Trilateration and Triangulation(3 hr)
CHAPTERCHAPTERCHAPTERCHAPTER 8888
Asst. Prof. Pramesh Hada
BE Civil, MSC Urban planning
Assistant Professor
Nepal Engineering College,
Changunarayan,Bhaktapur
By:-
Chp 8. Trilateration and Triangulation (3 Hour)
(Important for Short Notes)
• Principles of Trilateration
• Principles and Classification of Triangulation
Systems (pu2013)
• Strength of Figure
Satellite Stations and Inter – Visibility of• Satellite Stations and Inter – Visibility of
Triangulation Stations (pu,2011)
• Instruction on Field Works
Short note – traingulation and trilateration (Pu 2008,09*2,010,012)
Distinguish between traingulation and trilateration (2011)
Advantages of Trilateration (2011)
Er. Pramesh Hada, Assistant Professor, nec
Er. Pramesh Hada, Assistant Professor, nec
Trilateration (Length Measured all sides- angles computed by Cosine rule)
• Method in which the lengths of all sides
of chain of triangles, polygons, or quadril
aterals (or any combination of them) are
measured with an electronic instrument
orothers; the angles then may be compu
ted from these field measurements.
• Uses in the construction of a chain or ne
twork of interconnected triangles in
• Uses in the construction of a chain or ne
twork of interconnected triangles in
a given area and the measurement of
all three sides of each triangle.
Er. Pramesh Hada, Assistant Professor, nec
•Angles of the triangles and the coordinates of their vertices
are determined by trigonometric computations.
•In contrast to triangulation, it does not involve the
measurement of angles in a field.
•Trilateration has the same purpose as triangulation.
Trilateration Network
Er. Pramesh Hada, Assistant Professor, nec
Er. Pramesh Hada, Assistant Professor, nec
Sine Rule & cosine rule (for both methods)
Trilateration and its Principles
• Trilateration is a highly accurate and precise method of establishing and
expanding horizontal control.
• Method of control survey in which a network of triangles is used as in
triangulation system.
• All the three sides of each triangle are measured in the field with the distance
measuring instruments(EDMs, tapes, other apparatus).
• Horizontal angles are not measured in the field.
• Angles in a trilateration system are computed indirectly from the lengths of the
sides of triangle by cosine formula.
• Few horizontal angles are also sometimes measured to provide a check on• Few horizontal angles are also sometimes measured to provide a check on
computed angles.
• Trilateration is adjusted after the computation of the angles and then
coordinates of the stations are determined.
• Vertical angles are also measured where elevations have not been established.
Er. Pramesh Hada, Assistant Professor, nec
Triangulation and its Principles
• It is the process of measuring the angles of a chain
or network of triangles formed by stations marked
on the surface of the earth.
• The system consists of a number of interconnected
triangles in which the length of only one base line
and the angles of the triangles are measured veryand the angles of the triangles are measured very
precisely which are used to calculate the coordinate
of vertices.
Er. Pramesh Hada, Assistant Professor, nec
Er. Pramesh Hada, Assistant Professor, nec
Note : Red – base line
Principle of triangulation
• If all the three angles and the length of one side of a triangle are
known, then by trigonometry the lengths of the remaining sides
of the triangle can be calculated.
• Again, if the coordinates of any vertex of the triangle and
azimuth of any side are also known, then coordinates of the
remaining vertices may be computed.
Er. Pramesh Hada, Assistant Professor, nec
Bridge site survey
By Triangulation
Method
Er. Pramesh Hada, Assistant Professor, nec
Bridge site Survey by Triangulation
Bridge site Survey by Triangulation
Er. Pramesh Hada, Assistant Professor, nec
Triangulation
Background
• In survey ,it is necessary to determine the ground
position i.e. coordinates of the station which prevent
the accumulation of errors and will form a frame work
on which entire survey is to be based. This is called
control point establishment.
• Such provision of control point can be made either one• Such provision of control point can be made either one
or combination of both the following methods
1. Traverse
2. Triangulation
Triangulation is considered to be more accurate than
traversing as there is less accumulation of errors than
that in traverse.
Er. Pramesh Hada, Assistant Professor, nec
Er. Pramesh Hada, Assistant Professor, nec
Er. Pramesh Hada, Assistant Professor, nec
•Triangulation using AB as a base line.
•Distance AB is measured precisely.
•Then C, D, E, F, G, H, I, J and K can be fixed by angular measurement only.Er. Pramesh Hada, Assistant Professor, nec
• In triangulation all the three angles of each triangle are
measured in the field along with one baseline.
• The side of the first triangle whose length is
predetermined is called the base line and vertices of the
individual triangles are known as triangulation stations
and the whole figure is called the triangulation system or
triangulation figure.
• The length and azimuth of each line is based on the
Triangulation and its Principles
• The length and azimuth of each line is based on the
length and azimuth of preceding line.
• To minimize accumulation of errors in lengths, subsidiary
bases at suitable intervals are provided
• To control errors in azimuth of stations, astronomical
observations are made at intermediate stations.
Er. Pramesh Hada, Assistant Professor, nec
Formula to compute co-ordinate of vetices
Er. Pramesh Hada, Assistant Professor, nec
Purpose of Triangulation Surveys
Triangulation surveys are carried out for:
1. Establishment of accurate control points for
plane and geodetic surveys of large areas, by
ground methods.
1. Establishment of accurate control points for
photogrammetric surveys of large areas.
2. Accurate location of engineering works i.e.2. Accurate location of engineering works i.e.
a. Fixing the centre line, terminal points and shafts
for long tunnels,
b. Fixing centre line and abutments of long bridges
over large rivers
c. Transferring the control points across wide sea
channels, large water bodies etc.
Er. Pramesh Hada, Assistant Professor, nec
Er. Pramesh Hada, Assistant Professor, nec
Classification of Triangulations
• The basis of the classification of triangulation figures is the accuracy
with which the length and azimuth of a line of the triangulation are
determined.
• On the basis of quality , accuracy & purpose, triangulations are
classified as:
1. Primary or First order Triangulation
2. Secondary or Second order Triangulation
3. Tertiary or Third order Triangulation
Primary or First order Triangulation:Primary or First order Triangulation:
• Is the highest grade of triangulation system.
• To determine the shape & size of earth surface or to provide precise
planimetric control points to which subsidiary triangulations may be
connected.
• Stations of first order triangulation are generally selected 16 to 150
Km apart.
• Every possible precaution is taken in making linear, angular and
astronomical observations, and also in their computation.
Er. Pramesh Hada, Assistant Professor, nec
2. Secondary or Second order Triangulation:
• The secondary triangulation consists of a number of points fixed within
the framework of primary triangulation.
• To provide control points closer together than those of primary.
• Secondary is classified, If primary doesnot attain standard of accuracy.
• The stations are fixed at close intervals so that the sizes of the triangles
formed are smaller than the primary triangulation. (length = 8-65km)
3. Tertiary or Third order Triangulation:3. Tertiary or Third order Triangulation:
• Employed to provide control points between stations of primary &
second order series.
• The third order triangulation consists of a number of points fixed within
the framework of secondary triangulation, and forms the immediate
control for detailed engineering and other surveys.
• The sizes of the triangles are small and instrument with moderate
precision may be used.
• For topogaphical details, tertiary triangulations forms immediate
control points. (length = 1.5 -10km)
Er. Pramesh Hada, Assistant Professor, nec
STRENGTH OF FIGURE(well condition Triangle)
• These are Accuracy in Triangle depend upon –
- Magnitude of angles in individual traingle.
- Arrangement of traingles (shape of triangles) -
• The strength of figure is a factor to be considered in establishing a
triangulation system to maintain the computations within a desired
degree of precision.
• It plays also an important role in deciding the layout of a triangulation
system.
• U.S. Coast and Geodetic Surveys has developed a convenient method of• U.S. Coast and Geodetic Surveys has developed a convenient method of
evaluating the strength of a triangulation figure.
• It is based on the fact that computations in triangulation involve use of
angles of triangle and length of one known side. The other two sides
are computed by sine law.
• For a given change in the angles, the sine of small angles change more
rapidly than those of large angles.
• This suggests that smaller angles less than 30° should not be used
in the computation of triangulation.
Er. Pramesh Hada, Assistant Professor, nec
Layout of Triangulation
• The arrangement of the triangles of a series is known as the layout of
triangulation.
A series of triangulation may consists of:
1. Single chain of triangles
- narrow strip is cover
2. Double chain of triangles
-- cover large area
3. Centred Figures
--cover area and give satisfactory
result in flat area.-Progress slow
4.Quadrilaterals
--best for hilly areas.-accurate
Er. Pramesh Hada, Assistant Professor, nec
Satellite Stations
• To secure well-conditioned triangles or to have good visibility,
objects such as chimneys, flat poles, towers, lighthouse, etc. are
selected as triangulation stations.
• Such stations can be sighted from other stations but it is not
possible to occupy the station directly below such excellent
targets for making the observations by setting up the instrument
over the station point.over the station point.
• Also, signals are frequently blown out of position, and angles read
on them have to be corrected to the true position of the
triangulation station. Thus, there are two types of problems:
1. When the instrument is not set up over the true station
2. When the target is out of position.
Er. Pramesh Hada, Assistant Professor, nec
• In Fig. 1.39, A, B, and C are the three triangulation
stations.
• It is not possible to place instrument at C.
• To solve this problem another station S, in the vicinity
of C, is selected where the instrument can be set up,
and from where all the three stations are visible for
making the angle observations.making the angle observations.
• Such station is known as satellite station.
• As the observations from C are not possible, the
observations form S are made on A, B, and, C from A
and B on C.
• From the observations made, the required angle ACB is
calculated. This is known as reduction to centre.
Er. Pramesh Hada, Assistant Professor, nec
Criteria for selection of triangulation stations
• Triangulation stations should be intervisible. For this
purpose the station points should be on the highest
ground such as hill tops, house tops, etc.
• Stations should be easily accessible with instruments.
• Station should form well-conditioned triangles.
• Stations should be at commanding positions so as to
serve as control for subsidiary triangulation, and for
• Stations should be at commanding positions so as to
serve as control for subsidiary triangulation, and for
possible extension of the main triangulation scheme.
• Stations should be useful for providing intersected points
and also for detail survey.
• Stations should be selected such that the cost of clearing
and cutting, and building towers, is minimum.
Er. Pramesh Hada, Assistant Professor, nec
Field work of Triangulation Survey
• Field work of triangulation involves the following
steps:
1. Reconnaissance
2. Erection of signals
3. Measurement of the base lines3. Measurement of the base lines
4. Measurement of horizontal angles
5. Astronomical observations
6. Computations
Short note – traingulation and trilateration (Pu
2008,09*2,010,012)
Distinguish between traingulation and trilateration
(2011)
Advantages of Trilateration (2011)
Tutorial 3 – PH (T & T)
Advantages of Trilateration (2011)
Write about Principles and Classification of
Triangulation Systems (pu2013)
Write short notes on Strength of Figure.
Explain about Satellite Stations and Inter – Visibility
of Triangulation Stations

Weitere ähnliche Inhalte

Was ist angesagt?

Lecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetryLecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetryVidhi Khokhani
 
Traverse Survey Part 1/2
Traverse Survey Part 1/2Traverse Survey Part 1/2
Traverse Survey Part 1/2Muhammad Zubair
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingDolat Ram
 
Remote sensing in Civil Engineering
Remote sensing in Civil EngineeringRemote sensing in Civil Engineering
Remote sensing in Civil EngineeringManishkumar Dubey
 
Photogrammetry- Surveying
Photogrammetry- SurveyingPhotogrammetry- Surveying
Photogrammetry- SurveyingGokul Saud
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveyingMujeeb Muji
 
Hydrographics surveying
Hydrographics surveyingHydrographics surveying
Hydrographics surveyingMir Zafarullah
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying neharajpl
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveyingstooty s
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying pptNaufil Sayyad
 
Hydrographic survey for std not print
Hydrographic survey for std not printHydrographic survey for std not print
Hydrographic survey for std not printGokul Saud
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levellingParimal Jha
 
Curves and there application in Survey
Curves and there application in SurveyCurves and there application in Survey
Curves and there application in SurveyLord1911
 

Was ist angesagt? (20)

Lecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetryLecture 1-aerial photogrammetry
Lecture 1-aerial photogrammetry
 
Triangulation survey
Triangulation surveyTriangulation survey
Triangulation survey
 
Traverse Survey Part 1/2
Traverse Survey Part 1/2Traverse Survey Part 1/2
Traverse Survey Part 1/2
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
 
Remote sensing in Civil Engineering
Remote sensing in Civil EngineeringRemote sensing in Civil Engineering
Remote sensing in Civil Engineering
 
Photogrammetry- Surveying
Photogrammetry- SurveyingPhotogrammetry- Surveying
Photogrammetry- Surveying
 
tacheometric surveying
tacheometric surveyingtacheometric surveying
tacheometric surveying
 
Hydrographics surveying
Hydrographics surveyingHydrographics surveying
Hydrographics surveying
 
GPS Surveying
GPS SurveyingGPS Surveying
GPS Surveying
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Theodolite survey
Theodolite surveyTheodolite survey
Theodolite survey
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveying
 
surveying contouring
surveying contouring surveying contouring
surveying contouring
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying ppt
 
Plane Table Surveying PPt
Plane Table Surveying PPtPlane Table Surveying PPt
Plane Table Surveying PPt
 
Contouring
ContouringContouring
Contouring
 
Hydrographic survey for std not print
Hydrographic survey for std not printHydrographic survey for std not print
Hydrographic survey for std not print
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
 
Curves
CurvesCurves
Curves
 
Curves and there application in Survey
Curves and there application in SurveyCurves and there application in Survey
Curves and there application in Survey
 

Ähnlich wie Triangulation and Trilateration

Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxTriangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxRomil Mishra
 
Lecture note triangulation_and_trilatera2016
Lecture note triangulation_and_trilatera2016Lecture note triangulation_and_trilatera2016
Lecture note triangulation_and_trilatera2016Mitiku Chachu
 
UNIT 1_Chapter 2_Adv Survey.pptx
UNIT 1_Chapter 2_Adv Survey.pptxUNIT 1_Chapter 2_Adv Survey.pptx
UNIT 1_Chapter 2_Adv Survey.pptxMrunmayee Manjari
 
TECHNIQUES IN BASIC SURVEYING.ppt
TECHNIQUES IN BASIC SURVEYING.pptTECHNIQUES IN BASIC SURVEYING.ppt
TECHNIQUES IN BASIC SURVEYING.pptArisamTom
 
7. GEODETIC SYRVEYING (SUR) 3140601 GTU
7. GEODETIC SYRVEYING (SUR) 3140601 GTU7. GEODETIC SYRVEYING (SUR) 3140601 GTU
7. GEODETIC SYRVEYING (SUR) 3140601 GTUVATSAL PATEL
 
Fundamentals of surveying
Fundamentals of surveyingFundamentals of surveying
Fundamentals of surveyingSimonReuben2
 
fundamentals_of_surveying (2).pdf
fundamentals_of_surveying (2).pdffundamentals_of_surveying (2).pdf
fundamentals_of_surveying (2).pdfsandipanpaul16
 
Theory of theodolite traversing
Theory of theodolite traversingTheory of theodolite traversing
Theory of theodolite traversingEr. Suman Jyoti
 
Various Types of Triangulation Figure.
Various Types of Triangulation Figure.Various Types of Triangulation Figure.
Various Types of Triangulation Figure.Rushikesh Katkar
 
TOTAL STATION: THEORY, USES AND APPLICATIONS.
TOTAL STATION: THEORY, USES AND APPLICATIONS. TOTAL STATION: THEORY, USES AND APPLICATIONS.
TOTAL STATION: THEORY, USES AND APPLICATIONS. Ahmed Nassar
 
Week1 introductiontobasicsurveying
Week1 introductiontobasicsurveyingWeek1 introductiontobasicsurveying
Week1 introductiontobasicsurveyingJackie Arul
 
Traversing Notes |surveying II | Sudip khadka
Traversing Notes |surveying II | Sudip khadka Traversing Notes |surveying II | Sudip khadka
Traversing Notes |surveying II | Sudip khadka Sudip khadka
 
Chain surveying and offset
Chain surveying and offsetChain surveying and offset
Chain surveying and offsetMir Zafarullah
 
S2 5 traverses
S2 5 traversesS2 5 traverses
S2 5 traversesEst
 
Distance Measurement & Chain Surveying
Distance Measurement & Chain SurveyingDistance Measurement & Chain Surveying
Distance Measurement & Chain SurveyingBahzad5
 
Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveysbrett_grocock
 

Ähnlich wie Triangulation and Trilateration (20)

Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxTriangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
 
Lecture note triangulation_and_trilatera2016
Lecture note triangulation_and_trilatera2016Lecture note triangulation_and_trilatera2016
Lecture note triangulation_and_trilatera2016
 
UNIT 1_Chapter 2_Adv Survey.pptx
UNIT 1_Chapter 2_Adv Survey.pptxUNIT 1_Chapter 2_Adv Survey.pptx
UNIT 1_Chapter 2_Adv Survey.pptx
 
TECHNIQUES IN BASIC SURVEYING.ppt
TECHNIQUES IN BASIC SURVEYING.pptTECHNIQUES IN BASIC SURVEYING.ppt
TECHNIQUES IN BASIC SURVEYING.ppt
 
7. GEODETIC SYRVEYING (SUR) 3140601 GTU
7. GEODETIC SYRVEYING (SUR) 3140601 GTU7. GEODETIC SYRVEYING (SUR) 3140601 GTU
7. GEODETIC SYRVEYING (SUR) 3140601 GTU
 
BCE U3.pptx
BCE U3.pptxBCE U3.pptx
BCE U3.pptx
 
Module-I SURVEYING-I [BTCVC304]
Module-I SURVEYING-I [BTCVC304]Module-I SURVEYING-I [BTCVC304]
Module-I SURVEYING-I [BTCVC304]
 
Fundamentals of surveying
Fundamentals of surveyingFundamentals of surveying
Fundamentals of surveying
 
fundamentals_of_surveying (2).pdf
fundamentals_of_surveying (2).pdffundamentals_of_surveying (2).pdf
fundamentals_of_surveying (2).pdf
 
Theory of theodolite traversing
Theory of theodolite traversingTheory of theodolite traversing
Theory of theodolite traversing
 
Surveying 2
Surveying   2Surveying   2
Surveying 2
 
Various Types of Triangulation Figure.
Various Types of Triangulation Figure.Various Types of Triangulation Figure.
Various Types of Triangulation Figure.
 
TOTAL STATION: THEORY, USES AND APPLICATIONS.
TOTAL STATION: THEORY, USES AND APPLICATIONS. TOTAL STATION: THEORY, USES AND APPLICATIONS.
TOTAL STATION: THEORY, USES AND APPLICATIONS.
 
Week1 introductiontobasicsurveying
Week1 introductiontobasicsurveyingWeek1 introductiontobasicsurveying
Week1 introductiontobasicsurveying
 
Traversing Notes |surveying II | Sudip khadka
Traversing Notes |surveying II | Sudip khadka Traversing Notes |surveying II | Sudip khadka
Traversing Notes |surveying II | Sudip khadka
 
Chain surveying and offset
Chain surveying and offsetChain surveying and offset
Chain surveying and offset
 
S2 5 traverses
S2 5 traversesS2 5 traverses
S2 5 traverses
 
Surveying pdf
Surveying pdfSurveying pdf
Surveying pdf
 
Distance Measurement & Chain Surveying
Distance Measurement & Chain SurveyingDistance Measurement & Chain Surveying
Distance Measurement & Chain Surveying
 
Wall Station Surveys
Wall Station SurveysWall Station Surveys
Wall Station Surveys
 

Kürzlich hochgeladen

HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfsmsksolar
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxnuruddin69
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...Health
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 

Kürzlich hochgeladen (20)

HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 

Triangulation and Trilateration

  • 1. Trilateration and Triangulation(3 hr) CHAPTERCHAPTERCHAPTERCHAPTER 8888 Asst. Prof. Pramesh Hada BE Civil, MSC Urban planning Assistant Professor Nepal Engineering College, Changunarayan,Bhaktapur By:-
  • 2. Chp 8. Trilateration and Triangulation (3 Hour) (Important for Short Notes) • Principles of Trilateration • Principles and Classification of Triangulation Systems (pu2013) • Strength of Figure Satellite Stations and Inter – Visibility of• Satellite Stations and Inter – Visibility of Triangulation Stations (pu,2011) • Instruction on Field Works Short note – traingulation and trilateration (Pu 2008,09*2,010,012) Distinguish between traingulation and trilateration (2011) Advantages of Trilateration (2011) Er. Pramesh Hada, Assistant Professor, nec
  • 3. Er. Pramesh Hada, Assistant Professor, nec
  • 4. Trilateration (Length Measured all sides- angles computed by Cosine rule) • Method in which the lengths of all sides of chain of triangles, polygons, or quadril aterals (or any combination of them) are measured with an electronic instrument orothers; the angles then may be compu ted from these field measurements. • Uses in the construction of a chain or ne twork of interconnected triangles in • Uses in the construction of a chain or ne twork of interconnected triangles in a given area and the measurement of all three sides of each triangle. Er. Pramesh Hada, Assistant Professor, nec •Angles of the triangles and the coordinates of their vertices are determined by trigonometric computations. •In contrast to triangulation, it does not involve the measurement of angles in a field. •Trilateration has the same purpose as triangulation.
  • 5. Trilateration Network Er. Pramesh Hada, Assistant Professor, nec
  • 6. Er. Pramesh Hada, Assistant Professor, nec Sine Rule & cosine rule (for both methods)
  • 7. Trilateration and its Principles • Trilateration is a highly accurate and precise method of establishing and expanding horizontal control. • Method of control survey in which a network of triangles is used as in triangulation system. • All the three sides of each triangle are measured in the field with the distance measuring instruments(EDMs, tapes, other apparatus). • Horizontal angles are not measured in the field. • Angles in a trilateration system are computed indirectly from the lengths of the sides of triangle by cosine formula. • Few horizontal angles are also sometimes measured to provide a check on• Few horizontal angles are also sometimes measured to provide a check on computed angles. • Trilateration is adjusted after the computation of the angles and then coordinates of the stations are determined. • Vertical angles are also measured where elevations have not been established. Er. Pramesh Hada, Assistant Professor, nec
  • 8. Triangulation and its Principles • It is the process of measuring the angles of a chain or network of triangles formed by stations marked on the surface of the earth. • The system consists of a number of interconnected triangles in which the length of only one base line and the angles of the triangles are measured veryand the angles of the triangles are measured very precisely which are used to calculate the coordinate of vertices. Er. Pramesh Hada, Assistant Professor, nec
  • 9. Er. Pramesh Hada, Assistant Professor, nec Note : Red – base line
  • 10. Principle of triangulation • If all the three angles and the length of one side of a triangle are known, then by trigonometry the lengths of the remaining sides of the triangle can be calculated. • Again, if the coordinates of any vertex of the triangle and azimuth of any side are also known, then coordinates of the remaining vertices may be computed. Er. Pramesh Hada, Assistant Professor, nec Bridge site survey By Triangulation Method
  • 11. Er. Pramesh Hada, Assistant Professor, nec Bridge site Survey by Triangulation
  • 12. Bridge site Survey by Triangulation Er. Pramesh Hada, Assistant Professor, nec
  • 13. Triangulation Background • In survey ,it is necessary to determine the ground position i.e. coordinates of the station which prevent the accumulation of errors and will form a frame work on which entire survey is to be based. This is called control point establishment. • Such provision of control point can be made either one• Such provision of control point can be made either one or combination of both the following methods 1. Traverse 2. Triangulation Triangulation is considered to be more accurate than traversing as there is less accumulation of errors than that in traverse. Er. Pramesh Hada, Assistant Professor, nec
  • 14. Er. Pramesh Hada, Assistant Professor, nec
  • 15. Er. Pramesh Hada, Assistant Professor, nec
  • 16. •Triangulation using AB as a base line. •Distance AB is measured precisely. •Then C, D, E, F, G, H, I, J and K can be fixed by angular measurement only.Er. Pramesh Hada, Assistant Professor, nec
  • 17. • In triangulation all the three angles of each triangle are measured in the field along with one baseline. • The side of the first triangle whose length is predetermined is called the base line and vertices of the individual triangles are known as triangulation stations and the whole figure is called the triangulation system or triangulation figure. • The length and azimuth of each line is based on the Triangulation and its Principles • The length and azimuth of each line is based on the length and azimuth of preceding line. • To minimize accumulation of errors in lengths, subsidiary bases at suitable intervals are provided • To control errors in azimuth of stations, astronomical observations are made at intermediate stations. Er. Pramesh Hada, Assistant Professor, nec
  • 18. Formula to compute co-ordinate of vetices Er. Pramesh Hada, Assistant Professor, nec
  • 19. Purpose of Triangulation Surveys Triangulation surveys are carried out for: 1. Establishment of accurate control points for plane and geodetic surveys of large areas, by ground methods. 1. Establishment of accurate control points for photogrammetric surveys of large areas. 2. Accurate location of engineering works i.e.2. Accurate location of engineering works i.e. a. Fixing the centre line, terminal points and shafts for long tunnels, b. Fixing centre line and abutments of long bridges over large rivers c. Transferring the control points across wide sea channels, large water bodies etc. Er. Pramesh Hada, Assistant Professor, nec
  • 20. Er. Pramesh Hada, Assistant Professor, nec
  • 21. Classification of Triangulations • The basis of the classification of triangulation figures is the accuracy with which the length and azimuth of a line of the triangulation are determined. • On the basis of quality , accuracy & purpose, triangulations are classified as: 1. Primary or First order Triangulation 2. Secondary or Second order Triangulation 3. Tertiary or Third order Triangulation Primary or First order Triangulation:Primary or First order Triangulation: • Is the highest grade of triangulation system. • To determine the shape & size of earth surface or to provide precise planimetric control points to which subsidiary triangulations may be connected. • Stations of first order triangulation are generally selected 16 to 150 Km apart. • Every possible precaution is taken in making linear, angular and astronomical observations, and also in their computation. Er. Pramesh Hada, Assistant Professor, nec
  • 22. 2. Secondary or Second order Triangulation: • The secondary triangulation consists of a number of points fixed within the framework of primary triangulation. • To provide control points closer together than those of primary. • Secondary is classified, If primary doesnot attain standard of accuracy. • The stations are fixed at close intervals so that the sizes of the triangles formed are smaller than the primary triangulation. (length = 8-65km) 3. Tertiary or Third order Triangulation:3. Tertiary or Third order Triangulation: • Employed to provide control points between stations of primary & second order series. • The third order triangulation consists of a number of points fixed within the framework of secondary triangulation, and forms the immediate control for detailed engineering and other surveys. • The sizes of the triangles are small and instrument with moderate precision may be used. • For topogaphical details, tertiary triangulations forms immediate control points. (length = 1.5 -10km) Er. Pramesh Hada, Assistant Professor, nec
  • 23. STRENGTH OF FIGURE(well condition Triangle) • These are Accuracy in Triangle depend upon – - Magnitude of angles in individual traingle. - Arrangement of traingles (shape of triangles) - • The strength of figure is a factor to be considered in establishing a triangulation system to maintain the computations within a desired degree of precision. • It plays also an important role in deciding the layout of a triangulation system. • U.S. Coast and Geodetic Surveys has developed a convenient method of• U.S. Coast and Geodetic Surveys has developed a convenient method of evaluating the strength of a triangulation figure. • It is based on the fact that computations in triangulation involve use of angles of triangle and length of one known side. The other two sides are computed by sine law. • For a given change in the angles, the sine of small angles change more rapidly than those of large angles. • This suggests that smaller angles less than 30° should not be used in the computation of triangulation. Er. Pramesh Hada, Assistant Professor, nec
  • 24. Layout of Triangulation • The arrangement of the triangles of a series is known as the layout of triangulation. A series of triangulation may consists of: 1. Single chain of triangles - narrow strip is cover 2. Double chain of triangles -- cover large area 3. Centred Figures --cover area and give satisfactory result in flat area.-Progress slow 4.Quadrilaterals --best for hilly areas.-accurate Er. Pramesh Hada, Assistant Professor, nec
  • 25. Satellite Stations • To secure well-conditioned triangles or to have good visibility, objects such as chimneys, flat poles, towers, lighthouse, etc. are selected as triangulation stations. • Such stations can be sighted from other stations but it is not possible to occupy the station directly below such excellent targets for making the observations by setting up the instrument over the station point.over the station point. • Also, signals are frequently blown out of position, and angles read on them have to be corrected to the true position of the triangulation station. Thus, there are two types of problems: 1. When the instrument is not set up over the true station 2. When the target is out of position. Er. Pramesh Hada, Assistant Professor, nec
  • 26. • In Fig. 1.39, A, B, and C are the three triangulation stations. • It is not possible to place instrument at C. • To solve this problem another station S, in the vicinity of C, is selected where the instrument can be set up, and from where all the three stations are visible for making the angle observations.making the angle observations. • Such station is known as satellite station. • As the observations from C are not possible, the observations form S are made on A, B, and, C from A and B on C. • From the observations made, the required angle ACB is calculated. This is known as reduction to centre. Er. Pramesh Hada, Assistant Professor, nec
  • 27. Criteria for selection of triangulation stations • Triangulation stations should be intervisible. For this purpose the station points should be on the highest ground such as hill tops, house tops, etc. • Stations should be easily accessible with instruments. • Station should form well-conditioned triangles. • Stations should be at commanding positions so as to serve as control for subsidiary triangulation, and for • Stations should be at commanding positions so as to serve as control for subsidiary triangulation, and for possible extension of the main triangulation scheme. • Stations should be useful for providing intersected points and also for detail survey. • Stations should be selected such that the cost of clearing and cutting, and building towers, is minimum. Er. Pramesh Hada, Assistant Professor, nec
  • 28. Field work of Triangulation Survey • Field work of triangulation involves the following steps: 1. Reconnaissance 2. Erection of signals 3. Measurement of the base lines3. Measurement of the base lines 4. Measurement of horizontal angles 5. Astronomical observations 6. Computations
  • 29. Short note – traingulation and trilateration (Pu 2008,09*2,010,012) Distinguish between traingulation and trilateration (2011) Advantages of Trilateration (2011) Tutorial 3 – PH (T & T) Advantages of Trilateration (2011) Write about Principles and Classification of Triangulation Systems (pu2013) Write short notes on Strength of Figure. Explain about Satellite Stations and Inter – Visibility of Triangulation Stations