report 16-Feb-14 24-Jul-14 QR444,321 QR0 QR444,321 0% QR0 
QS0041169 Volume 2 - Geotechnical Factual Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041170 Volume 2 - Geotechnical Interpretative Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041172 Volume 4A - Surface and Ground Water Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041173 Volume 4B - Foul Water Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041174 Volume 4C - Treated Sewage Effluent Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041175 Volume 5 - Environmental and Sustainability 16-Feb-14 24-Jul-14 QR296,214 QR0 QR296,214 0% QR0 
QS0041176 Volume 6 - Drawings 16-Feb-14 24-Jul-14 QR592,428 QR0 QR592,428 0% QR0 
QS0041177 Volume 7 - Stakeholders Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041178 Volume 8 - Commercial Report 16-Feb-14 24-Jul-14 QR296,214 QR0 QR296,214 0% QR0 
QS0041180 Volume 9C - Road Safety Audit - Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
QS0041181 Volume 9D - Road Safety Audit - Designer's Res 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 
PMC Acceptance with Comments (20%) 13-Aug-14 21-Aug-14 QR987,380 QR0 QR987,380 0% QR0 
QS0041219 PMC Accpetance with Comments 13-Aug-14 21-Aug-14 QR987,380 QR0 QR987,380 0% QR0 
PMC Acceptance (10%) 31-Aug-14 02-Sep-14 QR493,690 QR0 QR493,690 0% QR0 
QS0041229 PMC Accpetance 31-Aug-14 02-Sep-14 QR493,690 QR0 QR493,690 0% QR0 
PWA Approval (10%) 03-Sep-14 16-Sep-14 QR493,690 QR0 QR493,690 0% QR0 
QS0041239 PWA Approval 03-Sep-14 16-Sep-14 QR493,690 QR0 QR493,690 0% QR0 
Tender Documents 26-Jun-14 16-Sep-14 QR1,851,337 QR0 QR1,851,337 0% QR0 
Submission of Tender Documents (60%) 26-Jun-14 12-Aug-14 QR1,110,802 QR0 QR1,110,802 0% QR0 
QS0045470 Specification  Drawings 26-Jun-14 12-Aug-14 QR388,781 QR0 QR388,781 0% QR0 
QS0045471 Conditions of Contract 26-Jun-14 12-Aug-14 QR111,080 QR0 QR111,080 0% QR0 
QS0045472 Particular Conditions of Contract  Nominate S/C 26-Jun-14 12-Aug-14 QR55,540 QR0 QR55,540 0% QR0 
QS0045473 Preliminary Bill of Quantity 26-Jun-14 12-Aug-14 QR55,540 QR0 QR55,540 0% QR0 
QS0045474 Final Bill of Quantities 26-Jun-14 12-Aug-14 QR111,080 QR0 QR111,080 0% QR0 
QS0045475 Pre-Tender Estimate 26-Jun-14 12-Aug-14 QR222,160 QR0 QR222,160 0% QR0 
QS0045476 Project Programme 26-Jun-14 12-Aug-14 QR166,620 QR0 QR166,620 0% QR0 
PMC Acceptance with Comments (20%) 13-Aug-14 21-Aug-14 QR370,267 QR0 QR370,267 0% QR0 
QS0045477 PMC Accpetance with Comments 13-Aug-14 21-Aug-14 QR370,267 QR0 QR370,267 0% QR0 
PMC Acceptance (10%) 31-Aug-14 02-Sep-14 QR185,134 QR0 QR185,134 0% QR0 
QS0045499 PMC Accpetance 31-Aug-14 02-Sep-14 QR185,134 QR0 QR185,134 0% QR0 
PWA Approval (10%) 03-Sep-14 16-Sep-14 QR185,134 QR0 QR185,134 0% QR0 
QS0045100 PWA Approval 03-Sep-14 16-Sep-14 QR185,134 QR0 QR185,134 0% QR0 
Tender 18-Sep-14 05-Nov-14 QR1,851,337 QR0 QR1,851,337 0% QR0 
PWA Approval (100%) 18-Sep-14 05-Nov-14 QR1,851,337 QR0 QR1,851,337 0% QR0 
QS0045478 Issue Invitation toTender 18-Sep-14 18-Sep-14 QR185,134 QR0 QR185,134 0% QR0 
QS0045479 Tender Queries / Pre Tender Workshop 18-Sep-14 12-Oct-14 QR370,267 QR0 QR370,267 0% QR0 
QS0045480 Tender Evaluation  Report 13-Oct-14 21-Oct-14 QR370,267 QR0 QR370,267 0% QR0 
QS0045481 Award of Contract (Work Order) 22-Oct-14 04-Nov-14 QR555,401 QR0 QR555,401 0% QR0 
QS0045482 Prepare and Issue Notice to Proceed 05-Nov-14 05-Nov-14 QR370,267 QR0 QR370,267 0% QR0 
2013 2014 2015 
D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D J F 
Updated Project Sch 
Volume 1 - Main Rep 
Volume 2 - Geotechn 
Volume 2 - Geotechn 
Volume 4A - Surface 
Volume 4B - Foul W 
Volume 4C - Treated 
Volume 5 - Environm 
Volume 6 - Drawings 
Volume 7 - Stakehol 
Volume 8 - Commerc 
Volume 9C - Road S 
Volume 9D - Road S 
PMC Accpetance 
PMC Accpetanc 
PWA Approval 
Specification  Dra 
Conditions of Cont 
Particular Conditio 
Preliminary Bill of Q 
Final Bill of Quanti 
Pre-Tender Estima 
Project Programme 
PMC Accpetance 
PMC Accpetanc 
PWA Approval 
Issue Invitation 
Tender Quer 
Tender Eval 
Award of C 
Prepare an 
Public Works Authority 
Local Roads and Drainage Programme 
Earned Value as of 31-Oct-13 
Remaining Level of Effort 
Actual Level of Effort 
Baseline 
Project Start:- 11-Apr-13 
Project Finish:- 02-Aug-18 
Layout:- A4 - QS004 - Monthly EVM 
Report 
Data Date : 31-Oct-13 
Page : 2 of 3 
Printed On : 07-Nov-13 
Date Revision Checked Approved 
30-Sep-13 Payment Schedule Update MN 
31-Oct-13 Payment Schedule Update MN
Activity ID Activity Name Planned Start Planned Finish Budgeted Payment 
(QAR) 
Actual Payment 
(QAR) 
Remaining Payment 
(QAR) 
Payment % 
Complete 
Earned Value Cost 
Contract 06-Nov-14 19-Nov-14 QR1,234,224 QR0 QR1,234,224 0% QR0 
PWA Approval (100%) 06-Nov-14 19-Nov-14 QR1,234,224 QR0 QR1,234,224 0% QR0 
QS0045483 Prepare Contract Documents for Work Order 06-Nov-14 12-Nov-14 QR740,535 QR0 QR740,535 0% QR0 
QS0045484 Contract Signed Off by Contractor 13-Nov-14 18-Nov-14 QR185,134 QR0 QR185,134 0% QR0 
QS0045485 Contract Signed Off by PWA 13-Nov-14 18-Nov-14 QR185,134 QR0 QR185,134 0% QR0 
QS0045486 Exchange of Contract 19-Nov-14 19-Nov-14 QR123,422 QR0 QR123,422 0% QR0 
2013 2014 2015 
D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D J F 
Prepare C 
Contract 
Contract 
Exchang 
QR20,000,000QR 
QR16,000,000QR 
QR12,000,000QR 
QR8,000,000QR 
D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D J F 
2013 2014 2015 
QR3,000,000QR 
QR2,400,000QR 
QR1,800,000QR 
QR1,200,000QR 
QR600,000QR 
QR0QR 
QR4,000,000QR 
Actual Expense Cost 
Planned Value Cost 
Earned Value Cost 
BL Project Expense Cost 
Public Works Authority 
Local Roads and Drainage Programme 
Earned Value as of 31-Oct-13 
Remaining Level of Effort 
Actual Level of Effort 
Baseline 
Project Start:- 11-Apr-13 
Project Finish:- 02-Aug-18 
Layout:- A4 - QS004 - Monthly EVM 
Report 
Data Date : 31-Oct-13 
Page : 3 of 3 
Printed On : 07-Nov-13 
Date Revision Checked Approved 
30-Sep-13 Payment Schedule Update MN 
31-Oct-13 Payment Schedule Update MN
Contract 2 
Local Roads and Drainage Programme 
QS015-RoadsInfrastructure in Rawdat Rashed Village 
QATAR 
ACCOUNT 
MANAGEMENT 
PROGRAM
2 
Schedule Dashboard 
Projects Milestones 
Actual / 
Forecast 
Total 
Variance 
QS015 - Roads and Infrastructure in Rawdat QQQSSS000111555 --- RRRoooaaadddsss aaannnddd IIInnnfffrrraaassstttrrruuuccctttuuurrreee iiinnn RRRaaawwwdddaaattt RRRRaaaasssshhhheeeedddd VVVViiiillllllllaaaaggggeeee Plan. Act. 
Initiation G1 19-Dec-12 19-Dec-12 0 100% 100% 0 
Concept Design G2 17-Apr-13 03-Jul-13 -77 100% 100% -77 
Preliminary Design 30-Jul-13 26-Aug-13 -27 100% 100% -27 
Detailed DesignTender Documents G3 18-Dec-13 17-Dec-13 1 57.7% 17.0% 1 
Tendering 03-Mar-14 03-Mar-14 0 0% 0% 0 
Construction G5 18-Nov-15 18-Nov-15 0 0% 0% 0 
Maintenance Period G6 16-Nov-16 04-Jan-17 -49 0% 0% -49 
Monthly Progress Report No. 13 ­Oct 
2013 
Milestones Gateway Planned % Progress Trend 
Initiation 
Concept Design 
Preliminary Design 
Detailed DesignTender 
Documents 
Tendering 
Construction 
Maintenance Period 
Planned 
Actual/Forecast 
G1 
G2 
G3 
G5 
G6 
Behind Schedule No Change 
Upward Trend Downward Trend 
On Schedule 
Detailed 
Design  
Tender Docs. 
Current Segment 
16.9 0.29 
Progress % Complete 
47 
Days Until Completion 
(Starting from 1st Nov) 
SPI 
File :- Schedule Management - Oct 13 Printed On :- 11/11/2013 at 16:06
Activity ID Activity Name Planned 
Duration 
Current 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
Project Wide - High Level Schedule 1017 1049 04-Nov-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% 
Programme Wide -High Level Schedule 1017 1049 04-Nov-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% 
Programme Wide High Level Schedule 1017 1049 04-Nov-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% 
Initiation 33 33 04-Nov-12 19-Dec-12 04-Nov-12 A 19-Dec-12 A 0% 
Initiation 20 20 04-Nov-12 29-Nov-12 04-Nov-12 A 03-Dec-12 A 0% 
QS015 020000 PWA Formal Notification of Candidate Project 0 0 04-Nov-12 04-Nov-12 A 0% 
QS015 020330 Initiation 20 20 04-Nov-12 29-Nov-12 04-Nov-12 A 03-Dec-12 A 100% 
QS015 020340 Initiation Slides Submission 0 0 29-Nov-12 03-Dec-12 A 0% 
18 Day Review 19 19 01-Dec-12 19-Dec-12 04-Dec-12 A 19-Dec-12 A 0% 
QS015 212101 PMC/PWA Initiation Review 18 18 01-Dec-12 18-Dec-12 04-Dec-12 A 18-Dec-12 A 100% 
QS015 020061 Gateway 1 Review Meeting 0 0 19-Dec-12 19-Dec-12 A 0% 
Concept Design 82 82 20-Dec-12 17-Apr-13 20-Dec-12 A 03-Jul-13 A 0% 
Concept Design 56 56 20-Dec-12 12-Mar-13 20-Dec-12 A 02-May-13 A 0% 
QS015 212411 Concept Design Submission 0 0 12-Mar-13 12-Mar-13 A 0% 
QS015 020070 Concept Design 56 56 20-Dec-12 12-Mar-13 20-Dec-12 A 02-May-13 A 100% 
35 Day Review 36 36 13-Mar-13 17-Apr-13 07-Apr-13 A 03-Jul-13 A 0% 
QS015 212421 PMC Concept Design Review 10 10 13-Mar-13 22-Mar-13 07-Apr-13 A 05-May-13 A 100% 
QS015 212431 GEC Response to PMC Comments 7 7 23-Mar-13 29-Mar-13 07-Apr-13 A 05-May-13 A 100% 
QS015 212441 PMC Review of GEC Response 4 4 30-Mar-13 02-Apr-13 04-May-13 A 08-May-13 A 100% 
QS015 212451 PWA Review 14 14 03-Apr-13 16-Apr-13 08-May-13 A 15-May-13 A 100% 
QS015 212461 Gateway 2 Review Meeting 0 0 17-Apr-13 03-Jul-13 A 0% 
Preliminary Design 96 142 18-Apr-13 03-Sep-13 04-Jul-13 A 11-Nov-13 0 0% 
Preliminary Design 74 74 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 0% 
QS015 020130 Preliminary Design 74 35 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 100% Prelim design duration 
reduced to 35 
QS015 212471 Preliminary Design Submission 0 0 30-Jul-13 26-Aug-13 A 100% 
35 Day Review 35 104 31-Jul-13 03-Sep-13 27-Aug-13 A 11-Nov-13 0 0% 
QS015 212481 PMC Preliminary Design Review 10 10 31-Jul-13 09-Aug-13 27-Aug-13 A 07-Sep-13 A 100% 
QS015 212491 GEC Response to PMC Comments 7 7 10-Aug-13 16-Aug-13 08-Sep-13 A 01-Nov-13 0 80% 
QS015 212501 PMC Review of GEC Response 4 4 17-Aug-13 20-Aug-13 02-Nov-13 05-Nov-13 0 0% 
QS015 212511 PWA Review 14 6 21-Aug-13 03-Sep-13 06-Nov-13 11-Nov-13 0 0% 
Detailed Design  Tender Documents 94 94 31-Jul-13 18-Dec-13 27-Aug-13 A 18-Dec-13 0 0% 
Detailed Design  Tender Documents 68 68 31-Jul-13 12-Nov-13 27-Aug-13 A 12-Nov-13 0 0% 
QS015 020140 Detailed Design 60 44 31-Jul-13 30-Oct-13 27-Aug-13 A 11-Nov-13 0 35.86% Detailed design duration 
reduced to 44 
QS015 020150 Tender Documents 28 28 30-Sep-13 11-Nov-13 30-Sep-13 A 11-Nov-13 0 4.78% 
QS015 212521 Detailed DesignTender Documents Submission 0 0 12-Nov-13 12-Nov-13 0 0% 
35 Day Review 36 36 13-Nov-13 18-Dec-13 13-Nov-13 18-Dec-13 0 0% 
QS015 212531 PMC Detailed DesignTender Documents Review 10 10 13-Nov-13 22-Nov-13 13-Nov-13 22-Nov-13 0 0% 
QS015 212541 GEC Response to PMC Comments 7 7 23-Nov-13 29-Nov-13 23-Nov-13 29-Nov-13 0 0% 
QS015 212551 PMC Review of GEC Response 4 4 30-Nov-13 03-Dec-13 30-Nov-13 03-Dec-13 0 0% 
QS015 212561 PWA Review 14 14 04-Dec-13 17-Dec-13 04-Dec-13 17-Dec-13 0 0% 
QS015 020180 Gateway 3 Review Meeting 0 0 18-Dec-13 18-Dec-13 0 0% 
Tendering 61 61 19-Dec-13 18-Mar-14 19-Dec-13 18-Mar-14 13 0% 
2013 2014 2015 2016 2017 2018 2019 
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 
PWA Formal Notification of Candidate Project 
Initiation 
Initiation Slides Submission 
PMC/PWA Initiation Review 
Gateway 1 Review Meeting 
Concept Design Submission 
Concept Design 
PMC Concept Design Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 2 Review Meeting 
Preliminary Design 
Preliminary Design Submission 
PMC Preliminary Design Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Detailed Design 
Tender Documents 
Detailed DesignTender Documents Submission 
PMC Detailed DesignTender Documents Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 3 Review Meeting 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 1 of 4 
Printed On : 07-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS015 - Roads and Infrastrucutre in Rawdat Rashed Village 
Update as of 31-Oct-2013 
Date Revision Ch... Appro... 
31-Aug-13 Schedule Update - Aug-13 MN 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 MN
Activity ID Activity Name Planned 
Duration 
Current 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
Tender and Awarding 61 61 19-Dec-13 18-Mar-14 19-Dec-13 18-Mar-14 13 0% 
QS015 020210 Tendering of the Project 30 30 19-Dec-13 02-Feb-14 19-Dec-13 02-Feb-14 0 0% 
QS015 020240 Tender AssessmentRecommendations 10 10 03-Feb-14 17-Feb-14 03-Feb-14 17-Feb-14 0 0% 
QS015 020220 Award of the Construction Contract (Work Order) 0 0 03-Mar-14 03-Mar-14 0 0% 
QS015 020250 PMC/PWA Approval 10 10 18-Feb-14 03-Mar-14 18-Feb-14 03-Mar-14 0 0% 
QS015 020350 Prepare and Issue Notice to Proceed 1 1 04-Mar-14 04-Mar-14 04-Mar-14 04-Mar-14 0 0% 
QS015 020270 Prepare Contract Documents for Work Order 5 5 05-Mar-14 11-Mar-14 05-Mar-14 11-Mar-14 0 0% 
QS015 020280 Contract Signed Off by ContractorPWA 4 4 12-Mar-14 17-Mar-14 12-Mar-14 17-Mar-14 0 0% 
QS015 020310 Exchange of Contract 1 1 18-Mar-14 18-Mar-14 18-Mar-14 18-Mar-14 13 0% 
Construction 430 430 05-Mar-14 18-Nov-15 05-Mar-14 18-Nov-15 0 0% 
Construction Period 404 404 05-Mar-14 13-Oct-15 05-Mar-14 13-Oct-15 0 0% 
QS015 020300 Contractor Mobilization Period 23 23 05-Mar-14 06-Apr-14 05-Mar-14 06-Apr-14 0 0% 
QS015 020230 Construction of the Project 381 381 07-Apr-14 13-Oct-15 07-Apr-14 13-Oct-15 0 0% 
QS015 212611 Construction Documents Submission 0 0 13-Oct-15 13-Oct-15 0 0% 
35 Day Review 36 36 14-Oct-15 18-Nov-15 14-Oct-15 18-Nov-15 0 0% 
QS015 212571 PMC Construction Documents Review 10 10 14-Oct-15 23-Oct-15 14-Oct-15 23-Oct-15 0 0% 
QS015 212581 GEC Response to PMC Comments 7 7 24-Oct-15 30-Oct-15 24-Oct-15 30-Oct-15 0 0% 
QS015 212591 PMC Review of GEC Response 4 4 31-Oct-15 03-Nov-15 31-Oct-15 03-Nov-15 0 0% 
QS015 212601 PWA Review 14 14 04-Nov-15 17-Nov-15 04-Nov-15 17-Nov-15 0 0% 
QS015 020260 Gateway 5 Review Meeting 0 0 18-Nov-15 18-Nov-15 0 0% 
Maintenance Period 364 413 19-Nov-15 16-Nov-16 19-Nov-15 04-Jan-17 0 0% 
Maintenance Period 328 365 19-Nov-15 11-Oct-16 19-Nov-15 17-Nov-16 0 0% 
QS015 020290 Maintenance Period 227 365 19-Nov-15 11-Oct-16 19-Nov-15 17-Nov-16 0 0% 
QS015 212621 Maintenance Documents Submission 0 0 11-Oct-16 17-Nov-16 0 0% 
35 Day Review 36 48 12-Oct-16 16-Nov-16 18-Nov-16 04-Jan-17 0 0% 
QS015 212631 PMC Maintenance Documents Review 10 10 12-Oct-16 21-Oct-16 18-Nov-16 27-Nov-16 0 0% 
QS015 212641 GEC Response to PMC Comments 7 7 22-Oct-16 28-Oct-16 28-Nov-16 04-Dec-16 0 0% 
QS015 212651 PMC Review of GEC Response 4 4 29-Oct-16 01-Nov-16 05-Dec-16 08-Dec-16 0 0% 
QS015 212661 PWA Review 14 14 02-Nov-16 15-Nov-16 09-Dec-16 22-Dec-16 0 0% 
QS015 020320 Gateway 6 Review Meeting 0 0 16-Nov-16 04-Jan-17 0 0% 
QS015 020360 Project Completion 0 0 16-Nov-16 04-Jan-17 0 0% 
MMUP  MOE 282 281 21-Jan-13 05-Mar-14 29-Jan-13 A 04-Mar-14 23 0% 
Ministry of Municipality and Urban Planning 11 11 21-Jan-13 04-Feb-13 27-Mar-13 A 15-Apr-13 A 0% 
Ministry of Municipality and Urban Planning 11 11 21-Jan-13 04-Feb-13 27-Mar-13 A 15-Apr-13 A 0% 
QS015 020080 Submission of TTN to PMC 0 0 21-Jan-13 27-Mar-13 A 0% 
QS015 020120 Review TTN by PMC 14 14 21-Jan-13 03-Feb-13 28-Mar-13 A 14-Apr-13 A 100% 
QS015 020090 Approval of TTN by PMC 0 0 04-Feb-13 15-Apr-13 A 0% 
Ministry of Environment 276 275 29-Jan-13 05-Mar-14 29-Jan-13 A 04-Mar-14 23 0% 
Ministry of Environment 276 275 29-Jan-13 05-Mar-14 29-Jan-13 A 04-Mar-14 23 0% 
QS015 440060 Preparation of Environmental Permit Application 30 30 29-Jan-13 12-Mar-13 29-Jan-13 A 06-Mar-13 A 100% 
QS015 440080 Permit Application Submission 0 0 13-Mar-13 07-Mar-13 A 0% 
QS015 440000 PMC/MOE Review 30 30 14-Mar-13 12-Apr-13 08-Mar-13 A 04-Aug-13 A 100% 
QS015 440010 Environmental Scoping 39 10 14-Apr-13 05-Jun-13 30-Jul-13 A 06-Aug-13 A 100% 
QS015 440090 Environmental Scoping Submission 0 0 06-Jun-13 06-Aug-13 A 0% 
2013 2014 2015 2016 2017 2018 2019 
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 
Tendering of the Project 
Tender AssessmentRecommendations 
Award of the Construction Contract (Work Order) 
PMC/PWA Approval 
Prepare and Issue Notice to Proceed 
Prepare Contract Documents for Work Order 
Contract Signed Off by ContractorPWA 
Exchange of Contract 
Contractor Mobilization Period 
Construction of the Project 
Construction Documents Submission 
PMC Construction Documents Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 5 Review Meeting 
Maintenance Period 
Maintenance Documents Submission 
PMC Maintenance Documents Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 6 Review Meeting 
Project Completion 
Submission of TTN to PMC 
Review TTN by PMC 
Approval of TTN by PMC 
Preparation of Environmental Permit Application 
Permit Application Submission 
PMC/MOE Review 
Environmental Scoping 
Environmental Scoping Submission 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 2 of 4 
Printed On : 07-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS015 - Roads and Infrastrucutre in Rawdat Rashed Village 
Update as of 31-Oct-2013 
Date Revision Ch... Appro... 
31-Aug-13 Schedule Update - Aug-13 MN 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 MN
Activity ID Activity Name Planned 
Duration 
Current 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
QS015 440020 PMC/MOE Review 30 30 07-Jun-13 06-Jul-13 07-Aug-13 A 01-Oct-13 A 100% 
QS015 440030 Environmental Impact Assessment (EIA) 66 15 07-Jul-13 09-Oct-13 02-Oct-13 A 03-Nov-13 2 90% 
QS015 440100 EIA Submission 0 0 10-Oct-13 05-Nov-13 2 0% 
QS015 440040 PMC/MOE Review 30 2 11-Oct-13 09-Nov-13 06-Nov-13 07-Nov-13 3 0% 
QS015 440050 Environmental Permit Issued 0 0 10-Nov-13 10-Nov-13 2 0% 
QS015 440070 Review Contractor CEMP 5 2 05-Feb-14 12-Feb-14 04-Feb-14 05-Feb-14 41 0% 
QS015 440110 CEMP Submission to MOE 0 0 05-Mar-14 04-Mar-14 23 0% 
Stakeholders Engagement 984 1016 20-Dec-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% 
Concept Design 82 82 20-Dec-12 17-Apr-13 20-Dec-12 A 03-Jul-13 A 0% 
Concept Design 82 82 20-Dec-12 17-Apr-13 20-Dec-12 A 03-Jul-13 A 0% 
QS015 021020 Liaison with Stakeholders - Concept Design 82 82 20-Dec-12 17-Apr-13 20-Dec-12 A 03-Jul-13 A 100% 
Preliminary Design 74 26 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 0% 
Preliminary Design 74 26 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 0% 
QS015 212671 Liaison with Stakeholders - Preliminary Design 74 26 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 100% 
Detailed Design  Tendering 145 129 31-Jul-13 04-Mar-14 27-Aug-13 A 04-Mar-14 0 0% 
Detailed Design  Tendering 145 129 31-Jul-13 04-Mar-14 27-Aug-13 A 04-Mar-14 0 0% 
QS015 212681 Liaison with Stakeholders - Detailed Design  Tendering 145 129 31-Jul-13 04-Mar-14 27-Aug-13 A 04-Mar-14 0 42.07% 
Construction 430 430 05-Mar-14 18-Nov-15 05-Mar-14 18-Nov-15 0 0% 
Construction 430 430 05-Mar-14 18-Nov-15 05-Mar-14 18-Nov-15 0 0% 
QS015 212701 Liaison with Stakeholders - Construction 430 430 05-Mar-14 18-Nov-15 05-Mar-14 18-Nov-15 0 0% 
Maintenance Period 984 1016 20-Dec-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% 
Maintenance Period 253 253 19-Nov-15 16-Nov-16 04-Jan-16 04-Jan-17 0 0% 
QS015 212711 Liaison with Stakeholders - Maintenance Period 253 253 19-Nov-15 16-Nov-16 04-Jan-16 04-Jan-17 0 0% 
MMUP Utility Investigation 90 242 20-Dec-12 29-Apr-13 04-Nov-12 A 05-Dec-13 8 0% 
QS015 440240 Superimpose Data on Proposed Road Layout 10 10 11-Feb-13 25-Feb-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440260 Agencies Approval 15 15 26-Feb-13 18-Mar-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440210 Utility Investigation by Owner/Consultant/Client 10 10 20-Dec-12 06-Jan-13 20-Dec-12 A 06-Jan-13 A 100% 
QS015 440220 Collect Data (Existing  Proposed Utilties) 10 10 07-Jan-13 20-Jan-13 07-Jan-13 A 20-Jan-13 A 100% 
QS015 440290 MMUP Approval 15 10 19-Mar-13 08-Apr-13 03-Nov-13 14-Nov-13 23 0% 
QS015 440230 Topo Survey,Trial Pits and Radio Detection 15 15 21-Jan-13 10-Feb-13 03-Nov-13 21-Nov-13 8 0% 
QS015 440300 Final Report to MMUP 15 10 09-Apr-13 29-Apr-13 24-Nov-13 05-Dec-13 8 0% 
KAHRAMA 75 75 20-Dec-12 08-Apr-13 20-Dec-12 A 05-Nov-13 5 0% 
QS015 440310 Send an Introductory Letters to KAHRAMA 10 10 20-Dec-12 06-Jan-13 20-Dec-12 A 06-Jan-13 A 100% 
QS015 440320 Request for Information about KAHRAMA's Current/Futu 10 10 07-Jan-13 20-Jan-13 07-Jan-13 A 20-Jan-13 A 100% 
QS015 440330 Receive Information about KAHRAMA's Current/Future P 15 15 21-Jan-13 10-Feb-13 21-Jan-13 A 10-Feb-13 A 100% 
QS015 440340 Superimpose the Plans on Proposed Project to Identify C 10 10 11-Feb-13 25-Feb-13 11-Feb-13 A 03-Nov-13 5 75% 
QS015 440370 Drawings Submission to KAHRAMA for Approval 10 10 26-Mar-13 08-Apr-13 26-Mar-13 A 04-Nov-13 5 25% 
QS015 440350 Report the Conflicts to KAHRAMA 10 10 26-Feb-13 11-Mar-13 26-Feb-13 A 05-Nov-13 5 75% 
QS015 440360 Amend the Drawings 10 10 12-Mar-13 25-Mar-13 12-Mar-13 A 05-Nov-13 5 75% 
Communication (Oredoo/Vodafone) 75 75 20-Dec-12 08-Apr-13 20-Dec-12 A 07-Nov-13 2 0% 
QS015 440380 Send an Introductory Letters to Oredoo/Vodafone 10 10 20-Dec-12 06-Jan-13 20-Dec-12 A 06-Jan-13 A 100% 
QS015 440390 Request for Information about Oredo/Vodafone's Curren 10 10 07-Jan-13 20-Jan-13 07-Jan-13 A 20-Jan-13 A 100% 
QS015 440400 Receive Information about Oredo/Vodafone's Current/Fu 15 15 21-Jan-13 10-Feb-13 21-Jan-13 A 10-Feb-13 A 100% 
QS015 440410 Superimpose the Plans on Proposed Project to Identify C 10 10 11-Feb-13 25-Feb-13 11-Feb-13 A 25-Feb-13 A 100% 
2013 2014 2015 2016 2017 2018 2019 
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 
PMC/MOE Review 
Environmental Impact Assessment (EIA) 
EIA Submission 
PMC/MOE Review 
Environmental Permit Issued 
Review Contractor CEMP 
CEMP Submission to MOE 
Liaison with Stakeholders - Concept Design 
Liaison with Stakeholders - Preliminary Design 
Liaison with Stakeholders - Detailed Design  Tendering 
Liaison with Stakeholders - Construction 
Liaison with Stakeholders - Maintena 
Superimpose Data on Proposed Road Layout 
Agencies Approval 
Utility Investigation by Owner/Consultant/Client 
Collect Data (Existing  Proposed Utilties) 
MMUP Approval 
Topo Survey,Trial Pits and Radio Detection 
Final Report to MMUP 
Send an Introductory Letters to KAHRAMA 
Request for Information about KAHRAMA's Current/Future Projects 
Receive Information about KAHRAMA's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Drawings Submission to KAHRAMA for Approval 
Report the Conflicts to KAHRAMA 
Amend the Drawings 
Send an Introductory Letters to Oredoo/Vodafone 
Request for Information about Oredo/Vodafone's Current/Future Projects 
Receive Information about Oredo/Vodafone's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 3 of 4 
Printed On : 07-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS015 - Roads and Infrastrucutre in Rawdat Rashed Village 
Update as of 31-Oct-2013 
Date Revision Ch... Appro... 
31-Aug-13 Schedule Update - Aug-13 MN 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 MN
Activity ID Activity Name Planned 
Duration 
Current 
Duration 
Planned Start Planned Finish Actual/Forecast 
Start 
Actual/Forecast 
Finish 
Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
QS015 440420 Report the Conflicts to Oredoo/Vodafone 10 10 26-Feb-13 11-Mar-13 26-Feb-13 A 11-Mar-13 A 100% 
QS015 440430 Amend the Drawings 10 10 12-Mar-13 25-Mar-13 12-Mar-13 A 25-Mar-13 A 100% 
QS015 440440 Drawings Submission to Oredoo/Vodafone for Approval 10 10 26-Mar-13 08-Apr-13 26-Mar-13 A 07-Nov-13 2 10% 
Natural Reserves (NR) 75 75 20-Dec-12 08-Apr-13 04-Nov-12 A 04-Nov-12 A 0% 
QS015 440450 Send an Introductory Letters to NR 10 10 20-Dec-12 06-Jan-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440460 Request for Information about NR's Current/Future Proje 10 10 07-Jan-13 20-Jan-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440470 Receive Information about NR's Current/Future Projects 15 15 21-Jan-13 10-Feb-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440480 Superimpose the Plans on Proposed Project to Identify C 10 10 11-Feb-13 25-Feb-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440490 Report the Conflicts to NR 10 10 26-Feb-13 11-Mar-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440500 Amend the Drawings 10 10 12-Mar-13 25-Mar-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440510 Drawings Submission to NR for Approval 10 10 26-Mar-13 08-Apr-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
Private Engineer Office (PEO) 75 224 20-Dec-12 08-Apr-13 04-Nov-12 A 11-Nov-13 0 0% 
QS015 440570 Amend the Drawings 10 10 12-Mar-13 25-Mar-13 04-Nov-12 A 04-Nov-12 A 100% Escaped 
QS015 440520 Send an Introductory Letters to PEO 10 10 20-Dec-12 06-Jan-13 20-Dec-12 A 07-Jan-13 A 100% 
QS015 440530 Request for Information about PEO's Current/Future Pro 10 10 07-Jan-13 20-Jan-13 07-Jan-13 A 20-Jan-13 A 100% 
QS015 440540 Receive Information about PEO's Current/Future Projects 15 15 21-Jan-13 10-Feb-13 21-Jan-13 A 10-Feb-13 A 100% 
QS015 440550 Superimpose the Plans on Proposed Project to Identify C 10 10 11-Feb-13 25-Feb-13 11-Feb-13 A 25-Feb-13 A 100% 
QS015 440560 Report the Conflicts to PEO 10 10 26-Feb-13 11-Mar-13 01-Oct-13 A 03-Nov-13 0 50% 
QS015 440580 Drawings Submission to PEO for Approval 10 7 26-Mar-13 08-Apr-13 03-Nov-13 11-Nov-13 0 0% 
2013 2014 2015 2016 2017 2018 2019 
3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 
Report the Conflicts to Oredoo/Vodafone 
Amend the Drawings 
Drawings Submission to Oredoo/Vodafone for Approval 
Send an Introductory Letters to NR 
Request for Information about NR's Current/Future Projects 
Receive Information about NR's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Report the Conflicts to NR 
Amend the Drawings 
Drawings Submission to NR for Approval 
Amend the Drawings 
Send an Introductory Letters to PEO 
Request for Information about PEO's Current/Future Projects 
Receive Information about PEO's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Report the Conflicts to PEO 
Drawings Submission to PEO for Approval 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 4 of 4 
Printed On : 07-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS015 - Roads and Infrastrucutre in Rawdat Rashed Village 
Update as of 31-Oct-2013 
Date Revision Ch... Appro... 
31-Aug-13 Schedule Update - Aug-13 MN 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 MN
Activity ID Activity Name Planned Start Planned Finish Budgeted Payment 
(QAR) 
Actual Payment 
(QAR) 
Remaining Payment 
(QAR) 
Payment % 
Complete 
Progress % 
Complete 
Earned Value Cost 
Total 20-Dec-12 18-Mar-14 QR5,622,663 QR2,198,449 QR3,424,215 39.1% 39.1% QR2,198,451 
Concept Design 20-Dec-12 16-Apr-13 QR1,385,832 QR1,302,682 QR83,151 94% 94% QR1,302,682 
Submission of Concept Design (60%) 20-Dec-12 27-Mar-13 QR831,499 QR831,500 QR0 100% 100% QR831,499 
QS0151088 Project Schedule 04-Mar-13 27-Mar-13 QR124,725 QR124,725 QR0 100% 100% QR124,725 
QS0151098 Main Report (Volume 1) 02-Jan-13 27-Feb-13 QR124,725 QR124,725 QR0 100% 100% QR124,725 
QS0151108 Geotechnical Report (Volume 2) 22-Jan-13 24-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 
QS0151118 Traffic Analysis Report (Volume 3) 20-Dec-12 24-Feb-13 QR83,150 QR83,150 QR0 100% 100% QR83,150 
QS0151128 Drainage Part A (SW  GW) (Volume 4A) 20-Jan-13 10-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 
QS0151138 Drainage Part B (FS) (Volume 4B) 20-Jan-13 10-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 
QS0151148 Drainage Part C (TSE) (Volume 4C) 03-Feb-13 27-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 
QS0151158 Environmental and Sustainablity (Volume 5) 29-Jan-13 12-Mar-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 
QS0151168 Drawings (Volume 6) 26-Dec-12 11-Mar-13 QR124,725 QR124,725 QR0 100% 100% QR124,725 
QS0151178 Stakeholders (Volume 7) 08-Jan-13 23-Jan-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 
QS0151188 Commercial Report (Volume 8) 28-Feb-13 06-Mar-13 QR83,150 QR83,150 QR0 100% 100% QR83,150 
QS0151198 RSA - Review (Volume 9A) 02-Jan-13 27-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 
PMC Acceptance with Comments (20%) 13-Mar-13 21-Mar-13 QR277,166 QR277,166 QR0 100% 100% QR277,166 
QS0151199 PMC Accpetance with Comments 13-Mar-13 21-Mar-13 QR277,166 QR277,166 QR0 100% 100% QR277,166 
PMC Acceptance (10%) 31-Mar-13 02-Apr-13 QR138,583 QR97,008 QR41,575 70% 70% QR97,008 
QS0151200 PMC Accpetance 31-Mar-13 02-Apr-13 QR138,583 QR97,008 QR41,575 70% 70% QR97,008 
PWA Approval (10%) 03-Apr-13 16-Apr-13 QR138,583 QR97,008 QR41,575 70% 70% QR97,008 
QS0151201 PWA Approval 03-Apr-13 16-Apr-13 QR138,583 QR97,008 QR41,575 70% 70% QR97,008 
Preliminiary Design 04-Mar-13 03-Sep-13 QR847,366 QR531,093 QR316,274 62.68% 62.68% QR531,095 
Submission of Preliminary Design (60%) 04-Mar-13 17-Jul-13 QR508,420 QR505,672 QR2,748 99.46% 99.46% QR505,674 
QS0151000 Updated Project Schedule 04-Mar-13 27-Mar-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 
QS0151001 Volume 1 - Main Report 30-May-13 16-Jul-13 QR50,842 QR50,842 QR0 100% 100% QR50,842 
QS0151002 Volume 2 - Geotechnical Investigation Report 30-Apr-13 08-May-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 
QS0151003 Volume 3 - Traffic Analysis Report 30-May-13 16-Jul-13 QR63,552 QR63,552 QR0 100% 100% QR63,552 
QS0151004 Volume 4A - Surface and Ground Water Report 05-Jun-13 15-Jul-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 
QS0151005 Volume 4B - Foul Water Report 12-Jun-13 17-Jul-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 
QS0151006 Volume 4C - Treated Sewage Effluent Report 27-May-13 16-Jul-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 
QS0151007 Volume 5 - Environmental and Sustainability 16-May-13 16-Jul-13 QR63,552 QR63,552 QR0 100% 100% QR63,552 
QS0151008 Volume 6 - Drawings 18-Apr-13 16-Jul-13 QR88,973 QR88,973 QR0 100% 100% QR88,973 
QS0151009 Volume 7 - Stakeholders Report 21-May-13 16-Jul-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 
QS0151019 Volume 8 - Commercial Report 24-Jun-13 10-Jul-13 QR50,842 QR48,097 QR2,745 94.6% 94.6% QR48,097 
QS0151029 Volume 9B - Road Safety Audit - Brief 23-Jun-13 16-Jul-13 QR12,710 QR12,710 QR0 100% 100% QR12,710 
QS0151039 Volume 9C - Road Safety Audit - Report 23-Jun-13 16-Jul-13 QR12,710 QR12,710 QR0 100% 100% QR12,710 
QS0151049 Volume 9D - Road Safety Audit - Designer's Res 23-Jun-13 16-Jul-13 QR12,710 QR12,710 QR0 100% 100% QR12,710 
PMC Acceptance with Comments (20%) 31-Jul-13 07-Aug-13 QR169,473 QR16,947 QR152,526 10% 10% QR16,947 
QS0151059 PMC Accpetance with Comments 31-Jul-13 07-Aug-13 QR169,473 QR16,947 QR152,526 10% 10% QR16,947 
PMC Acceptance (10%) 18-Aug-13 20-Aug-13 QR84,737 QR4,237 QR80,500 5% 5% QR4,237 
QS0151069 PMC Accpetance 18-Aug-13 20-Aug-13 QR84,737 QR4,237 QR80,500 5% 5% QR4,237 
PWA Approval (10%) 21-Aug-13 03-Sep-13 QR84,737 QR4,237 QR80,500 5% 5% QR4,237 
QS0151079 PWA Approval 21-Aug-13 03-Sep-13 QR84,737 QR4,237 QR80,500 5% 5% QR4,237 
2013 2014 
S O N D J F M A M J Jul A S O N D J F M A M J Jul A S 
Project Schedule 
Main Report (Volume 1) 
Geotechnical Report (Volume 2) 
Traffic Analysis Report (Volume 3) 
Drainage Part A (SW  GW) (Volume 4A) 
Drainage Part B (FS) (Volume 4B) 
Drainage Part C (TSE) (Volume 4C) 
Environmental and Sustainablity (Volume 5) 
Drawings (Volume 6) 
Stakeholders (Volume 7) 
Commercial Report (Volume 8) 
RSA - Review (Volume 9A) 
PMC Accpetance with Comments 
PMC Accpetance 
PWA Approval 
Updated Project Schedule 
Volume 1 - Main Report 
Volume 2 - Geotechnical Investigation 
Volume 3 - Traffic Analysis Report 
Volume 4A - Surface and Ground W 
Volume 4B - Foul Water Report 
Volume 4C - Treated Sewage Effluen 
Volume 5 - Environmental and Sustain 
Volume 6 - Drawings 
Volume 7 - Stakeholders Report 
Volume 8 - Commercial Repo 
Volume 9B - Road Safety Audit - Brief 
Volume 9C - Road Safety Audit - Repo 
Volume 9D - Road Safety Audit - Desi 
PMC Accpetance with Comments 
PMC Accpetance 
PWA Approval 
Public Works Authority 
Local Roads and Drainage Programme 
Earned Value as of 31-Oct-13 
Remaining Level of Effort 
Actual Level of Effort 
Baseline 
Project Start:- 04-Nov-12 
Project Finish:- 04-Jan-17 
Layout:- A4 - QS015 - Monthly EVM 
Report 
Data Date : 31-Oct-13 
Page : 1 of 3 
Printed On : 07-Nov-13 
Date Revision Checked Approved 
30-Sep-13 Payment Schedule Update MN 
31-Oct-13 Payment Schedule Update MN
Activity ID Activity Name Planned Start Planned Finish Budgeted Payment 
(QAR) 
Actual Payment 
(QAR) 
Remaining Payment 
(QAR) 
Payment % 
Complete 
Progress % 
Complete 
Earned Value Cost 
Detailed Design 31-Jul-13 17-Dec-13 QR1,694,732 QR364,674 QR1,330,058 21.52% 21.52% QR364,674 
Submission of Detailed Design (60%) 31-Jul-13 03-Nov-13 QR1,016,839 QR364,674 QR652,165 35.86% 35.86% QR364,674 
QS0151167 Updated Project Schedule 18-Sep-13 20-Oct-13 QR50,842 QR50,842 QR0 100% 100% QR50,842 
QS0151168 Volume 1 - Main Report 18-Sep-13 21-Oct-13 QR152,526 QR83,371 QR69,155 54.66% 54.66% QR83,371 
QS0151169 Volume 2 - Geotechnical Factual Report 27-Aug-13 23-Sep-13 QR50,842 QR5,084 QR45,758 10% 10% QR5,084 
QS0151170 Volume 2 - Geotechnical Interpretative Report 29-Sep-13 29-Oct-13 QR50,842 QR5,084 QR45,758 10% 10% QR5,084 
QS0151172 Volume 4A - Surface and Ground Water Report 27-Aug-13 24-Oct-13 QR50,842 QR27,343 QR23,499 53.78% 53.78% QR27,343 
QS0151173 Volume 4B - Foul Water Report 27-Aug-13 28-Oct-13 QR50,842 QR27,353 QR23,489 53.8% 53.8% QR27,353 
QS0151174 Volume 4C - Treated Sewage Effluent Report 27-Aug-13 21-Oct-13 QR50,842 QR27,658 QR23,184 54.4% 54.4% QR27,658 
QS0151175 Volume 5 - Environmental and Sustainability 09-Sep-13 22-Oct-13 QR101,684 QR7,077 QR94,607 6.96% 6.96% QR7,077 
QS0151176 Volume 6 - Drawings 31-Jul-13 23-Oct-13 QR203,368 QR109,534 QR93,834 53.86% 53.86% QR109,534 
QS0151177 Volume 7 - Stakeholders Report 12-Sep-13 20-Oct-13 QR50,842 QR11,160 QR39,682 21.95% 21.95% QR11,160 
QS0151178 Volume 8 - Commercial Report 22-Oct-13 03-Nov-13 QR101,684 QR0 QR101,684 0% 0% QR0 
QS0151180 Volume 9C - Road Safety Audit - Report 25-Sep-13 30-Oct-13 QR50,842 QR5,084 QR45,758 10% 10% QR5,084 
QS0151181 Volume 9D - Road Safety Audit - Designer's Res 25-Sep-13 27-Oct-13 QR50,842 QR5,084 QR45,758 10% 10% QR5,084 
PMC Acceptance with Comments (20%) 12-Nov-13 21-Nov-13 QR338,946 QR0 QR338,946 0% 0% QR0 
QS0151219 PMC Accpetance with Comments 12-Nov-13 21-Nov-13 QR338,946 QR0 QR338,946 0% 0% QR0 
PMC Acceptance (10%) 01-Dec-13 03-Dec-13 QR169,473 QR0 QR169,473 0% 0% QR0 
QS0151229 PMC Accpetance 01-Dec-13 03-Dec-13 QR169,473 QR0 QR169,473 0% 0% QR0 
PWA Approval (10%) 04-Dec-13 17-Dec-13 QR169,473 QR0 QR169,473 0% 0% QR0 
QS0151239 PWA Approval 04-Dec-13 17-Dec-13 QR169,473 QR0 QR169,473 0% 0% QR0 
Tender Documents 31-Jul-13 17-Dec-13 QR635,525 QR0 QR635,525 0% 0% QR0 
Submission of Tender Documents (60%) 31-Jul-13 27-Nov-13 QR381,315 QR0 QR381,315 0% 0% QR0 
QS0155470 Specification  Drawings 31-Jul-13 03-Nov-13 QR133,460 QR0 QR133,460 0% 0% QR0 
QS0155471 Conditions of Contract 30-Sep-13 30-Oct-13 QR38,131 QR0 QR38,131 0% 0% QR0 
QS0155472 Particular Conditions of Contract  Nominate S/C 30-Sep-13 30-Oct-13 QR19,066 QR0 QR19,066 0% 0% QR0 
QS0155473 Preliminary Bill of Quantity 07-Oct-13 03-Nov-13 QR19,066 QR0 QR19,066 0% 0% QR0 
QS0155474 Final Bill of Quantities 24-Nov-13 27-Nov-13 QR38,131 QR0 QR38,131 0% 0% QR0 
QS0155475 Pre-Tender Estimate 10-Oct-13 03-Nov-13 QR76,263 QR0 QR76,263 0% 0% QR0 
QS0155476 Project Programme 30-Sep-13 28-Oct-13 QR57,197 QR0 QR57,197 0% 0% QR0 
PMC Acceptance with Comments (20%) 12-Nov-13 21-Nov-13 QR127,105 QR0 QR127,105 0% 0% QR0 
QS0155477 PMC Accpetance with Comments 12-Nov-13 21-Nov-13 QR127,105 QR0 QR127,105 0% 0% QR0 
PMC Acceptance (10%) 01-Dec-13 03-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 
QS0155499 PMC Accpetance 01-Dec-13 03-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 
PWA Approval (10%) 04-Dec-13 17-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 
QS0155100 PWA Approval 04-Dec-13 17-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 
Tender 19-Dec-13 04-Mar-14 QR635,525 QR0 QR635,525 0% 0% QR0 
PWA Approval (100%) 19-Dec-13 04-Mar-14 QR635,525 QR0 QR635,525 0% 0% QR0 
QS0155478 Issue Invitation toTender 19-Dec-13 19-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 
QS0155479 Tender Queries / Pre Tender Workshop 22-Dec-13 02-Feb-14 QR127,105 QR0 QR127,105 0% 0% QR0 
QS0155480 Tender Evaluation  Report 03-Feb-14 17-Feb-14 QR127,105 QR0 QR127,105 0% 0% QR0 
QS0155481 Award of Contract (Work Order) 18-Feb-14 03-Mar-14 QR190,657 QR0 QR190,657 0% 0% QR0 
QS0155482 Prepare and Issue Notice to Proceed 04-Mar-14 04-Mar-14 QR127,105 QR0 QR127,105 0% 0% QR0 
2013 2014 
S O N D J F M A M J Jul A S O N D J F M A M J Jul A S 
Updated Project Schedule 
Volume 1 - Main Report 
Volume 2 - Geotechnical Fac 
Volume 2 - Geotechnical Inte 
Volume 4A - Surface and Gro 
Volume 4B - Foul Water Rep 
Volume 4C - Treated Sewage 
Volume 5 - Environmental an 
Volume 6 - Drawings, Volume 
Volume 7 - Stakeholders Re 
Volume 8 - Commercial Repo 
Volume 9C - Road Safety Au 
Volume 9D - Road Safety Au 
PMC Accpetance with Com 
PMC Accpetance 
PWA Approval 
Specification  Drawings, S 
Conditions of Contract, Cond 
Particular Conditions of Cont 
Preliminary Bill of Quantity, P 
Final Bill of Quantities 
Pre-Tender Estimate, Pre-Te 
Project Programme, Project 
PMC Accpetance with Com 
PMC Accpetance 
PWA Approval 
Issue Invitation toTender 
Tender Queries / Pre 
Tender Evaluation  
Award of Contract 
Prepare and Issue 
Public Works Authority 
Local Roads and Drainage Programme 
Earned Value as of 31-Oct-13 
Remaining Level of Effort 
Actual Level of Effort 
Baseline 
Project Start:- 04-Nov-12 
Project Finish:- 04-Jan-17 
Layout:- A4 - QS015 - Monthly EVM 
Report 
Data Date : 31-Oct-13 
Page : 2 of 3 
Printed On : 07-Nov-13 
Date Revision Checked Approved 
30-Sep-13 Payment Schedule Update MN 
31-Oct-13 Payment Schedule Update MN
Activity ID Activity Name Planned Start Planned Finish Budgeted Payment 
(QAR) 
Actual Payment 
(QAR) 
Remaining Payment 
(QAR) 
Payment % 
Complete 
Progress % 
Complete 
Earned Value Cost 
Contract 05-Mar-14 18-Mar-14 QR423,683 QR0 QR423,683 0% 0% QR0 
PWA Approval (100%) 05-Mar-14 18-Mar-14 QR423,683 QR0 QR423,683 0% 0% QR0 
QS0155483 Prepare Contract Documents for Work Order 05-Mar-14 11-Mar-14 QR254,210 QR0 QR254,210 0% 0% QR0 
QS0155484 Contract Signed Off by Contractor 12-Mar-14 13-Mar-14 QR63,552 QR0 QR63,552 0% 0% QR0 
QS0155485 Contract Signed Off by PWA 14-Mar-14 17-Mar-14 QR63,552 QR0 QR63,552 0% 0% QR0 
QS0155486 Exchange of Contract 18-Mar-14 18-Mar-14 QR42,368 QR0 QR42,368 0% 0% QR0 
2013 2014 
S O N D J F M A M J Jul A S O N D J F M A M J Jul A S 
Prepare Contract 
Contract Signed 
Contract Signed 
Exchange of Con 
QR10,000,000QR 
QR8,000,000QR 
QR6,000,000QR 
QR4,000,000QR 
S O N D J F M A M J Jul A S O N D J F M A M J Jul A S 
2013 2014 
QR1,000,000QR 
QR800,000QR 
QR600,000QR 
QR400,000QR 
QR200,000QR 
QR0QR 
QR2,000,000QR 
Actual Expense Cost 
Planned Value Cost 
Earned Value Cost 
BL Project Expense Cost 
Public Works Authority 
Local Roads and Drainage Programme 
Earned Value as of 31-Oct-13 
Remaining Level of Effort 
Actual Level of Effort 
Baseline 
Project Start:- 04-Nov-12 
Project Finish:- 04-Jan-17 
Layout:- A4 - QS015 - Monthly EVM 
Report 
Data Date : 31-Oct-13 
Page : 3 of 3 
Printed On : 07-Nov-13 
Date Revision Checked Approved 
30-Sep-13 Payment Schedule Update MN 
31-Oct-13 Payment Schedule Update MN
Contract 2 
Local Roads and Drainage Programme 
QS016 - Access Road to Rashid Village 
QATAR 
ACCOUNT 
MANAGEMENT 
PROGRAM
3 
SScchheedduulele D Parsohgbreosasrd 
Projects Milestones 
Milestones Gateway Planned 
Actual / 
Forecast 
QQQQSSSS000011116666 ---- AAAAcccccccceeeessssssss RRRRooooaaaadddd ttttoooo RRRRaaaasssshhhhiiiidddd VVVViiiillllllllaaaaggggeeee Plan. Act. 
Initiation G1 22-Oct-12 22-Oct-12 0 100% 100% 0 
Concept Design G2 20-Feb-13 03-Jul-13 -133 100% 100% -133 
Preliminary Design 20-Jun-13 12-Nov-13 -145 100% 60.0% -145 
Detailed Design  Tender Documents G3 18-Dec-13 17-Dec-13 1 58% 13% 1 
Tendering 04-Mar-14 04-Mar-14 0 0% 0% 0 
Construction G5 16-Sep-15 16-Sep-15 0 0% 0% 0 
Maintenance Period G6 21-Sep-16 02-Nov-16 -42 0% 0% -42 
Monthly Progress Report No. 13 ­Oct 
2013 
Total 
Variance 
% Progress Trend 
Initiation 
Concept Design 
Preliminary Design 
Detailed Design  Tender 
Documents 
Tendering 
Construction 
Maintenance Period 
Planned 
Actual/Forecast 
G1 
G2 
G3 
G5 
G6 
Behind Schedule No Change 
On Schedule 
47 
Days Until Completion 
(Starting from 1st Nov) 
Detailed 
Design  
Tender Docs. 
Current Segment 
13.4 0.23 
Progress % Complete SPI 
Upward Trend 
Downward 
Trend 
File :- Schedule Management - Oct 13 Printed On :- 11/11/2013 at 16:06
Activity ID Activity Name Planned 
Duration 
Cur rent 
Duration 
Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
Project Wide - HHiigghh LLeevveell SScchheedduullee 1019 1049 02-Sep-12 21-Sep-16 02-Sep-12 A 02-Nov-16 0 0% 
PPrrooggrraammmmee WWiiddee --HHiigghh LLeevveell SScchheedduullee 1019 1049 02-Sep-12 21-Sep-16 02-Sep-12 A 02-Nov-16 0 0% 
PPrrooggrraammmmee WWiiddee HHiigghh LLeevveell SScchheedduullee 1019 1049 02-Sep-12 21-Sep-16 02-Sep-12 A 02-Nov-16 0 0% 
2012 2013 2014 2015 2016 2017 
IInniittiiaattiioonn 37 37 02-Sep-12 22-Oct-12 02-Sep-12 A 22-Oct-12 A 0% 
IInniittiiaattiioonn 24 24 02-Sep-12 03-Oct-12 02-Sep-12 A 03-Oct-12 A 0% 
QS016 020000 PWA Formal Notificat ion of Candidate Project 0 0 02-Sep-12 02-Sep-12 A 100% 
QS016 212001 Init iation Slides Submission 0 0 03-Oct-12 03-Oct-12 A 100% 
QS016 020010 Init iation 24 24 02-Sep-12 03-Oct-12 02-Sep-12 A 03-Oct-12 A 100% 
1188 DDaayy RReevviieeww 19 19 04-Oct-12 22-Oct-12 04-Oct-12 A 22-Oct-12 A 0% 
QS016 212101 PMC/PWA Initiation Review 18 18 04-Oct-12 21-Oct-12 04-Oct-12 A 21-Oct-12 A 100% 
QS016 010040 Gateway 1 Review Meeting 0 0 22-Oct-12 22-Oct-12 A 100% 
CCoonncceepptt DDeessiiggnn 80 80 23-Oct-12 20-Feb-13 23-Oct-12 A 03-Jul-13 A 0% 
CCoonncceepptt DDeessiiggnn 55 55 23-Oct-12 15-Jan-13 23-Oct-12 A 18-Mar-13 A 0% 
QS016 020070 Concept Design 55 55 23-Oct-12 15-Jan-13 23-Oct-12 A 18-Mar-13 A 100% 
QS016 212411 Concept Design Submission 0 0 15-Jan-13 18-Mar-13 A 100% 
3355 DDaayy RReevviieeww 36 36 16-Jan-13 20-Feb-13 10-Feb-13 A 03-Jul-13 A 0% 
QS016 212421 PMC Concept Design Review 10 10 16-Jan-13 25-Jan-13 10-Feb-13 A 30-Mar-13 A 100% 
QS016 212431 GEC Response to PMC Comments 7 7 26-Jan-13 01-Feb-13 19-Feb-13 A 20-May-13 A 100% 
QS016 212441 PMC Review of GEC Response 4 4 02-Feb-13 05-Feb-13 02-Mar-13 A 21-May-13 A 100% 
QS016 212451 PWA Review 14 14 06-Feb-13 19-Feb-13 02-Mar-13 A 21-May-13 A 100% 
QS016 020100 Gateway 2 Review Meeting 0 0 20-Feb-13 03-Jul-13 A 100% 
PPrreelliimmiinnaarryy DDeessiiggnn 111 208 21-Feb-13 25-Jul-13 04-Jul-13 A 17-Dec-13 0 0% 
PPrreelliimmiinnaarryy DDeessiiggnn 86 183 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 0% 
QS016 020130 Preliminary Design 86 86 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 60% 
QS016 440190 Preliminary Design Submission 0 0 20-Jun-13 12-Nov-13 1 0% 
3355 DDaayy RReevviieeww 35 35 21-Jun-13 25-Jul-13 13-Nov-13 17-Dec-13 1 0% 
QS016 440060 PMC Preliminary Design Review 10 10 21-Jun-13 30-Jun-13 13-Nov-13 22-Nov-13 1 0% 
QS016 440070 GEC Response to PMC Comments 7 7 01-Jul-13 07-Jul-13 23-Nov-13 29-Nov-13 1 0% 
QS016 440080 PMC Review of GEC Response 4 4 08-Jul-13 11-Jul-13 30-Nov-13 03-Dec-13 1 0% 
QS016 440090 PWA Review 14 14 12-Jul-13 25-Jul-13 04-Dec-13 17-Dec-13 1 0% 
DDeettaaiilleedd DDeessiiggnn  TTeennddeerr DDooccuummeennttss 122 44 23-Jun-13 18-Dec-13 01-Sep-13 A 17-Dec-13 0 0% 
DDeettaaiilleedd DDeessiiggnn  TTeennddeerr DDooccuummeennttss 97 19 23-Jun-13 12-Nov-13 01-Sep-13 A 12-Nov-13 1 0% 
QS016 020140 Detailed Design 87 13 23-Jun-13 29-Oct-13 01-Sep-13 A 12-Nov-13 1 18.48% Detailed Design duration was 
reduced from 87 to 13 days as 
the detailed and preliminary 
designs are running 
concurrently. 
QS016 020150 Tender Documents 28 8 01-Oct-13 12-Nov-13 03-Nov-13 12-Nov-13 1 0% 
QS016 212461 Draft Detailed DesignTender Documents Submission 0 0 12-Nov-13 12-Nov-13 1 0% 
3355 DDaayy RReevviieeww 36 35 13-Nov-13 18-Dec-13 13-Nov-13 17-Dec-13 1 0% 
QS016 212471 PMC Detailed DesignTender Documents Review 10 10 13-Nov-13 22-Nov-13 13-Nov-13 22-Nov-13 1 0% 
QS016 212481 GEC Response to PMC Comments 7 7 23-Nov-13 29-Nov-13 23-Nov-13 29-Nov-13 1 0% 
QS016 212491 PMC Review of GEC Response 4 4 30-Nov-13 03-Dec-13 30-Nov-13 03-Dec-13 1 0% 
QS016 020180 Gateway 3 Review Meeting 0 0 18-Dec-13 17-Dec-13 1 0% 
Q3 Q4 Q1 Q Q3 Q4 Q Q2 Q3 Q4 Q Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q Q4 
PWA Formal Notificat ion of Candidate Project 
Init iation Slides Submission 
Init iation 
PMC/PWA Initiation Review 
Gateway 1 Review Meeting 
Concept Design 
Concept Design Submission 
PMC Concept Design Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 2 Review Meeting 
Preliminary Design 
Preliminary Design Submission 
PMC Preliminary Design Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Detailed Design 
Tender Documents 
Draft Detailed DesignTender Documents Submission 
PMC Detailed DesignTender Documents Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
Gateway 3 Review Meeting 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 1 of 4 
Printed On : 10-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS016 - Access Road to Rawdat Rashed Village 
Update as of 31-Oct-2013 
Date Revision Checked Approved 
16-Apr-13 Project Baseline Schedule/QS016-AEC-PMG-SCH-00237... SK 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 SK
Activity ID Activity Name Planned 
Duration 
Cur rent 
Duration 
Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
QS016 212501 PWA Review 14 14 04-Dec-13 17-Dec-13 04-Dec-13 17-Dec-13 1 0% 
TTeennddeerriinngg 64 64 19-Dec-13 23-Mar-14 19-Dec-13 23-Mar-14 10 0% 
TTeennddeerr aanndd AAwwaarrddiinngg 64 64 19-Dec-13 23-Mar-14 19-Dec-13 23-Mar-14 10 0% 
QS016 020210 Tendering of the Project 30 30 19-Dec-13 02-Feb-14 19-Dec-13 02-Feb-14 0 0% 
QS016 020240 Tender AssessmentRecommendat ions 10 10 03-Feb-14 17-Feb-14 03-Feb-14 17-Feb-14 0 0% 
QS016 020220 Award of the Construction Contract (Work Order) 0 0 04-Mar-14 04-Mar-14 0 0% 
QS016 020250 PMC/PWA Approval 11 11 18-Feb-14 04-Mar-14 18-Feb-14 04-Mar-14 0 0% 
QS016 020330 Prepare and Issue Notice to Proceed 1 1 05-Mar-14 05-Mar-14 05-Mar-14 05-Mar-14 0 0% 
QS016 020270 Prepare Contract Documents for Work Order 6 6 06-Mar-14 13-Mar-14 06-Mar-14 13-Mar-14 0 0% 
QS016 020280 Contract Signed Off by ContractorPWA 5 5 16-Mar-14 20-Mar-14 16-Mar-14 20-Mar-14 0 0% 
QS016 020310 Exchange of Contract 1 1 23-Mar-14 23-Mar-14 23-Mar-14 23-Mar-14 10 0% 
CCoonnssttrruuccttiioonn 387 387 06-Mar-14 16-Sep-15 06-Mar-14 16-Sep-15 0 0% 
CCoonnssttrruuccttiioonn PPeerriioodd 361 361 06-Mar-14 11-Aug-15 06-Mar-14 11-Aug-15 0 0% 
QS016 020300 Contractor Mobilization Period 22 22 06-Mar-14 06-Apr-14 06-Mar-14 06-Apr-14 0 0% 
QS016 020230 Construction of the Project 339 339 07-Apr-14 11-Aug-15 07-Apr-14 11-Aug-15 0 0% 
QS016 212511 Construction Documents Submission 0 0 11-Aug-15 11-Aug-15 0 0% 
3355 DDaayy RReevviieeww 36 36 12-Aug-15 16-Sep-15 12-Aug-15 16-Sep-15 0 0% 
QS016 212521 PMC Construct ion Documents Review 10 10 12-Aug-15 21-Aug-15 12-Aug-15 21-Aug-15 0 0% 
QS016 212531 GEC Response to PMC Comments 7 7 22-Aug-15 28-Aug-15 22-Aug-15 28-Aug-15 0 0% 
QS016 212541 PMC Review of GEC Response 4 4 29-Aug-15 01-Sep-15 29-Aug-15 01-Sep-15 0 0% 
QS016 212551 PWA Review 14 14 02-Sep-15 15-Sep-15 02-Sep-15 15-Sep-15 0 0% 
QS016 020260 Gateway 5 Review Meeting 0 0 16-Sep-15 16-Sep-15 0 0% 
MMaaiinntteennaannccee PPeerriioodd 371 413 17-Sep-15 21-Sep-16 17-Sep-15 02-Nov-16 0 0% 
MMaaiinntteennaannccee PPeerriioodd 335 365 17-Sep-15 16-Aug-16 17-Sep-15 15-Sep-16 0 0% 
QS016 020290 Maintenance Period 232 365 17-Sep-15 16-Aug-16 17-Sep-15 15-Sep-16 0 0% 
QS016 212561 Maintenance Documents Submission 0 0 16-Aug-16 15-Sep-16 0 0% 
3355 DDaayy RReevviieeww 36 48 17-Aug-16 21-Sep-16 16-Sep-16 02-Nov-16 0 0% 
QS016 212571 PMC Maintenance Documents Review 10 10 17-Aug-16 26-Aug-16 16-Sep-16 25-Sep-16 0 0% 
QS016 212581 GEC Response to PMC Comments 7 7 27-Aug-16 02-Sep-16 26-Sep-16 02-Oct-16 0 0% 
QS016 212591 PMC Review of GEC Response 4 4 03-Sep-16 06-Sep-16 03-Oct-16 06-Oct-16 0 0% 
QS016 212601 PWA Review 14 14 07-Sep-16 20-Sep-16 07-Oct-16 20-Oct-16 0 0% 
QS016 020320 Gateway 6 Review Meeting 0 0 21-Sep-16 02-Nov-16 0 0% 
QS016 020340 Project Completion 0 0 21-Sep-16 02-Nov-16* 0 0% 
MMMMUUPP aanndd MMOOEE 320 320 26-Nov-12 06-Mar-14 12-Dec-12 A 06-Mar-14 21 0% 
MMiinniissttrryy ooff MMuunniicciippaalliittyy aanndd UUrrbbaann PPllaannnniinngg 11 11 26-Nov-12 10-Dec-12 12-Dec-12 A 27-Dec-12 A 0% 
MMiinniissttrryy ooff MMuunniicciippaalliittyy aanndd UUrrbbaann PPllaannnniinngg 11 11 26-Nov-12 10-Dec-12 12-Dec-12 A 27-Dec-12 A 0% 
QS016 020080 Submission of TTN to PMC 0 0 26-Nov-12 12-Dec-12 A 100% 
QS016 020090 Approval of TTN by PMC 0 0 10-Dec-12 27-Dec-12 A 100% 
QS016 020110 ReviewTTN by PMC 14 14 26-Nov-12 09-Dec-12 13-Dec-12 A 27-Dec-12 A 100% 
MMiinniissttrryy ooff EEnnvviirroonnmmeenntt 276 276 30-Jan-13 06-Mar-14 30-Jan-13 A 06-Mar-14 21 0% 
MMiinniissttrryy ooff EEnnvviirroonnmmeenntt 276 276 30-Jan-13 06-Mar-14 30-Jan-13 A 06-Mar-14 21 0% 
QS016 440100 Preparation of Environmental Permit Application 30 30 30-Jan-13 13-Mar-13 30-Jan-13 A 16-Feb-13 A 100% 
QS016 440110 Permit Application Submission 0 0 13-Mar-13 17-Feb-13 A 100% 
QS016 440000 PMC/MOE Review 30 30 14-Mar-13 12-Apr-13 18-Feb-13 A 21-Apr-13 A 100% 
2012 2013 2014 2015 2016 2017 
Q3 Q4 Q1 Q Q3 Q4 Q Q2 Q3 Q4 Q Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q Q4 
PWA Review 
Tendering of the Project 
Tender AssessmentRecommendat ions 
Award of the Construction Contract (Work Order) 
PMC/PWA Approval 
Prepare and Issue Notice to Proceed 
Prepare Contract Documents for Work Order 
Contract Signed Off by ContractorPWA 
Exchange of Contract 
Contractor Mobilization Period 
Construction of the Project 
Construction Documents Submission 
PMC Construct ion Documents Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 5 Review Meeting 
Maintenance Period 
Maintenance Documents Submission 
PMC Maintenance Documents Review 
GEC Response to PMC Comments 
PMC Review of GEC Response 
PWA Review 
Gateway 6 Review Meeting 
Project Completion 
Submission of TTN to PMC 
Approval of TTN by PMC 
ReviewTTN by PMC 
Preparation of Environmental Permit Application 
Permit Application Submission 
PMC/MOE Review 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 2 of 4 
Printed On : 10-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS016 - Access Road to Rawdat Rashed Village 
Update as of 31-Oct-2013 
Date Revision Checked Approved 
16-Apr-13 Project Baseline Schedule/QS016-AEC-PMG-SCH-00237... SK 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 SK
Activity ID Activity Name Planned 
Duration 
Cur rent 
Duration 
Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
QS016 440010 Environmental Scoping 39 39 14-Apr-13 05-Jun-13 22-Apr-13 A 23-May-13 A 100% 
QS016 440120 Environmental Scoping Submission 0 0 05-Jun-13 23-May-13 A 100% 
QS016 440020 PMC/MOE Review 30 30 06-Jun-13 05-Jul-13 24-May-13 A 01-Nov-13 12 80% 
QS016 440030 Environmental Impact Assessment (EIA) 65 65 07-Jul-13 08-Oct-13 10-Jul-13 A 04-Nov-13 8 49.5% 
QS016 440130 EIA Submission 0 0 08-Oct-13 04-Nov-13 8 0% 
QS016 440040 PMC/MOE Review 30 30 09-Oct-13 07-Nov-13 05-Nov-13 04-Dec-13 12 0% 
QS016 440050 Environmental Permit Issued 0 0 10-Nov-13 05-Dec-13 8 0% 
QS016 440160 Review Contractor CEMP 5 5 05-Feb-14 12-Feb-14 05-Feb-14 12-Feb-14 36 0% 
QS016 440200 CEMP Submission to MOE 0 0 06-Mar-14 06-Mar-14 21 0% 
Stakeholders EEnnggaaggeemmeenntt 981 1011 24-Oct-12 21-Sep-16 02-Sep-12 A 02-Nov-16 0 0% 
CCoonncceepptt DDeessiiggnn 79 79 24-Oct-12 20-Feb-13 23-Oct-12 A 21-May-13 A 0% 
CCoonncceepptt DDeessiiggnn 79 79 24-Oct-12 20-Feb-13 23-Oct-12 A 21-May-13 A 0% 
QS016 021020 Liaison with Stakeholders - Concept Design 79 79 24-Oct-12 20-Feb-13 23-Oct-12 A 21-May-13 A 100% 
PPrreelliimmiinnaarryy DDeessiiggnn 86 86 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 0% 
PPrreelliimmiinnaarryy DDeessiiggnn 86 86 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 0% 
QS016 440140 Liaison with Stakeholders - Preliminary Design 86 86 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 99% 
DDeettaaiilleedd DDeessiiggnn  TTeennddeerriinngg 174 105 23-Jun-13 05-Mar-14 01-Sep-13 A 05-Mar-14 0 0% 
DDeettaaiilleedd DDeessiiggnn  TTeennddeerriinngg 174 105 23-Jun-13 05-Mar-14 01-Sep-13 A 05-Mar-14 0 0% 
QS016 440150 Liaison with Stakeholders - Detailed Design  Tendering 174 105 23-Jun-13 05-Mar-14 01-Sep-13 A 05-Mar-14 0 51.15% 
CCoonnssttrruuccttiioonn 387 387 06-Mar-14 16-Sep-15 06-Mar-14 16-Sep-15 0 0% 
CCoonnssttrruuccttiioonn 387 387 06-Mar-14 16-Sep-15 06-Mar-14 16-Sep-15 0 0% 
QS016 440170 Liaison with Stakeholders - Construct ion 387 387 06-Mar-14 16-Sep-15 06-Mar-14 16-Sep-15 0 0% 
MMaaiinntteennaannccee PPeerriioodd 255 255 17-Sep-15 21-Sep-16 03-Nov-15 02-Nov-16 0 0% 
MMaaiinntteennaannccee PPeerriioodd 255 255 17-Sep-15 21-Sep-16 03-Nov-15 02-Nov-16 0 0% 
QS016 440180 Liaison with Stakeholders - Maintenance Period 255 255 17-Sep-15 21-Sep-16 03-Nov-15 02-Nov-16 0 0% 
MMMMUUPP UUttiilliittyy IInnvveessttiiggaatt iioonn 90 60 24-Oct-12 07-Mar-13 02-Sep-12 A 12-Nov-13 1 0% 
QS016 440240 Superimpose Data on Proposed Road Layout 10 10 17-Dec-12 02-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440260 Agencies Approval 15 15 03-Jan-13 23-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440210 Utility Investigation by Owner/Consultant/Client 10 10 24-Oct-12 11-Nov-12 01-Oct-12 A 31-Oct-12 A 100% 
QS016 440220 Collect Data (Existing  Proposed Utilties) 10 10 12-Nov-12 25-Nov-12 01-Nov-12 A 08-Nov-12 A 100% 
QS016 440230 Topo Survey,Trial Pits and Radio Detection 15 15 26-Nov-12 16-Dec-12 11-Nov-12 A 09-Dec-12 A 100% 
QS016 440290 MMUP Approval 15 8 24-Jan-13 14-Feb-13 03-Nov-13 12-Nov-13 1 0% 
QS016 440300 Final Report to MMUP 15 8 17-Feb-13 07-Mar-13 03-Nov-13 12-Nov-13 1 0% 
KKAAHHRRAAMMAA 75 45 24-Oct-12 14-Feb-13 01-Oct-12 A 12-Nov-13 1 0% 
QS016 440310 Send an Introductory Letters to KAHRAMA 10 10 24-Oct-12 11-Nov-12 01-Oct-12 A 07-Oct-12 A 100% 
QS016 440320 Request for Information about KAHRAMA's Current/Future Projects 10 10 12-Nov-12 25-Nov-12 08-Oct-12 A 15-Oct-12 A 100% 
QS016 440330 Receive Information about KAHRAMA's Current/Future Projects 15 15 26-Nov-12 16-Dec-12 23-Oct-12 A 29-Oct-12 A 100% 
QS016 440340 Superimpose the Plans on Proposed Project to Identify Conflict 10 10 17-Dec-12 02-Jan-13 31-Oct-12 A 03-Nov-13 1 25% 
QS016 440350 Report the Conflicts to KAHRAMA 10 8 03-Jan-13 16-Jan-13 03-Nov-13 12-Nov-13 1 0% 
QS016 440360 Amend the Drawings 10 8 17-Jan-13 30-Jan-13 03-Nov-13 12-Nov-13 1 0% 
QS016 440370 Drawings Submission to KAHRAMA for Approval 10 8 31-Jan-13 14-Feb-13 03-Nov-13 12-Nov-13 1 0% 
CCoommmmuunniiccaatt iioonn ((OOrreeddoooo//VVooddaaffoonnee)) 75 45 24-Oct-12 14-Feb-13 01-Oct-12 A 12-Nov-13 1 0% 
QS016 440380 Send an Introductory Letters to Oredoo/Vodafone 10 10 24-Oct-12 11-Nov-12 01-Oct-12 A 07-Oct-12 A 100% 
QS016 440390 Request for Information about Oredo/Vodafone's Current /Future Projects 10 10 12-Nov-12 25-Nov-12 08-Oct-12 A 15-Oct-12 A 100% 
2012 2013 2014 2015 2016 2017 
Q3 Q4 Q1 Q Q3 Q4 Q Q2 Q3 Q4 Q Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q Q4 
Environmental Scoping 
Environmental Scoping Submission 
PMC/MOE Review 
Environmental Impact Assessment (EIA) 
EIA Submission 
PMC/MOE Review 
Environmental Permit Issued 
Review Contractor CEMP 
CEMP Submission to MOE 
Liaison with Stakeholders - Concept Design 
Liaison with Stakeholders - Preliminary Design 
Liaison with Stakeholders - Detailed Design  Tendering 
Liaison with Stakeholders - Construct ion 
Liaison with Stakeholders - Maintenance Superimpose Data on Proposed Road Layout 
Agencies Approval 
Utility Investigation by Owner/Consultant/Client 
Collect Data (Existing  Proposed Utilties) 
Topo Survey,Trial Pits and Radio Detection 
MMUP Approval 
Final Report to MMUP 
Send an Introductory Letters to KAHRAMA 
Request for Information about KAHRAMA's Current/Future Projects 
Receive Information about KAHRAMA's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Report the Conflicts to KAHRAMA 
Amend the Drawings 
Drawings Submission to KAHRAMA for Approval 
Send an Introductory Letters to Oredoo/Vodafone 
Request for Information about Oredo/Vodafone's Current /Future Projects 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 3 of 4 
Printed On : 10-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS016 - Access Road to Rawdat Rashed Village 
Update as of 31-Oct-2013 
Date Revision Checked Approved 
16-Apr-13 Project Baseline Schedule/QS016-AEC-PMG-SCH-00237... SK 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 SK
Activity ID Activity Name Planned 
Duration 
Cur rent 
Duration 
Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % 
Complete 
. AECOM Mitigation Plan 
QS016 440400 Receive Information about Oredo/Vodafone's Current/Future Projects 15 15 26-Nov-12 16-Dec-12 23-Oct-12 A 29-Oct-12 A 100% 
QS016 440410 Superimpose the Plans on Proposed Project to Identify Conflict 10 10 17-Dec-12 02-Jan-13 31-Oct-12 A 04-Nov-13 1 50% 
QS016 440420 Report the Conflicts to Oredoo/Vodafone 10 8 03-Jan-13 16-Jan-13 03-Nov-13 12-Nov-13 1 0% 
QS016 440430 Amend the Drawings 10 8 17-Jan-13 30-Jan-13 03-Nov-13 12-Nov-13 1 0% 
QS016 440440 Drawings Submission to Oredoo/Vodafone for Approval 10 8 31-Jan-13 14-Feb-13 03-Nov-13 12-Nov-13 1 0% 
Natural RReesseerrvveess ((NNRR)) 75 75 24-Oct-12 14-Feb-13 02-Sep-12 A 02-Sep-12 A 0% 
QS016 440450 Send an Introductory Letters to NR 10 10 24-Oct-12 11-Nov-12 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440460 Request for Information about NR's Current /Future Projects 10 10 12-Nov-12 25-Nov-12 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440470 Receive Information about NR's Current/Future Projects 15 15 26-Nov-12 16-Dec-12 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440480 Superimpose the Plans on Proposed Project to Identify Conflict 10 10 17-Dec-12 02-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440490 Report the Conflicts to NR 10 10 03-Jan-13 16-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440500 Amend the Drawings 10 10 17-Jan-13 30-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440510 Drawings Submission to NR for Approval 10 10 31-Jan-13 14-Feb-13 02-Sep-12 A 02-Sep-12 A 100% Escaped 
PPrriivvaattee EEnnggiinneeeerr OOffffiiccee ((PPEEOO)) 75 75 24-Oct-12 14-Feb-13 02-Sep-12 A 11-Nov-13 2 0% 
QS016 440550 Superimpose the Plans on Proposed Project to Identify Conflict 10 10 17-Dec-12 02-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped 
QS016 440520 Send an Introductory Letters to PEO 10 10 24-Oct-12 11-Nov-12 01-Oct-12 A 07-Oct-12 A 100% 
QS016 440530 Request for Information about PEO's Current/Future Projects 10 10 12-Nov-12 25-Nov-12 08-Oct-12 A 15-Oct-12 A 100% 
QS016 440540 Receive Information about PEO's Current /Future Projects 15 15 26-Nov-12 16-Dec-12 23-Oct-12 A 29-Oct-12 A 100% 
QS016 440560 Report the Conflicts to PEO 10 10 03-Jan-13 16-Jan-13 25-Nov-12 A 04-Dec-12 A 100% 
QS016 440570 Amend the Drawings 10 10 17-Jan-13 30-Jan-13 10-Dec-12 A 15-Jan-13 A 100% 
QS016 440580 Drawings Submission to PEO for Approval 10 10 31-Jan-13 14-Feb-13 16-Jan-13 A 11-Nov-13 2 5% 
PPhh 11 -- 22 FFeeaassiibbiilliittyy  OOppttiioonnss ((CCoonncceepptt DDeessiiggnn)) 117 117 02-Sep-12 20-Feb-13 02-Sep-12 A 03-Jul-13 A 100% 
PPhh 22 -- 33 DDeessiiggnn  CCoonnttrraacctt AAwwaarrdd 272 272 21-Feb-13 23-Mar-14 02-Sep-12 A 23-Mar-14 0 19.39% 
2012 2013 2014 2015 2016 2017 
Q3 Q4 Q1 Q Q3 Q4 Q Q2 Q3 Q4 Q Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q Q4 
Receive Information about Oredo/Vodafone's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Report the Conflicts to Oredoo/Vodafone 
Amend the Drawings 
Drawings Submission to Oredoo/Vodafone for Approval 
Send an Introductory Letters to NR 
Request for Information about NR's Current /Future Projects 
Receive Information about NR's Current/Future Projects 
Superimpose the Plans on Proposed Project to Identify Conflict 
Report the Conflicts to NR 
Amend the Drawings 
Drawings Submission to NR for Approval 
Superimpose the Plans on Proposed Project to Identify Conflict 
Send an Introductory Letters to PEO 
Request for Information about PEO's Current/Future Projects 
Receive Information about PEO's Current/Future Projects 
Report the Conflicts to PEO 
Amend the Drawings 
Drawings Submission to PEO for Approval 
Public Works Authority - Contract 2 
Local Roads and Drainage Programme 
Data Date : 31-Oct-13 
Page : 4 of 4 
Printed On : 10-Nov-13 
Baseline 
Actual Work 
Critical Remaining Work 
Baseline Milestone 
Curernt Milestone 
Delay Bar 
Project Baseline Schedule 
QS016 - Access Road to Rawdat Rashed Village 
Update as of 31-Oct-2013 
Date Revision Checked Approved 
16-Apr-13 Project Baseline Schedule/QS016-AEC-PMG-SCH-00237... SK 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 SK
Activity ID Activity Name Planned Start Planned Finish Budgeted Payment 
(QAR) 
Actual Payment 
(QAR) 
Remaining Payment 
(QAR) 
Payment % 
Complete 
2013-09-01:Earned 
Value Cost 
TToottaall 24-Oct-12 23-Mar-14 QR9,746,172 QR2,552,136 QR7,194,037 26.19% QR1,185,555 
CCoonncceepptt DDeessiiggnn 24-Oct-12 19-Feb-13 QR930,816 QR763,264 QR167,552 82% QR930,816 
SSuubbmmiissssiioonn ooff CCoonncceepptt DDeessiiggnn ((6600%%)) 24-Oct-12 06-Feb-13 QR558,490 QR558,485 QR5 100% QR558,490 
QS0161088 Project Schedule 10-Jan-13 31-Jan-13 QR83,773 QR83,773 QR0 100% QR83,773 
QS0161098 Main Report (Volume 1) 19-Nov-12 06-Jan-13 QR83,773 QR83,773 QR0 100% QR83,773 
QS0161108 Geotechnical Report (Volume 2) 06-Dec-12 24-Dec-12 QR27,924 QR27,924 QR0 100% QR27,924 
QS0161118 Traffic Analysis Report (Volume 3) 24-Oct-12 02-Jan-13 QR55,849 QR55,849 QR0 100% QR55,849 
QS0161128 Drainage Part A (SW  GW) (Volume 4A) 09-Dec-12 06-Jan-13 QR27,924 QR27,924 QR0 100% QR27,924 
QS0161138 Drainage Part B (FS) (Volume 4B) 09-Dec-12 06-Jan-13 QR27,924 QR27,924 QR0 100% QR27,924 
QS0161148 Drainage Part C (TSE) (Volume 4C) 09-Dec-12 06-Jan-13 QR27,924 QR27,924 QR0 100% QR27,924 
QS0161158 Environmental and Sustainablity (Volume 5) 30-Jan-13 06-Feb-13 QR27,924 QR27,924 QR0 100% QR27,924 
QS0161168 Drawings (Volume 6) 06-Nov-12 22-Jan-13 QR83,773 QR83,773 QR0 100% QR83,773 
QS0161178 Stakeholders (Volume 7) 12-Nov-12 16-Dec-12 QR27,924 QR27,924 QR0 100% QR27,924 
QS0161188 Commercial Report (Volume 8) 07-Jan-13 10-Jan-13 QR55,849 QR55,849 QR0 100% QR55,849 
QS0161198 RSA - Review (Volume 9A) 19-Nov-12 06-Jan-13 QR27,924 QR27,924 QR0 100% QR27,924 
PPMMCC AAcccceeppttaannccee wwiitthh CCoommmmeennttss ((2200%%)) 16-Jan-13 24-Jan-13 QR186,163 QR186,163 QR0 100% QR186,163 
QS0161199 PMC Accpetance with Comments 16-Jan-13 24-Jan-13 QR186,163 QR186,163 QR0 100% QR186,163 
PPMMCC AAcccceeppttaannccee ((1100%%)) 03-Feb-13 05-Feb-13 QR93,082 QR18,616 QR74,466 20% QR93,082 
QS0161200 PMC Accpetance 03-Feb-13 05-Feb-13 QR93,082 QR18,616 QR74,466 20% QR93,082 
PPWWAA AApppprroovvaall ((1100%%)) 06-Feb-13 19-Feb-13 QR93,082 QR0 QR93,082 0% QR93,082 
QS0161201 PWA Approval 06-Feb-13 19-Feb-13 QR93,082 QR0 QR93,082 0% QR93,082 
PPrreelliimmiinniiaarryy DDeessiiggnn 21-Feb-13 25-Jul-13 QR1,763,071 QR1,101,917 QR661,154 62.5% QR235,486 
SSuubbmmiissssiioonn ooff PPrreelliimmiinnaarryy DDeessiiggnn ((6600%%)) 21-Feb-13 19-Jun-13 QR1,057,843 QR1,057,840 QR3 100% QR235,486 
QS0161000 Updated Project Schedule 25-Apr-13 04-Jun-13 QR52,892 QR52,892 QR0 100% QR52,892 
QS0161001 Volume 1 - Main Report 10-Mar-13 16-Jun-13 QR105,784 QR105,784 QR0 100% QR7,447 
QS0161002 Volume 2 - Geotechnical Investigation Report 28-Apr-13 13-Jun-13 QR52,892 QR52,892 QR0 100% QR52,892 
QS0161003 Volume 3 - Traffic Analysis Report 09-Apr-13 13-Jun-13 QR132,230 QR132,230 QR0 100% QR0 
QS0161004 Volume 4A - Surface and Ground Water Report 18-Apr-13 19-Jun-13 QR52,892 QR52,892 QR0 100% QR4,797 
QS0161005 Volume 4B - Foul Water Report 24-Apr-13 16-Jun-13 QR52,892 QR52,892 QR0 100% QR4,025 
QS0161006 Volume 4C - Treated Sewage Effluent Report 02-May-13 09-May-13 QR52,892 QR52,892 QR0 100% QR0 
QS0161007 Volume 5 - Environmental and Sustainability 26-Feb-13 06-May-13 QR132,230 QR132,230 QR0 100% QR0 
QS0161008 Volume 6 - Drawings 21-Feb-13 16-Jun-13 QR185,122 QR185,122 QR0 100% QR39,394 
QS0161009 Volume 7 - Stakeholders Report 10-Mar-13 09-May-13 QR52,892 QR52,892 QR0 100% QR0 
QS0161019 Volume 8 - Commercial Report 26-May-13 13-Jun-13 QR105,784 QR105,784 QR0 100% QR74,038 
QS0161029 Volume 9B - Road Safety Audit - Brief 13-May-13 02-Jun-13 QR26,446 QR26,446 QR0 100% QR0 
QS0161039 Volume 9C - Road Safety Audi t - Report 13-May-13 02-Jun-13 QR26,446 QR26,446 QR0 100% QR0 
QS0161049 Volume 9D - Road Safety Audi t - Designer's Response 13-May-13 02-Jun-13 QR26,446 QR26,446 QR0 100% QR0 
PPMMCC AAcccceeppttaannccee wwiitthh CCoommmmeennttss ((2200%%)) 23-Jun-13 30-Jun-13 QR352,614 QR35,261 QR317,353 10% QR0 
QS0161059 PMC Accpetance with Comments 23-Jun-13 30-Jun-13 QR352,614 QR35,261 QR317,353 10% QR0 
PPMMCC AAcccceeppttaannccee ((1100%%)) 08-Jul-13 11-Jul-13 QR176,307 QR8,815 QR167,492 5% QR0 
QS0161069 PMC Accpetance 08-Jul-13 11-Jul-13 QR176,307 QR8,815 QR167,492 5% QR0 
PPWWAA AApppprroovvaall ((1100%%)) 14-Jul-13 25-Jul-13 QR176,307 QR0 QR176,307 0% QR0 
QS0161079 PWA Approval 14-Jul-13 25-Jul-13 QR176,307 QR0 QR176,307 0% QR0 
2013 2014 
S Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul A S Oct N Dec 
Project Schedule 
Main Report (Volume 1) 
Geotechnical Report (Volume 2) 
Traffic Analysis Report (Volume 3) 
Drainage Part A (SW  GW) (Volume 4A) 
Drainage Part B (FS) (Volume 4B) 
Drainage Part C (TSE) (Volume 4C) 
Environmental and Sustainablity (Volume 5) 
Drawings (Volume 6) 
Stakeholders (Volume 7) 
Commercial Report (Volume 8) 
RSA - Review (Volume 9A) 
PMC Accpetance with Comments 
PMC Accpetance 
PWA Approval 
Updated Project Schedule 
Volume 1 - Main Report 
Volume 2 - Geotechnical Investigation Report 
Volume 3 - Traffic Analysis Report 
Volume 4A - Surface and Ground Water Report 
Volume 4B - Foul Water Report 
Volume 4C - Treated Sewage Effluent Report 
Volume 5 - Environmental and Sustainability 
Volume 6 - Drawings 
Volume 7 - Stakeholders Report 
Volume 8 - Commercial Report 
Volume 9B - Road Safety Audit - Brief 
Volume 9C - Road Safety Audi t - Report 
Volume 9D - Road Safety Audi t - Designer's Response 
PMC Accpetance with Comments 
PMC Accpetance 
PWA Approval 
Public Works Authority 
Local Roads and Drainage Programme 
Earned Value as of 31-Oct-13 
Remaining Level of Effort 
Actual Level of Effort 
Baseline 
Project Start:- 02-Sep-12 
Project Finish:- 02-Nov-16 
Layout:- A4 - QS016 - Monthly EV 
Report 
Data Date : 31-Oct-13 
Page : 1 of 3 
Printed On : 07-Nov-13 
Date Revision Checked Approved 
31-Aug-13 Schedule Update - Aug-13 SK 
30-Sep-13 Schedule Update - Sep-13 SK 
31-Oct-13 Schedule Update - Oct-13 SK
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13

Weitere ähnliche Inhalte

Was ist angesagt?

Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
Tom Atkinson
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
yang lu
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
James Zhang (Chi, Zhang)
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Arun Bharadwaj
 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.
Mourad Iskandar
 
Mauli Engineering Services Presentation
Mauli Engineering Services PresentationMauli Engineering Services Presentation
Mauli Engineering Services Presentation
Mauli Engineering
 
NGS Owners Initial Proposal Timeline Discussion
NGS Owners Initial Proposal Timeline DiscussionNGS Owners Initial Proposal Timeline Discussion
NGS Owners Initial Proposal Timeline Discussion
en3pro
 
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit FeesAlamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
ahcitycouncil
 
Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu Resume
Kalyan Chunchu Resume
Kalyan Chunchu
 
-Strategy Planning Report
-Strategy Planning Report-Strategy Planning Report
-Strategy Planning Report
yang lu
 
TQMI project Updated
TQMI project UpdatedTQMI project Updated
TQMI project Updated
Gunjan Naik
 

Was ist angesagt? (19)

DAMAC Heights Project
DAMAC Heights ProjectDAMAC Heights Project
DAMAC Heights Project
 
Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
 
Monitoring Programme Review
Monitoring Programme ReviewMonitoring Programme Review
Monitoring Programme Review
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-Portfolio
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
 
NNP Shutdown 2014 Plans - Scurve and npt graph
NNP Shutdown 2014 Plans - Scurve and npt graphNNP Shutdown 2014 Plans - Scurve and npt graph
NNP Shutdown 2014 Plans - Scurve and npt graph
 
Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.Payment Method for Work item Studies and Design November 26, 2010.
Payment Method for Work item Studies and Design November 26, 2010.
 
Dada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisonsDada enterprise cost management solution comparisons
Dada enterprise cost management solution comparisons
 
Mauli Engineering Services Presentation
Mauli Engineering Services PresentationMauli Engineering Services Presentation
Mauli Engineering Services Presentation
 
NGS Owners Initial Proposal Timeline Discussion
NGS Owners Initial Proposal Timeline DiscussionNGS Owners Initial Proposal Timeline Discussion
NGS Owners Initial Proposal Timeline Discussion
 
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit FeesAlamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
 
Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu Resume
Kalyan Chunchu Resume
 
Manish Engineering Works
Manish Engineering WorksManish Engineering Works
Manish Engineering Works
 
-Strategy Planning Report
-Strategy Planning Report-Strategy Planning Report
-Strategy Planning Report
 
TQMI project Updated
TQMI project UpdatedTQMI project Updated
TQMI project Updated
 
Abdul basit resume
Abdul basit resumeAbdul basit resume
Abdul basit resume
 

Ähnlich wie Contract 2 - Project Progress Status. Oct-13

ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)
Jamal Nelson, CCM
 
Project MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning PlanProject MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning Plan
Osvaldo Zumba
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
MUHAMMAD SALEEM
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
Manish Shah
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
Nixzalis Bourdier
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
nkarthik21
 

Ähnlich wie Contract 2 - Project Progress Status. Oct-13 (20)

Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
Torkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdfTorkham Project Work Plan (18-Apr-2019).pdf
Torkham Project Work Plan (18-Apr-2019).pdf
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)ICOM Schedule & Logistics (1)
ICOM Schedule & Logistics (1)
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
Project MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning PlanProject MDBKU Installation and commissioning Plan
Project MDBKU Installation and commissioning Plan
 
Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6Activities - Presentation (NESPAK) v1.6
Activities - Presentation (NESPAK) v1.6
 
CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816CICPA Updated Schedule Dtd 130816
CICPA Updated Schedule Dtd 130816
 
MPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptxMPR OCT-22 PPT COMBINE.pptx
MPR OCT-22 PPT COMBINE.pptx
 
C&I July-2022.pptx
C&I July-2022.pptxC&I July-2022.pptx
C&I July-2022.pptx
 
KVMRT Dashboard V2 July 16.pdf
KVMRT Dashboard V2 July 16.pdfKVMRT Dashboard V2 July 16.pdf
KVMRT Dashboard V2 July 16.pdf
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
 
SAG NPD PPT APR2022 (00000002) (1).pptx
SAG NPD PPT  APR2022 (00000002) (1).pptxSAG NPD PPT  APR2022 (00000002) (1).pptx
SAG NPD PPT APR2022 (00000002) (1).pptx
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
Man power justification.pptx
Man power justification.pptxMan power justification.pptx
Man power justification.pptx
 
2 in 1 showcase
2 in 1 showcase2 in 1 showcase
2 in 1 showcase
 
Presentation
PresentationPresentation
Presentation
 
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
APRIL  -23 TO  Feb 24 FINAL PPT (3).pptxAPRIL  -23 TO  Feb 24 FINAL PPT (3).pptx
APRIL -23 TO Feb 24 FINAL PPT (3).pptx
 

Mehr von Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

Mehr von Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
N1
N1N1
N1
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Resources Histograms
Resources HistogramsResources Histograms
Resources Histograms
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Kandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _bKandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _b
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 

Contract 2 - Project Progress Status. Oct-13

  • 1. UPDATE Contract 2-Projects Progress Status October 2013
  • 2. Contract 2 Local Roads and Drainage Programme Planned Dates Actual Dates Planned Dates Actual Dates % Complete High Level Schedule Payment Schedule Current Approved Baselines Schedules Dashboard Updated Schedules Gateway 4 History QATAR ACCOUNT MANAGEMENT PROGRAM SPI Days till Completion
  • 3. Current Approved Baselines Public Works Authority ASHGHAL Local Roads and Drainage Programme Master Programme Milestones Approved Baselines G1 G2 G3 G5 G6 Baseline 15-May-13 20-Nov-13 13-Feb-14 17-Sep-14 4-Nov-14 21-Jun-17 18-Jul-18 Actual 15-May-13 20-Nov-13 13-Feb-14 17-Sep-14 4-Nov-14 21-Jun-17 1-Aug-18 Baseline 19-Dec-12 17-Apr-13 30-Jul-13 18-Dec-13 3-Mar-14 18-Nov-15 16-Nov-16 Actual 19-Dec-12 3-Jul-13 26-Aug-13 17-Dec-13 3-Mar-14 18-Nov-15 4-Jan-17 Baseline 22-Oct-12 20-Feb-13 20-Jun-13 18-Dec-13 4-Mar-14 16-Sep-15 21-Sep-16 Actual 22-Oct-12 3-Jul-13 12-Nov-13 17-Dec-13 4-Mar-14 16-Sep-15 2-Nov-16 QS016 Access Road to Rashid Village Prelim. Design Baseline 17-Apr-13 21-Aug-13 17-Dec-13 18-Jun-14 7-Sep-14 20-Jul-16 20-Sep-17 Actual 1-May-13 2-Oct-13 17-Dec-13 18-Jun-14 7-Sep-14 20-Jul-16 6-Sep-17 Baseline 21-Nov-12 3-Jul-13 23-Sep-13 19-Feb-14 6-May-14 19-Aug-15 21-Sep-16 QS017 Roads and Infrastructure in Al Karanna Village Concept Design QS004 Roads and Infrastructure in Wadi Aba Seleel Concept Design QS015 Roads and Infrastructure in Rawdat Rashed Village Prelim. Design Construction Detailed Design/ Tender Documents Tendering Project Code Project Name Current Stage Initiation Concept Design Preliminary Design Maintenance P eriod QS028 Roads Infrastructure in Birkat Al Awamer Industrial Area Prelim. Design Actual 21-Nov-12 3-Jul-13 18-Nov-13 19-Feb-14 6-May-14 19-Aug-15 5-Oct-16 Baseline 15-May-13 20-Nov-13 7-May-14 15-Oct-14 31-Dec-14 15-Feb-17 18-Apr-18 Actual 6-Nov-13 21-May-14 9-Nov-14 6-May-15 23-Jul-15 20-Sep-17 7-Nov-18 Baseline 22-Oct-12 27-Feb-13 25-Jun-13 17-Dec-13 18-Feb-14 15-Apr-15 18-May-16 Actual 22-Oct-12 27-Feb-13 25-Jun-13 17-Dec-13 18-Feb-14 15-Apr-15 1-Jun-16 Baseline 22-Oct-12 1-Aug-13 27-Oct-13 19-Mar-14 19-May-14 16-Mar-16 15-Mar-17 Actual 22-Oct-12 1-Aug-13 18-Nov-13 19-Mar-14 19-May-14 16-Mar-16 3-May-17 QS032 Link Road to Masyabiah Farm QS034 Salwa International Highway - Landscaping Irrigation Prelim. Design Baseline Concept/ On 21-Feb-13 19-Jun-13 21-Oct-13 19-Mar-14 3-Jun-14 16-Mar-16 15-Mar-17 Actual Hold 20-Feb-13 2-Oct-13 13-Jan-14 4-Jun-14 24-Aug-14 1-Jun-16 7-Jun-17 Concept Design Baseline 27-Feb-13 18-Sep-13 19-Feb-14 21-May-14 5-Aug-14 19-Aug-15 17-Aug-16 Actual 27-Feb-13 20-Nov-13 19-Mar-14 18-Jun-14 2-Sep-14 7-Oct-15 16-Nov-16 QS035 Al Kharrara/AlWakra Road Tareenah/Al Kharrara Road Roads and Infrastructure for Government Residential Division Project Gateway 4 History Project No. Gateway 4 Date Status QS004- Roads and Infrastructure in Wadi Aba Seleel 3-Jul-13 Approved QS034- Salwa International Highway - Landscaping Irrigation 1-Aug-13 Approved QS036 Detailed Design QS029 Roads and Infrastructure in Umm Al Zubar East West Village Initiation/ On Hold QS035- Al Kharrara/AlWakra Road Tareenah/Al Kharrara Road 4-Sep-13 Approved QS032- Link Road to Masyabiah Farm 2-Oct-13 Approved QS016- Access Road to Rashid Village 6-Nov-13 Not Approved File:- Current Approved Baseline Page 1 of 1 Printed On :- 11/11/2013 at 16:01
  • 4. Contract 2 Local Roads and Drainage Programme QS004 – Roads and Infrastructure in Wadi Aba Saleel QATAR ACCOUNT MANAGEMENT PROGRAM
  • 5. 1 Schedule Dashboard Projects Milestones QS004 - Roads and Infrastructure QQQSSS000000444 --- RRRoooaaadddsss aaannnddd IIInnnfffrrraaassstttrrruuuccctttuuurrreee iiiinnnn WWWWaaaaddddiiii AAAAbbbbaaaa SSSSeeeelllleeeeeeeellll Plan. Act. Initiation G1 15-May-13 15-May-13 0 100% 100% 0 Concept Design G2 20-Nov-13 20-Nov-13 0 90.0% 73.7% 0 Preliminary Design 13-Feb-14 13-Feb-14 0 0% 0% 0 Detailed DesignTender Documents G3 17-Sep-14 17-Sep-14 0 0% 0% 0 Tendering 04-Nov-14 04-Nov-14 0 0% 0% 0 Construction G5 21-Jun-17 21-Jun-17 0 0% 0% 0 Maintenance Period G6 18-Jul-18 01-Aug-18 -14 0% 0% -14 Monthly Progress Report No. 13 ­Oct 2013 Milestones Gateway Planned Actual / Forecast Total Variance % Progress Trend Initiation Concept Design Preliminary Design Detailed DesignTender Documents Tendering Construction Maintenance Period Planned Actual/Forecast G1 G2 G3 G5 G6 Behind Schedule No Change Downward Trend On Schedule Concept Design Current Segment 20 Days Until Completion (Starting from 1st Nov) 73.7 0.82 Progress % Complete SPI Upward Trend File :- Schedule Management - Oct 13 Printed On :- 11/11/2013 at 16:06
  • 6. Activity ID Activity Name Planned Duration Current Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan Project Wide - High Level Schedule 1325 1335 11-Apr-13 18-Jul-18 11-Apr-13 A 01-Aug-18 0 0% Programme Wide -High Level Schedule 1325 1335 11-Apr-13 18-Jul-18 11-Apr-13 A 01-Aug-18 0 0% Programme Wide High Level Schedule 1325 1335 11-Apr-13 18-Jul-18 11-Apr-13 A 01-Aug-18 0 0% Initiation 25 25 11-Apr-13 15-May-13 11-Apr-13 A 15-May-13 A 0% Initiation 11 11 11-Apr-13 25-Apr-13 11-Apr-13 A 25-Apr-13 A 0% QS004 020000 Formal Confirmation Letter from PMC 0 0 11-Apr-13 11-Apr-13 A 100% QS004 020330 Initiation 11 11 11-Apr-13 25-Apr-13 11-Apr-13 A 25-Apr-13 A 100% QS004 020340 Initiation Slides Submission 0 0 25-Apr-13 25-Apr-13 A 100% 18 Day Review 19 19 27-Apr-13 15-May-13 27-Apr-13 A 15-May-13 A 0% QS004 212101 PMC/PWA Initiation Review 18 18 27-Apr-13 14-May-13 27-Apr-13 A 14-May-13 A 100% QS004 020061 Gateway 1 Review Meeting 0 0 15-May-13 15-May-13 A 100% Concept Design 129 129 16-May-13 20-Nov-13 16-May-13 A 20-Nov-13 0 0% Concept Design 103 103 16-May-13 10-Oct-13 16-May-13 A 10-Oct-13 A 0% QS004 020070 Concept Design 103 103 16-May-13 10-Oct-13 16-May-13 A 10-Oct-13 A 100% QS004 212411 Concept Design Submission 0 0 10-Oct-13 10-Oct-13 A 100% 35 Day Review 41 41 11-Oct-13 20-Nov-13 11-Oct-13 A 20-Nov-13 0 0% QS004 212421 PMC Concept Design Review 10 10 11-Oct-13 20-Oct-13 11-Oct-13 A 01-Nov-13 0 60% QS004 212431 GEC Response to PMC Comments 7 7 21-Oct-13 27-Oct-13 21-Oct-13 A 01-Nov-13 0 34.03% QS004 212441 PMC Review of GEC Response 4 4 28-Oct-13 31-Oct-13 02-Nov-13 05-Nov-13 0 0% QS004 212451 PWA Review 14 14 01-Nov-13 14-Nov-13 06-Nov-13 19-Nov-13 0 0% QS004 212461 Gateway 2 Review Meeting 0 0 20-Nov-13 20-Nov-13 0 0% Preliminary Design 82 82 21-Nov-13 20-Mar-14 21-Nov-13 20-Mar-14 90 0% Preliminary Design 57 57 21-Nov-13 13-Feb-14 21-Nov-13 13-Feb-14 0 0% QS004 020130 Preliminary Design 57 57 21-Nov-13 13-Feb-14 21-Nov-13 13-Feb-14 0 0% QS004 212471 Preliminary Design Submission 0 0 13-Feb-14 13-Feb-14 0 0% 35 Day Review 35 35 14-Feb-14 20-Mar-14 14-Feb-14 20-Mar-14 126 0% QS004 212481 PMC Preliminary Design Review 10 10 14-Feb-14 23-Feb-14 14-Feb-14 23-Feb-14 126 0% QS004 212491 GEC Response to PMC Comments 7 7 24-Feb-14 02-Mar-14 24-Feb-14 02-Mar-14 126 0% QS004 212501 PMC Review of GEC Response 4 4 03-Mar-14 06-Mar-14 03-Mar-14 06-Mar-14 126 0% QS004 212511 PWA Review 14 14 07-Mar-14 20-Mar-14 07-Mar-14 20-Mar-14 126 0% Detailed Design Tender Documents 151 151 16-Feb-14 17-Sep-14 16-Feb-14 17-Sep-14 0 0% Detailed Design Tender Documents 125 125 16-Feb-14 12-Aug-14 16-Feb-14 12-Aug-14 0 0% QS004 020140 Detailed Design 115 115 16-Feb-14 24-Jul-14 16-Feb-14 24-Jul-14 0 0% QS004 020150 Tender Documents 31 31 26-Jun-14 12-Aug-14 26-Jun-14 12-Aug-14 0 0% QS004 212521 Detailed DesignTender Documents Submission 0 0 12-Aug-14 12-Aug-14 0 0% 35 Day Review 36 36 13-Aug-14 17-Sep-14 13-Aug-14 17-Sep-14 0 0% QS004 212531 PMC Detailed DesignTender Documents Review 10 10 13-Aug-14 22-Aug-14 13-Aug-14 22-Aug-14 0 0% QS004 212541 GEC Response to PMC Comments 7 7 23-Aug-14 29-Aug-14 23-Aug-14 29-Aug-14 0 0% QS004 212551 PMC Review of GEC Response 4 4 30-Aug-14 02-Sep-14 30-Aug-14 02-Sep-14 0 0% QS004 212561 PWA Review 14 14 03-Sep-14 16-Sep-14 03-Sep-14 16-Sep-14 0 0% QS004 020180 Gateway 3 Review Meeting 0 0 17-Sep-14 17-Sep-14 0 0% Tendering 42 42 18-Sep-14 19-Nov-14 18-Sep-14 19-Nov-14 12 0% Tendering and Awarding 42 42 18-Sep-14 19-Nov-14 18-Sep-14 19-Nov-14 12 0% QS004 020210 Tendering of the Project 14 14 18-Sep-14 12-Oct-14 18-Sep-14 12-Oct-14 0 0% 2013 2014 2015 2016 2017 2018 2019 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Formal Confirmation Letter from PMC Initiation Initiation Slides Submission PMC/PWA Initiation Review Gateway 1 Review Meeting Concept Design Concept Design Submission PMC Concept Design Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 2 Review Meeting Preliminary Design Preliminary Design Submission PMC Preliminary Design Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Detailed Design Tender Documents Detailed DesignTender Documents Submission PMC Detailed DesignTender Documents Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 3 Review Meeting Tendering of the Project Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 1 of 4 Printed On : 07-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS004 - Roads and Infrastrucutre in Wadi Aba Seleel Update as of 31-Oct-2013 Date Revision Ch... Appro... 31-Aug-13 Schedule Update - Aug-13 MN 30-Sep-13 Schedule Update - Sep-13 MN 31-Oct-13 Schedule Update - Oct-13 MN
  • 7. Activity ID Activity Name Planned Duration Current Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan QS004 020250 Tender AssessmentRecommendations 7 7 13-Oct-14 21-Oct-14 13-Oct-14 21-Oct-14 0 0% QS004 020220 Award of the Construction Contract (Work Order) 0 0 04-Nov-14 04-Nov-14 0 0% QS004 020270 PMC/PWA Approval 10 10 22-Oct-14 04-Nov-14 22-Oct-14 04-Nov-14 0 0% QS004 020360 Prepare and Issue Notice to Proceed 1 1 05-Nov-14 05-Nov-14 05-Nov-14 05-Nov-14 0 0% QS004 020280 Prepare Contract Documents for Work Order 5 5 06-Nov-14 12-Nov-14 06-Nov-14 12-Nov-14 12 0% QS004 020300 Contract Signed off by ContractorPWA 4 4 13-Nov-14 18-Nov-14 13-Nov-14 18-Nov-14 12 0% QS004 020380 Exchange of Contract 1 1 19-Nov-14 19-Nov-14 19-Nov-14 19-Nov-14 12 0% Construction 664 664 06-Nov-14 21-Jun-17 06-Nov-14 21-Jun-17 0 0% Construction Period 638 638 06-Nov-14 16-May-17 06-Nov-14 16-May-17 0 0% QS004 020310 Contractor Mobilization Period 22 22 06-Nov-14 07-Dec-14 06-Nov-14 07-Dec-14 0 0% QS004 020230 Construction of the Project 616 616 08-Dec-14 16-May-17 08-Dec-14 16-May-17 0 0% QS004 212611 Construction Documents Submission 0 0 16-May-17 16-May-17 0 0% 35 Day Review 36 36 17-May-17 21-Jun-17 17-May-17 21-Jun-17 0 0% QS004 212571 PMC Construction Documents Review 10 10 17-May-17 26-May-17 17-May-17 26-May-17 0 0% QS004 212581 GEC Response to PMC Comments 7 7 27-May-17 02-Jun-17 27-May-17 02-Jun-17 0 0% QS004 212591 PMC Review of GEC Response 4 4 03-Jun-17 06-Jun-17 03-Jun-17 06-Jun-17 0 0% QS004 212601 PWA Review 14 14 07-Jun-17 20-Jun-17 07-Jun-17 20-Jun-17 0 0% QS004 020260 Gateway 5 Review Meeting 0 0 21-Jun-17 21-Jun-17 0 0% Maintenance Period 392 406 22-Jun-17 18-Jul-18 22-Jun-17 01-Aug-18 0 0% Maintenance Period 356 365 22-Jun-17 12-Jun-18 22-Jun-17 21-Jun-18 0 0% QS004 020290 Maintenance Period 244 365 22-Jun-17 12-Jun-18 22-Jun-17 21-Jun-18 0 0% QS004 212621 Maintenance Documents Submission 0 0 12-Jun-18 21-Jun-18 0 0% 35 Day Review 36 41 13-Jun-18 18-Jul-18 22-Jun-18 01-Aug-18 0 0% QS004 212631 PMC Maintenance Documents Review 10 10 13-Jun-18 22-Jun-18 22-Jun-18 01-Jul-18 0 0% QS004 212641 GEC Response to PMC Comments 7 7 23-Jun-18 29-Jun-18 02-Jul-18 08-Jul-18 0 0% QS004 212651 PMC Review of GEC Response 4 4 30-Jun-18 03-Jul-18 09-Jul-18 12-Jul-18 0 0% QS004 212661 PWA Review 14 14 04-Jul-18 17-Jul-18 13-Jul-18 26-Jul-18 0 0% QS004 020320 Gateway 6 Review Meeting 0 0 18-Jul-18 01-Aug-18 0 0% QS004 020350 Project Completion 0 0 18-Jul-18 01-Aug-18 0 0% MMUP and MOE 267 275 13-Oct-13 06-Nov-14 11-Apr-13 A 06-Nov-14 21 0% Ministry of Environment 267 275 13-Oct-13 06-Nov-14 11-Apr-13 A 06-Nov-14 21 0% Ministry of Environment 267 275 13-Oct-13 06-Nov-14 11-Apr-13 A 06-Nov-14 21 0% QS004 440000 PMC/MOE Review 30 30 25-Dec-13 23-Jan-14 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440010 Enviromental Scoping 30 30 26-Jan-14 09-Mar-14 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440020 PMC/MOE Review 30 30 11-Mar-14 09-Apr-14 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440030 Environmental Impact Assessment (EIA) 61 61 10-Apr-14 03-Jul-14 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440040 PMC/MOE Review 30 30 07-Jul-14 05-Aug-14 11-Apr-13 A 11-Apr-13 A 100% QS004 440050 Enviromental Permit Issued 0 0 06-Aug-14 11-Apr-13 A 0% QS004 440080 Permit Application Submission 0 0 24-Dec-13 11-Apr-13 A 0% Escaped QS004 440090 Enviromental Scoping Submission 0 0 10-Mar-14 11-Apr-13 A 0% Escaped QS004 440100 EIA Submission 0 0 06-Jul-14 11-Apr-13 A 0% Escaped QS004 440060 Preparation of Enviromental Permit Application 48 48 13-Oct-13 23-Dec-13 15-May-13 A 26-May-13 A 100% QS004 440070 Review Contractor CEMP 6 6 15-Oct-14 22-Oct-14 15-Oct-14 22-Oct-14 31 0% QS004 440110 CEMP Submission to MOE 0 0 06-Nov-14 06-Nov-14 21 0% 2013 2014 2015 2016 2017 2018 2019 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Tender AssessmentRecommendations Award of the Construction Contract (Work Order) PMC/PWA Approval Prepare and Issue Notice to Proceed Prepare Contract Documents for Work Order Contract Signed off by ContractorPWA Exchange of Contract Contractor Mobilization Period Construction of the Project Construction Documents Subm PMC Construction Documents GEC Response to PMC Comm PMC Review of GEC Respon PWA Review Gateway 5 Review Meeting Maintenance P Maintenance D PMC Mainten GEC Respon PMC Review PWA Review Gateway 6 R Project Com PMC/MOE Review Enviromental Scoping PMC/MOE Review Environmental Impact Assessment (EIA) PMC/MOE Review Enviromental Permit Issued Permit Application Submission Enviromental Scoping Submission EIA Submission Preparation of Enviromental Permit Application Review Contractor CEMP CEMP Submission to MOE Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 2 of 4 Printed On : 07-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS004 - Roads and Infrastrucutre in Wadi Aba Seleel Update as of 31-Oct-2013 Date Revision Ch... Appro... 31-Aug-13 Schedule Update - Aug-13 MN 30-Sep-13 Schedule Update - Sep-13 MN 31-Oct-13 Schedule Update - Oct-13 MN
  • 8. Activity ID Activity Name Planned Duration Current Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan Stakeholders Engagement 1258 1268 15-Jul-13 18-Jul-18 11-Apr-13 A 01-Aug-18 0 0% Concept Design 87 87 15-Jul-13 20-Nov-13 16-May-13 A 20-Nov-13 0 0% Concept Design 87 87 15-Jul-13 20-Nov-13 16-May-13 A 20-Nov-13 0 0% QS004 021020 Liaison with Stakeholders - Concept Design 87 87 15-Jul-13 20-Nov-13 16-May-13 A 20-Nov-13 0 88.89% Preliminary Design 60 60 18-Nov-13 13-Feb-14 18-Nov-13 13-Feb-14 0 0% Preliminary Design 60 60 18-Nov-13 13-Feb-14 18-Nov-13 13-Feb-14 0 0% QS004 212671 Liaison with Stakeholders - Preliminary Design 60 60 18-Nov-13 13-Feb-14 18-Nov-13 13-Feb-14 0 0% Detailed Design Tendering 180 180 19-Feb-14 05-Nov-14 19-Feb-14 05-Nov-14 0 0% Detailed Design Tendering 180 180 19-Feb-14 05-Nov-14 19-Feb-14 05-Nov-14 0 0% QS004 212681 Liaison with Stakeholders - Detailed Design Tendering 180 180 19-Feb-14 05-Nov-14 19-Feb-14 05-Nov-14 0 0% Construction 664 664 06-Nov-14 21-Jun-17 06-Nov-14 21-Jun-17 0 0% Construction 664 664 06-Nov-14 21-Jun-17 06-Nov-14 21-Jun-17 0 0% QS004 212701 Liaison with Stakeholders - Construction 664 664 06-Nov-14 21-Jun-17 06-Nov-14 21-Jun-17 0 0% Maintenance Period 267 267 22-Jun-17 18-Jul-18 11-Jul-17 01-Aug-18 0 0% Maintenance Period 267 267 22-Jun-17 18-Jul-18 11-Jul-17 01-Aug-18 0 0% QS004 212711 Liaison with Stakeholders - Maintenance Period 267 267 22-Jun-17 18-Jul-18 11-Jul-17 01-Aug-18 0 0% MMUP Utility Investigation 90 104 15-Jul-13 25-Nov-13 11-Apr-13 A 15-Dec-13 40 0% QS004 440240 Superimpose Data on Proposed Road Layout 10 10 05-Sep-13 18-Sep-13 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440260 Agencies Approval 15 15 19-Sep-13 09-Oct-13 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440210 Utility Investigation by Owner/Consultant/Client 10 10 15-Jul-13 28-Jul-13 15-Jul-13 A 28-Jul-13 A 100% QS004 440220 Collect Data (Existing Proposed Utilties) 10 10 29-Jul-13 14-Aug-13 29-Jul-13 A 14-Aug-13 A 100% QS004 440230 Topo Survey,Trial Pits and Radio Detection 15 15 15-Aug-13 04-Sep-13 15-Aug-13 A 24-Nov-13 40 10% QS004 440290 MMUP Approval 15 15 10-Oct-13 04-Nov-13 04-Nov-13 24-Nov-13 40 0% QS004 440300 Final Report to MMUP 15 15 05-Nov-13 25-Nov-13 25-Nov-13 15-Dec-13 40 0% KAHRAMA 75 114 15-Jul-13 04-Nov-13 15-Jul-13 A 31-Dec-13 30 0% QS004 440310 Send an Introductory Letters to KAHRAMA 10 10 15-Jul-13 28-Jul-13 15-Jul-13 A 28-Jul-13 A 100% QS004 440320 Request for Information about KAHRAMA's Current/Futu 10 10 29-Jul-13 14-Aug-13 29-Jul-13 A 14-Aug-13 A 100% QS004 440340 Superimpose the Plans on Proposed Project to Identify C 10 10 05-Sep-13 18-Sep-13 05-Sep-13 A 17-Nov-13 30 50% QS004 440330 Receive Information about KAHRAMA's Current/Future P 15 15 15-Aug-13 04-Sep-13 15-Aug-13 A 24-Nov-13 30 50% QS004 440350 Report the Conflicts to KAHRAMA 10 10 19-Sep-13 02-Oct-13 18-Nov-13 01-Dec-13 30 0% QS004 440360 Amend the Drawings 10 10 03-Oct-13 21-Oct-13 02-Dec-13 15-Dec-13 30 0% QS004 440370 Drawings Submission to KAHRAMA for Approval 10 10 22-Oct-13 04-Nov-13 16-Dec-13 31-Dec-13 30 0% Communication (Oredoo/Vodafone) 75 114 15-Jul-13 04-Nov-13 15-Jul-13 A 31-Dec-13 30 0% QS004 440380 Send an Introductory Letters to Oredoo/Vodafone 10 10 15-Jul-13 28-Jul-13 15-Jul-13 A 28-Jul-13 A 100% QS004 440390 Request for Information about Oredo/Vodafone's Curren 10 10 29-Jul-13 14-Aug-13 29-Jul-13 A 14-Aug-13 A 100% QS004 440400 Receive Information about Oredo/Vodafone's Current/Fu 15 15 15-Aug-13 04-Sep-13 15-Aug-13 A 04-Sep-13 A 100% QS004 440410 Superimpose the Plans on Proposed Project to Identify C 10 10 05-Sep-13 18-Sep-13 05-Sep-13 A 17-Nov-13 30 25% QS004 440420 Report the Conflicts to Oredoo/Vodafone 10 10 19-Sep-13 02-Oct-13 18-Nov-13 01-Dec-13 30 0% QS004 440430 Amend the Drawings 10 10 03-Oct-13 21-Oct-13 02-Dec-13 15-Dec-13 30 0% QS004 440440 Drawings Submission to Oredoo/Vodafone for Approval 10 10 22-Oct-13 04-Nov-13 16-Dec-13 31-Dec-13 30 0% Natural Reserves (NR) 75 75 15-Jul-13 04-Nov-13 11-Apr-13 A 11-Apr-13 A 0% QS004 440450 Send an Introductory Letters to NR 10 10 15-Jul-13 28-Jul-13 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440460 Request for Information about NR's Current/Future Proje 10 10 29-Jul-13 14-Aug-13 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440470 Receive Information about NR's Current/Future Projects 15 15 15-Aug-13 04-Sep-13 11-Apr-13 A 11-Apr-13 A 100% Escaped 2013 2014 2015 2016 2017 2018 2019 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Liaison with Stakeholders - Concept Design Liaison with Stakeholders - Preliminary Design Liaison with Stakeholders - Detailed Design Tendering Liaison with Stakeholders - C Liaison with Superimpose Data on Proposed Road Layout Agencies Approval Utility Investigation by Owner/Consultant/Client Collect Data (Existing Proposed Utilties) Topo Survey,Trial Pits and Radio Detection MMUP Approval Final Report to MMUP Send an Introductory Letters to KAHRAMA Request for Information about KAHRAMA's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Receive Information about KAHRAMA's Current/Future Projects Report the Conflicts to KAHRAMA Amend the Drawings Drawings Submission to KAHRAMA for Approval Send an Introductory Letters to Oredoo/Vodafone Request for Information about Oredo/Vodafone's Current/Future Projects Receive Information about Oredo/Vodafone's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Report the Conflicts to Oredoo/Vodafone Amend the Drawings Drawings Submission to Oredoo/Vodafone for Approval Send an Introductory Letters to NR Request for Information about NR's Current/Future Projects Receive Information about NR's Current/Future Projects Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 3 of 4 Printed On : 07-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS004 - Roads and Infrastrucutre in Wadi Aba Seleel Update as of 31-Oct-2013 Date Revision Ch... Appro... 31-Aug-13 Schedule Update - Aug-13 MN 30-Sep-13 Schedule Update - Sep-13 MN 31-Oct-13 Schedule Update - Oct-13 MN
  • 9. Activity ID Activity Name Planned Duration Current Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan QS004 440480 Superimpose the Plans on Proposed Project to Identify C 10 10 05-Sep-13 18-Sep-13 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440490 Report the Conflicts to NR 10 10 19-Sep-13 02-Oct-13 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440500 Amend the Drawings 10 10 03-Oct-13 21-Oct-13 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440510 Drawings Submission to NR for Approval 10 10 22-Oct-13 04-Nov-13 11-Apr-13 A 11-Apr-13 A 100% Escaped Private Engineer Office (PEO) 75 94 15-Jul-13 04-Nov-13 11-Apr-13 A 01-Dec-13 50 0% QS004 440570 Amend the Drawings 10 10 03-Oct-13 21-Oct-13 11-Apr-13 A 11-Apr-13 A 100% Escaped QS004 440520 Send an Introductory Letters to PEO 10 10 15-Jul-13 28-Jul-13 15-Jul-13 A 28-Jul-13 A 100% QS004 440530 Request for Information about PEO's Current/Future Pro 10 10 29-Jul-13 14-Aug-13 29-Jul-13 A 14-Aug-13 A 100% QS004 440540 Receive Information about PEO's Current/Future Projects 15 15 15-Aug-13 04-Sep-13 15-Aug-13 A 04-Sep-13 A 100% QS004 440550 Superimpose the Plans on Proposed Project to Identify C 10 10 05-Sep-13 18-Sep-13 05-Sep-13 A 18-Sep-13 A 100% QS004 440560 Report the Conflicts to PEO 10 10 19-Sep-13 02-Oct-13 19-Sep-13 A 17-Nov-13 50 5% QS004 440580 Drawings Submission to PEO for Approval 10 10 22-Oct-13 04-Nov-13 18-Nov-13 01-Dec-13 50 0% 2013 2014 2015 2016 2017 2018 2019 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Superimpose the Plans on Proposed Project to Identify Conflict Report the Conflicts to NR Amend the Drawings Drawings Submission to NR for Approval Amend the Drawings Send an Introductory Letters to PEO Request for Information about PEO's Current/Future Projects Receive Information about PEO's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Report the Conflicts to PEO Drawings Submission to PEO for Approval Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 4 of 4 Printed On : 07-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS004 - Roads and Infrastrucutre in Wadi Aba Seleel Update as of 31-Oct-2013 Date Revision Ch... Appro... 31-Aug-13 Schedule Update - Aug-13 MN 30-Sep-13 Schedule Update - Sep-13 MN 31-Oct-13 Schedule Update - Oct-13 MN
  • 10. Activity ID Activity Name Planned Start Planned Finish Budgeted Payment (QAR) Actual Payment (QAR) Remaining Payment (QAR) Payment % Complete Earned Value Cost Total 16-May-13 19-Nov-14 QR18,219,504 QR3,702,675 QR14,516,831 20.32% QR3,702,673 Concept Design 16-May-13 14-Nov-13 QR5,877,259 QR3,702,675 QR2,174,587 63% QR3,702,673 Submission of Concept Design (60%) 16-May-13 07-Oct-13 QR3,526,356 QR3,526,357 QR1 100% QR3,526,356 QS0041088 Project Schedule 16-May-13 12-Jun-13 QR528,953 QR528,953 QR0 100% QR528,953 QS0041098 Main Report (Volume 1) 27-Aug-13 03-Oct-13 QR528,953 QR528,953 QR0 100% QR528,953 QS0041108 Geotechnical Report (Volume 2) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 QS0041118 Traffic Analysis Report (Volume 3) 05-Sep-13 02-Oct-13 QR352,636 QR352,636 QR0 100% QR352,636 QS0041128 Drainage Part A (SW GW) (Volume 4A) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 QS0041138 Drainage Part B (FS) (Volume 4B) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 QS0041148 Drainage Part C (TSE) (Volume 4C) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 QS0041158 Environmental and Sustainablity (Volume 5) 11-Sep-13 01-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 QS0041168 Drawings (Volume 6) 05-Sep-13 02-Oct-13 QR528,953 QR528,953 QR0 100% QR528,953 QS0041178 Stakeholders (Volume 7) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 QS0041188 Commercial Report (Volume 8) 10-Sep-13 07-Oct-13 QR352,636 QR352,636 QR0 100% QR352,636 QS0041198 RSA - Review (Volume 9A) 05-Sep-13 02-Oct-13 QR176,318 QR176,318 QR0 100% QR176,318 PMC Acceptance with Comments (20%) 13-Oct-13 20-Oct-13 QR1,175,452 QR117,545 QR1,057,907 10% QR117,545 QS0041199 PMC Accpetance with Comments 13-Oct-13 20-Oct-13 QR1,175,452 QR117,545 QR1,057,907 10% QR117,545 PMC Acceptance (10%) 28-Oct-13 31-Oct-13 QR587,726 QR58,773 QR528,953 10% QR58,773 QS0041200 PMC Accpetance 28-Oct-13 31-Oct-13 QR587,726 QR58,773 QR528,953 10% QR58,773 PWA Approval (10%) 03-Nov-13 14-Nov-13 QR587,726 QR0 QR587,726 0% QR0 QS0041201 PWA Approval 03-Nov-13 14-Nov-13 QR587,726 QR0 QR587,726 0% QR0 Preliminiary Design 21-Nov-13 20-Mar-14 QR2,468,449 QR0 QR2,468,449 0% QR0 Submission of Preliminary Design (60%) 21-Nov-13 13-Feb-14 QR1,481,069 QR0 QR1,481,069 0% QR0 QS0041000 Updated Project Schedule 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 QS0041001 Volume 1 - Main Report 21-Nov-13 13-Feb-14 QR148,107 QR0 QR148,107 0% QR0 QS0041002 Volume 2 - Geotechnical Investigation Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 QS0041003 Volume 3 - Traffic Analysis Report 21-Nov-13 13-Feb-14 QR185,134 QR0 QR185,134 0% QR0 QS0041004 Volume 4A - Surface and Ground Water Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 QS0041005 Volume 4B - Foul Water Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 QS0041006 Volume 4C - Treated Sewage Effluent Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 QS0041007 Volume 5 - Environmental and Sustainability 21-Nov-13 13-Feb-14 QR185,134 QR0 QR185,134 0% QR0 QS0041008 Volume 6 - Drawings 21-Nov-13 13-Feb-14 QR259,187 QR0 QR259,187 0% QR0 QS0041009 Volume 7 - Stakeholders Report 21-Nov-13 13-Feb-14 QR74,053 QR0 QR74,053 0% QR0 QS0041019 Volume 8 - Commercial Report 21-Nov-13 13-Feb-14 QR148,107 QR0 QR148,107 0% QR0 QS0041029 Volume 9B - Road Safety Audit - Brief 21-Nov-13 13-Feb-14 QR37,027 QR0 QR37,027 0% QR0 QS0041039 Volume 9C - Road Safety Audit - Report 21-Nov-13 13-Feb-14 QR37,027 QR0 QR37,027 0% QR0 QS0041049 Volume 9D - Road Safety Audit - Designer's Res 21-Nov-13 13-Feb-14 QR37,027 QR0 QR37,027 0% QR0 PMC Acceptance with Comments (20%) 16-Feb-14 23-Feb-14 QR493,690 QR0 QR493,690 0% QR0 QS0041059 PMC Accpetance with Comments 16-Feb-14 23-Feb-14 QR493,690 QR0 QR493,690 0% QR0 PMC Acceptance (10%) 03-Mar-14 06-Mar-14 QR246,845 QR0 QR246,845 0% QR0 QS0041069 PMC Accpetance 03-Mar-14 06-Mar-14 QR246,845 QR0 QR246,845 0% QR0 PWA Approval (10%) 09-Mar-14 20-Mar-14 QR246,845 QR0 QR246,845 0% QR0 QS0041079 PWA Approval 09-Mar-14 20-Mar-14 QR246,845 QR0 QR246,845 0% QR0 2013 2014 2015 D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D J F Project Schedule Main Report (Volume 1) Geotechnical Report (Volume 2) Traffic Analysis Report (Volume 3) Drainage Part A (SW GW) (Volume 4A) Drainage Part B (FS) (Volume 4B) Drainage Part C (TSE) (Volume 4C) Environmental and Sustainablity (Volume 5) Drawings (Volume 6) Stakeholders (Volume 7) Commercial Report (Volume 8) RSA - Review (Volume 9A) PMC Accpetance with Comments, PMC Accpe PMC Accpetance PWA Approval Updated Project Schedule Volume 1 - Main Report Volume 2 - Geotechnical Investigatio Volume 3 - Traffic Analysis Report Volume 4A - Surface and Ground Wa Volume 4B - Foul Water Report Volume 4C - Treated Sewage Effluen Volume 5 - Environmental and Susta Volume 6 - Drawings Volume 7 - Stakeholders Report Volume 8 - Commercial Report Volume 9B - Road Safety Audit - Brie Volume 9C - Road Safety Audit - Rep Volume 9D - Road Safety Audit - Des PMC Accpetance with Comments PMC Accpetance PWA Approval Public Works Authority Local Roads and Drainage Programme Earned Value as of 31-Oct-13 Remaining Level of Effort Actual Level of Effort Baseline Project Start:- 11-Apr-13 Project Finish:- 02-Aug-18 Layout:- A4 - QS004 - Monthly EVM Report Data Date : 31-Oct-13 Page : 1 of 3 Printed On : 07-Nov-13 Date Revision Checked Approved 30-Sep-13 Payment Schedule Update MN 31-Oct-13 Payment Schedule Update MN
  • 11. Activity ID Activity Name Planned Start Planned Finish Budgeted Payment (QAR) Actual Payment (QAR) Remaining Payment (QAR) Payment % Complete Earned Value Cost Detailed Design 16-Feb-14 16-Sep-14 QR4,936,898 QR0 QR4,936,898 0% QR0 Submission of Detailed Design (60%) 16-Feb-14 24-Jul-14 QR2,962,139 QR0 QR2,962,139 0% QR0 QS0041167 Updated Project Schedule 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 QS0041168 Volume 1 - Main Report 16-Feb-14 24-Jul-14 QR444,321 QR0 QR444,321 0% QR0 QS0041169 Volume 2 - Geotechnical Factual Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 QS0041170 Volume 2 - Geotechnical Interpretative Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 QS0041172 Volume 4A - Surface and Ground Water Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 QS0041173 Volume 4B - Foul Water Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 QS0041174 Volume 4C - Treated Sewage Effluent Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 QS0041175 Volume 5 - Environmental and Sustainability 16-Feb-14 24-Jul-14 QR296,214 QR0 QR296,214 0% QR0 QS0041176 Volume 6 - Drawings 16-Feb-14 24-Jul-14 QR592,428 QR0 QR592,428 0% QR0 QS0041177 Volume 7 - Stakeholders Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 QS0041178 Volume 8 - Commercial Report 16-Feb-14 24-Jul-14 QR296,214 QR0 QR296,214 0% QR0 QS0041180 Volume 9C - Road Safety Audit - Report 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 QS0041181 Volume 9D - Road Safety Audit - Designer's Res 16-Feb-14 24-Jul-14 QR148,107 QR0 QR148,107 0% QR0 PMC Acceptance with Comments (20%) 13-Aug-14 21-Aug-14 QR987,380 QR0 QR987,380 0% QR0 QS0041219 PMC Accpetance with Comments 13-Aug-14 21-Aug-14 QR987,380 QR0 QR987,380 0% QR0 PMC Acceptance (10%) 31-Aug-14 02-Sep-14 QR493,690 QR0 QR493,690 0% QR0 QS0041229 PMC Accpetance 31-Aug-14 02-Sep-14 QR493,690 QR0 QR493,690 0% QR0 PWA Approval (10%) 03-Sep-14 16-Sep-14 QR493,690 QR0 QR493,690 0% QR0 QS0041239 PWA Approval 03-Sep-14 16-Sep-14 QR493,690 QR0 QR493,690 0% QR0 Tender Documents 26-Jun-14 16-Sep-14 QR1,851,337 QR0 QR1,851,337 0% QR0 Submission of Tender Documents (60%) 26-Jun-14 12-Aug-14 QR1,110,802 QR0 QR1,110,802 0% QR0 QS0045470 Specification Drawings 26-Jun-14 12-Aug-14 QR388,781 QR0 QR388,781 0% QR0 QS0045471 Conditions of Contract 26-Jun-14 12-Aug-14 QR111,080 QR0 QR111,080 0% QR0 QS0045472 Particular Conditions of Contract Nominate S/C 26-Jun-14 12-Aug-14 QR55,540 QR0 QR55,540 0% QR0 QS0045473 Preliminary Bill of Quantity 26-Jun-14 12-Aug-14 QR55,540 QR0 QR55,540 0% QR0 QS0045474 Final Bill of Quantities 26-Jun-14 12-Aug-14 QR111,080 QR0 QR111,080 0% QR0 QS0045475 Pre-Tender Estimate 26-Jun-14 12-Aug-14 QR222,160 QR0 QR222,160 0% QR0 QS0045476 Project Programme 26-Jun-14 12-Aug-14 QR166,620 QR0 QR166,620 0% QR0 PMC Acceptance with Comments (20%) 13-Aug-14 21-Aug-14 QR370,267 QR0 QR370,267 0% QR0 QS0045477 PMC Accpetance with Comments 13-Aug-14 21-Aug-14 QR370,267 QR0 QR370,267 0% QR0 PMC Acceptance (10%) 31-Aug-14 02-Sep-14 QR185,134 QR0 QR185,134 0% QR0 QS0045499 PMC Accpetance 31-Aug-14 02-Sep-14 QR185,134 QR0 QR185,134 0% QR0 PWA Approval (10%) 03-Sep-14 16-Sep-14 QR185,134 QR0 QR185,134 0% QR0 QS0045100 PWA Approval 03-Sep-14 16-Sep-14 QR185,134 QR0 QR185,134 0% QR0 Tender 18-Sep-14 05-Nov-14 QR1,851,337 QR0 QR1,851,337 0% QR0 PWA Approval (100%) 18-Sep-14 05-Nov-14 QR1,851,337 QR0 QR1,851,337 0% QR0 QS0045478 Issue Invitation toTender 18-Sep-14 18-Sep-14 QR185,134 QR0 QR185,134 0% QR0 QS0045479 Tender Queries / Pre Tender Workshop 18-Sep-14 12-Oct-14 QR370,267 QR0 QR370,267 0% QR0 QS0045480 Tender Evaluation Report 13-Oct-14 21-Oct-14 QR370,267 QR0 QR370,267 0% QR0 QS0045481 Award of Contract (Work Order) 22-Oct-14 04-Nov-14 QR555,401 QR0 QR555,401 0% QR0 QS0045482 Prepare and Issue Notice to Proceed 05-Nov-14 05-Nov-14 QR370,267 QR0 QR370,267 0% QR0 2013 2014 2015 D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D J F Updated Project Sch Volume 1 - Main Rep Volume 2 - Geotechn Volume 2 - Geotechn Volume 4A - Surface Volume 4B - Foul W Volume 4C - Treated Volume 5 - Environm Volume 6 - Drawings Volume 7 - Stakehol Volume 8 - Commerc Volume 9C - Road S Volume 9D - Road S PMC Accpetance PMC Accpetanc PWA Approval Specification Dra Conditions of Cont Particular Conditio Preliminary Bill of Q Final Bill of Quanti Pre-Tender Estima Project Programme PMC Accpetance PMC Accpetanc PWA Approval Issue Invitation Tender Quer Tender Eval Award of C Prepare an Public Works Authority Local Roads and Drainage Programme Earned Value as of 31-Oct-13 Remaining Level of Effort Actual Level of Effort Baseline Project Start:- 11-Apr-13 Project Finish:- 02-Aug-18 Layout:- A4 - QS004 - Monthly EVM Report Data Date : 31-Oct-13 Page : 2 of 3 Printed On : 07-Nov-13 Date Revision Checked Approved 30-Sep-13 Payment Schedule Update MN 31-Oct-13 Payment Schedule Update MN
  • 12. Activity ID Activity Name Planned Start Planned Finish Budgeted Payment (QAR) Actual Payment (QAR) Remaining Payment (QAR) Payment % Complete Earned Value Cost Contract 06-Nov-14 19-Nov-14 QR1,234,224 QR0 QR1,234,224 0% QR0 PWA Approval (100%) 06-Nov-14 19-Nov-14 QR1,234,224 QR0 QR1,234,224 0% QR0 QS0045483 Prepare Contract Documents for Work Order 06-Nov-14 12-Nov-14 QR740,535 QR0 QR740,535 0% QR0 QS0045484 Contract Signed Off by Contractor 13-Nov-14 18-Nov-14 QR185,134 QR0 QR185,134 0% QR0 QS0045485 Contract Signed Off by PWA 13-Nov-14 18-Nov-14 QR185,134 QR0 QR185,134 0% QR0 QS0045486 Exchange of Contract 19-Nov-14 19-Nov-14 QR123,422 QR0 QR123,422 0% QR0 2013 2014 2015 D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D J F Prepare C Contract Contract Exchang QR20,000,000QR QR16,000,000QR QR12,000,000QR QR8,000,000QR D J F M A M J Jul A S Oct N D J F M Apr M J Jul A S Oct N D J F 2013 2014 2015 QR3,000,000QR QR2,400,000QR QR1,800,000QR QR1,200,000QR QR600,000QR QR0QR QR4,000,000QR Actual Expense Cost Planned Value Cost Earned Value Cost BL Project Expense Cost Public Works Authority Local Roads and Drainage Programme Earned Value as of 31-Oct-13 Remaining Level of Effort Actual Level of Effort Baseline Project Start:- 11-Apr-13 Project Finish:- 02-Aug-18 Layout:- A4 - QS004 - Monthly EVM Report Data Date : 31-Oct-13 Page : 3 of 3 Printed On : 07-Nov-13 Date Revision Checked Approved 30-Sep-13 Payment Schedule Update MN 31-Oct-13 Payment Schedule Update MN
  • 13. Contract 2 Local Roads and Drainage Programme QS015-RoadsInfrastructure in Rawdat Rashed Village QATAR ACCOUNT MANAGEMENT PROGRAM
  • 14. 2 Schedule Dashboard Projects Milestones Actual / Forecast Total Variance QS015 - Roads and Infrastructure in Rawdat QQQSSS000111555 --- RRRoooaaadddsss aaannnddd IIInnnfffrrraaassstttrrruuuccctttuuurrreee iiinnn RRRaaawwwdddaaattt RRRRaaaasssshhhheeeedddd VVVViiiillllllllaaaaggggeeee Plan. Act. Initiation G1 19-Dec-12 19-Dec-12 0 100% 100% 0 Concept Design G2 17-Apr-13 03-Jul-13 -77 100% 100% -77 Preliminary Design 30-Jul-13 26-Aug-13 -27 100% 100% -27 Detailed DesignTender Documents G3 18-Dec-13 17-Dec-13 1 57.7% 17.0% 1 Tendering 03-Mar-14 03-Mar-14 0 0% 0% 0 Construction G5 18-Nov-15 18-Nov-15 0 0% 0% 0 Maintenance Period G6 16-Nov-16 04-Jan-17 -49 0% 0% -49 Monthly Progress Report No. 13 ­Oct 2013 Milestones Gateway Planned % Progress Trend Initiation Concept Design Preliminary Design Detailed DesignTender Documents Tendering Construction Maintenance Period Planned Actual/Forecast G1 G2 G3 G5 G6 Behind Schedule No Change Upward Trend Downward Trend On Schedule Detailed Design Tender Docs. Current Segment 16.9 0.29 Progress % Complete 47 Days Until Completion (Starting from 1st Nov) SPI File :- Schedule Management - Oct 13 Printed On :- 11/11/2013 at 16:06
  • 15. Activity ID Activity Name Planned Duration Current Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan Project Wide - High Level Schedule 1017 1049 04-Nov-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% Programme Wide -High Level Schedule 1017 1049 04-Nov-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% Programme Wide High Level Schedule 1017 1049 04-Nov-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% Initiation 33 33 04-Nov-12 19-Dec-12 04-Nov-12 A 19-Dec-12 A 0% Initiation 20 20 04-Nov-12 29-Nov-12 04-Nov-12 A 03-Dec-12 A 0% QS015 020000 PWA Formal Notification of Candidate Project 0 0 04-Nov-12 04-Nov-12 A 0% QS015 020330 Initiation 20 20 04-Nov-12 29-Nov-12 04-Nov-12 A 03-Dec-12 A 100% QS015 020340 Initiation Slides Submission 0 0 29-Nov-12 03-Dec-12 A 0% 18 Day Review 19 19 01-Dec-12 19-Dec-12 04-Dec-12 A 19-Dec-12 A 0% QS015 212101 PMC/PWA Initiation Review 18 18 01-Dec-12 18-Dec-12 04-Dec-12 A 18-Dec-12 A 100% QS015 020061 Gateway 1 Review Meeting 0 0 19-Dec-12 19-Dec-12 A 0% Concept Design 82 82 20-Dec-12 17-Apr-13 20-Dec-12 A 03-Jul-13 A 0% Concept Design 56 56 20-Dec-12 12-Mar-13 20-Dec-12 A 02-May-13 A 0% QS015 212411 Concept Design Submission 0 0 12-Mar-13 12-Mar-13 A 0% QS015 020070 Concept Design 56 56 20-Dec-12 12-Mar-13 20-Dec-12 A 02-May-13 A 100% 35 Day Review 36 36 13-Mar-13 17-Apr-13 07-Apr-13 A 03-Jul-13 A 0% QS015 212421 PMC Concept Design Review 10 10 13-Mar-13 22-Mar-13 07-Apr-13 A 05-May-13 A 100% QS015 212431 GEC Response to PMC Comments 7 7 23-Mar-13 29-Mar-13 07-Apr-13 A 05-May-13 A 100% QS015 212441 PMC Review of GEC Response 4 4 30-Mar-13 02-Apr-13 04-May-13 A 08-May-13 A 100% QS015 212451 PWA Review 14 14 03-Apr-13 16-Apr-13 08-May-13 A 15-May-13 A 100% QS015 212461 Gateway 2 Review Meeting 0 0 17-Apr-13 03-Jul-13 A 0% Preliminary Design 96 142 18-Apr-13 03-Sep-13 04-Jul-13 A 11-Nov-13 0 0% Preliminary Design 74 74 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 0% QS015 020130 Preliminary Design 74 35 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 100% Prelim design duration reduced to 35 QS015 212471 Preliminary Design Submission 0 0 30-Jul-13 26-Aug-13 A 100% 35 Day Review 35 104 31-Jul-13 03-Sep-13 27-Aug-13 A 11-Nov-13 0 0% QS015 212481 PMC Preliminary Design Review 10 10 31-Jul-13 09-Aug-13 27-Aug-13 A 07-Sep-13 A 100% QS015 212491 GEC Response to PMC Comments 7 7 10-Aug-13 16-Aug-13 08-Sep-13 A 01-Nov-13 0 80% QS015 212501 PMC Review of GEC Response 4 4 17-Aug-13 20-Aug-13 02-Nov-13 05-Nov-13 0 0% QS015 212511 PWA Review 14 6 21-Aug-13 03-Sep-13 06-Nov-13 11-Nov-13 0 0% Detailed Design Tender Documents 94 94 31-Jul-13 18-Dec-13 27-Aug-13 A 18-Dec-13 0 0% Detailed Design Tender Documents 68 68 31-Jul-13 12-Nov-13 27-Aug-13 A 12-Nov-13 0 0% QS015 020140 Detailed Design 60 44 31-Jul-13 30-Oct-13 27-Aug-13 A 11-Nov-13 0 35.86% Detailed design duration reduced to 44 QS015 020150 Tender Documents 28 28 30-Sep-13 11-Nov-13 30-Sep-13 A 11-Nov-13 0 4.78% QS015 212521 Detailed DesignTender Documents Submission 0 0 12-Nov-13 12-Nov-13 0 0% 35 Day Review 36 36 13-Nov-13 18-Dec-13 13-Nov-13 18-Dec-13 0 0% QS015 212531 PMC Detailed DesignTender Documents Review 10 10 13-Nov-13 22-Nov-13 13-Nov-13 22-Nov-13 0 0% QS015 212541 GEC Response to PMC Comments 7 7 23-Nov-13 29-Nov-13 23-Nov-13 29-Nov-13 0 0% QS015 212551 PMC Review of GEC Response 4 4 30-Nov-13 03-Dec-13 30-Nov-13 03-Dec-13 0 0% QS015 212561 PWA Review 14 14 04-Dec-13 17-Dec-13 04-Dec-13 17-Dec-13 0 0% QS015 020180 Gateway 3 Review Meeting 0 0 18-Dec-13 18-Dec-13 0 0% Tendering 61 61 19-Dec-13 18-Mar-14 19-Dec-13 18-Mar-14 13 0% 2013 2014 2015 2016 2017 2018 2019 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 PWA Formal Notification of Candidate Project Initiation Initiation Slides Submission PMC/PWA Initiation Review Gateway 1 Review Meeting Concept Design Submission Concept Design PMC Concept Design Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 2 Review Meeting Preliminary Design Preliminary Design Submission PMC Preliminary Design Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Detailed Design Tender Documents Detailed DesignTender Documents Submission PMC Detailed DesignTender Documents Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 3 Review Meeting Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 1 of 4 Printed On : 07-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS015 - Roads and Infrastrucutre in Rawdat Rashed Village Update as of 31-Oct-2013 Date Revision Ch... Appro... 31-Aug-13 Schedule Update - Aug-13 MN 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 MN
  • 16. Activity ID Activity Name Planned Duration Current Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan Tender and Awarding 61 61 19-Dec-13 18-Mar-14 19-Dec-13 18-Mar-14 13 0% QS015 020210 Tendering of the Project 30 30 19-Dec-13 02-Feb-14 19-Dec-13 02-Feb-14 0 0% QS015 020240 Tender AssessmentRecommendations 10 10 03-Feb-14 17-Feb-14 03-Feb-14 17-Feb-14 0 0% QS015 020220 Award of the Construction Contract (Work Order) 0 0 03-Mar-14 03-Mar-14 0 0% QS015 020250 PMC/PWA Approval 10 10 18-Feb-14 03-Mar-14 18-Feb-14 03-Mar-14 0 0% QS015 020350 Prepare and Issue Notice to Proceed 1 1 04-Mar-14 04-Mar-14 04-Mar-14 04-Mar-14 0 0% QS015 020270 Prepare Contract Documents for Work Order 5 5 05-Mar-14 11-Mar-14 05-Mar-14 11-Mar-14 0 0% QS015 020280 Contract Signed Off by ContractorPWA 4 4 12-Mar-14 17-Mar-14 12-Mar-14 17-Mar-14 0 0% QS015 020310 Exchange of Contract 1 1 18-Mar-14 18-Mar-14 18-Mar-14 18-Mar-14 13 0% Construction 430 430 05-Mar-14 18-Nov-15 05-Mar-14 18-Nov-15 0 0% Construction Period 404 404 05-Mar-14 13-Oct-15 05-Mar-14 13-Oct-15 0 0% QS015 020300 Contractor Mobilization Period 23 23 05-Mar-14 06-Apr-14 05-Mar-14 06-Apr-14 0 0% QS015 020230 Construction of the Project 381 381 07-Apr-14 13-Oct-15 07-Apr-14 13-Oct-15 0 0% QS015 212611 Construction Documents Submission 0 0 13-Oct-15 13-Oct-15 0 0% 35 Day Review 36 36 14-Oct-15 18-Nov-15 14-Oct-15 18-Nov-15 0 0% QS015 212571 PMC Construction Documents Review 10 10 14-Oct-15 23-Oct-15 14-Oct-15 23-Oct-15 0 0% QS015 212581 GEC Response to PMC Comments 7 7 24-Oct-15 30-Oct-15 24-Oct-15 30-Oct-15 0 0% QS015 212591 PMC Review of GEC Response 4 4 31-Oct-15 03-Nov-15 31-Oct-15 03-Nov-15 0 0% QS015 212601 PWA Review 14 14 04-Nov-15 17-Nov-15 04-Nov-15 17-Nov-15 0 0% QS015 020260 Gateway 5 Review Meeting 0 0 18-Nov-15 18-Nov-15 0 0% Maintenance Period 364 413 19-Nov-15 16-Nov-16 19-Nov-15 04-Jan-17 0 0% Maintenance Period 328 365 19-Nov-15 11-Oct-16 19-Nov-15 17-Nov-16 0 0% QS015 020290 Maintenance Period 227 365 19-Nov-15 11-Oct-16 19-Nov-15 17-Nov-16 0 0% QS015 212621 Maintenance Documents Submission 0 0 11-Oct-16 17-Nov-16 0 0% 35 Day Review 36 48 12-Oct-16 16-Nov-16 18-Nov-16 04-Jan-17 0 0% QS015 212631 PMC Maintenance Documents Review 10 10 12-Oct-16 21-Oct-16 18-Nov-16 27-Nov-16 0 0% QS015 212641 GEC Response to PMC Comments 7 7 22-Oct-16 28-Oct-16 28-Nov-16 04-Dec-16 0 0% QS015 212651 PMC Review of GEC Response 4 4 29-Oct-16 01-Nov-16 05-Dec-16 08-Dec-16 0 0% QS015 212661 PWA Review 14 14 02-Nov-16 15-Nov-16 09-Dec-16 22-Dec-16 0 0% QS015 020320 Gateway 6 Review Meeting 0 0 16-Nov-16 04-Jan-17 0 0% QS015 020360 Project Completion 0 0 16-Nov-16 04-Jan-17 0 0% MMUP MOE 282 281 21-Jan-13 05-Mar-14 29-Jan-13 A 04-Mar-14 23 0% Ministry of Municipality and Urban Planning 11 11 21-Jan-13 04-Feb-13 27-Mar-13 A 15-Apr-13 A 0% Ministry of Municipality and Urban Planning 11 11 21-Jan-13 04-Feb-13 27-Mar-13 A 15-Apr-13 A 0% QS015 020080 Submission of TTN to PMC 0 0 21-Jan-13 27-Mar-13 A 0% QS015 020120 Review TTN by PMC 14 14 21-Jan-13 03-Feb-13 28-Mar-13 A 14-Apr-13 A 100% QS015 020090 Approval of TTN by PMC 0 0 04-Feb-13 15-Apr-13 A 0% Ministry of Environment 276 275 29-Jan-13 05-Mar-14 29-Jan-13 A 04-Mar-14 23 0% Ministry of Environment 276 275 29-Jan-13 05-Mar-14 29-Jan-13 A 04-Mar-14 23 0% QS015 440060 Preparation of Environmental Permit Application 30 30 29-Jan-13 12-Mar-13 29-Jan-13 A 06-Mar-13 A 100% QS015 440080 Permit Application Submission 0 0 13-Mar-13 07-Mar-13 A 0% QS015 440000 PMC/MOE Review 30 30 14-Mar-13 12-Apr-13 08-Mar-13 A 04-Aug-13 A 100% QS015 440010 Environmental Scoping 39 10 14-Apr-13 05-Jun-13 30-Jul-13 A 06-Aug-13 A 100% QS015 440090 Environmental Scoping Submission 0 0 06-Jun-13 06-Aug-13 A 0% 2013 2014 2015 2016 2017 2018 2019 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Tendering of the Project Tender AssessmentRecommendations Award of the Construction Contract (Work Order) PMC/PWA Approval Prepare and Issue Notice to Proceed Prepare Contract Documents for Work Order Contract Signed Off by ContractorPWA Exchange of Contract Contractor Mobilization Period Construction of the Project Construction Documents Submission PMC Construction Documents Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 5 Review Meeting Maintenance Period Maintenance Documents Submission PMC Maintenance Documents Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 6 Review Meeting Project Completion Submission of TTN to PMC Review TTN by PMC Approval of TTN by PMC Preparation of Environmental Permit Application Permit Application Submission PMC/MOE Review Environmental Scoping Environmental Scoping Submission Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 2 of 4 Printed On : 07-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS015 - Roads and Infrastrucutre in Rawdat Rashed Village Update as of 31-Oct-2013 Date Revision Ch... Appro... 31-Aug-13 Schedule Update - Aug-13 MN 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 MN
  • 17. Activity ID Activity Name Planned Duration Current Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan QS015 440020 PMC/MOE Review 30 30 07-Jun-13 06-Jul-13 07-Aug-13 A 01-Oct-13 A 100% QS015 440030 Environmental Impact Assessment (EIA) 66 15 07-Jul-13 09-Oct-13 02-Oct-13 A 03-Nov-13 2 90% QS015 440100 EIA Submission 0 0 10-Oct-13 05-Nov-13 2 0% QS015 440040 PMC/MOE Review 30 2 11-Oct-13 09-Nov-13 06-Nov-13 07-Nov-13 3 0% QS015 440050 Environmental Permit Issued 0 0 10-Nov-13 10-Nov-13 2 0% QS015 440070 Review Contractor CEMP 5 2 05-Feb-14 12-Feb-14 04-Feb-14 05-Feb-14 41 0% QS015 440110 CEMP Submission to MOE 0 0 05-Mar-14 04-Mar-14 23 0% Stakeholders Engagement 984 1016 20-Dec-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% Concept Design 82 82 20-Dec-12 17-Apr-13 20-Dec-12 A 03-Jul-13 A 0% Concept Design 82 82 20-Dec-12 17-Apr-13 20-Dec-12 A 03-Jul-13 A 0% QS015 021020 Liaison with Stakeholders - Concept Design 82 82 20-Dec-12 17-Apr-13 20-Dec-12 A 03-Jul-13 A 100% Preliminary Design 74 26 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 0% Preliminary Design 74 26 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 0% QS015 212671 Liaison with Stakeholders - Preliminary Design 74 26 18-Apr-13 30-Jul-13 04-Jul-13 A 26-Aug-13 A 100% Detailed Design Tendering 145 129 31-Jul-13 04-Mar-14 27-Aug-13 A 04-Mar-14 0 0% Detailed Design Tendering 145 129 31-Jul-13 04-Mar-14 27-Aug-13 A 04-Mar-14 0 0% QS015 212681 Liaison with Stakeholders - Detailed Design Tendering 145 129 31-Jul-13 04-Mar-14 27-Aug-13 A 04-Mar-14 0 42.07% Construction 430 430 05-Mar-14 18-Nov-15 05-Mar-14 18-Nov-15 0 0% Construction 430 430 05-Mar-14 18-Nov-15 05-Mar-14 18-Nov-15 0 0% QS015 212701 Liaison with Stakeholders - Construction 430 430 05-Mar-14 18-Nov-15 05-Mar-14 18-Nov-15 0 0% Maintenance Period 984 1016 20-Dec-12 16-Nov-16 04-Nov-12 A 04-Jan-17 0 0% Maintenance Period 253 253 19-Nov-15 16-Nov-16 04-Jan-16 04-Jan-17 0 0% QS015 212711 Liaison with Stakeholders - Maintenance Period 253 253 19-Nov-15 16-Nov-16 04-Jan-16 04-Jan-17 0 0% MMUP Utility Investigation 90 242 20-Dec-12 29-Apr-13 04-Nov-12 A 05-Dec-13 8 0% QS015 440240 Superimpose Data on Proposed Road Layout 10 10 11-Feb-13 25-Feb-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440260 Agencies Approval 15 15 26-Feb-13 18-Mar-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440210 Utility Investigation by Owner/Consultant/Client 10 10 20-Dec-12 06-Jan-13 20-Dec-12 A 06-Jan-13 A 100% QS015 440220 Collect Data (Existing Proposed Utilties) 10 10 07-Jan-13 20-Jan-13 07-Jan-13 A 20-Jan-13 A 100% QS015 440290 MMUP Approval 15 10 19-Mar-13 08-Apr-13 03-Nov-13 14-Nov-13 23 0% QS015 440230 Topo Survey,Trial Pits and Radio Detection 15 15 21-Jan-13 10-Feb-13 03-Nov-13 21-Nov-13 8 0% QS015 440300 Final Report to MMUP 15 10 09-Apr-13 29-Apr-13 24-Nov-13 05-Dec-13 8 0% KAHRAMA 75 75 20-Dec-12 08-Apr-13 20-Dec-12 A 05-Nov-13 5 0% QS015 440310 Send an Introductory Letters to KAHRAMA 10 10 20-Dec-12 06-Jan-13 20-Dec-12 A 06-Jan-13 A 100% QS015 440320 Request for Information about KAHRAMA's Current/Futu 10 10 07-Jan-13 20-Jan-13 07-Jan-13 A 20-Jan-13 A 100% QS015 440330 Receive Information about KAHRAMA's Current/Future P 15 15 21-Jan-13 10-Feb-13 21-Jan-13 A 10-Feb-13 A 100% QS015 440340 Superimpose the Plans on Proposed Project to Identify C 10 10 11-Feb-13 25-Feb-13 11-Feb-13 A 03-Nov-13 5 75% QS015 440370 Drawings Submission to KAHRAMA for Approval 10 10 26-Mar-13 08-Apr-13 26-Mar-13 A 04-Nov-13 5 25% QS015 440350 Report the Conflicts to KAHRAMA 10 10 26-Feb-13 11-Mar-13 26-Feb-13 A 05-Nov-13 5 75% QS015 440360 Amend the Drawings 10 10 12-Mar-13 25-Mar-13 12-Mar-13 A 05-Nov-13 5 75% Communication (Oredoo/Vodafone) 75 75 20-Dec-12 08-Apr-13 20-Dec-12 A 07-Nov-13 2 0% QS015 440380 Send an Introductory Letters to Oredoo/Vodafone 10 10 20-Dec-12 06-Jan-13 20-Dec-12 A 06-Jan-13 A 100% QS015 440390 Request for Information about Oredo/Vodafone's Curren 10 10 07-Jan-13 20-Jan-13 07-Jan-13 A 20-Jan-13 A 100% QS015 440400 Receive Information about Oredo/Vodafone's Current/Fu 15 15 21-Jan-13 10-Feb-13 21-Jan-13 A 10-Feb-13 A 100% QS015 440410 Superimpose the Plans on Proposed Project to Identify C 10 10 11-Feb-13 25-Feb-13 11-Feb-13 A 25-Feb-13 A 100% 2013 2014 2015 2016 2017 2018 2019 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 PMC/MOE Review Environmental Impact Assessment (EIA) EIA Submission PMC/MOE Review Environmental Permit Issued Review Contractor CEMP CEMP Submission to MOE Liaison with Stakeholders - Concept Design Liaison with Stakeholders - Preliminary Design Liaison with Stakeholders - Detailed Design Tendering Liaison with Stakeholders - Construction Liaison with Stakeholders - Maintena Superimpose Data on Proposed Road Layout Agencies Approval Utility Investigation by Owner/Consultant/Client Collect Data (Existing Proposed Utilties) MMUP Approval Topo Survey,Trial Pits and Radio Detection Final Report to MMUP Send an Introductory Letters to KAHRAMA Request for Information about KAHRAMA's Current/Future Projects Receive Information about KAHRAMA's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Drawings Submission to KAHRAMA for Approval Report the Conflicts to KAHRAMA Amend the Drawings Send an Introductory Letters to Oredoo/Vodafone Request for Information about Oredo/Vodafone's Current/Future Projects Receive Information about Oredo/Vodafone's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 3 of 4 Printed On : 07-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS015 - Roads and Infrastrucutre in Rawdat Rashed Village Update as of 31-Oct-2013 Date Revision Ch... Appro... 31-Aug-13 Schedule Update - Aug-13 MN 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 MN
  • 18. Activity ID Activity Name Planned Duration Current Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan QS015 440420 Report the Conflicts to Oredoo/Vodafone 10 10 26-Feb-13 11-Mar-13 26-Feb-13 A 11-Mar-13 A 100% QS015 440430 Amend the Drawings 10 10 12-Mar-13 25-Mar-13 12-Mar-13 A 25-Mar-13 A 100% QS015 440440 Drawings Submission to Oredoo/Vodafone for Approval 10 10 26-Mar-13 08-Apr-13 26-Mar-13 A 07-Nov-13 2 10% Natural Reserves (NR) 75 75 20-Dec-12 08-Apr-13 04-Nov-12 A 04-Nov-12 A 0% QS015 440450 Send an Introductory Letters to NR 10 10 20-Dec-12 06-Jan-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440460 Request for Information about NR's Current/Future Proje 10 10 07-Jan-13 20-Jan-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440470 Receive Information about NR's Current/Future Projects 15 15 21-Jan-13 10-Feb-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440480 Superimpose the Plans on Proposed Project to Identify C 10 10 11-Feb-13 25-Feb-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440490 Report the Conflicts to NR 10 10 26-Feb-13 11-Mar-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440500 Amend the Drawings 10 10 12-Mar-13 25-Mar-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440510 Drawings Submission to NR for Approval 10 10 26-Mar-13 08-Apr-13 04-Nov-12 A 04-Nov-12 A 100% Escaped Private Engineer Office (PEO) 75 224 20-Dec-12 08-Apr-13 04-Nov-12 A 11-Nov-13 0 0% QS015 440570 Amend the Drawings 10 10 12-Mar-13 25-Mar-13 04-Nov-12 A 04-Nov-12 A 100% Escaped QS015 440520 Send an Introductory Letters to PEO 10 10 20-Dec-12 06-Jan-13 20-Dec-12 A 07-Jan-13 A 100% QS015 440530 Request for Information about PEO's Current/Future Pro 10 10 07-Jan-13 20-Jan-13 07-Jan-13 A 20-Jan-13 A 100% QS015 440540 Receive Information about PEO's Current/Future Projects 15 15 21-Jan-13 10-Feb-13 21-Jan-13 A 10-Feb-13 A 100% QS015 440550 Superimpose the Plans on Proposed Project to Identify C 10 10 11-Feb-13 25-Feb-13 11-Feb-13 A 25-Feb-13 A 100% QS015 440560 Report the Conflicts to PEO 10 10 26-Feb-13 11-Mar-13 01-Oct-13 A 03-Nov-13 0 50% QS015 440580 Drawings Submission to PEO for Approval 10 7 26-Mar-13 08-Apr-13 03-Nov-13 11-Nov-13 0 0% 2013 2014 2015 2016 2017 2018 2019 3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Report the Conflicts to Oredoo/Vodafone Amend the Drawings Drawings Submission to Oredoo/Vodafone for Approval Send an Introductory Letters to NR Request for Information about NR's Current/Future Projects Receive Information about NR's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Report the Conflicts to NR Amend the Drawings Drawings Submission to NR for Approval Amend the Drawings Send an Introductory Letters to PEO Request for Information about PEO's Current/Future Projects Receive Information about PEO's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Report the Conflicts to PEO Drawings Submission to PEO for Approval Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 4 of 4 Printed On : 07-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS015 - Roads and Infrastrucutre in Rawdat Rashed Village Update as of 31-Oct-2013 Date Revision Ch... Appro... 31-Aug-13 Schedule Update - Aug-13 MN 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 MN
  • 19. Activity ID Activity Name Planned Start Planned Finish Budgeted Payment (QAR) Actual Payment (QAR) Remaining Payment (QAR) Payment % Complete Progress % Complete Earned Value Cost Total 20-Dec-12 18-Mar-14 QR5,622,663 QR2,198,449 QR3,424,215 39.1% 39.1% QR2,198,451 Concept Design 20-Dec-12 16-Apr-13 QR1,385,832 QR1,302,682 QR83,151 94% 94% QR1,302,682 Submission of Concept Design (60%) 20-Dec-12 27-Mar-13 QR831,499 QR831,500 QR0 100% 100% QR831,499 QS0151088 Project Schedule 04-Mar-13 27-Mar-13 QR124,725 QR124,725 QR0 100% 100% QR124,725 QS0151098 Main Report (Volume 1) 02-Jan-13 27-Feb-13 QR124,725 QR124,725 QR0 100% 100% QR124,725 QS0151108 Geotechnical Report (Volume 2) 22-Jan-13 24-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 QS0151118 Traffic Analysis Report (Volume 3) 20-Dec-12 24-Feb-13 QR83,150 QR83,150 QR0 100% 100% QR83,150 QS0151128 Drainage Part A (SW GW) (Volume 4A) 20-Jan-13 10-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 QS0151138 Drainage Part B (FS) (Volume 4B) 20-Jan-13 10-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 QS0151148 Drainage Part C (TSE) (Volume 4C) 03-Feb-13 27-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 QS0151158 Environmental and Sustainablity (Volume 5) 29-Jan-13 12-Mar-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 QS0151168 Drawings (Volume 6) 26-Dec-12 11-Mar-13 QR124,725 QR124,725 QR0 100% 100% QR124,725 QS0151178 Stakeholders (Volume 7) 08-Jan-13 23-Jan-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 QS0151188 Commercial Report (Volume 8) 28-Feb-13 06-Mar-13 QR83,150 QR83,150 QR0 100% 100% QR83,150 QS0151198 RSA - Review (Volume 9A) 02-Jan-13 27-Feb-13 QR41,575 QR41,575 QR0 100% 100% QR41,575 PMC Acceptance with Comments (20%) 13-Mar-13 21-Mar-13 QR277,166 QR277,166 QR0 100% 100% QR277,166 QS0151199 PMC Accpetance with Comments 13-Mar-13 21-Mar-13 QR277,166 QR277,166 QR0 100% 100% QR277,166 PMC Acceptance (10%) 31-Mar-13 02-Apr-13 QR138,583 QR97,008 QR41,575 70% 70% QR97,008 QS0151200 PMC Accpetance 31-Mar-13 02-Apr-13 QR138,583 QR97,008 QR41,575 70% 70% QR97,008 PWA Approval (10%) 03-Apr-13 16-Apr-13 QR138,583 QR97,008 QR41,575 70% 70% QR97,008 QS0151201 PWA Approval 03-Apr-13 16-Apr-13 QR138,583 QR97,008 QR41,575 70% 70% QR97,008 Preliminiary Design 04-Mar-13 03-Sep-13 QR847,366 QR531,093 QR316,274 62.68% 62.68% QR531,095 Submission of Preliminary Design (60%) 04-Mar-13 17-Jul-13 QR508,420 QR505,672 QR2,748 99.46% 99.46% QR505,674 QS0151000 Updated Project Schedule 04-Mar-13 27-Mar-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 QS0151001 Volume 1 - Main Report 30-May-13 16-Jul-13 QR50,842 QR50,842 QR0 100% 100% QR50,842 QS0151002 Volume 2 - Geotechnical Investigation Report 30-Apr-13 08-May-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 QS0151003 Volume 3 - Traffic Analysis Report 30-May-13 16-Jul-13 QR63,552 QR63,552 QR0 100% 100% QR63,552 QS0151004 Volume 4A - Surface and Ground Water Report 05-Jun-13 15-Jul-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 QS0151005 Volume 4B - Foul Water Report 12-Jun-13 17-Jul-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 QS0151006 Volume 4C - Treated Sewage Effluent Report 27-May-13 16-Jul-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 QS0151007 Volume 5 - Environmental and Sustainability 16-May-13 16-Jul-13 QR63,552 QR63,552 QR0 100% 100% QR63,552 QS0151008 Volume 6 - Drawings 18-Apr-13 16-Jul-13 QR88,973 QR88,973 QR0 100% 100% QR88,973 QS0151009 Volume 7 - Stakeholders Report 21-May-13 16-Jul-13 QR25,421 QR25,421 QR0 100% 100% QR25,421 QS0151019 Volume 8 - Commercial Report 24-Jun-13 10-Jul-13 QR50,842 QR48,097 QR2,745 94.6% 94.6% QR48,097 QS0151029 Volume 9B - Road Safety Audit - Brief 23-Jun-13 16-Jul-13 QR12,710 QR12,710 QR0 100% 100% QR12,710 QS0151039 Volume 9C - Road Safety Audit - Report 23-Jun-13 16-Jul-13 QR12,710 QR12,710 QR0 100% 100% QR12,710 QS0151049 Volume 9D - Road Safety Audit - Designer's Res 23-Jun-13 16-Jul-13 QR12,710 QR12,710 QR0 100% 100% QR12,710 PMC Acceptance with Comments (20%) 31-Jul-13 07-Aug-13 QR169,473 QR16,947 QR152,526 10% 10% QR16,947 QS0151059 PMC Accpetance with Comments 31-Jul-13 07-Aug-13 QR169,473 QR16,947 QR152,526 10% 10% QR16,947 PMC Acceptance (10%) 18-Aug-13 20-Aug-13 QR84,737 QR4,237 QR80,500 5% 5% QR4,237 QS0151069 PMC Accpetance 18-Aug-13 20-Aug-13 QR84,737 QR4,237 QR80,500 5% 5% QR4,237 PWA Approval (10%) 21-Aug-13 03-Sep-13 QR84,737 QR4,237 QR80,500 5% 5% QR4,237 QS0151079 PWA Approval 21-Aug-13 03-Sep-13 QR84,737 QR4,237 QR80,500 5% 5% QR4,237 2013 2014 S O N D J F M A M J Jul A S O N D J F M A M J Jul A S Project Schedule Main Report (Volume 1) Geotechnical Report (Volume 2) Traffic Analysis Report (Volume 3) Drainage Part A (SW GW) (Volume 4A) Drainage Part B (FS) (Volume 4B) Drainage Part C (TSE) (Volume 4C) Environmental and Sustainablity (Volume 5) Drawings (Volume 6) Stakeholders (Volume 7) Commercial Report (Volume 8) RSA - Review (Volume 9A) PMC Accpetance with Comments PMC Accpetance PWA Approval Updated Project Schedule Volume 1 - Main Report Volume 2 - Geotechnical Investigation Volume 3 - Traffic Analysis Report Volume 4A - Surface and Ground W Volume 4B - Foul Water Report Volume 4C - Treated Sewage Effluen Volume 5 - Environmental and Sustain Volume 6 - Drawings Volume 7 - Stakeholders Report Volume 8 - Commercial Repo Volume 9B - Road Safety Audit - Brief Volume 9C - Road Safety Audit - Repo Volume 9D - Road Safety Audit - Desi PMC Accpetance with Comments PMC Accpetance PWA Approval Public Works Authority Local Roads and Drainage Programme Earned Value as of 31-Oct-13 Remaining Level of Effort Actual Level of Effort Baseline Project Start:- 04-Nov-12 Project Finish:- 04-Jan-17 Layout:- A4 - QS015 - Monthly EVM Report Data Date : 31-Oct-13 Page : 1 of 3 Printed On : 07-Nov-13 Date Revision Checked Approved 30-Sep-13 Payment Schedule Update MN 31-Oct-13 Payment Schedule Update MN
  • 20. Activity ID Activity Name Planned Start Planned Finish Budgeted Payment (QAR) Actual Payment (QAR) Remaining Payment (QAR) Payment % Complete Progress % Complete Earned Value Cost Detailed Design 31-Jul-13 17-Dec-13 QR1,694,732 QR364,674 QR1,330,058 21.52% 21.52% QR364,674 Submission of Detailed Design (60%) 31-Jul-13 03-Nov-13 QR1,016,839 QR364,674 QR652,165 35.86% 35.86% QR364,674 QS0151167 Updated Project Schedule 18-Sep-13 20-Oct-13 QR50,842 QR50,842 QR0 100% 100% QR50,842 QS0151168 Volume 1 - Main Report 18-Sep-13 21-Oct-13 QR152,526 QR83,371 QR69,155 54.66% 54.66% QR83,371 QS0151169 Volume 2 - Geotechnical Factual Report 27-Aug-13 23-Sep-13 QR50,842 QR5,084 QR45,758 10% 10% QR5,084 QS0151170 Volume 2 - Geotechnical Interpretative Report 29-Sep-13 29-Oct-13 QR50,842 QR5,084 QR45,758 10% 10% QR5,084 QS0151172 Volume 4A - Surface and Ground Water Report 27-Aug-13 24-Oct-13 QR50,842 QR27,343 QR23,499 53.78% 53.78% QR27,343 QS0151173 Volume 4B - Foul Water Report 27-Aug-13 28-Oct-13 QR50,842 QR27,353 QR23,489 53.8% 53.8% QR27,353 QS0151174 Volume 4C - Treated Sewage Effluent Report 27-Aug-13 21-Oct-13 QR50,842 QR27,658 QR23,184 54.4% 54.4% QR27,658 QS0151175 Volume 5 - Environmental and Sustainability 09-Sep-13 22-Oct-13 QR101,684 QR7,077 QR94,607 6.96% 6.96% QR7,077 QS0151176 Volume 6 - Drawings 31-Jul-13 23-Oct-13 QR203,368 QR109,534 QR93,834 53.86% 53.86% QR109,534 QS0151177 Volume 7 - Stakeholders Report 12-Sep-13 20-Oct-13 QR50,842 QR11,160 QR39,682 21.95% 21.95% QR11,160 QS0151178 Volume 8 - Commercial Report 22-Oct-13 03-Nov-13 QR101,684 QR0 QR101,684 0% 0% QR0 QS0151180 Volume 9C - Road Safety Audit - Report 25-Sep-13 30-Oct-13 QR50,842 QR5,084 QR45,758 10% 10% QR5,084 QS0151181 Volume 9D - Road Safety Audit - Designer's Res 25-Sep-13 27-Oct-13 QR50,842 QR5,084 QR45,758 10% 10% QR5,084 PMC Acceptance with Comments (20%) 12-Nov-13 21-Nov-13 QR338,946 QR0 QR338,946 0% 0% QR0 QS0151219 PMC Accpetance with Comments 12-Nov-13 21-Nov-13 QR338,946 QR0 QR338,946 0% 0% QR0 PMC Acceptance (10%) 01-Dec-13 03-Dec-13 QR169,473 QR0 QR169,473 0% 0% QR0 QS0151229 PMC Accpetance 01-Dec-13 03-Dec-13 QR169,473 QR0 QR169,473 0% 0% QR0 PWA Approval (10%) 04-Dec-13 17-Dec-13 QR169,473 QR0 QR169,473 0% 0% QR0 QS0151239 PWA Approval 04-Dec-13 17-Dec-13 QR169,473 QR0 QR169,473 0% 0% QR0 Tender Documents 31-Jul-13 17-Dec-13 QR635,525 QR0 QR635,525 0% 0% QR0 Submission of Tender Documents (60%) 31-Jul-13 27-Nov-13 QR381,315 QR0 QR381,315 0% 0% QR0 QS0155470 Specification Drawings 31-Jul-13 03-Nov-13 QR133,460 QR0 QR133,460 0% 0% QR0 QS0155471 Conditions of Contract 30-Sep-13 30-Oct-13 QR38,131 QR0 QR38,131 0% 0% QR0 QS0155472 Particular Conditions of Contract Nominate S/C 30-Sep-13 30-Oct-13 QR19,066 QR0 QR19,066 0% 0% QR0 QS0155473 Preliminary Bill of Quantity 07-Oct-13 03-Nov-13 QR19,066 QR0 QR19,066 0% 0% QR0 QS0155474 Final Bill of Quantities 24-Nov-13 27-Nov-13 QR38,131 QR0 QR38,131 0% 0% QR0 QS0155475 Pre-Tender Estimate 10-Oct-13 03-Nov-13 QR76,263 QR0 QR76,263 0% 0% QR0 QS0155476 Project Programme 30-Sep-13 28-Oct-13 QR57,197 QR0 QR57,197 0% 0% QR0 PMC Acceptance with Comments (20%) 12-Nov-13 21-Nov-13 QR127,105 QR0 QR127,105 0% 0% QR0 QS0155477 PMC Accpetance with Comments 12-Nov-13 21-Nov-13 QR127,105 QR0 QR127,105 0% 0% QR0 PMC Acceptance (10%) 01-Dec-13 03-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 QS0155499 PMC Accpetance 01-Dec-13 03-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 PWA Approval (10%) 04-Dec-13 17-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 QS0155100 PWA Approval 04-Dec-13 17-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 Tender 19-Dec-13 04-Mar-14 QR635,525 QR0 QR635,525 0% 0% QR0 PWA Approval (100%) 19-Dec-13 04-Mar-14 QR635,525 QR0 QR635,525 0% 0% QR0 QS0155478 Issue Invitation toTender 19-Dec-13 19-Dec-13 QR63,552 QR0 QR63,552 0% 0% QR0 QS0155479 Tender Queries / Pre Tender Workshop 22-Dec-13 02-Feb-14 QR127,105 QR0 QR127,105 0% 0% QR0 QS0155480 Tender Evaluation Report 03-Feb-14 17-Feb-14 QR127,105 QR0 QR127,105 0% 0% QR0 QS0155481 Award of Contract (Work Order) 18-Feb-14 03-Mar-14 QR190,657 QR0 QR190,657 0% 0% QR0 QS0155482 Prepare and Issue Notice to Proceed 04-Mar-14 04-Mar-14 QR127,105 QR0 QR127,105 0% 0% QR0 2013 2014 S O N D J F M A M J Jul A S O N D J F M A M J Jul A S Updated Project Schedule Volume 1 - Main Report Volume 2 - Geotechnical Fac Volume 2 - Geotechnical Inte Volume 4A - Surface and Gro Volume 4B - Foul Water Rep Volume 4C - Treated Sewage Volume 5 - Environmental an Volume 6 - Drawings, Volume Volume 7 - Stakeholders Re Volume 8 - Commercial Repo Volume 9C - Road Safety Au Volume 9D - Road Safety Au PMC Accpetance with Com PMC Accpetance PWA Approval Specification Drawings, S Conditions of Contract, Cond Particular Conditions of Cont Preliminary Bill of Quantity, P Final Bill of Quantities Pre-Tender Estimate, Pre-Te Project Programme, Project PMC Accpetance with Com PMC Accpetance PWA Approval Issue Invitation toTender Tender Queries / Pre Tender Evaluation Award of Contract Prepare and Issue Public Works Authority Local Roads and Drainage Programme Earned Value as of 31-Oct-13 Remaining Level of Effort Actual Level of Effort Baseline Project Start:- 04-Nov-12 Project Finish:- 04-Jan-17 Layout:- A4 - QS015 - Monthly EVM Report Data Date : 31-Oct-13 Page : 2 of 3 Printed On : 07-Nov-13 Date Revision Checked Approved 30-Sep-13 Payment Schedule Update MN 31-Oct-13 Payment Schedule Update MN
  • 21. Activity ID Activity Name Planned Start Planned Finish Budgeted Payment (QAR) Actual Payment (QAR) Remaining Payment (QAR) Payment % Complete Progress % Complete Earned Value Cost Contract 05-Mar-14 18-Mar-14 QR423,683 QR0 QR423,683 0% 0% QR0 PWA Approval (100%) 05-Mar-14 18-Mar-14 QR423,683 QR0 QR423,683 0% 0% QR0 QS0155483 Prepare Contract Documents for Work Order 05-Mar-14 11-Mar-14 QR254,210 QR0 QR254,210 0% 0% QR0 QS0155484 Contract Signed Off by Contractor 12-Mar-14 13-Mar-14 QR63,552 QR0 QR63,552 0% 0% QR0 QS0155485 Contract Signed Off by PWA 14-Mar-14 17-Mar-14 QR63,552 QR0 QR63,552 0% 0% QR0 QS0155486 Exchange of Contract 18-Mar-14 18-Mar-14 QR42,368 QR0 QR42,368 0% 0% QR0 2013 2014 S O N D J F M A M J Jul A S O N D J F M A M J Jul A S Prepare Contract Contract Signed Contract Signed Exchange of Con QR10,000,000QR QR8,000,000QR QR6,000,000QR QR4,000,000QR S O N D J F M A M J Jul A S O N D J F M A M J Jul A S 2013 2014 QR1,000,000QR QR800,000QR QR600,000QR QR400,000QR QR200,000QR QR0QR QR2,000,000QR Actual Expense Cost Planned Value Cost Earned Value Cost BL Project Expense Cost Public Works Authority Local Roads and Drainage Programme Earned Value as of 31-Oct-13 Remaining Level of Effort Actual Level of Effort Baseline Project Start:- 04-Nov-12 Project Finish:- 04-Jan-17 Layout:- A4 - QS015 - Monthly EVM Report Data Date : 31-Oct-13 Page : 3 of 3 Printed On : 07-Nov-13 Date Revision Checked Approved 30-Sep-13 Payment Schedule Update MN 31-Oct-13 Payment Schedule Update MN
  • 22. Contract 2 Local Roads and Drainage Programme QS016 - Access Road to Rashid Village QATAR ACCOUNT MANAGEMENT PROGRAM
  • 23. 3 SScchheedduulele D Parsohgbreosasrd Projects Milestones Milestones Gateway Planned Actual / Forecast QQQQSSSS000011116666 ---- AAAAcccccccceeeessssssss RRRRooooaaaadddd ttttoooo RRRRaaaasssshhhhiiiidddd VVVViiiillllllllaaaaggggeeee Plan. Act. Initiation G1 22-Oct-12 22-Oct-12 0 100% 100% 0 Concept Design G2 20-Feb-13 03-Jul-13 -133 100% 100% -133 Preliminary Design 20-Jun-13 12-Nov-13 -145 100% 60.0% -145 Detailed Design Tender Documents G3 18-Dec-13 17-Dec-13 1 58% 13% 1 Tendering 04-Mar-14 04-Mar-14 0 0% 0% 0 Construction G5 16-Sep-15 16-Sep-15 0 0% 0% 0 Maintenance Period G6 21-Sep-16 02-Nov-16 -42 0% 0% -42 Monthly Progress Report No. 13 ­Oct 2013 Total Variance % Progress Trend Initiation Concept Design Preliminary Design Detailed Design Tender Documents Tendering Construction Maintenance Period Planned Actual/Forecast G1 G2 G3 G5 G6 Behind Schedule No Change On Schedule 47 Days Until Completion (Starting from 1st Nov) Detailed Design Tender Docs. Current Segment 13.4 0.23 Progress % Complete SPI Upward Trend Downward Trend File :- Schedule Management - Oct 13 Printed On :- 11/11/2013 at 16:06
  • 24. Activity ID Activity Name Planned Duration Cur rent Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan Project Wide - HHiigghh LLeevveell SScchheedduullee 1019 1049 02-Sep-12 21-Sep-16 02-Sep-12 A 02-Nov-16 0 0% PPrrooggrraammmmee WWiiddee --HHiigghh LLeevveell SScchheedduullee 1019 1049 02-Sep-12 21-Sep-16 02-Sep-12 A 02-Nov-16 0 0% PPrrooggrraammmmee WWiiddee HHiigghh LLeevveell SScchheedduullee 1019 1049 02-Sep-12 21-Sep-16 02-Sep-12 A 02-Nov-16 0 0% 2012 2013 2014 2015 2016 2017 IInniittiiaattiioonn 37 37 02-Sep-12 22-Oct-12 02-Sep-12 A 22-Oct-12 A 0% IInniittiiaattiioonn 24 24 02-Sep-12 03-Oct-12 02-Sep-12 A 03-Oct-12 A 0% QS016 020000 PWA Formal Notificat ion of Candidate Project 0 0 02-Sep-12 02-Sep-12 A 100% QS016 212001 Init iation Slides Submission 0 0 03-Oct-12 03-Oct-12 A 100% QS016 020010 Init iation 24 24 02-Sep-12 03-Oct-12 02-Sep-12 A 03-Oct-12 A 100% 1188 DDaayy RReevviieeww 19 19 04-Oct-12 22-Oct-12 04-Oct-12 A 22-Oct-12 A 0% QS016 212101 PMC/PWA Initiation Review 18 18 04-Oct-12 21-Oct-12 04-Oct-12 A 21-Oct-12 A 100% QS016 010040 Gateway 1 Review Meeting 0 0 22-Oct-12 22-Oct-12 A 100% CCoonncceepptt DDeessiiggnn 80 80 23-Oct-12 20-Feb-13 23-Oct-12 A 03-Jul-13 A 0% CCoonncceepptt DDeessiiggnn 55 55 23-Oct-12 15-Jan-13 23-Oct-12 A 18-Mar-13 A 0% QS016 020070 Concept Design 55 55 23-Oct-12 15-Jan-13 23-Oct-12 A 18-Mar-13 A 100% QS016 212411 Concept Design Submission 0 0 15-Jan-13 18-Mar-13 A 100% 3355 DDaayy RReevviieeww 36 36 16-Jan-13 20-Feb-13 10-Feb-13 A 03-Jul-13 A 0% QS016 212421 PMC Concept Design Review 10 10 16-Jan-13 25-Jan-13 10-Feb-13 A 30-Mar-13 A 100% QS016 212431 GEC Response to PMC Comments 7 7 26-Jan-13 01-Feb-13 19-Feb-13 A 20-May-13 A 100% QS016 212441 PMC Review of GEC Response 4 4 02-Feb-13 05-Feb-13 02-Mar-13 A 21-May-13 A 100% QS016 212451 PWA Review 14 14 06-Feb-13 19-Feb-13 02-Mar-13 A 21-May-13 A 100% QS016 020100 Gateway 2 Review Meeting 0 0 20-Feb-13 03-Jul-13 A 100% PPrreelliimmiinnaarryy DDeessiiggnn 111 208 21-Feb-13 25-Jul-13 04-Jul-13 A 17-Dec-13 0 0% PPrreelliimmiinnaarryy DDeessiiggnn 86 183 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 0% QS016 020130 Preliminary Design 86 86 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 60% QS016 440190 Preliminary Design Submission 0 0 20-Jun-13 12-Nov-13 1 0% 3355 DDaayy RReevviieeww 35 35 21-Jun-13 25-Jul-13 13-Nov-13 17-Dec-13 1 0% QS016 440060 PMC Preliminary Design Review 10 10 21-Jun-13 30-Jun-13 13-Nov-13 22-Nov-13 1 0% QS016 440070 GEC Response to PMC Comments 7 7 01-Jul-13 07-Jul-13 23-Nov-13 29-Nov-13 1 0% QS016 440080 PMC Review of GEC Response 4 4 08-Jul-13 11-Jul-13 30-Nov-13 03-Dec-13 1 0% QS016 440090 PWA Review 14 14 12-Jul-13 25-Jul-13 04-Dec-13 17-Dec-13 1 0% DDeettaaiilleedd DDeessiiggnn TTeennddeerr DDooccuummeennttss 122 44 23-Jun-13 18-Dec-13 01-Sep-13 A 17-Dec-13 0 0% DDeettaaiilleedd DDeessiiggnn TTeennddeerr DDooccuummeennttss 97 19 23-Jun-13 12-Nov-13 01-Sep-13 A 12-Nov-13 1 0% QS016 020140 Detailed Design 87 13 23-Jun-13 29-Oct-13 01-Sep-13 A 12-Nov-13 1 18.48% Detailed Design duration was reduced from 87 to 13 days as the detailed and preliminary designs are running concurrently. QS016 020150 Tender Documents 28 8 01-Oct-13 12-Nov-13 03-Nov-13 12-Nov-13 1 0% QS016 212461 Draft Detailed DesignTender Documents Submission 0 0 12-Nov-13 12-Nov-13 1 0% 3355 DDaayy RReevviieeww 36 35 13-Nov-13 18-Dec-13 13-Nov-13 17-Dec-13 1 0% QS016 212471 PMC Detailed DesignTender Documents Review 10 10 13-Nov-13 22-Nov-13 13-Nov-13 22-Nov-13 1 0% QS016 212481 GEC Response to PMC Comments 7 7 23-Nov-13 29-Nov-13 23-Nov-13 29-Nov-13 1 0% QS016 212491 PMC Review of GEC Response 4 4 30-Nov-13 03-Dec-13 30-Nov-13 03-Dec-13 1 0% QS016 020180 Gateway 3 Review Meeting 0 0 18-Dec-13 17-Dec-13 1 0% Q3 Q4 Q1 Q Q3 Q4 Q Q2 Q3 Q4 Q Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q Q4 PWA Formal Notificat ion of Candidate Project Init iation Slides Submission Init iation PMC/PWA Initiation Review Gateway 1 Review Meeting Concept Design Concept Design Submission PMC Concept Design Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 2 Review Meeting Preliminary Design Preliminary Design Submission PMC Preliminary Design Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Detailed Design Tender Documents Draft Detailed DesignTender Documents Submission PMC Detailed DesignTender Documents Review GEC Response to PMC Comments PMC Review of GEC Response Gateway 3 Review Meeting Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 1 of 4 Printed On : 10-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS016 - Access Road to Rawdat Rashed Village Update as of 31-Oct-2013 Date Revision Checked Approved 16-Apr-13 Project Baseline Schedule/QS016-AEC-PMG-SCH-00237... SK 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 SK
  • 25. Activity ID Activity Name Planned Duration Cur rent Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan QS016 212501 PWA Review 14 14 04-Dec-13 17-Dec-13 04-Dec-13 17-Dec-13 1 0% TTeennddeerriinngg 64 64 19-Dec-13 23-Mar-14 19-Dec-13 23-Mar-14 10 0% TTeennddeerr aanndd AAwwaarrddiinngg 64 64 19-Dec-13 23-Mar-14 19-Dec-13 23-Mar-14 10 0% QS016 020210 Tendering of the Project 30 30 19-Dec-13 02-Feb-14 19-Dec-13 02-Feb-14 0 0% QS016 020240 Tender AssessmentRecommendat ions 10 10 03-Feb-14 17-Feb-14 03-Feb-14 17-Feb-14 0 0% QS016 020220 Award of the Construction Contract (Work Order) 0 0 04-Mar-14 04-Mar-14 0 0% QS016 020250 PMC/PWA Approval 11 11 18-Feb-14 04-Mar-14 18-Feb-14 04-Mar-14 0 0% QS016 020330 Prepare and Issue Notice to Proceed 1 1 05-Mar-14 05-Mar-14 05-Mar-14 05-Mar-14 0 0% QS016 020270 Prepare Contract Documents for Work Order 6 6 06-Mar-14 13-Mar-14 06-Mar-14 13-Mar-14 0 0% QS016 020280 Contract Signed Off by ContractorPWA 5 5 16-Mar-14 20-Mar-14 16-Mar-14 20-Mar-14 0 0% QS016 020310 Exchange of Contract 1 1 23-Mar-14 23-Mar-14 23-Mar-14 23-Mar-14 10 0% CCoonnssttrruuccttiioonn 387 387 06-Mar-14 16-Sep-15 06-Mar-14 16-Sep-15 0 0% CCoonnssttrruuccttiioonn PPeerriioodd 361 361 06-Mar-14 11-Aug-15 06-Mar-14 11-Aug-15 0 0% QS016 020300 Contractor Mobilization Period 22 22 06-Mar-14 06-Apr-14 06-Mar-14 06-Apr-14 0 0% QS016 020230 Construction of the Project 339 339 07-Apr-14 11-Aug-15 07-Apr-14 11-Aug-15 0 0% QS016 212511 Construction Documents Submission 0 0 11-Aug-15 11-Aug-15 0 0% 3355 DDaayy RReevviieeww 36 36 12-Aug-15 16-Sep-15 12-Aug-15 16-Sep-15 0 0% QS016 212521 PMC Construct ion Documents Review 10 10 12-Aug-15 21-Aug-15 12-Aug-15 21-Aug-15 0 0% QS016 212531 GEC Response to PMC Comments 7 7 22-Aug-15 28-Aug-15 22-Aug-15 28-Aug-15 0 0% QS016 212541 PMC Review of GEC Response 4 4 29-Aug-15 01-Sep-15 29-Aug-15 01-Sep-15 0 0% QS016 212551 PWA Review 14 14 02-Sep-15 15-Sep-15 02-Sep-15 15-Sep-15 0 0% QS016 020260 Gateway 5 Review Meeting 0 0 16-Sep-15 16-Sep-15 0 0% MMaaiinntteennaannccee PPeerriioodd 371 413 17-Sep-15 21-Sep-16 17-Sep-15 02-Nov-16 0 0% MMaaiinntteennaannccee PPeerriioodd 335 365 17-Sep-15 16-Aug-16 17-Sep-15 15-Sep-16 0 0% QS016 020290 Maintenance Period 232 365 17-Sep-15 16-Aug-16 17-Sep-15 15-Sep-16 0 0% QS016 212561 Maintenance Documents Submission 0 0 16-Aug-16 15-Sep-16 0 0% 3355 DDaayy RReevviieeww 36 48 17-Aug-16 21-Sep-16 16-Sep-16 02-Nov-16 0 0% QS016 212571 PMC Maintenance Documents Review 10 10 17-Aug-16 26-Aug-16 16-Sep-16 25-Sep-16 0 0% QS016 212581 GEC Response to PMC Comments 7 7 27-Aug-16 02-Sep-16 26-Sep-16 02-Oct-16 0 0% QS016 212591 PMC Review of GEC Response 4 4 03-Sep-16 06-Sep-16 03-Oct-16 06-Oct-16 0 0% QS016 212601 PWA Review 14 14 07-Sep-16 20-Sep-16 07-Oct-16 20-Oct-16 0 0% QS016 020320 Gateway 6 Review Meeting 0 0 21-Sep-16 02-Nov-16 0 0% QS016 020340 Project Completion 0 0 21-Sep-16 02-Nov-16* 0 0% MMMMUUPP aanndd MMOOEE 320 320 26-Nov-12 06-Mar-14 12-Dec-12 A 06-Mar-14 21 0% MMiinniissttrryy ooff MMuunniicciippaalliittyy aanndd UUrrbbaann PPllaannnniinngg 11 11 26-Nov-12 10-Dec-12 12-Dec-12 A 27-Dec-12 A 0% MMiinniissttrryy ooff MMuunniicciippaalliittyy aanndd UUrrbbaann PPllaannnniinngg 11 11 26-Nov-12 10-Dec-12 12-Dec-12 A 27-Dec-12 A 0% QS016 020080 Submission of TTN to PMC 0 0 26-Nov-12 12-Dec-12 A 100% QS016 020090 Approval of TTN by PMC 0 0 10-Dec-12 27-Dec-12 A 100% QS016 020110 ReviewTTN by PMC 14 14 26-Nov-12 09-Dec-12 13-Dec-12 A 27-Dec-12 A 100% MMiinniissttrryy ooff EEnnvviirroonnmmeenntt 276 276 30-Jan-13 06-Mar-14 30-Jan-13 A 06-Mar-14 21 0% MMiinniissttrryy ooff EEnnvviirroonnmmeenntt 276 276 30-Jan-13 06-Mar-14 30-Jan-13 A 06-Mar-14 21 0% QS016 440100 Preparation of Environmental Permit Application 30 30 30-Jan-13 13-Mar-13 30-Jan-13 A 16-Feb-13 A 100% QS016 440110 Permit Application Submission 0 0 13-Mar-13 17-Feb-13 A 100% QS016 440000 PMC/MOE Review 30 30 14-Mar-13 12-Apr-13 18-Feb-13 A 21-Apr-13 A 100% 2012 2013 2014 2015 2016 2017 Q3 Q4 Q1 Q Q3 Q4 Q Q2 Q3 Q4 Q Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q Q4 PWA Review Tendering of the Project Tender AssessmentRecommendat ions Award of the Construction Contract (Work Order) PMC/PWA Approval Prepare and Issue Notice to Proceed Prepare Contract Documents for Work Order Contract Signed Off by ContractorPWA Exchange of Contract Contractor Mobilization Period Construction of the Project Construction Documents Submission PMC Construct ion Documents Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 5 Review Meeting Maintenance Period Maintenance Documents Submission PMC Maintenance Documents Review GEC Response to PMC Comments PMC Review of GEC Response PWA Review Gateway 6 Review Meeting Project Completion Submission of TTN to PMC Approval of TTN by PMC ReviewTTN by PMC Preparation of Environmental Permit Application Permit Application Submission PMC/MOE Review Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 2 of 4 Printed On : 10-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS016 - Access Road to Rawdat Rashed Village Update as of 31-Oct-2013 Date Revision Checked Approved 16-Apr-13 Project Baseline Schedule/QS016-AEC-PMG-SCH-00237... SK 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 SK
  • 26. Activity ID Activity Name Planned Duration Cur rent Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan QS016 440010 Environmental Scoping 39 39 14-Apr-13 05-Jun-13 22-Apr-13 A 23-May-13 A 100% QS016 440120 Environmental Scoping Submission 0 0 05-Jun-13 23-May-13 A 100% QS016 440020 PMC/MOE Review 30 30 06-Jun-13 05-Jul-13 24-May-13 A 01-Nov-13 12 80% QS016 440030 Environmental Impact Assessment (EIA) 65 65 07-Jul-13 08-Oct-13 10-Jul-13 A 04-Nov-13 8 49.5% QS016 440130 EIA Submission 0 0 08-Oct-13 04-Nov-13 8 0% QS016 440040 PMC/MOE Review 30 30 09-Oct-13 07-Nov-13 05-Nov-13 04-Dec-13 12 0% QS016 440050 Environmental Permit Issued 0 0 10-Nov-13 05-Dec-13 8 0% QS016 440160 Review Contractor CEMP 5 5 05-Feb-14 12-Feb-14 05-Feb-14 12-Feb-14 36 0% QS016 440200 CEMP Submission to MOE 0 0 06-Mar-14 06-Mar-14 21 0% Stakeholders EEnnggaaggeemmeenntt 981 1011 24-Oct-12 21-Sep-16 02-Sep-12 A 02-Nov-16 0 0% CCoonncceepptt DDeessiiggnn 79 79 24-Oct-12 20-Feb-13 23-Oct-12 A 21-May-13 A 0% CCoonncceepptt DDeessiiggnn 79 79 24-Oct-12 20-Feb-13 23-Oct-12 A 21-May-13 A 0% QS016 021020 Liaison with Stakeholders - Concept Design 79 79 24-Oct-12 20-Feb-13 23-Oct-12 A 21-May-13 A 100% PPrreelliimmiinnaarryy DDeessiiggnn 86 86 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 0% PPrreelliimmiinnaarryy DDeessiiggnn 86 86 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 0% QS016 440140 Liaison with Stakeholders - Preliminary Design 86 86 21-Feb-13 20-Jun-13 04-Jul-13 A 12-Nov-13 1 99% DDeettaaiilleedd DDeessiiggnn TTeennddeerriinngg 174 105 23-Jun-13 05-Mar-14 01-Sep-13 A 05-Mar-14 0 0% DDeettaaiilleedd DDeessiiggnn TTeennddeerriinngg 174 105 23-Jun-13 05-Mar-14 01-Sep-13 A 05-Mar-14 0 0% QS016 440150 Liaison with Stakeholders - Detailed Design Tendering 174 105 23-Jun-13 05-Mar-14 01-Sep-13 A 05-Mar-14 0 51.15% CCoonnssttrruuccttiioonn 387 387 06-Mar-14 16-Sep-15 06-Mar-14 16-Sep-15 0 0% CCoonnssttrruuccttiioonn 387 387 06-Mar-14 16-Sep-15 06-Mar-14 16-Sep-15 0 0% QS016 440170 Liaison with Stakeholders - Construct ion 387 387 06-Mar-14 16-Sep-15 06-Mar-14 16-Sep-15 0 0% MMaaiinntteennaannccee PPeerriioodd 255 255 17-Sep-15 21-Sep-16 03-Nov-15 02-Nov-16 0 0% MMaaiinntteennaannccee PPeerriioodd 255 255 17-Sep-15 21-Sep-16 03-Nov-15 02-Nov-16 0 0% QS016 440180 Liaison with Stakeholders - Maintenance Period 255 255 17-Sep-15 21-Sep-16 03-Nov-15 02-Nov-16 0 0% MMMMUUPP UUttiilliittyy IInnvveessttiiggaatt iioonn 90 60 24-Oct-12 07-Mar-13 02-Sep-12 A 12-Nov-13 1 0% QS016 440240 Superimpose Data on Proposed Road Layout 10 10 17-Dec-12 02-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440260 Agencies Approval 15 15 03-Jan-13 23-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440210 Utility Investigation by Owner/Consultant/Client 10 10 24-Oct-12 11-Nov-12 01-Oct-12 A 31-Oct-12 A 100% QS016 440220 Collect Data (Existing Proposed Utilties) 10 10 12-Nov-12 25-Nov-12 01-Nov-12 A 08-Nov-12 A 100% QS016 440230 Topo Survey,Trial Pits and Radio Detection 15 15 26-Nov-12 16-Dec-12 11-Nov-12 A 09-Dec-12 A 100% QS016 440290 MMUP Approval 15 8 24-Jan-13 14-Feb-13 03-Nov-13 12-Nov-13 1 0% QS016 440300 Final Report to MMUP 15 8 17-Feb-13 07-Mar-13 03-Nov-13 12-Nov-13 1 0% KKAAHHRRAAMMAA 75 45 24-Oct-12 14-Feb-13 01-Oct-12 A 12-Nov-13 1 0% QS016 440310 Send an Introductory Letters to KAHRAMA 10 10 24-Oct-12 11-Nov-12 01-Oct-12 A 07-Oct-12 A 100% QS016 440320 Request for Information about KAHRAMA's Current/Future Projects 10 10 12-Nov-12 25-Nov-12 08-Oct-12 A 15-Oct-12 A 100% QS016 440330 Receive Information about KAHRAMA's Current/Future Projects 15 15 26-Nov-12 16-Dec-12 23-Oct-12 A 29-Oct-12 A 100% QS016 440340 Superimpose the Plans on Proposed Project to Identify Conflict 10 10 17-Dec-12 02-Jan-13 31-Oct-12 A 03-Nov-13 1 25% QS016 440350 Report the Conflicts to KAHRAMA 10 8 03-Jan-13 16-Jan-13 03-Nov-13 12-Nov-13 1 0% QS016 440360 Amend the Drawings 10 8 17-Jan-13 30-Jan-13 03-Nov-13 12-Nov-13 1 0% QS016 440370 Drawings Submission to KAHRAMA for Approval 10 8 31-Jan-13 14-Feb-13 03-Nov-13 12-Nov-13 1 0% CCoommmmuunniiccaatt iioonn ((OOrreeddoooo//VVooddaaffoonnee)) 75 45 24-Oct-12 14-Feb-13 01-Oct-12 A 12-Nov-13 1 0% QS016 440380 Send an Introductory Letters to Oredoo/Vodafone 10 10 24-Oct-12 11-Nov-12 01-Oct-12 A 07-Oct-12 A 100% QS016 440390 Request for Information about Oredo/Vodafone's Current /Future Projects 10 10 12-Nov-12 25-Nov-12 08-Oct-12 A 15-Oct-12 A 100% 2012 2013 2014 2015 2016 2017 Q3 Q4 Q1 Q Q3 Q4 Q Q2 Q3 Q4 Q Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q Q4 Environmental Scoping Environmental Scoping Submission PMC/MOE Review Environmental Impact Assessment (EIA) EIA Submission PMC/MOE Review Environmental Permit Issued Review Contractor CEMP CEMP Submission to MOE Liaison with Stakeholders - Concept Design Liaison with Stakeholders - Preliminary Design Liaison with Stakeholders - Detailed Design Tendering Liaison with Stakeholders - Construct ion Liaison with Stakeholders - Maintenance Superimpose Data on Proposed Road Layout Agencies Approval Utility Investigation by Owner/Consultant/Client Collect Data (Existing Proposed Utilties) Topo Survey,Trial Pits and Radio Detection MMUP Approval Final Report to MMUP Send an Introductory Letters to KAHRAMA Request for Information about KAHRAMA's Current/Future Projects Receive Information about KAHRAMA's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Report the Conflicts to KAHRAMA Amend the Drawings Drawings Submission to KAHRAMA for Approval Send an Introductory Letters to Oredoo/Vodafone Request for Information about Oredo/Vodafone's Current /Future Projects Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 3 of 4 Printed On : 10-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS016 - Access Road to Rawdat Rashed Village Update as of 31-Oct-2013 Date Revision Checked Approved 16-Apr-13 Project Baseline Schedule/QS016-AEC-PMG-SCH-00237... SK 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 SK
  • 27. Activity ID Activity Name Planned Duration Cur rent Duration Planned Start Planned Finish Actual/Forecast Start Actual/Forecast Finish Total Float Actual % Complete . AECOM Mitigation Plan QS016 440400 Receive Information about Oredo/Vodafone's Current/Future Projects 15 15 26-Nov-12 16-Dec-12 23-Oct-12 A 29-Oct-12 A 100% QS016 440410 Superimpose the Plans on Proposed Project to Identify Conflict 10 10 17-Dec-12 02-Jan-13 31-Oct-12 A 04-Nov-13 1 50% QS016 440420 Report the Conflicts to Oredoo/Vodafone 10 8 03-Jan-13 16-Jan-13 03-Nov-13 12-Nov-13 1 0% QS016 440430 Amend the Drawings 10 8 17-Jan-13 30-Jan-13 03-Nov-13 12-Nov-13 1 0% QS016 440440 Drawings Submission to Oredoo/Vodafone for Approval 10 8 31-Jan-13 14-Feb-13 03-Nov-13 12-Nov-13 1 0% Natural RReesseerrvveess ((NNRR)) 75 75 24-Oct-12 14-Feb-13 02-Sep-12 A 02-Sep-12 A 0% QS016 440450 Send an Introductory Letters to NR 10 10 24-Oct-12 11-Nov-12 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440460 Request for Information about NR's Current /Future Projects 10 10 12-Nov-12 25-Nov-12 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440470 Receive Information about NR's Current/Future Projects 15 15 26-Nov-12 16-Dec-12 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440480 Superimpose the Plans on Proposed Project to Identify Conflict 10 10 17-Dec-12 02-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440490 Report the Conflicts to NR 10 10 03-Jan-13 16-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440500 Amend the Drawings 10 10 17-Jan-13 30-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440510 Drawings Submission to NR for Approval 10 10 31-Jan-13 14-Feb-13 02-Sep-12 A 02-Sep-12 A 100% Escaped PPrriivvaattee EEnnggiinneeeerr OOffffiiccee ((PPEEOO)) 75 75 24-Oct-12 14-Feb-13 02-Sep-12 A 11-Nov-13 2 0% QS016 440550 Superimpose the Plans on Proposed Project to Identify Conflict 10 10 17-Dec-12 02-Jan-13 02-Sep-12 A 02-Sep-12 A 100% Escaped QS016 440520 Send an Introductory Letters to PEO 10 10 24-Oct-12 11-Nov-12 01-Oct-12 A 07-Oct-12 A 100% QS016 440530 Request for Information about PEO's Current/Future Projects 10 10 12-Nov-12 25-Nov-12 08-Oct-12 A 15-Oct-12 A 100% QS016 440540 Receive Information about PEO's Current /Future Projects 15 15 26-Nov-12 16-Dec-12 23-Oct-12 A 29-Oct-12 A 100% QS016 440560 Report the Conflicts to PEO 10 10 03-Jan-13 16-Jan-13 25-Nov-12 A 04-Dec-12 A 100% QS016 440570 Amend the Drawings 10 10 17-Jan-13 30-Jan-13 10-Dec-12 A 15-Jan-13 A 100% QS016 440580 Drawings Submission to PEO for Approval 10 10 31-Jan-13 14-Feb-13 16-Jan-13 A 11-Nov-13 2 5% PPhh 11 -- 22 FFeeaassiibbiilliittyy OOppttiioonnss ((CCoonncceepptt DDeessiiggnn)) 117 117 02-Sep-12 20-Feb-13 02-Sep-12 A 03-Jul-13 A 100% PPhh 22 -- 33 DDeessiiggnn CCoonnttrraacctt AAwwaarrdd 272 272 21-Feb-13 23-Mar-14 02-Sep-12 A 23-Mar-14 0 19.39% 2012 2013 2014 2015 2016 2017 Q3 Q4 Q1 Q Q3 Q4 Q Q2 Q3 Q4 Q Q2 Q3 Q Q1 Q2 Q3 Q Q1 Q2 Q Q4 Receive Information about Oredo/Vodafone's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Report the Conflicts to Oredoo/Vodafone Amend the Drawings Drawings Submission to Oredoo/Vodafone for Approval Send an Introductory Letters to NR Request for Information about NR's Current /Future Projects Receive Information about NR's Current/Future Projects Superimpose the Plans on Proposed Project to Identify Conflict Report the Conflicts to NR Amend the Drawings Drawings Submission to NR for Approval Superimpose the Plans on Proposed Project to Identify Conflict Send an Introductory Letters to PEO Request for Information about PEO's Current/Future Projects Receive Information about PEO's Current/Future Projects Report the Conflicts to PEO Amend the Drawings Drawings Submission to PEO for Approval Public Works Authority - Contract 2 Local Roads and Drainage Programme Data Date : 31-Oct-13 Page : 4 of 4 Printed On : 10-Nov-13 Baseline Actual Work Critical Remaining Work Baseline Milestone Curernt Milestone Delay Bar Project Baseline Schedule QS016 - Access Road to Rawdat Rashed Village Update as of 31-Oct-2013 Date Revision Checked Approved 16-Apr-13 Project Baseline Schedule/QS016-AEC-PMG-SCH-00237... SK 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 SK
  • 28. Activity ID Activity Name Planned Start Planned Finish Budgeted Payment (QAR) Actual Payment (QAR) Remaining Payment (QAR) Payment % Complete 2013-09-01:Earned Value Cost TToottaall 24-Oct-12 23-Mar-14 QR9,746,172 QR2,552,136 QR7,194,037 26.19% QR1,185,555 CCoonncceepptt DDeessiiggnn 24-Oct-12 19-Feb-13 QR930,816 QR763,264 QR167,552 82% QR930,816 SSuubbmmiissssiioonn ooff CCoonncceepptt DDeessiiggnn ((6600%%)) 24-Oct-12 06-Feb-13 QR558,490 QR558,485 QR5 100% QR558,490 QS0161088 Project Schedule 10-Jan-13 31-Jan-13 QR83,773 QR83,773 QR0 100% QR83,773 QS0161098 Main Report (Volume 1) 19-Nov-12 06-Jan-13 QR83,773 QR83,773 QR0 100% QR83,773 QS0161108 Geotechnical Report (Volume 2) 06-Dec-12 24-Dec-12 QR27,924 QR27,924 QR0 100% QR27,924 QS0161118 Traffic Analysis Report (Volume 3) 24-Oct-12 02-Jan-13 QR55,849 QR55,849 QR0 100% QR55,849 QS0161128 Drainage Part A (SW GW) (Volume 4A) 09-Dec-12 06-Jan-13 QR27,924 QR27,924 QR0 100% QR27,924 QS0161138 Drainage Part B (FS) (Volume 4B) 09-Dec-12 06-Jan-13 QR27,924 QR27,924 QR0 100% QR27,924 QS0161148 Drainage Part C (TSE) (Volume 4C) 09-Dec-12 06-Jan-13 QR27,924 QR27,924 QR0 100% QR27,924 QS0161158 Environmental and Sustainablity (Volume 5) 30-Jan-13 06-Feb-13 QR27,924 QR27,924 QR0 100% QR27,924 QS0161168 Drawings (Volume 6) 06-Nov-12 22-Jan-13 QR83,773 QR83,773 QR0 100% QR83,773 QS0161178 Stakeholders (Volume 7) 12-Nov-12 16-Dec-12 QR27,924 QR27,924 QR0 100% QR27,924 QS0161188 Commercial Report (Volume 8) 07-Jan-13 10-Jan-13 QR55,849 QR55,849 QR0 100% QR55,849 QS0161198 RSA - Review (Volume 9A) 19-Nov-12 06-Jan-13 QR27,924 QR27,924 QR0 100% QR27,924 PPMMCC AAcccceeppttaannccee wwiitthh CCoommmmeennttss ((2200%%)) 16-Jan-13 24-Jan-13 QR186,163 QR186,163 QR0 100% QR186,163 QS0161199 PMC Accpetance with Comments 16-Jan-13 24-Jan-13 QR186,163 QR186,163 QR0 100% QR186,163 PPMMCC AAcccceeppttaannccee ((1100%%)) 03-Feb-13 05-Feb-13 QR93,082 QR18,616 QR74,466 20% QR93,082 QS0161200 PMC Accpetance 03-Feb-13 05-Feb-13 QR93,082 QR18,616 QR74,466 20% QR93,082 PPWWAA AApppprroovvaall ((1100%%)) 06-Feb-13 19-Feb-13 QR93,082 QR0 QR93,082 0% QR93,082 QS0161201 PWA Approval 06-Feb-13 19-Feb-13 QR93,082 QR0 QR93,082 0% QR93,082 PPrreelliimmiinniiaarryy DDeessiiggnn 21-Feb-13 25-Jul-13 QR1,763,071 QR1,101,917 QR661,154 62.5% QR235,486 SSuubbmmiissssiioonn ooff PPrreelliimmiinnaarryy DDeessiiggnn ((6600%%)) 21-Feb-13 19-Jun-13 QR1,057,843 QR1,057,840 QR3 100% QR235,486 QS0161000 Updated Project Schedule 25-Apr-13 04-Jun-13 QR52,892 QR52,892 QR0 100% QR52,892 QS0161001 Volume 1 - Main Report 10-Mar-13 16-Jun-13 QR105,784 QR105,784 QR0 100% QR7,447 QS0161002 Volume 2 - Geotechnical Investigation Report 28-Apr-13 13-Jun-13 QR52,892 QR52,892 QR0 100% QR52,892 QS0161003 Volume 3 - Traffic Analysis Report 09-Apr-13 13-Jun-13 QR132,230 QR132,230 QR0 100% QR0 QS0161004 Volume 4A - Surface and Ground Water Report 18-Apr-13 19-Jun-13 QR52,892 QR52,892 QR0 100% QR4,797 QS0161005 Volume 4B - Foul Water Report 24-Apr-13 16-Jun-13 QR52,892 QR52,892 QR0 100% QR4,025 QS0161006 Volume 4C - Treated Sewage Effluent Report 02-May-13 09-May-13 QR52,892 QR52,892 QR0 100% QR0 QS0161007 Volume 5 - Environmental and Sustainability 26-Feb-13 06-May-13 QR132,230 QR132,230 QR0 100% QR0 QS0161008 Volume 6 - Drawings 21-Feb-13 16-Jun-13 QR185,122 QR185,122 QR0 100% QR39,394 QS0161009 Volume 7 - Stakeholders Report 10-Mar-13 09-May-13 QR52,892 QR52,892 QR0 100% QR0 QS0161019 Volume 8 - Commercial Report 26-May-13 13-Jun-13 QR105,784 QR105,784 QR0 100% QR74,038 QS0161029 Volume 9B - Road Safety Audit - Brief 13-May-13 02-Jun-13 QR26,446 QR26,446 QR0 100% QR0 QS0161039 Volume 9C - Road Safety Audi t - Report 13-May-13 02-Jun-13 QR26,446 QR26,446 QR0 100% QR0 QS0161049 Volume 9D - Road Safety Audi t - Designer's Response 13-May-13 02-Jun-13 QR26,446 QR26,446 QR0 100% QR0 PPMMCC AAcccceeppttaannccee wwiitthh CCoommmmeennttss ((2200%%)) 23-Jun-13 30-Jun-13 QR352,614 QR35,261 QR317,353 10% QR0 QS0161059 PMC Accpetance with Comments 23-Jun-13 30-Jun-13 QR352,614 QR35,261 QR317,353 10% QR0 PPMMCC AAcccceeppttaannccee ((1100%%)) 08-Jul-13 11-Jul-13 QR176,307 QR8,815 QR167,492 5% QR0 QS0161069 PMC Accpetance 08-Jul-13 11-Jul-13 QR176,307 QR8,815 QR167,492 5% QR0 PPWWAA AApppprroovvaall ((1100%%)) 14-Jul-13 25-Jul-13 QR176,307 QR0 QR176,307 0% QR0 QS0161079 PWA Approval 14-Jul-13 25-Jul-13 QR176,307 QR0 QR176,307 0% QR0 2013 2014 S Oct N D Jan F Mar Apr M Jun Jul A S Oct N D Jan F Mar Apr M Jun Jul A S Oct N Dec Project Schedule Main Report (Volume 1) Geotechnical Report (Volume 2) Traffic Analysis Report (Volume 3) Drainage Part A (SW GW) (Volume 4A) Drainage Part B (FS) (Volume 4B) Drainage Part C (TSE) (Volume 4C) Environmental and Sustainablity (Volume 5) Drawings (Volume 6) Stakeholders (Volume 7) Commercial Report (Volume 8) RSA - Review (Volume 9A) PMC Accpetance with Comments PMC Accpetance PWA Approval Updated Project Schedule Volume 1 - Main Report Volume 2 - Geotechnical Investigation Report Volume 3 - Traffic Analysis Report Volume 4A - Surface and Ground Water Report Volume 4B - Foul Water Report Volume 4C - Treated Sewage Effluent Report Volume 5 - Environmental and Sustainability Volume 6 - Drawings Volume 7 - Stakeholders Report Volume 8 - Commercial Report Volume 9B - Road Safety Audit - Brief Volume 9C - Road Safety Audi t - Report Volume 9D - Road Safety Audi t - Designer's Response PMC Accpetance with Comments PMC Accpetance PWA Approval Public Works Authority Local Roads and Drainage Programme Earned Value as of 31-Oct-13 Remaining Level of Effort Actual Level of Effort Baseline Project Start:- 02-Sep-12 Project Finish:- 02-Nov-16 Layout:- A4 - QS016 - Monthly EV Report Data Date : 31-Oct-13 Page : 1 of 3 Printed On : 07-Nov-13 Date Revision Checked Approved 31-Aug-13 Schedule Update - Aug-13 SK 30-Sep-13 Schedule Update - Sep-13 SK 31-Oct-13 Schedule Update - Oct-13 SK