2. How do you address These Issues? Visibility into the planned and current project status Material availability / engineering drawing production Cost to complete Information management Reactive construction management Productivity of field labor 2 | WWW.BENTLEY.COM
4. Workface Planning Workface Planning is the process of organizing and delivering all the elements necessary, before work is started, to enable craft persons to perform quality work in a safe, effective and efficient manner. COAA Best Practice 4 | WWW.BENTLEY.COM
5. Crew Productivity Tool Time on large construction projects is typically quite low: 31 to 40% This number is largely due to resource-related issues. Approx 32% of crew’s time is spent waiting or idle COAA WFP Slide 5 | WWW.BENTLEY.COM
8. Construction Automation Why isn’t everybody doing Workface Planning? Manual MTOs and Level 5 Work Packs are extremely labor/time intensive and tedious Management of Change at the component / spool level can be a mind boggling nightmare for even the most experienced constructor Need a construction automation tool that integrates our various project IT systems (3D CAD, ISOs, Eng Lists, MMS, project controls, Primavera, etc) into an virtual construction model that is constantly kept up to date to facilitate and automate WorkFace Planning ConstructSim V8i Solves these issues and is the leading workface planning automation tool on the market today 7 | WWW.BENTLEY.COM
25. WFP Automation Bring your data together in one location Instrument Index Cable Schedule CAD Model Fabricator Status Erection Drawings Project Controls Primavera Hydro Test Plan Pipe isometrics Line Lists Equipment Lists T/O Systems MMS In/out EH&S Assessment ConstructSim V8i 11 | WWW.BENTLEY.COM
33. Early Construction Planning Construction Work Areas (CWAs) and Construction Work Packages (CWPs) are built in ConstructSim and organized by the schedule WBS
34. Streamline Materials Visualize Materials OnSite Track Purchase Orders / ETAs Drive Trial Allocation Priorities Bag-and-Tag By Work Pack
40. Target Date: 28-Feb-2009 CWA 01 – Lower Deck Overall View Full Materials Partial Materials No Materials
41. Levels of Planning & Scheduling L3 - Schedule Activity Example – A/G Piping Field Installation – Area 3A ConstructSim “Auto-links” Model Components to L3 Activities By Attribute Matching Rules L4 – Crew Work Packs Example – One “shift” of work (~1-2 weeks), includes scope identified with associated L5 tasks Work face planner “Builds”optimal path of construction using ConstructSim L5 - Tasks Example – Spool 101-A Erect, Fit-Up, Connect ConstructSim “Auto-Generates” L5 Tasks from Template “Rules of Progress” 18 | WWW.BENTLEY.COM
65. If you would like more information contact: Robin M. Mikaelsson Senior Work Process Consultant Bentley Systems +1 587 777 0407 Robin.Mikaelsson@Bentley.com Thank You! Eric Crivella Plant Construction Executive Bentley +1 713 249 4407 Eric.crivella@Bentley.com 34 | WWW.BENTLEY.COM
Hinweis der Redaktion
Hi I am … me!Today I am going to present ConstrucSim. ConstructSim is one of the portfolio of tools from Bentley for users in the global infrastructure community. ConstructSim is a pioneering application in the use of virtual models for construction.
Introducing ConstructSim – say it!ConstructSim is revolutionary system that provides a dynamic planning environment to address the nature of a wicked problem. ConstructSim can be used by various stakeholders on a project … ranging from contractors in a direct hire mode, to construction management and even by owner operators.ConstructSim can also be used across multiple phases of the project … from early interactive planning sessions prior to construction, through execution field level crew work packages … and into systems turnover and completions. and methodology to manage a construction effort within a virtual construction model. It can be used on all types of projects by the owner/operator, CM, direct hire and on many different types of projects regardless of the size. construction planning. throughout the project … all the way on a project from early planning, to The initial focus market has been on large industrial projects, but we are in the process of expanding the tool for use in the civil, commercial building and manufacturing segments.