SlideShare ist ein Scribd-Unternehmen logo
1 von 44
1
RUBNAWAZ
2015-UET-CCET-CIVIL-02
3rd SEMESTER
CIVIL ENGINEERING DEPARTMENT
February 2012
GOVERNMENT OF THE PUNJAB
COMMUNICATION & WORKS DEPARTMENT
Construction of Flyover on G.T Road
at Aziz Cross Gujranwala
February 2012
GOVERNMENT OF THE PUNJAB
CONSTRUCTION OF FLYOVER ON
G.T ROAD AT AZIZ CROSS GUJRANWALA
Construction of Flyover on G.T Road
at Aziz Cross Gujranwala
SALIENT FEATURE
 ADP (2016-17) Gr. Sr. No. 2775
 Approved Cost Rs. 6672 Million
 Construction Cost Rs. 3435 M
 Land Acquisition (80 Kanal) Rs. 2920 M
 Miscellaneous Rs. 317 M
 Consultant M/s NESPAK
 Contract M/s NLC
 Client C & W Dept
 Agreement Amount Rs.3115 M (9.35% below Est.cost)
 Date of Commencement 30.01.2016
 Date of Completion 29.11.2016
INTRODUCTION
 Aziz Cross project is a signal free interchange with partial clover
leaf system and two additional directional ramps.
Clover leaf interchange Partial Clover leaf
interchange with two
directional ramps instead
of loops
INTRODUCTION
 There are normally 32 conflicts at any interchange which are
completely resolved at Aziz Cross.
32 No. Traffic Conflicts
Traffic Count 2014
31,775
36,543
17,541
RAWALPINDI
LAHORE
GUJRANWALA
SIALKOT
13,000
NEW TRAFFIC DIRECTIONS & VOLUMES (ADT 2014)
BASIC COMPONENTS OF FLYOVER
Bridge cross-section can be divided
into two portions.
1. Super Structure
This portion receives the live load
directly. For example, Box Girder
2. Sub Structure
This Portion supports the entire
structure and live loads.
 Piles
 Pile cap
 Piers
 Abutments
Web
Web
Pier
Canopy
Pier
Shaft
Pile Cap
Pile
Pile
Pile
Super
Structure
Sub
Structure
CONCRETE PILES
A pile is a vertical structural element of a deep foundation which
transfers super structure loads to the earth farther down from the
surface to a subsurface layer.
PILE CAP
PILE CAP
Pile cap is a thick
reinforced concrete mat that
rests on concrete piles that
have been casted into ground.
concrete pile cap distributes the
load of the superstructure (from
piers and abutments into the
piles.
Pile Cap
Piles
Pier
PILE CAP AND PIER
PIER
A pier is a reinforced,
raised structure in form of
pillars typically supported by
well-spaced pile caps. It
transfers the loads from deck to
pile caps.
For this project, special shape
of pier is adopted. It as two
components
1. Pier Shaft as column
2. Pier Canopy as transom
Pier Canopy
Pier Shaft
Box Girder
Abutment refers to the substructure at the ends of a bridge span. It
supports;
 Super Structure load
 Live Load
 Lateral Earth Pressure
ABUTMENTS
Abutment
Pile Cap
Piles
REINFORCED EARTH WORK
 Reinforced earth wall is earth retaining structure and provided at
approaches (from road level to bridge level).
 The key components of a Reinforced Earth wall are geo-strips,
granular backfill and precast concrete facing panels.
 The frictional bond between the backfill supports the lateral earth
pressure and stresses induced due to traffic load.
ABUTMENT 01 ABUTMENT 06
LOOP 2 ABUTMENT 07
REINFORCED EARTH WORK
PRE-STRESSED BOX GIRDERS
Bottom View of Box Girder
Piers
 An optimal and most efficient design of beam is box girder. A box girder
consists of enclosed tube with multiple walls.
 The advantage of a box girder is that it better resists torsion. Having
multiple vertical webs, it can also carry more load than an I-shape girder
of equal height.
Pre-stressing Mechanism
SCOPE OF WORK
12/14/2016
Flyover 1
Length 301.5
Piles 80
P. Cap 15
Piers 15
Abt. 2
Spans 10Flyover 2
Length 301.5
Piles 66
P. Cap 11
Piers 12
Abt. 2
Spans 10
Flyover 5
Length 80.05
Piles 38
P. Cap 4
Piers 6
Abt. 2
Spans 3Flyover 3
Length 417.3
Piles 64
P. Cap 15
Piers 13
Abt. 2
Spans 14
Flyover 4
Length 564.41
Piles 84
P. Cap 20
Piers 18
Abt. 2
Spans 18
RWP
LHR
GRW
SKT
Pile= 332 Ramp 3 (L=361.14m) Ramp 6(L=369.39 m) Bridge approaches (841m)
Pile caps=65 Ramp 3A(L=573.11m) Ramp 7(L=369.39 m)
Abutment= 10 Ramp 4( L=379.35m) Loop 1(270.18m) Bridge Lengths(1664m)
Piers=60 Ramp 5 (L=846.94m) Loop 2(L=195.23) Road Length (4660m)
FLYOVER S– 1, 2, 3 & 4
 Piles 100 % Completed (294 out of 294)
 Pile Caps 100 % Completed (62 out of 62)
 Piers 100 % Completed (62 out of 62)
 Abutment 100 % Completed (8 out of 8)
 Box Girders 20% in progress (4 out of 17)
 Reinforce Earth Wall 50 % Completed (0.6 km out of 1.12 km)
 At Grade Roads 60% up to WBM (3 Km out of 5 Km)
RAILWAY BRIDGE
 Piles 100% Completed (38 out of 38)
 Pile Caps 100% Completed (4 out of 4)
 Piers 100% Completed (2 out of 2)
 Transoms 50% Completed (1 out of 2)
 Abutments 50% Completed (1 out of 2)
 Pre-cast Girders 100% Completed (21 out of 21)
PHYSICAL PROGRESS
Year Release Expr. %age Remarks
2014-15 2500 2500 100%
Payment made for land
acquisition.
2015-16 1555 1555 100%
Rs. 400 M land acquisition.
Rs. 215 M shifting of
services.
Rs. 940 M paid to NLC.
2016-17 1000 510 51% Rs. 510 M paid to NLC.
FINANCIAL PROGRESS
Presentation on Flyover at Aziz Cross on GT Road Gujranwala

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
 
WSM and LSM steel structures
WSM and LSM steel structuresWSM and LSM steel structures
WSM and LSM steel structures
 
Bridge foundation
Bridge foundationBridge foundation
Bridge foundation
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
Road Development and Maintenance of Rural Areas
Road Development and Maintenance of Rural AreasRoad Development and Maintenance of Rural Areas
Road Development and Maintenance of Rural Areas
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girder
 
Pavement construction methods
Pavement construction methodsPavement construction methods
Pavement construction methods
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
Lining of tunnel
Lining of tunnelLining of tunnel
Lining of tunnel
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
CBR Test
CBR TestCBR Test
CBR Test
 
Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Presentation1
Presentation1Presentation1
Presentation1
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
pavement-design-ppt.pptx
pavement-design-ppt.pptxpavement-design-ppt.pptx
pavement-design-ppt.pptx
 
Summer traning report BRPNNL by Amit Raj 14CE10005
Summer traning report BRPNNL by Amit Raj 14CE10005Summer traning report BRPNNL by Amit Raj 14CE10005
Summer traning report BRPNNL by Amit Raj 14CE10005
 
Design and analysis of flexible pavement
Design and analysis of flexible pavementDesign and analysis of flexible pavement
Design and analysis of flexible pavement
 
Soil nailing
Soil nailingSoil nailing
Soil nailing
 

Andere mochten auch

JAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITYJAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITY
Ankita Kolamkar
 

Andere mochten auch (20)

Chapter1
Chapter1Chapter1
Chapter1
 
Highway Construction
Highway Construction  Highway Construction
Highway Construction
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
 
LIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEMLIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEM
 
JAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITYJAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITY
 
Seminar on Environmental Impact Assessment
Seminar on Environmental Impact AssessmentSeminar on Environmental Impact Assessment
Seminar on Environmental Impact Assessment
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
Skybus metro as a mode of transportation
Skybus metro as a mode of transportationSkybus metro as a mode of transportation
Skybus metro as a mode of transportation
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar report
 
Recent construction technologies
Recent construction technologiesRecent construction technologies
Recent construction technologies
 
PWD, national highway
PWD, national highwayPWD, national highway
PWD, national highway
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminar
 
Piling of a flyover (AUST 2.2 A)
Piling of a flyover (AUST 2.2 A)Piling of a flyover (AUST 2.2 A)
Piling of a flyover (AUST 2.2 A)
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance ppt
 
Geological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway constructionGeological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway construction
 

Ähnlich wie Presentation on Flyover at Aziz Cross on GT Road Gujranwala

Design Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost AnalysisDesign Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost Analysis
Michael Masi, Jr. Eng.
 

Ähnlich wie Presentation on Flyover at Aziz Cross on GT Road Gujranwala (20)

Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
 Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K... Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K...
Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
 
Saurabhk601
Saurabhk601Saurabhk601
Saurabhk601
 
Floating Bridge
Floating BridgeFloating Bridge
Floating Bridge
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Summer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman NigamSummer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman Nigam
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Design Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost AnalysisDesign Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost Analysis
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed BridgeIRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
 
New mandovi bridge
New mandovi bridgeNew mandovi bridge
New mandovi bridge
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Turga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptxTurga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptx
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
Training PPT
Training PPTTraining PPT
Training PPT
 

Mehr von Rubnawaz Bhatti

Mehr von Rubnawaz Bhatti (12)

BRT.pptx
BRT.pptxBRT.pptx
BRT.pptx
 
Hydro Power Plants of Pakistan
Hydro Power Plants of PakistanHydro Power Plants of Pakistan
Hydro Power Plants of Pakistan
 
Characteristics of effective technical communication
Characteristics of effective technical communicationCharacteristics of effective technical communication
Characteristics of effective technical communication
 
Hydropower plants of pakistan
Hydropower plants of pakistanHydropower plants of pakistan
Hydropower plants of pakistan
 
Seasonal calendar Sindh Pakistan
Seasonal calendar Sindh PakistanSeasonal calendar Sindh Pakistan
Seasonal calendar Sindh Pakistan
 
Rivers of Pakistan
Rivers of PakistanRivers of Pakistan
Rivers of Pakistan
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industry
 
Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)
 
Al bairaj al bait
Al bairaj al bait  Al bairaj al bait
Al bairaj al bait
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic project
 
Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)
 
Religious Extremism in Pakistan
Religious Extremism in PakistanReligious Extremism in Pakistan
Religious Extremism in Pakistan
 

Kürzlich hochgeladen

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 

Kürzlich hochgeladen (20)

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 

Presentation on Flyover at Aziz Cross on GT Road Gujranwala

  • 1. 1
  • 3. February 2012 GOVERNMENT OF THE PUNJAB COMMUNICATION & WORKS DEPARTMENT Construction of Flyover on G.T Road at Aziz Cross Gujranwala
  • 4. February 2012 GOVERNMENT OF THE PUNJAB CONSTRUCTION OF FLYOVER ON G.T ROAD AT AZIZ CROSS GUJRANWALA Construction of Flyover on G.T Road at Aziz Cross Gujranwala
  • 5. SALIENT FEATURE  ADP (2016-17) Gr. Sr. No. 2775  Approved Cost Rs. 6672 Million  Construction Cost Rs. 3435 M  Land Acquisition (80 Kanal) Rs. 2920 M  Miscellaneous Rs. 317 M  Consultant M/s NESPAK  Contract M/s NLC  Client C & W Dept  Agreement Amount Rs.3115 M (9.35% below Est.cost)  Date of Commencement 30.01.2016  Date of Completion 29.11.2016
  • 6. INTRODUCTION  Aziz Cross project is a signal free interchange with partial clover leaf system and two additional directional ramps. Clover leaf interchange Partial Clover leaf interchange with two directional ramps instead of loops
  • 7. INTRODUCTION  There are normally 32 conflicts at any interchange which are completely resolved at Aziz Cross. 32 No. Traffic Conflicts Traffic Count 2014
  • 9. BASIC COMPONENTS OF FLYOVER Bridge cross-section can be divided into two portions. 1. Super Structure This portion receives the live load directly. For example, Box Girder 2. Sub Structure This Portion supports the entire structure and live loads.  Piles  Pile cap  Piers  Abutments Web Web Pier Canopy Pier Shaft Pile Cap Pile Pile Pile Super Structure Sub Structure
  • 10. CONCRETE PILES A pile is a vertical structural element of a deep foundation which transfers super structure loads to the earth farther down from the surface to a subsurface layer.
  • 11.
  • 12.
  • 13.
  • 14. PILE CAP PILE CAP Pile cap is a thick reinforced concrete mat that rests on concrete piles that have been casted into ground. concrete pile cap distributes the load of the superstructure (from piers and abutments into the piles. Pile Cap Piles Pier
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21. PILE CAP AND PIER PIER A pier is a reinforced, raised structure in form of pillars typically supported by well-spaced pile caps. It transfers the loads from deck to pile caps. For this project, special shape of pier is adopted. It as two components 1. Pier Shaft as column 2. Pier Canopy as transom Pier Canopy Pier Shaft Box Girder
  • 22.
  • 23.
  • 24.
  • 25.
  • 26. Abutment refers to the substructure at the ends of a bridge span. It supports;  Super Structure load  Live Load  Lateral Earth Pressure ABUTMENTS Abutment Pile Cap Piles
  • 27.
  • 28.
  • 29.
  • 30. REINFORCED EARTH WORK  Reinforced earth wall is earth retaining structure and provided at approaches (from road level to bridge level).  The key components of a Reinforced Earth wall are geo-strips, granular backfill and precast concrete facing panels.  The frictional bond between the backfill supports the lateral earth pressure and stresses induced due to traffic load.
  • 31. ABUTMENT 01 ABUTMENT 06 LOOP 2 ABUTMENT 07
  • 33. PRE-STRESSED BOX GIRDERS Bottom View of Box Girder Piers  An optimal and most efficient design of beam is box girder. A box girder consists of enclosed tube with multiple walls.  The advantage of a box girder is that it better resists torsion. Having multiple vertical webs, it can also carry more load than an I-shape girder of equal height. Pre-stressing Mechanism
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41. SCOPE OF WORK 12/14/2016 Flyover 1 Length 301.5 Piles 80 P. Cap 15 Piers 15 Abt. 2 Spans 10Flyover 2 Length 301.5 Piles 66 P. Cap 11 Piers 12 Abt. 2 Spans 10 Flyover 5 Length 80.05 Piles 38 P. Cap 4 Piers 6 Abt. 2 Spans 3Flyover 3 Length 417.3 Piles 64 P. Cap 15 Piers 13 Abt. 2 Spans 14 Flyover 4 Length 564.41 Piles 84 P. Cap 20 Piers 18 Abt. 2 Spans 18 RWP LHR GRW SKT Pile= 332 Ramp 3 (L=361.14m) Ramp 6(L=369.39 m) Bridge approaches (841m) Pile caps=65 Ramp 3A(L=573.11m) Ramp 7(L=369.39 m) Abutment= 10 Ramp 4( L=379.35m) Loop 1(270.18m) Bridge Lengths(1664m) Piers=60 Ramp 5 (L=846.94m) Loop 2(L=195.23) Road Length (4660m)
  • 42. FLYOVER S– 1, 2, 3 & 4  Piles 100 % Completed (294 out of 294)  Pile Caps 100 % Completed (62 out of 62)  Piers 100 % Completed (62 out of 62)  Abutment 100 % Completed (8 out of 8)  Box Girders 20% in progress (4 out of 17)  Reinforce Earth Wall 50 % Completed (0.6 km out of 1.12 km)  At Grade Roads 60% up to WBM (3 Km out of 5 Km) RAILWAY BRIDGE  Piles 100% Completed (38 out of 38)  Pile Caps 100% Completed (4 out of 4)  Piers 100% Completed (2 out of 2)  Transoms 50% Completed (1 out of 2)  Abutments 50% Completed (1 out of 2)  Pre-cast Girders 100% Completed (21 out of 21) PHYSICAL PROGRESS
  • 43. Year Release Expr. %age Remarks 2014-15 2500 2500 100% Payment made for land acquisition. 2015-16 1555 1555 100% Rs. 400 M land acquisition. Rs. 215 M shifting of services. Rs. 940 M paid to NLC. 2016-17 1000 510 51% Rs. 510 M paid to NLC. FINANCIAL PROGRESS