© POSEIDON WATER 2015 1
Seawater Desalination Project
at Huntington Beach
Local, Drought-Proof Source of Drinking Water
For Orange County
American Society of Civil Engineers
April 28, 2016
© POSEIDON WATER 2015 2
Poseidon at a Glance
 Founded in 1995 to develop water infrastructure projects through a Public-Private
Partnership approach
 Use best available technology in an environmentally sensitive way
 Senior management team has collectively developed, financed and constructed over
$10bn in infrastructure projects
 Primary focus on seawater desalination project development but, with experience in
other water treatment project opportunities
 Headquartered in Boston, MA with regional offices in California, Florida and Texas
Leading water infrastructure developer and manager with significant experience partnering
with water agencies to deliver essential water infrastructure projects
© POSEIDON WATER 2015 3
Future 2035 OCWD Water Supply Sources
Total Water Demand 515,000 af/y without desalination
SAR Baseflows,
100,000, 19%
SAR Stormflows,
70,000, 14%
Natural Incidental
Recharge, 60,000,
12%
GWRS including
Final Expansion,
130,000, 25%
Misc, 25,000, 5%
Imported Water,
130,000, 25%
Orange County Water District
Water Issues Committee
July 17, 2013
© POSEIDON WATER 2015 4
Future 2035 OCWD Water Supply Sources
Total Water Demand 515,000 af/y with desalination
SAR Baseflows,
100,000, 19%
SAR Stormflows,
70,000, 14%
Natural Incidental
Recharge, 60,000,
12%
GWRS including
Final Expansion,
130,000, 25%
Misc, 25,000, 5%
Imported Water,
74,000, 14%
Ocean Desalination,
56,000, 11%
Orange County Water District
Water Issues Committee
July 17, 2013
© POSEIDON WATER 2015 5
Huntington Beach Site Existing
© POSEIDON WATER 2015 6
Huntington Beach Desalination Project
© POSEIDON WATER 2015 7
Huntington Beach Desalination Project
© POSEIDON WATER 2015 8
Permitting Status
Local Land Use
Permits:
EIR Certified – Sept 2005
SEIR Certified – Sept 2010
HB Conditional Use Permit – Feb 2006/10
HB Coastal Development Permit- Feb 2006/10
NPDES Permit Permit Issued –Aug 2006
Permit Renewed – Feb 2012
Department of Public
Health Services
Conceptual Approval –
August 2002
State Lands
Commission
Lease for Intake and Discharge Piping –
Approved - October 2010
California Coastal
Commission
Coastal Development Permit – Pending
© POSEIDON WATER 2015 9
Intake Technology
• Non-swimming Planktonic
organisms (i.e., fish eggs)
need to float within 15-yards
of the intake to be at risk of
entrainment.
© POSEIDON WATER 2015 10
Minimizing Fish Egg Entrainment
• Less than two plankton will be
entrained per 1,000 gallons of
seawater withdrawn. This
equates to roughly 0.03% of
the plankton in the source
water.
© POSEIDON WATER 2015 11
Discharge Technology
• The elevated salinity levels in the concentrated seawater discharged by the
desalination plant comply with state regulations and will not impact water
quality or marine life.
• There are over 15,000 desalination plants operating around the world today.
Studies and data from these plants show the concentrated seawater is being
diluted without impacts to marine life or the ecology.
© POSEIDON WATER 2015 12
WHAT IS A SEAFLOOR INFILTRATION GALLERY?
© POSEIDON WATER 2015 13
CONCEPTUAL DESIGN - LOCATION
Water Depth at Gallery:
Approx. 40’ Deep
Distance Offshore:
Approx. 2, 500 LF
© POSEIDON WATER 2015 14
CONSTRUCTION HIGHLIGHTS
© POSEIDON WATER 2015 15
SIG vs. Screened Intake Pipe
SIG Existing Pipe
Construction Time 7 years 1 year
Construction Cost $1.5 billion $0
Seafloor Excavation 500,000 cubic yards 0 cubic yards
Seafloor habitat 30 acres removed 0 acres removed
Impact on Public
Beach Access
Yes No
Increased GHG Yes No
Environmental
Impacts at the Beach
Yes No
Impingement of Fish No No
Entrainment of
Microscopic Fish Eggs
No Yes – 2 per 1,000
gallons
© POSEIDON WATER 2015 16
Commitment to Carbon Neutrality and GHG Reduction
 Clean Air: The Reverse Osmosis process produces no
greenhouse gases
 Renewable Power: Poseidon is exploring powering
project with 100% green power
 Energy Minimization and GHG Reduction Plan: If green
power cannot be procured, Poseidon will purchase carbon
offsets to make the project carbon neutral
© POSEIDON WATER 2015 17
Project Risk Allocation – Original Proposal
Risk Description Poseidon OCWD
Permitting
Project Financing
Construction
Interest Rate
Change in Law
Technology
Water Demand
Operations & Maintenance
Efficiency and cost basis Inflation
Pipeline Distribution System
Electricity Consumption & Price
Consumption Pricing
© POSEIDON WATER 2015 18
Risk Allocation – Staff Negotiated Term Sheet
Risk Description Poseidon OCWD
Permitting
Project Financing
Construction
Interest Rate
Change in Law
Technology
Water Demand
Operations & Maintenance
Pipeline Distribution System
Electricity Consumption & Price
© POSEIDON WATER 2015 19
Key Term Sheet Issues
 Linking price of desalinated water to
avoided cost of MWD
 50-year contract term
 Pricing adjustment at year 15
 Substantially all financial risks are
Poseidon’s responsibility
© POSEIDON WATER 2015 20
Project Progress
• Orange County Water District approved term sheet
‒ May 14, 2015
• Independent review process of subsurface intakes
‒ Two year process concluded / SIG determined “infeasible”
• Coastal Commission Development Permit application
pending
• Coastal Commission Hearing
‒ July 2016
• OCWD / Poseidon Water Reliability Agreement
‒ Q3 / Q4 2016
© POSEIDON WATER 2015 21
Carlsbad Project
© POSEIDON WATER 2015 22
Carlsbad Project – Dedication Ceremony – 12/15/15
© POSEIDON WATER 2015 23
Seawater Desalination Project
at Huntington Beach
Local, Drought-Proof Source of Drinking Water
For Orange County
American Society of Civil Engineers
April 28, 2016

Weitere ähnliche Inhalte

Was ist angesagt?

TWCA Annual Convention: Regional Wastewater management Stakeholder Process, C...
TWCA Annual Convention: Regional Wastewater management Stakeholder Process, C...TWCA Annual Convention: Regional Wastewater management Stakeholder Process, C...
TWCA Annual Convention: Regional Wastewater management Stakeholder Process, C...
TWCA
 
Desalination & membrane technologies 2015...dr. nicole carter
Desalination & membrane technologies 2015...dr. nicole carterDesalination & membrane technologies 2015...dr. nicole carter
Desalination & membrane technologies 2015...dr. nicole carter
Jeffrey Pickett
 
TWCA Annual Convention: GCD's Role in Protection of Water Quality, Bill Dugat...
TWCA Annual Convention: GCD's Role in Protection of Water Quality, Bill Dugat...TWCA Annual Convention: GCD's Role in Protection of Water Quality, Bill Dugat...
TWCA Annual Convention: GCD's Role in Protection of Water Quality, Bill Dugat...
TWCA
 
Amr fadlelmawla desalination-kuwait (1)
Amr fadlelmawla desalination-kuwait (1)Amr fadlelmawla desalination-kuwait (1)
Amr fadlelmawla desalination-kuwait (1)
Nidaa Majali
 
Beneficialuses produced-water
Beneficialuses produced-waterBeneficialuses produced-water
Beneficialuses produced-water
Mohanned Mahjoup
 

Was ist angesagt? (20)

Produced Water | Session XII - A. Judson Hill
Produced Water | Session XII -  A. Judson HillProduced Water | Session XII -  A. Judson Hill
Produced Water | Session XII - A. Judson Hill
 
TWCA Annual Convention: Regional Wastewater management Stakeholder Process, C...
TWCA Annual Convention: Regional Wastewater management Stakeholder Process, C...TWCA Annual Convention: Regional Wastewater management Stakeholder Process, C...
TWCA Annual Convention: Regional Wastewater management Stakeholder Process, C...
 
WHCRWA 2013 Town Hall
WHCRWA 2013 Town HallWHCRWA 2013 Town Hall
WHCRWA 2013 Town Hall
 
Produced Water | Session XI - Alleman
Produced Water | Session XI - AllemanProduced Water | Session XI - Alleman
Produced Water | Session XI - Alleman
 
Comp Plan 2020 Public Input Summary
Comp Plan 2020 Public Input SummaryComp Plan 2020 Public Input Summary
Comp Plan 2020 Public Input Summary
 
Desalination & membrane technologies 2015...dr. nicole carter
Desalination & membrane technologies 2015...dr. nicole carterDesalination & membrane technologies 2015...dr. nicole carter
Desalination & membrane technologies 2015...dr. nicole carter
 
TWCA Annual Convention: GCD's Role in Protection of Water Quality, Bill Dugat...
TWCA Annual Convention: GCD's Role in Protection of Water Quality, Bill Dugat...TWCA Annual Convention: GCD's Role in Protection of Water Quality, Bill Dugat...
TWCA Annual Convention: GCD's Role in Protection of Water Quality, Bill Dugat...
 
Texas water report
Texas water reportTexas water report
Texas water report
 
Signpost Seminar: Water quality - national problems, local solutions
Signpost Seminar: Water quality - national problems, local solutionsSignpost Seminar: Water quality - national problems, local solutions
Signpost Seminar: Water quality - national problems, local solutions
 
Formal Technical Report
Formal Technical ReportFormal Technical Report
Formal Technical Report
 
Amr fadlelmawla desalination-kuwait (1)
Amr fadlelmawla desalination-kuwait (1)Amr fadlelmawla desalination-kuwait (1)
Amr fadlelmawla desalination-kuwait (1)
 
Bay-Delta Activities Update
Bay-Delta Activities UpdateBay-Delta Activities Update
Bay-Delta Activities Update
 
Bay Delta Overview - March 28, 2013
Bay Delta Overview - March 28, 2013Bay Delta Overview - March 28, 2013
Bay Delta Overview - March 28, 2013
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
T4: GROUNDWATER MANAGEMENT AND WATER GOVERNANCE THE EGYPTIAN EXPERIENCE
T4: GROUNDWATER MANAGEMENT AND WATER GOVERNANCETHE EGYPTIAN EXPERIENCET4: GROUNDWATER MANAGEMENT AND WATER GOVERNANCETHE EGYPTIAN EXPERIENCE
T4: GROUNDWATER MANAGEMENT AND WATER GOVERNANCE THE EGYPTIAN EXPERIENCE
 
Aggregateact 120611192330-phpapp02
Aggregateact 120611192330-phpapp02Aggregateact 120611192330-phpapp02
Aggregateact 120611192330-phpapp02
 
2015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 20152015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 2015
 
Beneficialuses produced-water
Beneficialuses produced-waterBeneficialuses produced-water
Beneficialuses produced-water
 
1. The state of Ireland's water environment - Micheal Lehane, EPA
1. The state of Ireland's water environment - Micheal Lehane, EPA1. The state of Ireland's water environment - Micheal Lehane, EPA
1. The state of Ireland's water environment - Micheal Lehane, EPA
 
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
 

Andere mochten auch

Efectos del entrenamiento de fuerza sobre la resistencia aeróbica y la capaci...
Efectos del entrenamiento de fuerza sobre la resistencia aeróbica y la capaci...Efectos del entrenamiento de fuerza sobre la resistencia aeróbica y la capaci...
Efectos del entrenamiento de fuerza sobre la resistencia aeróbica y la capaci...
Alejandra Fuentes Soriano
 
Letra pronunciación numeros y alfabeto
Letra pronunciación numeros y alfabetoLetra pronunciación numeros y alfabeto
Letra pronunciación numeros y alfabeto
roly0497
 
PRMG final Certificate
PRMG final CertificatePRMG final Certificate
PRMG final Certificate
Islam Nour
 

Andere mochten auch (19)

RBJ resumé
RBJ resuméRBJ resumé
RBJ resumé
 
Laporan prakytikum kimia anorganik
Laporan prakytikum kimia anorganikLaporan prakytikum kimia anorganik
Laporan prakytikum kimia anorganik
 
Laura rodriguez-gutierrez trabajo2
Laura rodriguez-gutierrez trabajo2Laura rodriguez-gutierrez trabajo2
Laura rodriguez-gutierrez trabajo2
 
2016 1 ebm_mrps
2016 1 ebm_mrps2016 1 ebm_mrps
2016 1 ebm_mrps
 
2016 1_ebm_base histórica e científica_3
2016 1_ebm_base histórica e científica_32016 1_ebm_base histórica e científica_3
2016 1_ebm_base histórica e científica_3
 
Guy birthday's gift (vietnamese)
Guy birthday's gift (vietnamese)Guy birthday's gift (vietnamese)
Guy birthday's gift (vietnamese)
 
Ed Batista, The Art of Self-Coaching @StanfordBiz, Class 5: Resilience
Ed Batista, The Art of Self-Coaching @StanfordBiz, Class 5: ResilienceEd Batista, The Art of Self-Coaching @StanfordBiz, Class 5: Resilience
Ed Batista, The Art of Self-Coaching @StanfordBiz, Class 5: Resilience
 
Plan de monitoreo simon bolivar 2016
Plan de monitoreo simon bolivar 2016Plan de monitoreo simon bolivar 2016
Plan de monitoreo simon bolivar 2016
 
Final Image Evaluation: Left Lateral Lumbar Spine
Final Image Evaluation: Left Lateral Lumbar SpineFinal Image Evaluation: Left Lateral Lumbar Spine
Final Image Evaluation: Left Lateral Lumbar Spine
 
Fisiología del ejercicio físico
Fisiología del ejercicio físicoFisiología del ejercicio físico
Fisiología del ejercicio físico
 
Efectos del entrenamiento de fuerza sobre la resistencia aeróbica y la capaci...
Efectos del entrenamiento de fuerza sobre la resistencia aeróbica y la capaci...Efectos del entrenamiento de fuerza sobre la resistencia aeróbica y la capaci...
Efectos del entrenamiento de fuerza sobre la resistencia aeróbica y la capaci...
 
Vendaje neuromuscular revista scielo
Vendaje neuromuscular revista scieloVendaje neuromuscular revista scielo
Vendaje neuromuscular revista scielo
 
Paradigma positivista
Paradigma positivistaParadigma positivista
Paradigma positivista
 
Manual E-PRANCE 0805 DashCam
Manual E-PRANCE 0805 DashCamManual E-PRANCE 0805 DashCam
Manual E-PRANCE 0805 DashCam
 
ASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
ASCE Seawater Desalination Project at Huntington Beach - Poseidon WaterASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
ASCE Seawater Desalination Project at Huntington Beach - Poseidon Water
 
Jayaho kuchipudi progress oct 3
Jayaho kuchipudi progress oct 3Jayaho kuchipudi progress oct 3
Jayaho kuchipudi progress oct 3
 
Letra pronunciación numeros y alfabeto
Letra pronunciación numeros y alfabetoLetra pronunciación numeros y alfabeto
Letra pronunciación numeros y alfabeto
 
PRMG final Certificate
PRMG final CertificatePRMG final Certificate
PRMG final Certificate
 
Resume
ResumeResume
Resume
 

Ähnlich wie Power point asce seawater desal project hb

_SCWD_FactSheet_051716
_SCWD_FactSheet_051716_SCWD_FactSheet_051716
_SCWD_FactSheet_051716
Sonja Morgan
 
Water Conservation In Citrus County Florida
Water Conservation In Citrus County FloridaWater Conservation In Citrus County Florida
Water Conservation In Citrus County Florida
brentmwhite
 
PBL_Civil_Engineering.pdf
PBL_Civil_Engineering.pdfPBL_Civil_Engineering.pdf
PBL_Civil_Engineering.pdf
DurgaSharma21
 
Writing Sample - Draft EIR
Writing Sample - Draft EIRWriting Sample - Draft EIR
Writing Sample - Draft EIR
Sharanya Ganesh
 
PADPIE Analysis LINAW Project.pptx
PADPIE Analysis LINAW Project.pptxPADPIE Analysis LINAW Project.pptx
PADPIE Analysis LINAW Project.pptx
AVAbraham1
 

Ähnlich wie Power point asce seawater desal project hb (20)

_SCWD_FactSheet_051716
_SCWD_FactSheet_051716_SCWD_FactSheet_051716
_SCWD_FactSheet_051716
 
10. CaBA Conference 2017 United Utilities and CaBA - Glynn Haworth uu ca ba s...
10. CaBA Conference 2017 United Utilities and CaBA - Glynn Haworth uu ca ba s...10. CaBA Conference 2017 United Utilities and CaBA - Glynn Haworth uu ca ba s...
10. CaBA Conference 2017 United Utilities and CaBA - Glynn Haworth uu ca ba s...
 
Water Conservation In Citrus County Florida
Water Conservation In Citrus County FloridaWater Conservation In Citrus County Florida
Water Conservation In Citrus County Florida
 
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
9/9 FRI 11:00 | Water Woes, Cash Flow Woes & Future Growth
 
Helen Davies
Helen DaviesHelen Davies
Helen Davies
 
Carlsbad Desalination Project Report o October 2012 Public Workshops - Oct. 2...
Carlsbad Desalination Project Report o October 2012 Public Workshops - Oct. 2...Carlsbad Desalination Project Report o October 2012 Public Workshops - Oct. 2...
Carlsbad Desalination Project Report o October 2012 Public Workshops - Oct. 2...
 
Port lavaca desalination study
Port lavaca desalination studyPort lavaca desalination study
Port lavaca desalination study
 
PBL_Civil_Engineering.pdf
PBL_Civil_Engineering.pdfPBL_Civil_Engineering.pdf
PBL_Civil_Engineering.pdf
 
Design of water supply system for a G+12 residential building by water neutra...
Design of water supply system for a G+12 residential building by water neutra...Design of water supply system for a G+12 residential building by water neutra...
Design of water supply system for a G+12 residential building by water neutra...
 
Writing Sample - Draft EIR
Writing Sample - Draft EIRWriting Sample - Draft EIR
Writing Sample - Draft EIR
 
Presentations_LAC water beam_TNC_Sep16_2013
Presentations_LAC water beam_TNC_Sep16_2013Presentations_LAC water beam_TNC_Sep16_2013
Presentations_LAC water beam_TNC_Sep16_2013
 
The Rivers Trust Autumn Conference: Day 2 - Session 1
The Rivers Trust Autumn Conference: Day 2 - Session 1The Rivers Trust Autumn Conference: Day 2 - Session 1
The Rivers Trust Autumn Conference: Day 2 - Session 1
 
Bay-Delta Conservation Plan: Review Update - August 22, 2013
Bay-Delta Conservation Plan: Review Update - August 22, 2013Bay-Delta Conservation Plan: Review Update - August 22, 2013
Bay-Delta Conservation Plan: Review Update - August 22, 2013
 
PADPIE Analysis LINAW Project.pptx
PADPIE Analysis LINAW Project.pptxPADPIE Analysis LINAW Project.pptx
PADPIE Analysis LINAW Project.pptx
 
Ccws Brochure April 10
Ccws Brochure April 10Ccws Brochure April 10
Ccws Brochure April 10
 
SHAC Water Conservation - Maggie Lawton
SHAC Water Conservation - Maggie LawtonSHAC Water Conservation - Maggie Lawton
SHAC Water Conservation - Maggie Lawton
 
Orange County Water Authority - Watershed Design Guide
Orange County Water Authority - Watershed Design GuideOrange County Water Authority - Watershed Design Guide
Orange County Water Authority - Watershed Design Guide
 
John Nemeth, Richmond Hill - Water & Cities
John Nemeth, Richmond Hill - Water & CitiesJohn Nemeth, Richmond Hill - Water & Cities
John Nemeth, Richmond Hill - Water & Cities
 
WRT CaBA/CRF Conference 02/12/14 - David Baxter
WRT CaBA/CRF Conference 02/12/14 - David BaxterWRT CaBA/CRF Conference 02/12/14 - David Baxter
WRT CaBA/CRF Conference 02/12/14 - David Baxter
 
Neptune FS Global Overview
Neptune FS Global OverviewNeptune FS Global Overview
Neptune FS Global Overview
 

Kürzlich hochgeladen

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Kürzlich hochgeladen (20)

Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 

Power point asce seawater desal project hb

  • 1. © POSEIDON WATER 2015 1 Seawater Desalination Project at Huntington Beach Local, Drought-Proof Source of Drinking Water For Orange County American Society of Civil Engineers April 28, 2016
  • 2. © POSEIDON WATER 2015 2 Poseidon at a Glance  Founded in 1995 to develop water infrastructure projects through a Public-Private Partnership approach  Use best available technology in an environmentally sensitive way  Senior management team has collectively developed, financed and constructed over $10bn in infrastructure projects  Primary focus on seawater desalination project development but, with experience in other water treatment project opportunities  Headquartered in Boston, MA with regional offices in California, Florida and Texas Leading water infrastructure developer and manager with significant experience partnering with water agencies to deliver essential water infrastructure projects
  • 3. © POSEIDON WATER 2015 3 Future 2035 OCWD Water Supply Sources Total Water Demand 515,000 af/y without desalination SAR Baseflows, 100,000, 19% SAR Stormflows, 70,000, 14% Natural Incidental Recharge, 60,000, 12% GWRS including Final Expansion, 130,000, 25% Misc, 25,000, 5% Imported Water, 130,000, 25% Orange County Water District Water Issues Committee July 17, 2013
  • 4. © POSEIDON WATER 2015 4 Future 2035 OCWD Water Supply Sources Total Water Demand 515,000 af/y with desalination SAR Baseflows, 100,000, 19% SAR Stormflows, 70,000, 14% Natural Incidental Recharge, 60,000, 12% GWRS including Final Expansion, 130,000, 25% Misc, 25,000, 5% Imported Water, 74,000, 14% Ocean Desalination, 56,000, 11% Orange County Water District Water Issues Committee July 17, 2013
  • 5. © POSEIDON WATER 2015 5 Huntington Beach Site Existing
  • 6. © POSEIDON WATER 2015 6 Huntington Beach Desalination Project
  • 7. © POSEIDON WATER 2015 7 Huntington Beach Desalination Project
  • 8. © POSEIDON WATER 2015 8 Permitting Status Local Land Use Permits: EIR Certified – Sept 2005 SEIR Certified – Sept 2010 HB Conditional Use Permit – Feb 2006/10 HB Coastal Development Permit- Feb 2006/10 NPDES Permit Permit Issued –Aug 2006 Permit Renewed – Feb 2012 Department of Public Health Services Conceptual Approval – August 2002 State Lands Commission Lease for Intake and Discharge Piping – Approved - October 2010 California Coastal Commission Coastal Development Permit – Pending
  • 9. © POSEIDON WATER 2015 9 Intake Technology • Non-swimming Planktonic organisms (i.e., fish eggs) need to float within 15-yards of the intake to be at risk of entrainment.
  • 10. © POSEIDON WATER 2015 10 Minimizing Fish Egg Entrainment • Less than two plankton will be entrained per 1,000 gallons of seawater withdrawn. This equates to roughly 0.03% of the plankton in the source water.
  • 11. © POSEIDON WATER 2015 11 Discharge Technology • The elevated salinity levels in the concentrated seawater discharged by the desalination plant comply with state regulations and will not impact water quality or marine life. • There are over 15,000 desalination plants operating around the world today. Studies and data from these plants show the concentrated seawater is being diluted without impacts to marine life or the ecology.
  • 12. © POSEIDON WATER 2015 12 WHAT IS A SEAFLOOR INFILTRATION GALLERY?
  • 13. © POSEIDON WATER 2015 13 CONCEPTUAL DESIGN - LOCATION Water Depth at Gallery: Approx. 40’ Deep Distance Offshore: Approx. 2, 500 LF
  • 14. © POSEIDON WATER 2015 14 CONSTRUCTION HIGHLIGHTS
  • 15. © POSEIDON WATER 2015 15 SIG vs. Screened Intake Pipe SIG Existing Pipe Construction Time 7 years 1 year Construction Cost $1.5 billion $0 Seafloor Excavation 500,000 cubic yards 0 cubic yards Seafloor habitat 30 acres removed 0 acres removed Impact on Public Beach Access Yes No Increased GHG Yes No Environmental Impacts at the Beach Yes No Impingement of Fish No No Entrainment of Microscopic Fish Eggs No Yes – 2 per 1,000 gallons
  • 16. © POSEIDON WATER 2015 16 Commitment to Carbon Neutrality and GHG Reduction  Clean Air: The Reverse Osmosis process produces no greenhouse gases  Renewable Power: Poseidon is exploring powering project with 100% green power  Energy Minimization and GHG Reduction Plan: If green power cannot be procured, Poseidon will purchase carbon offsets to make the project carbon neutral
  • 17. © POSEIDON WATER 2015 17 Project Risk Allocation – Original Proposal Risk Description Poseidon OCWD Permitting Project Financing Construction Interest Rate Change in Law Technology Water Demand Operations & Maintenance Efficiency and cost basis Inflation Pipeline Distribution System Electricity Consumption & Price Consumption Pricing
  • 18. © POSEIDON WATER 2015 18 Risk Allocation – Staff Negotiated Term Sheet Risk Description Poseidon OCWD Permitting Project Financing Construction Interest Rate Change in Law Technology Water Demand Operations & Maintenance Pipeline Distribution System Electricity Consumption & Price
  • 19. © POSEIDON WATER 2015 19 Key Term Sheet Issues  Linking price of desalinated water to avoided cost of MWD  50-year contract term  Pricing adjustment at year 15  Substantially all financial risks are Poseidon’s responsibility
  • 20. © POSEIDON WATER 2015 20 Project Progress • Orange County Water District approved term sheet ‒ May 14, 2015 • Independent review process of subsurface intakes ‒ Two year process concluded / SIG determined “infeasible” • Coastal Commission Development Permit application pending • Coastal Commission Hearing ‒ July 2016 • OCWD / Poseidon Water Reliability Agreement ‒ Q3 / Q4 2016
  • 21. © POSEIDON WATER 2015 21 Carlsbad Project
  • 22. © POSEIDON WATER 2015 22 Carlsbad Project – Dedication Ceremony – 12/15/15
  • 23. © POSEIDON WATER 2015 23 Seawater Desalination Project at Huntington Beach Local, Drought-Proof Source of Drinking Water For Orange County American Society of Civil Engineers April 28, 2016