This document provides a status report on material delivery for gas turbine generators (GTG) 6 and 7 from September 2015 to December 2015 at the Zirkuh Island power plant project in Abu Dhabi. It summarizes that 324 boxes of material were delivered with 100% receipt and 0% undelivered. Request for information (RFI) was completed for 85% of delivered boxes and pending for 15%. The majority of delivered material, 60%, remained unconsumed from production with 35% fully or partially consumed. Material was stored primarily at the airport laydown and plant warehouse facilities.
Flying High With Data Analytics & Optimization - Aviation Industry By Korina ...
GTG Material Report
1. GE Oil & Gas Supplied Material for GTG at Zirkuh Island
Abu Dhabi
Euro Mechanical & Electrical Co:
Project – P20054- Zakum Development Company
EPC for Power Upgrade At Zirkuh
Report from September 2015 to December 2015
2. No: of Boxes Received at Zirku No: of Boxes Undelivered
Total No: of Boxes (GT-6 + GT-7) 324 0
Delivered 324 Boxes- 100%
Undelivered 0 Boxes - 0 %
0
50
100
150
200
250
300
350
Material Delivery Status of GTG- 6 & GTG - 7
Total No: of Boxes
(GT-6 + GT-7)
No: of Boxes Received at Zirku No: of Boxes Undelivered
Sum of GT - 6 - Boxes 173 0
Sum of GT- 7 - Boxes 151 0
GT-6 - 173 Boxes - 100%
GT-6 - 0 Boxes 0%
GT-7 - 151 Boxes - 100%
GT-7- 0 Boxes , 0%
0
20
40
60
80
100
120
140
160
180
200
Sum of GT - 6 -
Boxes
Sum of GT- 7 -
Boxes
3. RFI Completed for Delivered Boxes
at Zirku - 274, 85%
Pending RFI for Delivered
Boxes at Zirku - 50, 15%
Pending RFI for UnDelivered Boxes
at Zirku - 0, 0%
Status of RFI Completion for GTG-6 & GTG-7
RFI Completed for Delivered Boxes at Zirku
Pending RFI for Delivered Boxes at Zirku
Pending RFI for UnDelivered Boxes at Zirku
Pending RFI for UnDelivered Boxes at Zirku Pending RFI for Delivered Boxes at Zirku RFI Completed for Delivered Boxes at Zirku
GT - 6 - Boxes 0 20 153
GT- 7 - Boxes 0 30 121
0
20
153
0
30
121
-20
0
20
40
60
80
100
120
140
160
180
GT - 6 - Boxes GT- 7 - Boxes Poly. (GT - 6 - Boxes) Poly. (GT- 7 - Boxes)
4. September October November December
GTG-6 87 450 1055
GTG-7 83 322 718 2
87
450
1055
83
322
718
2
0
200
400
600
800
1000
1200
1400
NUMBEROFTIEMSVERIFIEDFORRFI
NUMBER OF ITEMS VERIFIED FOR RFI
GTG RFI STATUS - MONTH WISE 2015
Sep Oct Oct Oct Oct Oct Oct Nov Nov Nov Nov Nov Nov Dec
MW MW 37 MW 41 MW 44 MW 45 MW 59 MW 62 MW 70 MW 80 MW 86 MW 93 MW 100 MW 126
GTG-6 87 64 12 202 172 56 474 356 3 4 162
GTG-7 83 64 52 111 88 7 112 49 5 346 206 2
87 64 12
202
172
56
474
356
3 4
162
83 64 52
111 88
7
112
49
5
346
206
2
0
50
100
150
200
250
300
350
400
450
500
NUMBEROFITEMSVERIFIEDFORRFI
NUMBER OF ITEMS VERIFIED FOR RFI
GTG RFI Status - RFI Number wise 2015
5. Sep Oct Nov Dec
GTG-6 87 191 342 79
GTG-7 83 129 65 290
87
191
342
7983
129
65
290
0
50
100
150
200
250
300
350
400
COUNTOFITEMSISSUEDFORPRODUCTIONLINE
COUNT OF ITEMS ISSUED FOR PRODUCTION LINE
Status of GTG Materials Issued to Plant - 2015
6. Consumed Completely Boxes - 115,
35%
Consumed Partial Boxes - 15,
5%
Unconsumed from Delivered
Boxes – 194,
60%
Undelivered Boxes at Zirkuh - 0,
0%
Status of GTG Materials under Production Line
Consumed
Completely
Consumed
Partial
Unconsumed
from Delivered
Boxes
Undelivered
Boxes at Zirkuh
Undelivered Boxes at Zirkuh Consumed Partial Consumed Completely Unconsumed from Delivered Boxes
GT - 6 - Total Consumption Boxes 0 6 73 94
GT - 7 Total Consumption of Boxes 0 9 42 100
0
6
73
94
0
9
42
100
0
20
40
60
80
100
120
Status of GTG Materials under Production Line - GTG WiseGT - 6 - Total Consumption
Boxes
GT - 7 Total Consumption
of Boxes
2 per. Mov. Avg. (GT - 6 -
Total Consumption Boxes)
2 per. Mov. Avg. (GT - 7
Total Consumption of
Boxes)
7. Airport Laydown-
144 Boxes,
45%
Granite Warehouse – 66 Boxes,
20%
Consumed for Production / Under
Production Line at Plant - 114 Boxes,
35%
Undelivered Boxes at Zirkuh -0 Boxes
0%
Storage Location of GTG Materials
Airport Laydown
Granite Warehouse
Consumed for
Production / Under
Production Line at Plant
Undelivered Boxes at
Zirkuh
Undelivered Boxes at Zirkuh Granite Warehouse
Consumed for Production / Under
Production Line at Plant
Airport Laydown
GTG-6 Total No: of Boxes 0 33 72 68
GTG-7 Total No: of Boxes 0 33 42 76
0
33
72
68
0
33
42
76
0
10
20
30
40
50
60
70
80
GTG Wise Storage Location of Materials
GTG-6 Total
No: of Boxes
GTG-7 Total
No: of Boxes