Case Study
Gwynt y Môr OWF (2014) - 37 cables / 41,700 m (ICC)
Towards the end of 2013 CT Offshore was contracted by RWE Npower Renewable to carry out free-
laying, installation and burial of 63 cables of the total 161 inter-array cables at one of Europe’s largest
offshore wind farms, Gwynt y Môr OWF (GyM).
Many challenges were met especially with the demanding soil conditions on the GyM project.
With Fugro as trenching partner, CT Offshore was able to overcome these challenges and accomplished
the installation and burial of the inter-array cables in the safest and most efficient way.
CT Offshore where also brought into the project when most of the towers were in position. This also
presented another challenge. Due to the limited headroom within the tower hang off area and the cable
type not being flexible, up to 9 hours of stripping back the cable to allow safe connection resulted.
1. Scope of Work
Free-laying, installation and burial of 63 inter-array cables, using the CPS system ‘Teklink’ from Tekmar.
 Cable load-out
 Pre-lay Multibeam survey (MBES)
 Rigging of towers and messenger wire work
 Array cable installation
 Post-lay inspection (PLI)
 Optical time delay reflection (OTDR) test
 Post-lay burial (PLB)
 ROV post-burial survey
 Activation of Tekmar seals by use of divers
Vessels and equipment utilized
Cable Installation: CLV SIA
Survey, Trenching: MV FUGRO SALTIRE
Execution period, surface laid cables
Start-up Dec. 2013 (initial delay due to 3 UXOs in park)
Completed 5 June 2014
Due to another contracted assignment to BKR1, CLV SIA had a cut-off date 5 June to meet.
In the time available she and the crew managed to install 37 cables out of the 63 contracted.
Team work with Fugro
To carry out the post lay burial of the cables in
scope, CT Offshore entered into a framework
agreement with Fugro Subsea Services Limited, as
principle subcontractor.
They brought in the vessel MV SALTIRE to bury the
cables subsequently using their Q1400 trencher.
Page 2 / 4
2. Raw Installation Time – 37 ICC Cables (Gwynt y Môr)
2.1 Improving learning curve
2.2. Min. / Average installation time (hrs.) of 37 cables.
Page 3 / 4
2.3. Assigned in Project – Overall time consumption (according to DPR report structure)
2.4. Assigned in Project – Overall time consumption, in further details (according to DPR report structure)
Challenges, UXOs
Due to three UXOs in the offshore wind park the work was delayed until safely cleared. Then the first
cable was laid 12 March 2014 and 37 cables were completed by 5 June 2014, when CLV SIA had to leave
site for another contracted assignment. Fugro Saltire completed the burial of the 37 cables by 1 July
2014.
Page 4 / 4
CLV SIA at GyM site

Weitere ähnliche Inhalte

Ähnlich wie Case study_GYM_rev1

04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptxAbdalmoedAlaiashy2
 
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...Follow me on Twitter @Stockshaman
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
Remote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar ProjectRemote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar ProjectAchmad Agung P
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAli Osman Öncel
 
Huawei Training for Dialog Reginal Staff-1
Huawei  Training for Dialog Reginal Staff-1Huawei  Training for Dialog Reginal Staff-1
Huawei Training for Dialog Reginal Staff-1Fazal Junkeer
 
My Status and References of Submarine Cable
My Status and References of Submarine CableMy Status and References of Submarine Cable
My Status and References of Submarine CableChristian Georges Chene
 
Inteligencia Windfarms.pptx
Inteligencia Windfarms.pptxInteligencia Windfarms.pptx
Inteligencia Windfarms.pptxLeyneth1
 
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Tahar Hajji
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Jerry Brown
 
Fibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].docFibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].docThandabantu Magengelele
 
Aberdeen Harbour Siklu CCTV Case Study
Aberdeen Harbour Siklu CCTV Case StudyAberdeen Harbour Siklu CCTV Case Study
Aberdeen Harbour Siklu CCTV Case StudyPurdicom
 
Case Study - Aberdeen Harbour use Siklu EtherHaul to Integrate CCTV & Access ...
Case Study - Aberdeen Harbour use Siklu EtherHaul to Integrate CCTV & Access ...Case Study - Aberdeen Harbour use Siklu EtherHaul to Integrate CCTV & Access ...
Case Study - Aberdeen Harbour use Siklu EtherHaul to Integrate CCTV & Access ...Purdicom
 
Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1robinking277
 
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdfsantosobudipray
 
Presentataion Oil&Gas Telecommunications Conference - Radio LInk Project
Presentataion  Oil&Gas Telecommunications Conference - Radio LInk Project Presentataion  Oil&Gas Telecommunications Conference - Radio LInk Project
Presentataion Oil&Gas Telecommunications Conference - Radio LInk Project Andrea Vallavanti
 
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_vaPresentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_vaAndrea Vallavanti
 
Sirrs Materials Day 2010 - C-Power
Sirrs Materials Day 2010 - C-PowerSirrs Materials Day 2010 - C-Power
Sirrs Materials Day 2010 - C-PowerSirris
 

Ähnlich wie Case study_GYM_rev1 (20)

RINA_Paper
RINA_PaperRINA_Paper
RINA_Paper
 
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
 
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
Vale,announces opening of Totten Mine (first mine opened in Sudbury in 40 yea...
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
Remote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar ProjectRemote Region LNG Supply Study - Makassar Project
Remote Region LNG Supply Study - Makassar Project
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
 
Huawei Training for Dialog Reginal Staff-1
Huawei  Training for Dialog Reginal Staff-1Huawei  Training for Dialog Reginal Staff-1
Huawei Training for Dialog Reginal Staff-1
 
My Status and References of Submarine Cable
My Status and References of Submarine CableMy Status and References of Submarine Cable
My Status and References of Submarine Cable
 
Inteligencia Windfarms.pptx
Inteligencia Windfarms.pptxInteligencia Windfarms.pptx
Inteligencia Windfarms.pptx
 
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
Pipeline tow cuts installation costs offshore Tunisia (OGJ-27 Feb 1995)-1
 
Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2Snw ht-sea-trial-paper-rev2
Snw ht-sea-trial-paper-rev2
 
Fibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].docFibre installation - Athene and Duffs Road Station[12].doc
Fibre installation - Athene and Duffs Road Station[12].doc
 
Aberdeen Harbour Siklu CCTV Case Study
Aberdeen Harbour Siklu CCTV Case StudyAberdeen Harbour Siklu CCTV Case Study
Aberdeen Harbour Siklu CCTV Case Study
 
Case Study - Aberdeen Harbour use Siklu EtherHaul to Integrate CCTV & Access ...
Case Study - Aberdeen Harbour use Siklu EtherHaul to Integrate CCTV & Access ...Case Study - Aberdeen Harbour use Siklu EtherHaul to Integrate CCTV & Access ...
Case Study - Aberdeen Harbour use Siklu EtherHaul to Integrate CCTV & Access ...
 
Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1Cv supplement-2003-1229274598762649-1
Cv supplement-2003-1229274598762649-1
 
CV_TAEHOON LIM
CV_TAEHOON LIMCV_TAEHOON LIM
CV_TAEHOON LIM
 
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
 
Presentataion Oil&Gas Telecommunications Conference - Radio LInk Project
Presentataion  Oil&Gas Telecommunications Conference - Radio LInk Project Presentataion  Oil&Gas Telecommunications Conference - Radio LInk Project
Presentataion Oil&Gas Telecommunications Conference - Radio LInk Project
 
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_vaPresentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
 
Sirrs Materials Day 2010 - C-Power
Sirrs Materials Day 2010 - C-PowerSirrs Materials Day 2010 - C-Power
Sirrs Materials Day 2010 - C-Power
 

Case study_GYM_rev1

  • 1. Page 1 / 4 Case Study Gwynt y Môr OWF (2014) - 37 cables / 41,700 m (ICC) Towards the end of 2013 CT Offshore was contracted by RWE Npower Renewable to carry out free- laying, installation and burial of 63 cables of the total 161 inter-array cables at one of Europe’s largest offshore wind farms, Gwynt y Môr OWF (GyM). Many challenges were met especially with the demanding soil conditions on the GyM project. With Fugro as trenching partner, CT Offshore was able to overcome these challenges and accomplished the installation and burial of the inter-array cables in the safest and most efficient way. CT Offshore where also brought into the project when most of the towers were in position. This also presented another challenge. Due to the limited headroom within the tower hang off area and the cable type not being flexible, up to 9 hours of stripping back the cable to allow safe connection resulted. 1. Scope of Work Free-laying, installation and burial of 63 inter-array cables, using the CPS system ‘Teklink’ from Tekmar.  Cable load-out  Pre-lay Multibeam survey (MBES)  Rigging of towers and messenger wire work  Array cable installation  Post-lay inspection (PLI)  Optical time delay reflection (OTDR) test  Post-lay burial (PLB)  ROV post-burial survey  Activation of Tekmar seals by use of divers Vessels and equipment utilized Cable Installation: CLV SIA Survey, Trenching: MV FUGRO SALTIRE Execution period, surface laid cables Start-up Dec. 2013 (initial delay due to 3 UXOs in park) Completed 5 June 2014 Due to another contracted assignment to BKR1, CLV SIA had a cut-off date 5 June to meet. In the time available she and the crew managed to install 37 cables out of the 63 contracted. Team work with Fugro To carry out the post lay burial of the cables in scope, CT Offshore entered into a framework agreement with Fugro Subsea Services Limited, as principle subcontractor. They brought in the vessel MV SALTIRE to bury the cables subsequently using their Q1400 trencher.
  • 2. Page 2 / 4 2. Raw Installation Time – 37 ICC Cables (Gwynt y Môr) 2.1 Improving learning curve 2.2. Min. / Average installation time (hrs.) of 37 cables.
  • 3. Page 3 / 4 2.3. Assigned in Project – Overall time consumption (according to DPR report structure) 2.4. Assigned in Project – Overall time consumption, in further details (according to DPR report structure) Challenges, UXOs Due to three UXOs in the offshore wind park the work was delayed until safely cleared. Then the first cable was laid 12 March 2014 and 37 cables were completed by 5 June 2014, when CLV SIA had to leave site for another contracted assignment. Fugro Saltire completed the burial of the 37 cables by 1 July 2014.
  • 4. Page 4 / 4 CLV SIA at GyM site