Steps of Project Development, Approvals and Clearances
PROJECT STAGES & PROCESSES
LAND/SITE ACQUISITION
This step includes two sub-steps which are – to achieve land lease agreement and changing land
category to industrial from agricultural. This step is very important before we start the project
DETAILED PROJECT REPORT (DPR) AND DETAILED BUSINESS PLAN
A detailed project report and business plan covering the site, technology, cost estimates, cash flows,
risks and returns will be prepared at this stage. The DPR would include information regarding the
potential equipment providers or vendors and must also exhibit the credibility of vendors shortlisted
for final selection. A Detailed Project Report is one of the most important documents to assess the
Calculation of solar PV array capacity, electricity generation and system losses
APPOINTMENT OF EPC CONTRACTOR, EQUIPMENT SUPPLIER/S AND DETAILED PLANT
DESIGN
Appointment of EPC contractor should be based on their past experience.The project developer
shall develop detailed guidelines (project uptime, performance of key systems and sub systems and
other design requirements, time for development, key tasks etc.) for project design and construction
and based on these guidelines appoint an EPC contractor. The EPC contractor shall undertake
detailed plant design with the developer based on inputs from the DPR. The project developer shall
also enter into a detailed EPC agreement with the EPC contractor which shall spell out key
deliverables like project completion timelines, performance guarantees and the specifications of the
equipment to be used during the project construction.Plant design be as per the drawing made by
the consultant in order to avoid any problem in future.
TRANSMISSION AGREEMENT
After the Above stage there is agreement stage, The project developer would need to sign a
transmission agreement with the RVPN. In case of other states it would be the respective STU.Thus
this is also important step in solar project.
CLEARANCES AND APPROVALS
Clearances from all the concerned department in order to avoid any delay in project. Approval or
clearances would need to be attained during project construction from various departments. The
State Nodal Agency (SNA/RREC) may in some of the states act as facilitator for obtaining these
clearances. Major clearances which form part of this step are;
 Pollution Control Board
 Import/Export Certificate
 No objection certificate from Civil Aviation Department
 No objection certificate from district collector for setting up the project
 Consent for establishment and consent to operate from state pollution control board
 Permission for laying power evacuation lines by chief electrical inspector
 Permission for ‘Implementation of Metering Code’, ‘Protection System’ to be obtained from
host Distribution Utility or the State Transmission Utility or the Central Transmission Utility as
the case may be.We must take permissions as per the policy of the state. Without all the
approval we cannot start our project.
PLACING EQUIPMENT PROCUREMENT ORDERS AND SIGNING PERFORMANCE
CONTRACTS WITH EQUIPMENT/ PANEL SUPPLIERS
Equipment Procurement is very important & it effects the performance of the project,The project
developer would need to place orders for the equipment and enter into performance guarantee
agreements with equipment suppliers. The project developer would also need to see the lead time
for equipment procurement and delivery while also provisioning time for obtaining customs and
import duty exemptions. Thus we can see without best quality equipment our performance will not be
good.
APPOINTMENT OF O&M CONTRACTOR
After the installation of the project maintenance of the project is very important so that we get beeter
performance continuously. The project developer shall appoint a private O&M contractor and enter
into an O&M contract. This shall specify details regarding project uptime, personnel required, spare
parts, acquisition for project for operation and management.
Some key tasks besides operation, preventive and routine maintenance shall include:
 Preventive maintenance policies
 Cleaning, washing of PV modules
 Tracker maintenance, if applicable
 BOS inspection
 Penalty on underperformance
 Quality service
 Timely maintenance.
 Trained & Skilled manpower with O&M Contractor.
APPLICABLE INSURANCE POLICY & RISK COVER
In order to make our project risk free Insurance Policy will have to be taken by the developer during
the Construction period related to:
 Damage to Equipment (During Procurement, Transit & Erection)
 Force Majeure
 PPA risk cover
 Non delivery
 Insurance Policy will have to be taken by the developer during the Operation period related
to:
 Theft and damage of equipment/project
 Machinery Breakdown
 Force Majeure
 Risk
These are the steps involved during the project development, Approval & Clearances these
steps are as per the Rajasthan Solar Policy for other state also steps remain same only few
point will change as per the solar Policy of that state.
Rambans Solar Project Techno-Economic Pre-Feasibility Studies & Detailed Project Report
[DPR] :
Any development will need to undertake a feasibility study to give you the information necessary to
decide whether to proceed or not. Prefeasibility and feasibility studies are crucial phases in the
development and growth of your Solar project.
Rambans Energy Systems broadly carry out preparatory / pre-feasibility / DPR studies thereby
enabling the Project Developers / Investors to undertake a decisive judgment for their particular
investment opportunity to invest in Solar Power Generation & for those who are willing to foray into
solar arena.
Generally the study will compromise solar sector investment options and priorities, initial scoping
and costing of the identified investment project and designing the execution and finance structures
for implementation of the Solar Power Project.
We hence educate & provide proper guidance to solar project developers during the project
allotment process so that they remain in line with their state policy without any violation of law.
For Details Regarding Solar Project & Consultancy
contact:+91-(8527)-02-1151 or
mail:rambansenergysystems@gmail.com or visit
www.rambans.com

Weitere ähnliche Inhalte

Was ist angesagt?

EPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_DeckEPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_Deck
Jaswin Sood
 
Site Instruction Provision
Site Instruction ProvisionSite Instruction Provision
Site Instruction Provision
Richard Retita
 
Whole life performance lecture south bank university
Whole life performance lecture   south bank universityWhole life performance lecture   south bank university
Whole life performance lecture south bank university
Kim Newman
 

Was ist angesagt? (19)

Epc Vs Epcm
Epc Vs EpcmEpc Vs Epcm
Epc Vs Epcm
 
EPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_DeckEPC_Enterprise_Systems_Deck
EPC_Enterprise_Systems_Deck
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
COE
COECOE
COE
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM Contracts
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Site Instruction Provision
Site Instruction ProvisionSite Instruction Provision
Site Instruction Provision
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Detailed engineering-design-phase
Detailed engineering-design-phaseDetailed engineering-design-phase
Detailed engineering-design-phase
 
Epc projects and cad tools
Epc projects and cad toolsEpc projects and cad tools
Epc projects and cad tools
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Front End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingFront End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control Training
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Thooyavun R 010715
Thooyavun R 010715Thooyavun R 010715
Thooyavun R 010715
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
 
Whole life performance lecture south bank university
Whole life performance lecture   south bank universityWhole life performance lecture   south bank university
Whole life performance lecture south bank university
 

Ähnlich wie PROJECT_STEPS

Dileep Kumar Kaviti
Dileep Kumar KavitiDileep Kumar Kaviti
Dileep Kumar Kaviti
Dileep Kumar
 
OST Energy - Global Services
OST Energy - Global Services OST Energy - Global Services
OST Energy - Global Services
Sion Haswell
 
RV Resume updated Mar'16
RV Resume updated Mar'16RV Resume updated Mar'16
RV Resume updated Mar'16
Rahul Vadgama
 
CV - Tarun (Electrical Engineer)
CV - Tarun (Electrical Engineer) CV - Tarun (Electrical Engineer)
CV - Tarun (Electrical Engineer)
Tarun Kumar
 
PATHIK MITRA-PROJECTS
PATHIK MITRA-PROJECTSPATHIK MITRA-PROJECTS
PATHIK MITRA-PROJECTS
pathik mitra
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
jitendra kumar biswas
 
Vikram Prabhakar Updated Resume
Vikram Prabhakar Updated ResumeVikram Prabhakar Updated Resume
Vikram Prabhakar Updated Resume
Vikram Prabhakar
 

Ähnlich wie PROJECT_STEPS (20)

Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
Dileep Kumar Kaviti
Dileep Kumar KavitiDileep Kumar Kaviti
Dileep Kumar Kaviti
 
OST Energy - Global Services
OST Energy - Global Services OST Energy - Global Services
OST Energy - Global Services
 
RV Resume updated Mar'16
RV Resume updated Mar'16RV Resume updated Mar'16
RV Resume updated Mar'16
 
CV
CVCV
CV
 
Project Careers Oil&Gas
Project Careers Oil&Gas Project Careers Oil&Gas
Project Careers Oil&Gas
 
Prudhivi__Rushi_CV
Prudhivi__Rushi_CVPrudhivi__Rushi_CV
Prudhivi__Rushi_CV
 
CV - Tarun (Electrical Engineer)
CV - Tarun (Electrical Engineer) CV - Tarun (Electrical Engineer)
CV - Tarun (Electrical Engineer)
 
NY_ CV
NY_ CVNY_ CV
NY_ CV
 
UON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfUON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdf
 
Srinivaskumar_cv_16
Srinivaskumar_cv_16Srinivaskumar_cv_16
Srinivaskumar_cv_16
 
PATHIK MITRA-PROJECTS
PATHIK MITRA-PROJECTSPATHIK MITRA-PROJECTS
PATHIK MITRA-PROJECTS
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 
Construction plan
Construction planConstruction plan
Construction plan
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Vikram Prabhakar Updated Resume
Vikram Prabhakar Updated ResumeVikram Prabhakar Updated Resume
Vikram Prabhakar Updated Resume
 
E governance project conceptualisation to implementation
E governance project conceptualisation to implementationE governance project conceptualisation to implementation
E governance project conceptualisation to implementation
 

Kürzlich hochgeladen

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 

Kürzlich hochgeladen (20)

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 

PROJECT_STEPS

  • 1. 2015 Save Energy Save Money RAMBANS ENERGY SYSTEMS 7/8/2015 Steps of Project Development, Approvals and Clearances
  • 2. PROJECT STAGES & PROCESSES LAND/SITE ACQUISITION This step includes two sub-steps which are – to achieve land lease agreement and changing land category to industrial from agricultural. This step is very important before we start the project DETAILED PROJECT REPORT (DPR) AND DETAILED BUSINESS PLAN A detailed project report and business plan covering the site, technology, cost estimates, cash flows, risks and returns will be prepared at this stage. The DPR would include information regarding the potential equipment providers or vendors and must also exhibit the credibility of vendors shortlisted for final selection. A Detailed Project Report is one of the most important documents to assess the Calculation of solar PV array capacity, electricity generation and system losses
  • 3. APPOINTMENT OF EPC CONTRACTOR, EQUIPMENT SUPPLIER/S AND DETAILED PLANT DESIGN Appointment of EPC contractor should be based on their past experience.The project developer shall develop detailed guidelines (project uptime, performance of key systems and sub systems and other design requirements, time for development, key tasks etc.) for project design and construction and based on these guidelines appoint an EPC contractor. The EPC contractor shall undertake detailed plant design with the developer based on inputs from the DPR. The project developer shall also enter into a detailed EPC agreement with the EPC contractor which shall spell out key deliverables like project completion timelines, performance guarantees and the specifications of the equipment to be used during the project construction.Plant design be as per the drawing made by the consultant in order to avoid any problem in future. TRANSMISSION AGREEMENT After the Above stage there is agreement stage, The project developer would need to sign a transmission agreement with the RVPN. In case of other states it would be the respective STU.Thus this is also important step in solar project. CLEARANCES AND APPROVALS Clearances from all the concerned department in order to avoid any delay in project. Approval or clearances would need to be attained during project construction from various departments. The State Nodal Agency (SNA/RREC) may in some of the states act as facilitator for obtaining these clearances. Major clearances which form part of this step are;  Pollution Control Board  Import/Export Certificate  No objection certificate from Civil Aviation Department  No objection certificate from district collector for setting up the project  Consent for establishment and consent to operate from state pollution control board  Permission for laying power evacuation lines by chief electrical inspector  Permission for ‘Implementation of Metering Code’, ‘Protection System’ to be obtained from host Distribution Utility or the State Transmission Utility or the Central Transmission Utility as the case may be.We must take permissions as per the policy of the state. Without all the approval we cannot start our project. PLACING EQUIPMENT PROCUREMENT ORDERS AND SIGNING PERFORMANCE CONTRACTS WITH EQUIPMENT/ PANEL SUPPLIERS Equipment Procurement is very important & it effects the performance of the project,The project developer would need to place orders for the equipment and enter into performance guarantee agreements with equipment suppliers. The project developer would also need to see the lead time for equipment procurement and delivery while also provisioning time for obtaining customs and import duty exemptions. Thus we can see without best quality equipment our performance will not be good.
  • 4. APPOINTMENT OF O&M CONTRACTOR After the installation of the project maintenance of the project is very important so that we get beeter performance continuously. The project developer shall appoint a private O&M contractor and enter into an O&M contract. This shall specify details regarding project uptime, personnel required, spare parts, acquisition for project for operation and management. Some key tasks besides operation, preventive and routine maintenance shall include:  Preventive maintenance policies  Cleaning, washing of PV modules  Tracker maintenance, if applicable  BOS inspection  Penalty on underperformance  Quality service  Timely maintenance.  Trained & Skilled manpower with O&M Contractor. APPLICABLE INSURANCE POLICY & RISK COVER In order to make our project risk free Insurance Policy will have to be taken by the developer during the Construction period related to:  Damage to Equipment (During Procurement, Transit & Erection)  Force Majeure  PPA risk cover  Non delivery  Insurance Policy will have to be taken by the developer during the Operation period related to:  Theft and damage of equipment/project  Machinery Breakdown  Force Majeure  Risk These are the steps involved during the project development, Approval & Clearances these steps are as per the Rajasthan Solar Policy for other state also steps remain same only few point will change as per the solar Policy of that state. Rambans Solar Project Techno-Economic Pre-Feasibility Studies & Detailed Project Report [DPR] : Any development will need to undertake a feasibility study to give you the information necessary to decide whether to proceed or not. Prefeasibility and feasibility studies are crucial phases in the development and growth of your Solar project.
  • 5. Rambans Energy Systems broadly carry out preparatory / pre-feasibility / DPR studies thereby enabling the Project Developers / Investors to undertake a decisive judgment for their particular investment opportunity to invest in Solar Power Generation & for those who are willing to foray into solar arena. Generally the study will compromise solar sector investment options and priorities, initial scoping and costing of the identified investment project and designing the execution and finance structures for implementation of the Solar Power Project. We hence educate & provide proper guidance to solar project developers during the project allotment process so that they remain in line with their state policy without any violation of law. For Details Regarding Solar Project & Consultancy contact:+91-(8527)-02-1151 or mail:rambansenergysystems@gmail.com or visit www.rambans.com