11. 1.5 EFFECT OF W/T In dry drilling of borehole ingress of small quantity of water from sides of the borehole reduces the Skin Friction and from the bottom of borehole reduces the End Bearing. In this condition concreting should be carried out with Tremmie Pipe otherwise segregation of concrete may occur as shown in Fig. SEGREGATION OF CONCRETE
22. 3.4 PROBLEMS IN SOFT GROUND In soft ground having undrained shear strength less than 15kn/m 2 causing the squeezing of the pile section near the head because lateral pressure of soil is more than the lateral pressure of concrete as shown in Fig. SQUEEZING OF THE PILE SECTION
23. CONCLUSIONS Full time supervision of pile construction should be carried out by an experienced Engineer which gives us the designed pile capacity