Goals
• Understand the goals and scope of estimation
• Study estimation approaches
• Learn and compare some estimation techniques
• Understand applicability for specific techniques
• Review common estimation mistakes
• Study of the effects of large scale projects on estimates
• Share practical experience in estimation
Scope: classical estimation techniques
3
What is necessary to make estimations?
• Software requirements
• Time for estimation
• Team of software experts to make estimations
• Subject matter experts to clarify the requirements
• Knowledge base for implementation approaches and required effort
• Information about special conditions (team size, technologies, client-specific)
Start when you are ready
4
Expected result
• Scope to be implemented
• Total effort to be spent to implement the project
• Project budget
• Project schedule
– Project decomposition
– Project and key stages’ duration
• Staffing plan
• Risk management plan
• Assumptions
It is all about resources
5
Need to be clarified
• Product requirements
– Functional requirements
– Non-functional requirements (performance, stability, scalability, and etc.)
– Production, testing and etc. environments
• Project requirements
– Technologies
– Business trip policy
– Support policy
6
Effective estimations
• Define estimation subject. What you are going to estimate?
• Make decomposition and work breakdown structure (WBS)
– Divide until you have easy explainable tasks with obvious implementation
– Keep breakdown hierarchy
– Add dependencies
• Use historical data and gathered experience
• Use several experts
• Make tasks clustering and average estimates
• Take into account real productivity of your team
Divide and empire
7
Good questions
• Explain in one sentence what have to be done?
• How this will be used? Who are the end users?
• What is the value? Can we drop this?
• What is the similar feature we have implemented/estimated before?
• What is the effort for implementation and what is estimated duration?
• What can be done to make this two times faster, cheaper?
• What can be done to parallelize work on this task? What pros and cons will be?
• What is the easiest way to implement this feature?
• What dependencies do we have from and to other tasks?
• Who can do this work? What experience is necessary?
• What environment for this task is assumed?
• What are the risks? How they can be mitigated?
• What is permanent and what can vary in the feature?
Communicate!
8
Typical mistakes
• Differences in definition of done
• Incomplete requirements
• Lack of time for clarification and making more precise estimation
• Unawareness of time factor for large systems (they are grown, not built)
• Mistakes in decomposition
• Loosing significant details or parts of functionality
• Neglect of communication delays (with customer, experts, and etc.)
• Team size is not taken into account (internal communications and other aspects)
• Lack of specific knowledge (business area or technology)
• Misconception of required and estimated delivery
• Ignoring cost of support produced code and data
• Ignoring risks
• Cognitive biases
You have to care about many things
9
Cognitive biases
• We do not examine every possible option or every scrap of data before we make a
decision
• We adopt certain rules of thumb and take other shortcuts when we make choices
• In some cases, our cognitive limitations lead to poor estimations
• Cognitive biases
– Overconfidence
– Sunk-cost effect
– Availability bias (recency effect)
– Confirmation bias
– Anchoring bias
– Illusory correlation
– Hindsight bias
Praemonitus, praemunitus
10
Classification of project estimations
• By type of estimation
– Product metrics
– Effort estimation
– Duration estimation
• By goals
– Commercial offer
– Forecast and planning
• By techniques
– By historical model
– Expert methods
– Parametric
What is your goal?
11
Estimation techniques
• Historical model usage
• Expert methods
– Three point estimation
– Delphi
– Wideband Delphi
– Planning poker
• Parametric methods
– Proxy-based estimation (PROBE)
– Function point
– Use case point
– Weighted Micro Function Points
What is your approach?
12
Basic steps: summary
• Decomposition
• Discovering dependencies
• Identification of experts for every specific area
• Gathering and clarifying requirements
• Analysis for applicability of existing solutions and technologies
• Estimating by expert
• Tracking reasoning and assumptions for decisions
• Identifications of risks
• Getting summary estimation for task
• Comparison with other tasks’ estimations
• Making summary estimation
Always have a checklist
13
Three point estimation
• Task estimation based on three values
– Optimistic (O)
– Most likely or normal (M)
– Pessimistic (P)
• Double triangular distribution is used
S = 0.5 S = 0.5
MO P
14
Three point estimation: math
Expected time 𝐸 =
𝑂 + 4 × 𝑀 + 𝑃
6
Standard deviation S𝐷 =
𝑃 − 𝑂
6
Project time 𝑃𝐸 = 𝐸
Project standard deviation 𝑃𝑆𝐷 = 𝑆𝐷2
Assumption: All project’s tasks are consecutive.
15
Three point estimation: confidence level
Confidence level Standard deviation
68 % SD
90 % 1.645 x SD
95 % 2 x SD
99.7 % 3 x SD
Note: Information systems typically use the 90% confidence level for all project and task estimates.
16
Three point estimation: example
Tasks O M P E SD
Task 1 1 3 8 1+4×3+8
6
= 3.5
8−1
6
= 1.17
Task 2 2 5 20 2+4×5+20
6
= 7
20−2
6
= 3
Confidence
68 %
(E ± SD )
90 %
(E ± 1.645*SD)
95 %
(E ± 2 *SD)
99.7 %
(E ± 3*SD)
Task 1 3.5 ± 1.17=> 2.33 to 4.66 1.58 to 5.42 1.17 to 5.83 1 𝑡𝑜 7
Task 2 7 ± 3 => 4 to 10 2.06 to 11.93 2 to 9 2 𝑡𝑜 16
𝑃𝑆𝐷 = 1.172 + 32 =3.22𝑃𝐸 = 𝐸1 + 𝐸2 = 10.5
Project (consecutive tasks):
17
Delphi method: estimation matrix
Expert 1 Expert 2 Expert 3 Average
Task 1 Attempt 1
Attempt 2
Attempt 3
10
10
11
5
8
10
20
15
12
11.7
11
11
Task 2 Attempt 1
Attempt 2
Attempt 3
15
16
18
30
20
18
8
20
19
17.7
18.7
18.3
Task 3 Attempt 1
Attempt 2
Attempt 3
11
10
8
4
5
6
6
7
7
7
7.3
7
• Decomposition into tasks
• Anonymous estimation
• Announcement of average estimation as well as reasons for them
• Transition to next estimation iteration
18
Delphi method: features and applicability
• Strengths
– Works well for ambiguity
– Lead to joint agreement and corporate liability
– Easy to adopt to time restrictions
– Anonymous estimations eliminate authority influence
– Assumptions are documented, discussed and agreed
• Weaknesses
– There is no formal reasoning for estimation. As a result there is no formal reasoning
for customer
– Decomposition rules are not defined
– Some creative ideas can be lost since majority opinion is prevail
– It is possible that people will agree with other’s estimate without cogitation
– Need to have at least 4 experts
19
Wideband Delphi method
Involves greater interaction and more communication between participants
Execution steps
1. Coordinator presents each expert with a specification and an estimation form.
2. Coordinator calls a group meeting in which the experts discuss estimation issues
with the coordinator and each other.
3. Experts fill out forms anonymously.
4. Coordinator prepares and distributes a summary of the estimates
5. Coordinator calls a group meeting, specifically focusing on having the experts
discuss points where their estimates vary widely
6. Experts fill out forms, again anonymously, and steps 4 to 6 are iterated for as
many rounds as appropriate.
20
Planning poker (sprint planning meeting, planning game)
• Make decomposition into tasks (sprint backlog)
• Involve whole team who will implement features (developers, testers)
• Provide deck of numbered cards with numbers:
0,1
2, 1, 2, 3, 5, 8, 13, 20, 40, 100, ‘?’, ‘Coffee’
• Timer for discussions
Procedure
• Provide short overview of feature to be implemented.
• Each individual lays a card face down representing their estimate.
• Everyone calls their cards simultaneously by turning them over.
• People with highest and lowest estimations are share they reasoning.
• Repeat the estimation process until a consensus is reached.
21
Planning poker: pros and cons
Pros:
• It is fun!
• Minimizes anchoring
• Team work which build up a team
• Corporate liability
• Expertized and reasoning sharing
Cons:
• Expensive
• Can take significant time for clarifications
• Difficult to implement in distributed projects
• Difficult to make “weight” to experts’ estimates
• Personalities can affect the estimates
22
Proxy-based estimation (PROBE) method
• Used mostly in feasibility studies (evaluating best process, economic feasibility of
the project)
• Divide requirements by classes
• Every class must be estimated by
– Complexity
– Size
• Class assigned to every specific task
23
Template for PROBE method
Requirement/task Class Effort
Retrieve image 1 3.5 hours
Print of screen 2 4.6 hours
Print on paper 2 4.6 hours
Class Size Complexity Effort
1: data retrieval 1 2 3.5 hours
2: image printing 2 2 4.6 hours
Small Medium Large
Simple 1.5 hours 2.3 hours 3.8 hours
Normal 3.5 hours 4.6 hours 5.9 hours
Complex 5.5 hours 6.7 hours 8.1 hours
24
PROBE: features and applicability
• Strengths
– Similar tasks estimates in the same way
– Simplifies staffing and resource assignment
• Weaknesses
– Need deep understanding of the technology
– Provides very rough estimations
25
Functional point analysis: terms
• Logical data types
– Internal logical file (ILF) – user visible internal data structure
– External interface file (EIF) – data, used by application, but exists outside of
application
• Processes
– External input (EI) – process of data transfer from user or EIF to ILF.
– External output (EO) – process of data transfer from one or many ILF to user or EIF
with mandatory data conversion (processing).
– External inquiries (EQ) – process of data transfer without conversion.
• Data elements
– Record Element Type (RET) - user recognizable sub group of data elements
– File Type Referenced (FTR) - file type referenced by a transaction
– Data Element Type (DET) - unique user recognizable, non-recursive field
26
FPA: sample
Application being measured
Another
application
ILF
EIF
math
User domain
EI EO
EO
EI
EQ
EQ
27
Functional point analysis: approach
• Assign specific weight to every data type, interface, and process
• Calculation of unadjusted function point (UFP) based on number of elements and
their weights.
• Calculate Value Adjustment Factor (VAF) based on technical and environmental
requirements (General System Characteristics (GSC) - by tables with weights for
every specific case).
• Calculation of adjusted function points (AFP) based on UFP and coefficient above.
28
FPA: features and applicability
• Strengths
– Indifferent to implementation process and technology
– Artifacts can be used for further architecture development
– Provide estimation in “common units” and shows project’s complexity independently
of supplier competency
– Can be made by one person or can be made in parallel to speed up
• Weaknesses
– Requires a lot of time to understand and apply in correct way.
– Difficult to adjust to specific company processes and experience.
– Doesn’t provide decomposition for production stages and operations.
29
Use Case Points
Used when Unified Modeling Language (UML) and Rational Unified Process (RUP)
methodologies are being used for software design and development.
• Unadjusted Use Case Weight (UUCW) – number and complexity of use cases
• Unadjusted Actor Weight (UAW) - number and complexity of actors
• Technical Complexity Factor (TCF) - technical aspects of development
• Environmental Complexity Factor (ECF) - environmental factors
30
Unadjusted Use Case Weight (UUCW)
• Based on the number and complexity of the use cases for the system
• To find the UUCW for a system, each of the use cases must be identified and
classified as Simple, Average or Complex based on the number of transactions the
use case contains
Use Case Classification No. of Transactions Weight
Simple 1 to 3 transactions 5
Average 4 to 7 transactions 10
Complex 8 or more transactions 15
𝑈𝑈𝐶𝑊 = 𝑊𝑒𝑖𝑔ℎ𝑡 𝑈𝑠𝑒 𝑐𝑎𝑠𝑒𝑖 = 5 ∗ 𝐶𝑜𝑢𝑛𝑡 𝑆𝑖𝑚𝑝𝑙𝑒 + 10 ∗ 𝐶𝑜𝑢𝑛𝑡 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 + 15 ∗ 𝐶𝑜𝑢𝑛𝑡(𝐶𝑜𝑚𝑝𝑙𝑒𝑥)
31
Unadjusted Actor Weight (UAW)
• Calculated based on the number and complexity of the actors for the system
• Actors must be identified and classified as Simple, Average or Complex based the
type of actor
Actor Classification Type of Actor Weight
Simple
External system that must interact with the system using
a well-defined API
1
Average
External system that must interact with the system using
standard communication protocols (e.g. TCP/IP, FTP,
HTTP, database)
2
Complex Human actor using a GUI application interface 3
𝑈𝐴𝑊 = 𝑊𝑒𝑖𝑔ℎ𝑡 𝐴𝑐𝑡𝑜𝑟𝑖 = 𝐶𝑜𝑢𝑛𝑡 𝑆𝑖𝑚𝑝𝑙𝑒 + 2 ∗ 𝐶𝑜𝑢𝑛𝑡 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 + 3 ∗ 𝐶𝑜𝑢𝑛𝑡(𝐶𝑜𝑚𝑝𝑙𝑒𝑥)
32
Technical Complexity Factor (TCF)
• Determined by assigning a score (perceived complexity factor) between 0 (factor
is irrelevant) and 5 (factor is essential) to each of the 13 technical factors listed in
the table
• This score is then multiplied by the defined weighted value for each factor.
Factor Description Weight
T1 Distributed system 2.0
T2 Response time/performance objectives 1.0
T3 End-user efficiency 1.0
T4 Internal processing complexity 1.0
… … …
𝑇𝐶𝐹 = 0.6 + 0.01 ∗ 𝑊𝑒𝑖𝑔ℎ𝑡 𝐹𝑎𝑐𝑡𝑜𝑟𝑖 ∗ 𝑆𝑐𝑜𝑟𝑒(𝐹𝑎𝑐𝑡𝑜𝑟𝑖)
33
Environmental Complexity Factor (ECF)
• It is determined by assigning a score between 0 (no experience) and 5 (expert) to
each of the 8 environmental factors listed in the table
• This score is then multiplied by the defined weighted value for each factor.
Factor Description Weight
E1 Familiarity with development process used 1.5
E2 Application experience 0.5
E3 Object-oriented experience of team 1.0
E4 Lead analyst capability 0.5
E5 Motivation of the team 1.0
… … …
𝐸𝐶𝐹 = 1.4 − 0.03 ∗ 𝑊𝑒𝑖𝑔ℎ𝑡 𝐹𝑎𝑐𝑡𝑜𝑟𝑖 ∗ 𝑆𝑐𝑜𝑟𝑒(𝐹𝑎𝑐𝑡𝑜𝑟𝑖)
34
Use Case Points (UCP)
Finally the UCP can be calculated once the unadjusted project size (UUCW and UAW),
technical factor (TCF) and environmental factor (ECF) have been determined. The
UCP is calculated based on the following formula:
UCP = (UUCW + UAW) * TCF * ECF
This estimation includes development only. It not consider testing, configuration
management, support, and etc.
35
Use case points: features and applicability
• Strengths
– Not necessary to involve the experts
– Technical expertize not needed
– Can be used for rough pre-sale estimation
– Can be made very fast
– Intuitive enough for the customer
• Weaknesses
– Estimates only requirements, but not tasks. They have to be estimated later.
– Strongly depends on requirements completeness
– Coefficients need to be adjusted for the company
36
Weighted Micro Function Points
• Produces more accurate results than traditional software sizing methodologies,
while requiring less configuration and knowledge from the end user, as most of
the estimation is based on automatic measurements of an existing source code.
• Uses a parser to understand the source code breaking it down into micro
functions and derive several code complexity and volume metrics, which are then
dynamically interpolated into a final effort score.
• As a result can be used only with analogy based cost predictions.
37
Project evaluation and review technique (PERT)
Statistical tool that is designed to analyze and represent the tasks involved in
completing a given project.
Commonly used in conjunction with the critical path method (CPM).
• A PERT chart is a tool that facilitates decision making. The first draft of a PERT
chart will number its events sequentially in 10s (10, 20, 30, etc.) to allow the later
insertion of additional events.
• Two consecutive events in a PERT chart are linked by activities, which are
conventionally represented as arrows.
• The events are presented in a logical sequence and no activity can commence
until its immediately preceding event is completed.
• The planner decides which milestones should be PERT events and also decides
their “proper” sequence.
• A PERT chart may have multiple pages with many sub-tasks.
38
PERT diagram
39
PERT: Advantages and disadvantages
• Strengths
– PERT chart explicitly defines and makes visible dependencies (precedence
relationships) between the work breakdown structure (commonly WBS) elements
– PERT facilitates identification of the critical path and makes this visible
– PERT facilitates identification of early start, late start, and slack for each activity
– PERT provides for potentially reduced project duration due to better understanding of
dependencies leading to improved overlapping of activities and tasks where feasible.
– The large amount of project data can be organized & presented in diagram for use in
decision making.
• Weaknesses
– There can be potentially hundreds or thousands of activities and individual
dependency relationships
– The lack of a timeframe on most PERT/CPM charts makes it harder to show status
40
Estimations for large scale projects
41
Why the project scale matters?
• Work can’t be perfectly partitioned
Team size
Duration
Team sizeDuration
Perfectly partitioned Not partitionable
42
Large scale project: How fast we can be?
43
Project size: communication overhead
Team size
Overhead,%
Establish
communication
processes
Dividing into
teams
44
Project size: Learning curve
Time
Overhead,%
Learning curve for
new developer
Effort spent
by buddy
Reference performance
45
Learning in large scale project
• Large amount of API, code, documents
• Many people share necessary knowledge
• Resources can be reassigned between domains or teams
• Requirements interference
Time
Overhead,%
Team size
Overhead,%
Project scale
Overhead,%
46
Brooks’ law
Team size
Projectduration
∝ +𝛽 ∗ 𝑇𝑒𝑎𝑚𝑆𝑖𝑧𝑒 + 𝛾 ∗ 𝑇𝑒𝑎𝑚𝑆𝑖𝑧𝑒2
𝑇𝑒𝑎𝑚𝑆𝑖𝑧𝑒
𝑃𝑟𝑜𝑗𝑒𝑐𝑡𝑆𝑖𝑧𝑒
𝑇𝑒𝑎𝑚𝑆𝑖𝑧𝑒
47
Brook law’s parameters
E0 – effort without communication overhead
TS – team size
RI – Requirements Interference, %
LO – Learning Overheads, %
CO – Communication Overheads, %
1+LO*RI*(TS-1)+CO*RI*TS*(TS-1)
TS
Duration = E0*
48
Brooks law with team granularity
For instance for 4 developers and 2 testers:
Team Granularity = (4+2)/4 = 1,5
Total number of people on a project
Maximum amount of people in specific activity
TG =
Team Granularity is a coefficient which shows number of possible parallel activities
on the project.
RI1 + LO *
TS
TG
– 1 + RI*
TS
TG
TS
TG
– 1*
D = E0*
TS
* CO*
49
To be continued…
• Planning
– Critical path method (CPM)
50
Are you awake?
No one knew what rabbit thought,
because he was very well-mannered.

Weitere ähnliche Inhalte

Was ist angesagt?

Selection of an appropriate project approach
Selection of an appropriate project approachSelection of an appropriate project approach
Selection of an appropriate project approachtumetr1
 
software-effort_estimation(updated)9 ch05
 software-effort_estimation(updated)9 ch05 software-effort_estimation(updated)9 ch05
software-effort_estimation(updated)9 ch05Shahid Riaz
 
Effective Project Communication
Effective Project CommunicationEffective Project Communication
Effective Project CommunicationMark Ritchie
 
1 b. project monitoring and control
1 b. project monitoring and control1 b. project monitoring and control
1 b. project monitoring and controlDr.R. SELVAM
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-Kanchana Devi
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementAndrew Mikityuk
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -Hossam Maghrabi
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsEJ (Ted) Lister
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management - dyaksa hanindito
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
Project Initiation Document
Project Initiation DocumentProject Initiation Document
Project Initiation DocumentDave Angelow
 

Was ist angesagt? (20)

Project Estimating
Project EstimatingProject Estimating
Project Estimating
 
Selection of an appropriate project approach
Selection of an appropriate project approachSelection of an appropriate project approach
Selection of an appropriate project approach
 
software-effort_estimation(updated)9 ch05
 software-effort_estimation(updated)9 ch05 software-effort_estimation(updated)9 ch05
software-effort_estimation(updated)9 ch05
 
Effective Project Communication
Effective Project CommunicationEffective Project Communication
Effective Project Communication
 
1 b. project monitoring and control
1 b. project monitoring and control1 b. project monitoring and control
1 b. project monitoring and control
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-
 
PMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration ManagementPMP Prep 3 - Project Integration Management
PMP Prep 3 - Project Integration Management
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and Turnarounds
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
Project Estimation
Project EstimationProject Estimation
Project Estimation
 
Project time management
Project time managementProject time management
Project time management
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Project Initiation Document
Project Initiation DocumentProject Initiation Document
Project Initiation Document
 

Ähnlich wie The Art of Project Estimation

Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test EstimationJatin Kochhar
 
Software Project management
Software Project managementSoftware Project management
Software Project managementsameer farooq
 
Wbs, estimation and scheduling
Wbs, estimation and schedulingWbs, estimation and scheduling
Wbs, estimation and schedulingSulman Ahmed
 
3. Lect 29_ 30_ 32 Project Planning.pptx
3. Lect 29_ 30_ 32 Project Planning.pptx3. Lect 29_ 30_ 32 Project Planning.pptx
3. Lect 29_ 30_ 32 Project Planning.pptxAbhishekKumar66407
 
Lecture 5 -6(CSC205).pptx jsksnxbbxjxksnsnz
Lecture 5 -6(CSC205).pptx jsksnxbbxjxksnsnzLecture 5 -6(CSC205).pptx jsksnxbbxjxksnsnz
Lecture 5 -6(CSC205).pptx jsksnxbbxjxksnsnzAhmadSajjad34
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyyaPMI2011
 
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02PMI_IREP_TP
 
2015 drupalcampcebu estimation_jrf
2015 drupalcampcebu estimation_jrf2015 drupalcampcebu estimation_jrf
2015 drupalcampcebu estimation_jrfJohnnie Fox
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsDarshak Mehta
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projectalpha1unity
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system projecta23ccb
 
An overview of agile methodologies
An overview of agile methodologiesAn overview of agile methodologies
An overview of agile methodologiesparvezmisarwala
 
Project Management
Project ManagementProject Management
Project ManagementAtif Rehmat
 
req engg (1).ppt
req engg (1).pptreq engg (1).ppt
req engg (1).pptWaniHBisen
 
Software engineering -core topics
Software engineering -core topicsSoftware engineering -core topics
Software engineering -core topicsAmnah_Ch
 

Ähnlich wie The Art of Project Estimation (20)

The art of project estimation
The art of project estimationThe art of project estimation
The art of project estimation
 
Software Test Estimation
Software Test EstimationSoftware Test Estimation
Software Test Estimation
 
Software Project management
Software Project managementSoftware Project management
Software Project management
 
Wbs
WbsWbs
Wbs
 
Wbs, estimation and scheduling
Wbs, estimation and schedulingWbs, estimation and scheduling
Wbs, estimation and scheduling
 
3. Lect 29_ 30_ 32 Project Planning.pptx
3. Lect 29_ 30_ 32 Project Planning.pptx3. Lect 29_ 30_ 32 Project Planning.pptx
3. Lect 29_ 30_ 32 Project Planning.pptx
 
Lecture 5 -6(CSC205).pptx jsksnxbbxjxksnsnz
Lecture 5 -6(CSC205).pptx jsksnxbbxjxksnsnzLecture 5 -6(CSC205).pptx jsksnxbbxjxksnsnz
Lecture 5 -6(CSC205).pptx jsksnxbbxjxksnsnz
 
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
Day 1   1620 - 1705 - maple - pranabendu bhattacharyyaDay 1   1620 - 1705 - maple - pranabendu bhattacharyya
Day 1 1620 - 1705 - maple - pranabendu bhattacharyya
 
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
Day1 1620-1705-maple-pranabendubhattacharyya-131008043643-phpapp02
 
2015 drupalcampcebu estimation_jrf
2015 drupalcampcebu estimation_jrf2015 drupalcampcebu estimation_jrf
2015 drupalcampcebu estimation_jrf
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
Unified process
Unified processUnified process
Unified process
 
Managing the information system project
Managing the information system projectManaging the information system project
Managing the information system project
 
An overview of agile methodologies
An overview of agile methodologiesAn overview of agile methodologies
An overview of agile methodologies
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Mg6088 spm unit-2
Mg6088 spm unit-2Mg6088 spm unit-2
Mg6088 spm unit-2
 
Project Management
Project ManagementProject Management
Project Management
 
req engg (1).ppt
req engg (1).pptreq engg (1).ppt
req engg (1).ppt
 
Software engineering -core topics
Software engineering -core topicsSoftware engineering -core topics
Software engineering -core topics
 

Mehr von Return on Intelligence

Unit Tests? It is Very Simple and Easy!
Unit Tests? It is Very Simple and Easy!Unit Tests? It is Very Simple and Easy!
Unit Tests? It is Very Simple and Easy!Return on Intelligence
 
Introduction to Backbone.js & Marionette.js
Introduction to Backbone.js & Marionette.jsIntroduction to Backbone.js & Marionette.js
Introduction to Backbone.js & Marionette.jsReturn on Intelligence
 
Types of testing and their classification
Types of testing and their classificationTypes of testing and their classification
Types of testing and their classificationReturn on Intelligence
 
Apache cassandra - future without boundaries (part3)
Apache cassandra - future without boundaries (part3)Apache cassandra - future without boundaries (part3)
Apache cassandra - future without boundaries (part3)Return on Intelligence
 
Apache cassandra - future without boundaries (part2)
Apache cassandra - future without boundaries (part2)Apache cassandra - future without boundaries (part2)
Apache cassandra - future without boundaries (part2)Return on Intelligence
 
Apache cassandra - future without boundaries (part1)
Apache cassandra - future without boundaries (part1)Apache cassandra - future without boundaries (part1)
Apache cassandra - future without boundaries (part1)Return on Intelligence
 

Mehr von Return on Intelligence (20)

Clean Code Approach
Clean Code ApproachClean Code Approach
Clean Code Approach
 
Code Coverage
Code CoverageCode Coverage
Code Coverage
 
Effective Communication in english
Effective Communication in englishEffective Communication in english
Effective Communication in english
 
Anti-patterns
Anti-patternsAnti-patterns
Anti-patterns
 
Conflicts Resolving
Conflicts ResolvingConflicts Resolving
Conflicts Resolving
 
Database versioning with liquibase
Database versioning with liquibaseDatabase versioning with liquibase
Database versioning with liquibase
 
Effective Feedback
Effective FeedbackEffective Feedback
Effective Feedback
 
English for Negotiations 2016
English for Negotiations 2016English for Negotiations 2016
English for Negotiations 2016
 
Lean Software Development
Lean Software DevelopmentLean Software Development
Lean Software Development
 
Unit Tests? It is Very Simple and Easy!
Unit Tests? It is Very Simple and Easy!Unit Tests? It is Very Simple and Easy!
Unit Tests? It is Very Simple and Easy!
 
Quick Start to AngularJS
Quick Start to AngularJSQuick Start to AngularJS
Quick Start to AngularJS
 
Introduction to Backbone.js & Marionette.js
Introduction to Backbone.js & Marionette.jsIntroduction to Backbone.js & Marionette.js
Introduction to Backbone.js & Marionette.js
 
Types of testing and their classification
Types of testing and their classificationTypes of testing and their classification
Types of testing and their classification
 
Introduction to EJB
Introduction to EJBIntroduction to EJB
Introduction to EJB
 
Enterprise Service Bus
Enterprise Service BusEnterprise Service Bus
Enterprise Service Bus
 
Apache cassandra - future without boundaries (part3)
Apache cassandra - future without boundaries (part3)Apache cassandra - future without boundaries (part3)
Apache cassandra - future without boundaries (part3)
 
Apache cassandra - future without boundaries (part2)
Apache cassandra - future without boundaries (part2)Apache cassandra - future without boundaries (part2)
Apache cassandra - future without boundaries (part2)
 
Apache cassandra - future without boundaries (part1)
Apache cassandra - future without boundaries (part1)Apache cassandra - future without boundaries (part1)
Apache cassandra - future without boundaries (part1)
 
Career development in exigen services
Career development in exigen servicesCareer development in exigen services
Career development in exigen services
 
Introduction to selenium web driver
Introduction to selenium web driverIntroduction to selenium web driver
Introduction to selenium web driver
 

Kürzlich hochgeladen

How To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerHow To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerThousandEyes
 
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...MyIntelliSource, Inc.
 
Diamond Application Development Crafting Solutions with Precision
Diamond Application Development Crafting Solutions with PrecisionDiamond Application Development Crafting Solutions with Precision
Diamond Application Development Crafting Solutions with PrecisionSolGuruz
 
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...OnePlan Solutions
 
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...Steffen Staab
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software DevelopersVinodh Ram
 
TECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providerTECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providermohitmore19
 
Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsUnveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsAlberto González Trastoy
 
5 Signs You Need a Fashion PLM Software.pdf
5 Signs You Need a Fashion PLM Software.pdf5 Signs You Need a Fashion PLM Software.pdf
5 Signs You Need a Fashion PLM Software.pdfWave PLM
 
DNT_Corporate presentation know about us
DNT_Corporate presentation know about usDNT_Corporate presentation know about us
DNT_Corporate presentation know about usDynamic Netsoft
 
Clustering techniques data mining book ....
Clustering techniques data mining book ....Clustering techniques data mining book ....
Clustering techniques data mining book ....ShaimaaMohamedGalal
 
How To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsHow To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsAndolasoft Inc
 
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...harshavardhanraghave
 
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfThe Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfkalichargn70th171
 
Unlocking the Future of AI Agents with Large Language Models
Unlocking the Future of AI Agents with Large Language ModelsUnlocking the Future of AI Agents with Large Language Models
Unlocking the Future of AI Agents with Large Language Modelsaagamshah0812
 
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...kellynguyen01
 

Kürzlich hochgeladen (20)

How To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected WorkerHow To Troubleshoot Collaboration Apps for the Modern Connected Worker
How To Troubleshoot Collaboration Apps for the Modern Connected Worker
 
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
Try MyIntelliAccount Cloud Accounting Software As A Service Solution Risk Fre...
 
Diamond Application Development Crafting Solutions with Precision
Diamond Application Development Crafting Solutions with PrecisionDiamond Application Development Crafting Solutions with Precision
Diamond Application Development Crafting Solutions with Precision
 
Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...Advancing Engineering with AI through the Next Generation of Strategic Projec...
Advancing Engineering with AI through the Next Generation of Strategic Projec...
 
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...
 
Professional Resume Template for Software Developers
Professional Resume Template for Software DevelopersProfessional Resume Template for Software Developers
Professional Resume Template for Software Developers
 
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
 
TECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service providerTECUNIQUE: Success Stories: IT Service provider
TECUNIQUE: Success Stories: IT Service provider
 
Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time ApplicationsUnveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
Unveiling the Tech Salsa of LAMs with Janus in Real-Time Applications
 
Vip Call Girls Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
Vip Call Girls Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS LiveVip Call Girls Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
Vip Call Girls Noida ➡️ Delhi ➡️ 9999965857 No Advance 24HRS Live
 
5 Signs You Need a Fashion PLM Software.pdf
5 Signs You Need a Fashion PLM Software.pdf5 Signs You Need a Fashion PLM Software.pdf
5 Signs You Need a Fashion PLM Software.pdf
 
Call Girls In Mukherjee Nagar 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SE...
Call Girls In Mukherjee Nagar 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SE...Call Girls In Mukherjee Nagar 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SE...
Call Girls In Mukherjee Nagar 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SE...
 
DNT_Corporate presentation know about us
DNT_Corporate presentation know about usDNT_Corporate presentation know about us
DNT_Corporate presentation know about us
 
Clustering techniques data mining book ....
Clustering techniques data mining book ....Clustering techniques data mining book ....
Clustering techniques data mining book ....
 
How To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.jsHow To Use Server-Side Rendering with Nuxt.js
How To Use Server-Side Rendering with Nuxt.js
 
Microsoft AI Transformation Partner Playbook.pdf
Microsoft AI Transformation Partner Playbook.pdfMicrosoft AI Transformation Partner Playbook.pdf
Microsoft AI Transformation Partner Playbook.pdf
 
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
Reassessing the Bedrock of Clinical Function Models: An Examination of Large ...
 
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdfThe Ultimate Test Automation Guide_ Best Practices and Tips.pdf
The Ultimate Test Automation Guide_ Best Practices and Tips.pdf
 
Unlocking the Future of AI Agents with Large Language Models
Unlocking the Future of AI Agents with Large Language ModelsUnlocking the Future of AI Agents with Large Language Models
Unlocking the Future of AI Agents with Large Language Models
 
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
Short Story: Unveiling the Reasoning Abilities of Large Language Models by Ke...
 

The Art of Project Estimation

  • 1. www.ExigenServices.com The art of project estimation Damir Tenishev Ph.D., Project Manager July 2013
  • 2. 2 Goals • Understand the goals and scope of estimation • Study estimation approaches • Learn and compare some estimation techniques • Understand applicability for specific techniques • Review common estimation mistakes • Study of the effects of large scale projects on estimates • Share practical experience in estimation Scope: classical estimation techniques
  • 3. 3 What is necessary to make estimations? • Software requirements • Time for estimation • Team of software experts to make estimations • Subject matter experts to clarify the requirements • Knowledge base for implementation approaches and required effort • Information about special conditions (team size, technologies, client-specific) Start when you are ready
  • 4. 4 Expected result • Scope to be implemented • Total effort to be spent to implement the project • Project budget • Project schedule – Project decomposition – Project and key stages’ duration • Staffing plan • Risk management plan • Assumptions It is all about resources
  • 5. 5 Need to be clarified • Product requirements – Functional requirements – Non-functional requirements (performance, stability, scalability, and etc.) – Production, testing and etc. environments • Project requirements – Technologies – Business trip policy – Support policy
  • 6. 6 Effective estimations • Define estimation subject. What you are going to estimate? • Make decomposition and work breakdown structure (WBS) – Divide until you have easy explainable tasks with obvious implementation – Keep breakdown hierarchy – Add dependencies • Use historical data and gathered experience • Use several experts • Make tasks clustering and average estimates • Take into account real productivity of your team Divide and empire
  • 7. 7 Good questions • Explain in one sentence what have to be done? • How this will be used? Who are the end users? • What is the value? Can we drop this? • What is the similar feature we have implemented/estimated before? • What is the effort for implementation and what is estimated duration? • What can be done to make this two times faster, cheaper? • What can be done to parallelize work on this task? What pros and cons will be? • What is the easiest way to implement this feature? • What dependencies do we have from and to other tasks? • Who can do this work? What experience is necessary? • What environment for this task is assumed? • What are the risks? How they can be mitigated? • What is permanent and what can vary in the feature? Communicate!
  • 8. 8 Typical mistakes • Differences in definition of done • Incomplete requirements • Lack of time for clarification and making more precise estimation • Unawareness of time factor for large systems (they are grown, not built) • Mistakes in decomposition • Loosing significant details or parts of functionality • Neglect of communication delays (with customer, experts, and etc.) • Team size is not taken into account (internal communications and other aspects) • Lack of specific knowledge (business area or technology) • Misconception of required and estimated delivery • Ignoring cost of support produced code and data • Ignoring risks • Cognitive biases You have to care about many things
  • 9. 9 Cognitive biases • We do not examine every possible option or every scrap of data before we make a decision • We adopt certain rules of thumb and take other shortcuts when we make choices • In some cases, our cognitive limitations lead to poor estimations • Cognitive biases – Overconfidence – Sunk-cost effect – Availability bias (recency effect) – Confirmation bias – Anchoring bias – Illusory correlation – Hindsight bias Praemonitus, praemunitus
  • 10. 10 Classification of project estimations • By type of estimation – Product metrics – Effort estimation – Duration estimation • By goals – Commercial offer – Forecast and planning • By techniques – By historical model – Expert methods – Parametric What is your goal?
  • 11. 11 Estimation techniques • Historical model usage • Expert methods – Three point estimation – Delphi – Wideband Delphi – Planning poker • Parametric methods – Proxy-based estimation (PROBE) – Function point – Use case point – Weighted Micro Function Points What is your approach?
  • 12. 12 Basic steps: summary • Decomposition • Discovering dependencies • Identification of experts for every specific area • Gathering and clarifying requirements • Analysis for applicability of existing solutions and technologies • Estimating by expert • Tracking reasoning and assumptions for decisions • Identifications of risks • Getting summary estimation for task • Comparison with other tasks’ estimations • Making summary estimation Always have a checklist
  • 13. 13 Three point estimation • Task estimation based on three values – Optimistic (O) – Most likely or normal (M) – Pessimistic (P) • Double triangular distribution is used S = 0.5 S = 0.5 MO P
  • 14. 14 Three point estimation: math Expected time 𝐸 = 𝑂 + 4 × 𝑀 + 𝑃 6 Standard deviation S𝐷 = 𝑃 − 𝑂 6 Project time 𝑃𝐸 = 𝐸 Project standard deviation 𝑃𝑆𝐷 = 𝑆𝐷2 Assumption: All project’s tasks are consecutive.
  • 15. 15 Three point estimation: confidence level Confidence level Standard deviation 68 % SD 90 % 1.645 x SD 95 % 2 x SD 99.7 % 3 x SD Note: Information systems typically use the 90% confidence level for all project and task estimates.
  • 16. 16 Three point estimation: example Tasks O M P E SD Task 1 1 3 8 1+4×3+8 6 = 3.5 8−1 6 = 1.17 Task 2 2 5 20 2+4×5+20 6 = 7 20−2 6 = 3 Confidence 68 % (E ± SD ) 90 % (E ± 1.645*SD) 95 % (E ± 2 *SD) 99.7 % (E ± 3*SD) Task 1 3.5 ± 1.17=> 2.33 to 4.66 1.58 to 5.42 1.17 to 5.83 1 𝑡𝑜 7 Task 2 7 ± 3 => 4 to 10 2.06 to 11.93 2 to 9 2 𝑡𝑜 16 𝑃𝑆𝐷 = 1.172 + 32 =3.22𝑃𝐸 = 𝐸1 + 𝐸2 = 10.5 Project (consecutive tasks):
  • 17. 17 Delphi method: estimation matrix Expert 1 Expert 2 Expert 3 Average Task 1 Attempt 1 Attempt 2 Attempt 3 10 10 11 5 8 10 20 15 12 11.7 11 11 Task 2 Attempt 1 Attempt 2 Attempt 3 15 16 18 30 20 18 8 20 19 17.7 18.7 18.3 Task 3 Attempt 1 Attempt 2 Attempt 3 11 10 8 4 5 6 6 7 7 7 7.3 7 • Decomposition into tasks • Anonymous estimation • Announcement of average estimation as well as reasons for them • Transition to next estimation iteration
  • 18. 18 Delphi method: features and applicability • Strengths – Works well for ambiguity – Lead to joint agreement and corporate liability – Easy to adopt to time restrictions – Anonymous estimations eliminate authority influence – Assumptions are documented, discussed and agreed • Weaknesses – There is no formal reasoning for estimation. As a result there is no formal reasoning for customer – Decomposition rules are not defined – Some creative ideas can be lost since majority opinion is prevail – It is possible that people will agree with other’s estimate without cogitation – Need to have at least 4 experts
  • 19. 19 Wideband Delphi method Involves greater interaction and more communication between participants Execution steps 1. Coordinator presents each expert with a specification and an estimation form. 2. Coordinator calls a group meeting in which the experts discuss estimation issues with the coordinator and each other. 3. Experts fill out forms anonymously. 4. Coordinator prepares and distributes a summary of the estimates 5. Coordinator calls a group meeting, specifically focusing on having the experts discuss points where their estimates vary widely 6. Experts fill out forms, again anonymously, and steps 4 to 6 are iterated for as many rounds as appropriate.
  • 20. 20 Planning poker (sprint planning meeting, planning game) • Make decomposition into tasks (sprint backlog) • Involve whole team who will implement features (developers, testers) • Provide deck of numbered cards with numbers: 0,1 2, 1, 2, 3, 5, 8, 13, 20, 40, 100, ‘?’, ‘Coffee’ • Timer for discussions Procedure • Provide short overview of feature to be implemented. • Each individual lays a card face down representing their estimate. • Everyone calls their cards simultaneously by turning them over. • People with highest and lowest estimations are share they reasoning. • Repeat the estimation process until a consensus is reached.
  • 21. 21 Planning poker: pros and cons Pros: • It is fun! • Minimizes anchoring • Team work which build up a team • Corporate liability • Expertized and reasoning sharing Cons: • Expensive • Can take significant time for clarifications • Difficult to implement in distributed projects • Difficult to make “weight” to experts’ estimates • Personalities can affect the estimates
  • 22. 22 Proxy-based estimation (PROBE) method • Used mostly in feasibility studies (evaluating best process, economic feasibility of the project) • Divide requirements by classes • Every class must be estimated by – Complexity – Size • Class assigned to every specific task
  • 23. 23 Template for PROBE method Requirement/task Class Effort Retrieve image 1 3.5 hours Print of screen 2 4.6 hours Print on paper 2 4.6 hours Class Size Complexity Effort 1: data retrieval 1 2 3.5 hours 2: image printing 2 2 4.6 hours Small Medium Large Simple 1.5 hours 2.3 hours 3.8 hours Normal 3.5 hours 4.6 hours 5.9 hours Complex 5.5 hours 6.7 hours 8.1 hours
  • 24. 24 PROBE: features and applicability • Strengths – Similar tasks estimates in the same way – Simplifies staffing and resource assignment • Weaknesses – Need deep understanding of the technology – Provides very rough estimations
  • 25. 25 Functional point analysis: terms • Logical data types – Internal logical file (ILF) – user visible internal data structure – External interface file (EIF) – data, used by application, but exists outside of application • Processes – External input (EI) – process of data transfer from user or EIF to ILF. – External output (EO) – process of data transfer from one or many ILF to user or EIF with mandatory data conversion (processing). – External inquiries (EQ) – process of data transfer without conversion. • Data elements – Record Element Type (RET) - user recognizable sub group of data elements – File Type Referenced (FTR) - file type referenced by a transaction – Data Element Type (DET) - unique user recognizable, non-recursive field
  • 26. 26 FPA: sample Application being measured Another application ILF EIF math User domain EI EO EO EI EQ EQ
  • 27. 27 Functional point analysis: approach • Assign specific weight to every data type, interface, and process • Calculation of unadjusted function point (UFP) based on number of elements and their weights. • Calculate Value Adjustment Factor (VAF) based on technical and environmental requirements (General System Characteristics (GSC) - by tables with weights for every specific case). • Calculation of adjusted function points (AFP) based on UFP and coefficient above.
  • 28. 28 FPA: features and applicability • Strengths – Indifferent to implementation process and technology – Artifacts can be used for further architecture development – Provide estimation in “common units” and shows project’s complexity independently of supplier competency – Can be made by one person or can be made in parallel to speed up • Weaknesses – Requires a lot of time to understand and apply in correct way. – Difficult to adjust to specific company processes and experience. – Doesn’t provide decomposition for production stages and operations.
  • 29. 29 Use Case Points Used when Unified Modeling Language (UML) and Rational Unified Process (RUP) methodologies are being used for software design and development. • Unadjusted Use Case Weight (UUCW) – number and complexity of use cases • Unadjusted Actor Weight (UAW) - number and complexity of actors • Technical Complexity Factor (TCF) - technical aspects of development • Environmental Complexity Factor (ECF) - environmental factors
  • 30. 30 Unadjusted Use Case Weight (UUCW) • Based on the number and complexity of the use cases for the system • To find the UUCW for a system, each of the use cases must be identified and classified as Simple, Average or Complex based on the number of transactions the use case contains Use Case Classification No. of Transactions Weight Simple 1 to 3 transactions 5 Average 4 to 7 transactions 10 Complex 8 or more transactions 15 𝑈𝑈𝐶𝑊 = 𝑊𝑒𝑖𝑔ℎ𝑡 𝑈𝑠𝑒 𝑐𝑎𝑠𝑒𝑖 = 5 ∗ 𝐶𝑜𝑢𝑛𝑡 𝑆𝑖𝑚𝑝𝑙𝑒 + 10 ∗ 𝐶𝑜𝑢𝑛𝑡 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 + 15 ∗ 𝐶𝑜𝑢𝑛𝑡(𝐶𝑜𝑚𝑝𝑙𝑒𝑥)
  • 31. 31 Unadjusted Actor Weight (UAW) • Calculated based on the number and complexity of the actors for the system • Actors must be identified and classified as Simple, Average or Complex based the type of actor Actor Classification Type of Actor Weight Simple External system that must interact with the system using a well-defined API 1 Average External system that must interact with the system using standard communication protocols (e.g. TCP/IP, FTP, HTTP, database) 2 Complex Human actor using a GUI application interface 3 𝑈𝐴𝑊 = 𝑊𝑒𝑖𝑔ℎ𝑡 𝐴𝑐𝑡𝑜𝑟𝑖 = 𝐶𝑜𝑢𝑛𝑡 𝑆𝑖𝑚𝑝𝑙𝑒 + 2 ∗ 𝐶𝑜𝑢𝑛𝑡 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 + 3 ∗ 𝐶𝑜𝑢𝑛𝑡(𝐶𝑜𝑚𝑝𝑙𝑒𝑥)
  • 32. 32 Technical Complexity Factor (TCF) • Determined by assigning a score (perceived complexity factor) between 0 (factor is irrelevant) and 5 (factor is essential) to each of the 13 technical factors listed in the table • This score is then multiplied by the defined weighted value for each factor. Factor Description Weight T1 Distributed system 2.0 T2 Response time/performance objectives 1.0 T3 End-user efficiency 1.0 T4 Internal processing complexity 1.0 … … … 𝑇𝐶𝐹 = 0.6 + 0.01 ∗ 𝑊𝑒𝑖𝑔ℎ𝑡 𝐹𝑎𝑐𝑡𝑜𝑟𝑖 ∗ 𝑆𝑐𝑜𝑟𝑒(𝐹𝑎𝑐𝑡𝑜𝑟𝑖)
  • 33. 33 Environmental Complexity Factor (ECF) • It is determined by assigning a score between 0 (no experience) and 5 (expert) to each of the 8 environmental factors listed in the table • This score is then multiplied by the defined weighted value for each factor. Factor Description Weight E1 Familiarity with development process used 1.5 E2 Application experience 0.5 E3 Object-oriented experience of team 1.0 E4 Lead analyst capability 0.5 E5 Motivation of the team 1.0 … … … 𝐸𝐶𝐹 = 1.4 − 0.03 ∗ 𝑊𝑒𝑖𝑔ℎ𝑡 𝐹𝑎𝑐𝑡𝑜𝑟𝑖 ∗ 𝑆𝑐𝑜𝑟𝑒(𝐹𝑎𝑐𝑡𝑜𝑟𝑖)
  • 34. 34 Use Case Points (UCP) Finally the UCP can be calculated once the unadjusted project size (UUCW and UAW), technical factor (TCF) and environmental factor (ECF) have been determined. The UCP is calculated based on the following formula: UCP = (UUCW + UAW) * TCF * ECF This estimation includes development only. It not consider testing, configuration management, support, and etc.
  • 35. 35 Use case points: features and applicability • Strengths – Not necessary to involve the experts – Technical expertize not needed – Can be used for rough pre-sale estimation – Can be made very fast – Intuitive enough for the customer • Weaknesses – Estimates only requirements, but not tasks. They have to be estimated later. – Strongly depends on requirements completeness – Coefficients need to be adjusted for the company
  • 36. 36 Weighted Micro Function Points • Produces more accurate results than traditional software sizing methodologies, while requiring less configuration and knowledge from the end user, as most of the estimation is based on automatic measurements of an existing source code. • Uses a parser to understand the source code breaking it down into micro functions and derive several code complexity and volume metrics, which are then dynamically interpolated into a final effort score. • As a result can be used only with analogy based cost predictions.
  • 37. 37 Project evaluation and review technique (PERT) Statistical tool that is designed to analyze and represent the tasks involved in completing a given project. Commonly used in conjunction with the critical path method (CPM). • A PERT chart is a tool that facilitates decision making. The first draft of a PERT chart will number its events sequentially in 10s (10, 20, 30, etc.) to allow the later insertion of additional events. • Two consecutive events in a PERT chart are linked by activities, which are conventionally represented as arrows. • The events are presented in a logical sequence and no activity can commence until its immediately preceding event is completed. • The planner decides which milestones should be PERT events and also decides their “proper” sequence. • A PERT chart may have multiple pages with many sub-tasks.
  • 39. 39 PERT: Advantages and disadvantages • Strengths – PERT chart explicitly defines and makes visible dependencies (precedence relationships) between the work breakdown structure (commonly WBS) elements – PERT facilitates identification of the critical path and makes this visible – PERT facilitates identification of early start, late start, and slack for each activity – PERT provides for potentially reduced project duration due to better understanding of dependencies leading to improved overlapping of activities and tasks where feasible. – The large amount of project data can be organized & presented in diagram for use in decision making. • Weaknesses – There can be potentially hundreds or thousands of activities and individual dependency relationships – The lack of a timeframe on most PERT/CPM charts makes it harder to show status
  • 40. 40 Estimations for large scale projects
  • 41. 41 Why the project scale matters? • Work can’t be perfectly partitioned Team size Duration Team sizeDuration Perfectly partitioned Not partitionable
  • 42. 42 Large scale project: How fast we can be?
  • 43. 43 Project size: communication overhead Team size Overhead,% Establish communication processes Dividing into teams
  • 44. 44 Project size: Learning curve Time Overhead,% Learning curve for new developer Effort spent by buddy Reference performance
  • 45. 45 Learning in large scale project • Large amount of API, code, documents • Many people share necessary knowledge • Resources can be reassigned between domains or teams • Requirements interference Time Overhead,% Team size Overhead,% Project scale Overhead,%
  • 46. 46 Brooks’ law Team size Projectduration ∝ +𝛽 ∗ 𝑇𝑒𝑎𝑚𝑆𝑖𝑧𝑒 + 𝛾 ∗ 𝑇𝑒𝑎𝑚𝑆𝑖𝑧𝑒2 𝑇𝑒𝑎𝑚𝑆𝑖𝑧𝑒 𝑃𝑟𝑜𝑗𝑒𝑐𝑡𝑆𝑖𝑧𝑒 𝑇𝑒𝑎𝑚𝑆𝑖𝑧𝑒
  • 47. 47 Brook law’s parameters E0 – effort without communication overhead TS – team size RI – Requirements Interference, % LO – Learning Overheads, % CO – Communication Overheads, % 1+LO*RI*(TS-1)+CO*RI*TS*(TS-1) TS Duration = E0*
  • 48. 48 Brooks law with team granularity For instance for 4 developers and 2 testers: Team Granularity = (4+2)/4 = 1,5 Total number of people on a project Maximum amount of people in specific activity TG = Team Granularity is a coefficient which shows number of possible parallel activities on the project. RI1 + LO * TS TG – 1 + RI* TS TG TS TG – 1* D = E0* TS * CO*
  • 49. 49 To be continued… • Planning – Critical path method (CPM)
  • 50. 50 Are you awake? No one knew what rabbit thought, because he was very well-mannered.

Hinweis der Redaktion

  1. Overconfidence Psychologists have shown that human beings are systematically overconfident in our judgments The sunk-cost effect refers to the tendency for people to escalate commitment to a course of action in which they have made substantial prior investments of time, money, or other resources. The recency effect is actually one particular form of what is called the availability bias – the last is most confidence. Confirmation bias refers to our tendency to gather and rely on information that confirms our existing views and to avoid or downplay information that disconfirms our preexisting hypotheses. Anchoring bias refers to the notion that we sometimes allow an initial reference point to distort our estimates. Illusory correlation - explains why stereotypes often form and persist. Hindsight bias - refers to the fact that we look back at past events and judge them as easily predictable when they clearly were not as easily foreseen.