Technical and Business Offer
     e-commerce site
        « ArtCase »
         2012-07-30
         ORN186C1




                               1/26
sommaire


1 needs understanding
2 our approach


3 our commercial bid
4 our resources



                        2/26
our understanding
   of the need




                    3/26
your need               our understanding of the need



>   project “ArtCase” organized in 3 phases :
     -   phase 1:
           •    launch on Sosh.fr through a corner on their accessories shop
           •    a personalization module to integrate into the Sosh customer journey
           •    planning forecast : November 2012
     -   phase 2:
           •    Artcase standalone site for France with customer journey from A to Z
           •    planning forecast : Q1 2013                       1st launch on Sosh.fr, then Artcase standalone site
     -   phase 3:
           •    replication of Artcase standalone site for          Q4 2012          Q1 2013
                France in OK and Spain.                                        Corner Artcase on SOSH accessories
           •    all sites must be optimized for tablets                       shop
                                                                              Totally integrated into the Sosh customer journey.
                                                                              Exclusive artists on Sosh.

>   constraints :                                                                                    Artcase.com eShop (FR
                                                                                                    then UK tbc)
     -   design, customer experience and visual design                                              •Standalone eshop
                                                                                                    •Cross link with Orange Shop
         will be done by a web agency
                                                                                                                                 Mid term opportunity
     -   furniture of templates, zoning and PSD                                                                                  ArtCase corner on
                                                                                                                                 Orange accessories
                                                                                                                                 eshop?
                                                                    10                         interne France Télécom - Orange




                                                             4/26
your need       the goals



> accessible and intuitive
> full functional coverage : content management, catalog and
  products management, customer spaces, order management, ...
> exchange security
    - compliance with norms and standards, best practices, …
    - lock access between servers
> ability to interface with your information system
> scalable solution to internal processes
> reduce your internal load and increase your Marketing chances
> respect of project schedule



                                    5/26
project management
methodology and process




                          6/26
Project methodology         A team working with agile software development methods

> Sequence of a release (version x.0)
          Sprint 0
                                  Sprint 1                 Sprint 2             Sprint n   End
         Initiation



> Project organized in sprint steps
    Initiating made by Product Owner :
     •   Defining features embedded in sprints : Product Backlog (to do list)
     •   Defining priority tasks (user stories)
    Evaluating made by the project team:
     •   Evaluating tasks duration (planning poker)
     •   Evaluating criteria defining the end of tasks
     •   Building the Sprint Backlog (To do list for each sprint)
    End of each sprint (Sprint review) :
     •   Showing work done through a demo and delivery for CIO
     •   Reporting problems
     •   Taking into account CIO feedbacks (bugs, changes)




                                                         7/26
Project methodology         A team working with agile software development methods

> Tools for agile software development
   The Product Backlog shows the entire to do list (user stories)
     •   some are well defined (forthcoming sprint)
     •   Other need to be reviewed


   Reporting
     •   Burn-up (or Burn-down) chart showing process




> Project steering process
   For each sprint review :
     •   Suggest features included for each sprint : Product Backlog
         (To Do List)
     •   Defining To do List (user stories)




                                                      8/26
Project methodology     Steering



> Profiles
      Project Director
      Project Leader
      Scrum Master
      Technical Expert (if needed)

> Project supervision
      Initiating
      Steering committee
      Steering committee/sprint review
      workshop/daily scrum

> reporting
    Workload consumption
    Defining roadmap
    Dashboard showing indicators




                                          9/26
Project methodology   Initiating



> Kick-off meeting
    Team presentations
    First roadmap with macro-planning

> Team organization
      Building core team and secondary teams
      Implementing project reports & reviews
      Development & integration platforms
      Tools for reviews

> Quality process
    Project Management Plan
    Risk & compliancy monitoring
    Indicators




                                          10/26
Project methodology      Roadmap



> Roadmap is a key document started during the project initiation meeting


> Roadmap lists the To Do list, the following items :
    Tasks and actions
    List of priority
    Continuous activities (corrective maintenance, support, steering,…)
    Complet planning – tasks done by IT&L@bs and stakeholder, project steps


> Roadmap includes :
    MS-Project planning includes the entire list of activities, materials, profiles and reliance
    Budget dash board showing
         Workload used and wahr remains to be done,
         Several indicators for project governance




                                                  11/26
Project methodology      Risk management


> Identifying risks
      id                                  Identify
      Level
      Probality of occurrence
      List actions done to reduce risks                     Estimate              Periodic
                                                               -
                                                            re-estimate            iteration
      trends
                                                                              Defining and updating
> Recognization of probems                                                    actions to reduce risks
  occured et and impact
                                                          Follow efficiency
  analysis on risks in progress                               of actions


> Monitoring risk and actions
  done during the project                   Close risks
  committee.




                                           12/26
Project methodology   Service level management – indicators


> Quality of service is analyzed using indicators defined during
  initialization phase and tracked in reporting

> Indicators evolves depending on project needs & project progress

> Indicators are calculated at least monthly and analyzed during the
  Steering Committee

> Indicators are used by IT&L@bs to highlight through Dashboard
  the quality of service provided on the project




                                         13/26
Project methodology    Global steering process



>   Steering process                                    Steering Committee
       Steering committee
       Project committee                   Steering
                                        Progress meeting
                                     Coordination, monitoring
                                     (action plan, indicators)
                                             Planning
>   Risks management

>   Planning management                                          Project                         Project
                                                                 Manager                        Committee
                                       Synthesis                                 Production
>   Gestion des écarts             Visibility on delivery                       Documentation,
                                    Risk Management                                monitoring
                                   Decisions & actions                       Project communication
                                         Planning




                                                            Project team




                                                14/26
Process                 Identify project steps

                              Step 1

                         Initiation
                Staffing / Quality process
                  Risks / requirements




Features                      Step 2
                                                        Step 3
                 specifications / design                                          Step 4
                                                     Integration/                                          Step 5
                                                    Development             Acceptance /
                       Workshop                                               Delivery         Deployment / support
                                                   Setting Magento                                   Go live
                     Specifications
                                                                            Delivery and
                       Technical                   Graphic charter       Acceptance platform
                                                                                                   Production
                      Architecture                   integration             deployment
                                                                                                   deployment
                       Document
                                                      Custom             Internal acceptance       Operational
                                                    developement
                                                                                                   qualification
                      Web design
                                                                          Client acceptance
                                                   Documentations              support           Go live support
                     Validation / tests
                        document




                                             Steering and Quality process management




                                                                 15/26
our approach




               16/26
our approach      why Magento ?


> an industrialized and recognized solution in the market of e-commerce
  software
     - efficient and respectful of standards (security, architecture, ...)
     - a vibrant community,
     - popular solution that facilitates the recovery of activity in-house or by
       a third party.


> an open source software foundation scalable and interoperable
     - open source that allows own customizations to evolve,
     - integration capability with significant third-party products (via web
       services or connectors and Magento internal API).




                                     17/26
our approach                   an appropriate project organization


Technical host
  manager                                                            Customer Project
                                                                         manager

                                                     Reporting




                                                                                        CV
                                                                               CV
                          CV
                     CV


  Project director


                               Project                                             Project manager
  Quality engineer
                               manager

                                                                              Technical expert

                     Technical expert
                                                                                 Developer

                                                                             ERP Provider
       Developer                         Developer


           Integration technical team



                                                      18/26
our approach          methodology and experience appropriate to large project scope


> experience
    -   IT&L@bs has real experience on large projects that require :
         •     to interface and work with other supplier companies
         •     organize the site into production in line with the overall project schedule


> approach with Quality Assurance (CMMI 3)
    -   monitoring of a quality permits :
         •     well reference the different actors and roles
         •     better track and follow the requirements for the project and its processes
               (via the project dashboard)
         •     track and share risks
         •     optimize actions definition and implementation




                                            19/26
IT&L@bs bid




              20/26
Workload               workload total by project steps

    > Workload display bys steps and profiles
                                       Total workload      Project    Project
               Steps                                                            Expert   DEV
                                        (men / day)        Director   Leader
Project Initiation                          10                1         5         3       1
Specifications and technical
                                            32                          3        8,5     20,5
design

Development & unit tests                    76                                   21      55

Technical integration & internal
                                            17                                    7      10
acceptance test
Delivery / client acceptance tests
                                            18                          2         9       7
& deployment

Project steering                            21                3         18

Risks Management                            10                          1        3,5     5,5

3 months guarantee                          12                                    4       8

                               Total        196               4         29       56      107




                                                   21/26
our bid              commercial bid

                                                                                 Total in € (excluding
                       Steps                                 Workload / travel
                                                                                          VAT)
Project Initiation                                                  10                       6 530,00 €
Specifications and technical design                                 32                      18 005,00 €

Development & unit tests                                            76                      41 750,00 €
Technical integration & internal acceptance test                    17                       9 500,00 €
Delivery / client acceptance tests & deployment                     18                      10 470,00 €
Project steering                                                    21                      14 640,00 €
Risks Management                                                    10                       5 695,00 €
3 months guarantee                                                  12                       6 640,00 €
Options                                                             4                        2 120,00 €
Travel expenses                                                  5 travels                   2 731,20 €

                                                   Total           196                   115 961,20 €

                        Total (including options)                  200                   118 081,20 €


  >    General Terms of sales (available in Annex)


                                                     22/26
our bid             billing schedule (without options)


>   Billing terms and conditions and schedule


            Description                   Milestone          Total HTVA

    30% (order validation)                    T0             34 788,00 €

    20 % delivery of
    specifications & technical          T0+4,5 weeks         23 192,00 €
    design

    25 % delivery for client
                                       T0+ 12,5 weeks        28 990,30 €
    acceptance test

    25 % operational                   En of operational
                                                             28 990,90 €
    acceptance period ended              acceptance

    Total                                                  115 961,20 € HT

>   General Terms of sales (available in Annex)


                                           23/26
our bid             project schedule


> schedule proposal with a T0 at 09/03/2012
   Step                       Marker         Cumulative time   Start date

   Launch                 T0 + 2 weeks      2 weeks            09/03/2012

   Design and
                          T1 + 4,5 weeks    2,5 weeks          09/17/2012
   specifications

   Development            T2 + 10,5 weeks   6 weeks            10/04/2012

   Internal tests (VAU)
                          T3 + 12,5 weeks   2 weeks            11/19/2012
   and delivery
                          T4 + 15 weeks
   End of acceptance
                          acceptance        2,5 weeks          12/03/2012
   support
                          support
                          Operationnal
   End of warranty        tests ended + 3   3 months           12/20/2012
                          month
> proposed dates
   •   production delivery date : 12/03/2012
   •   service phase start date : 12/20/2012


                                            24/26
our resources




                25/26
Gérald Noc                            Anthony Le Postec
"Portal" segment manager              Presales manager

Phone    : +33 2 51 85 16 35          Phone    : +33 2.51.85.16.21
Fax      : +33 2 51 85 16 58          Fax      : +33 2 51 85 16 58
Mobile   : +33 6 72 79 72 04          Mobile   : +33 6.78.53.18.42
gerald.noc@orange.com                 anthony.lepostec@orange.com

Orange Business Services              Orange Business Services
Europarc La Chantrerie                Europarc La Chantrerie
9, boulevard Nicéphore Niepce         9, boulevard Nicéphore Niepce
44300 Nantes                          44300 Nantes




                          IT&Labs Nantes
                                                              26/26

Weitere ähnliche Inhalte

Andere mochten auch

бизнес лига 2014 фотоальбом с открытия и 1 тура
бизнес лига 2014   фотоальбом с открытия и 1 турабизнес лига 2014   фотоальбом с открытия и 1 тура
бизнес лига 2014 фотоальбом с открытия и 1 тураSergio Dios
 
УТС по футболу и мини-футболу в Беларуси (Гомельская область)
УТС по футболу и мини-футболу в Беларуси (Гомельская область)УТС по футболу и мини-футболу в Беларуси (Гомельская область)
УТС по футболу и мини-футболу в Беларуси (Гомельская область)Sergio Dios
 
ФБЛ Гала-Фестиваль в Сочи, 29.09-02.10 2016
ФБЛ Гала-Фестиваль в Сочи, 29.09-02.10 2016ФБЛ Гала-Фестиваль в Сочи, 29.09-02.10 2016
ФБЛ Гала-Фестиваль в Сочи, 29.09-02.10 2016Sergio Dios
 
О "Бизнес Лиге"
О "Бизнес Лиге"О "Бизнес Лиге"
О "Бизнес Лиге"Sergio Dios
 
Презентация программ университета "Синергия"
Презентация программ университета "Синергия"Презентация программ университета "Синергия"
Презентация программ университета "Синергия"Sergio Dios
 
Designing Games for "the 43-year-old woman"
Designing Games for "the 43-year-old woman"Designing Games for "the 43-year-old woman"
Designing Games for "the 43-year-old woman"Chris Trottier
 
Чемпионат "Бизнес-лига" весна 2014 г. звк
Чемпионат "Бизнес-лига" весна 2014 г. звкЧемпионат "Бизнес-лига" весна 2014 г. звк
Чемпионат "Бизнес-лига" весна 2014 г. звкSergio Dios
 

Andere mochten auch (7)

бизнес лига 2014 фотоальбом с открытия и 1 тура
бизнес лига 2014   фотоальбом с открытия и 1 турабизнес лига 2014   фотоальбом с открытия и 1 тура
бизнес лига 2014 фотоальбом с открытия и 1 тура
 
УТС по футболу и мини-футболу в Беларуси (Гомельская область)
УТС по футболу и мини-футболу в Беларуси (Гомельская область)УТС по футболу и мини-футболу в Беларуси (Гомельская область)
УТС по футболу и мини-футболу в Беларуси (Гомельская область)
 
ФБЛ Гала-Фестиваль в Сочи, 29.09-02.10 2016
ФБЛ Гала-Фестиваль в Сочи, 29.09-02.10 2016ФБЛ Гала-Фестиваль в Сочи, 29.09-02.10 2016
ФБЛ Гала-Фестиваль в Сочи, 29.09-02.10 2016
 
О "Бизнес Лиге"
О "Бизнес Лиге"О "Бизнес Лиге"
О "Бизнес Лиге"
 
Презентация программ университета "Синергия"
Презентация программ университета "Синергия"Презентация программ университета "Синергия"
Презентация программ университета "Синергия"
 
Designing Games for "the 43-year-old woman"
Designing Games for "the 43-year-old woman"Designing Games for "the 43-year-old woman"
Designing Games for "the 43-year-old woman"
 
Чемпионат "Бизнес-лига" весна 2014 г. звк
Чемпионат "Бизнес-лига" весна 2014 г. звкЧемпионат "Бизнес-лига" весна 2014 г. звк
Чемпионат "Бизнес-лига" весна 2014 г. звк
 

Ähnlich wie Ptc saunier duval

Case tools and modern process of system development
Case tools and modern process of system development Case tools and modern process of system development
Case tools and modern process of system development tushar217
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software EngineeringMuhammad Yousuf Abdul Qadir
 
The Secret of Flow - My AgileIL11 Talk
The Secret of Flow - My AgileIL11 TalkThe Secret of Flow - My AgileIL11 Talk
The Secret of Flow - My AgileIL11 TalkYuval Yeret
 
SE_Module1new.ppt
SE_Module1new.pptSE_Module1new.ppt
SE_Module1new.pptADARSHN40
 
Examples of projects of the business architecture
Examples of projects of the business architectureExamples of projects of the business architecture
Examples of projects of the business architectureVasily Korablev
 
Why Scrum Why Now
Why Scrum Why NowWhy Scrum Why Now
Why Scrum Why Nowmtoppa
 
Agile planning with Rational Team Concert
Agile planning with Rational Team ConcertAgile planning with Rational Team Concert
Agile planning with Rational Team ConcertReedy Feggins Jr
 
É possível medir se um gigante é ágil?
É possível medir se um gigante é ágil?É possível medir se um gigante é ágil?
É possível medir se um gigante é ágil?Alan Braz
 
ERP solution architect role, part I
ERP solution architect role, part IERP solution architect role, part I
ERP solution architect role, part IViacheslav Nefedov
 
Metodologías agiles de desarrollo de software
Metodologías agiles de desarrollo de softwareMetodologías agiles de desarrollo de software
Metodologías agiles de desarrollo de softwareJuan Gomez
 
SDLC Methodologies
SDLC MethodologiesSDLC Methodologies
SDLC MethodologiesRavikanth-BA
 
RTC & Work Item Customization Overview
RTC & Work Item Customization OverviewRTC & Work Item Customization Overview
RTC & Work Item Customization OverviewBharat Malge
 

Ähnlich wie Ptc saunier duval (20)

CV_AliceParisis_en1
CV_AliceParisis_en1CV_AliceParisis_en1
CV_AliceParisis_en1
 
Case tools and modern process of system development
Case tools and modern process of system development Case tools and modern process of system development
Case tools and modern process of system development
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software Engineering
 
Asap overview
Asap overviewAsap overview
Asap overview
 
The Secret of Flow - My AgileIL11 Talk
The Secret of Flow - My AgileIL11 TalkThe Secret of Flow - My AgileIL11 Talk
The Secret of Flow - My AgileIL11 Talk
 
SE_Module1new.ppt
SE_Module1new.pptSE_Module1new.ppt
SE_Module1new.ppt
 
Examples of projects of the business architecture
Examples of projects of the business architectureExamples of projects of the business architecture
Examples of projects of the business architecture
 
Why Scrum Why Now
Why Scrum Why NowWhy Scrum Why Now
Why Scrum Why Now
 
Agile planning with Rational Team Concert
Agile planning with Rational Team ConcertAgile planning with Rational Team Concert
Agile planning with Rational Team Concert
 
É possível medir se um gigante é ágil?
É possível medir se um gigante é ágil?É possível medir se um gigante é ágil?
É possível medir se um gigante é ágil?
 
Syed Shohaib CV
Syed Shohaib CVSyed Shohaib CV
Syed Shohaib CV
 
Syed Shohaib CV
Syed Shohaib CVSyed Shohaib CV
Syed Shohaib CV
 
SAP sample
SAP sampleSAP sample
SAP sample
 
I nearshore
I nearshore I nearshore
I nearshore
 
ERP solution architect role, part I
ERP solution architect role, part IERP solution architect role, part I
ERP solution architect role, part I
 
Metodologías agiles de desarrollo de software
Metodologías agiles de desarrollo de softwareMetodologías agiles de desarrollo de software
Metodologías agiles de desarrollo de software
 
SDLC Methodologies
SDLC MethodologiesSDLC Methodologies
SDLC Methodologies
 
ASAP_Methodology.pptx
ASAP_Methodology.pptxASAP_Methodology.pptx
ASAP_Methodology.pptx
 
RTC & Work Item Customization Overview
RTC & Work Item Customization OverviewRTC & Work Item Customization Overview
RTC & Work Item Customization Overview
 
Project management software consulting
Project management software consultingProject management software consulting
Project management software consulting
 

Ptc saunier duval

  • 1. Technical and Business Offer e-commerce site « ArtCase » 2012-07-30 ORN186C1 1/26
  • 2. sommaire 1 needs understanding 2 our approach 3 our commercial bid 4 our resources 2/26
  • 3. our understanding of the need 3/26
  • 4. your need our understanding of the need > project “ArtCase” organized in 3 phases : - phase 1: • launch on Sosh.fr through a corner on their accessories shop • a personalization module to integrate into the Sosh customer journey • planning forecast : November 2012 - phase 2: • Artcase standalone site for France with customer journey from A to Z • planning forecast : Q1 2013 1st launch on Sosh.fr, then Artcase standalone site - phase 3: • replication of Artcase standalone site for Q4 2012 Q1 2013 France in OK and Spain.  Corner Artcase on SOSH accessories • all sites must be optimized for tablets shop Totally integrated into the Sosh customer journey. Exclusive artists on Sosh. > constraints :  Artcase.com eShop (FR then UK tbc) - design, customer experience and visual design •Standalone eshop •Cross link with Orange Shop will be done by a web agency Mid term opportunity - furniture of templates, zoning and PSD ArtCase corner on Orange accessories eshop? 10 interne France Télécom - Orange 4/26
  • 5. your need the goals > accessible and intuitive > full functional coverage : content management, catalog and products management, customer spaces, order management, ... > exchange security - compliance with norms and standards, best practices, … - lock access between servers > ability to interface with your information system > scalable solution to internal processes > reduce your internal load and increase your Marketing chances > respect of project schedule 5/26
  • 7. Project methodology A team working with agile software development methods > Sequence of a release (version x.0) Sprint 0 Sprint 1 Sprint 2 Sprint n End Initiation > Project organized in sprint steps  Initiating made by Product Owner : • Defining features embedded in sprints : Product Backlog (to do list) • Defining priority tasks (user stories)  Evaluating made by the project team: • Evaluating tasks duration (planning poker) • Evaluating criteria defining the end of tasks • Building the Sprint Backlog (To do list for each sprint)  End of each sprint (Sprint review) : • Showing work done through a demo and delivery for CIO • Reporting problems • Taking into account CIO feedbacks (bugs, changes) 7/26
  • 8. Project methodology A team working with agile software development methods > Tools for agile software development  The Product Backlog shows the entire to do list (user stories) • some are well defined (forthcoming sprint) • Other need to be reviewed  Reporting • Burn-up (or Burn-down) chart showing process > Project steering process  For each sprint review : • Suggest features included for each sprint : Product Backlog (To Do List) • Defining To do List (user stories) 8/26
  • 9. Project methodology Steering > Profiles  Project Director  Project Leader  Scrum Master  Technical Expert (if needed) > Project supervision  Initiating  Steering committee  Steering committee/sprint review  workshop/daily scrum > reporting  Workload consumption  Defining roadmap  Dashboard showing indicators 9/26
  • 10. Project methodology Initiating > Kick-off meeting  Team presentations  First roadmap with macro-planning > Team organization  Building core team and secondary teams  Implementing project reports & reviews  Development & integration platforms  Tools for reviews > Quality process  Project Management Plan  Risk & compliancy monitoring  Indicators 10/26
  • 11. Project methodology Roadmap > Roadmap is a key document started during the project initiation meeting > Roadmap lists the To Do list, the following items :  Tasks and actions  List of priority  Continuous activities (corrective maintenance, support, steering,…)  Complet planning – tasks done by IT&L@bs and stakeholder, project steps > Roadmap includes :  MS-Project planning includes the entire list of activities, materials, profiles and reliance  Budget dash board showing  Workload used and wahr remains to be done,  Several indicators for project governance 11/26
  • 12. Project methodology Risk management > Identifying risks  id Identify  Level  Probality of occurrence  List actions done to reduce risks Estimate Periodic - re-estimate iteration  trends Defining and updating > Recognization of probems actions to reduce risks occured et and impact Follow efficiency analysis on risks in progress of actions > Monitoring risk and actions done during the project Close risks committee. 12/26
  • 13. Project methodology Service level management – indicators > Quality of service is analyzed using indicators defined during initialization phase and tracked in reporting > Indicators evolves depending on project needs & project progress > Indicators are calculated at least monthly and analyzed during the Steering Committee > Indicators are used by IT&L@bs to highlight through Dashboard the quality of service provided on the project 13/26
  • 14. Project methodology Global steering process > Steering process Steering Committee  Steering committee  Project committee Steering Progress meeting Coordination, monitoring (action plan, indicators) Planning > Risks management > Planning management Project Project Manager Committee Synthesis Production > Gestion des écarts Visibility on delivery Documentation, Risk Management monitoring Decisions & actions Project communication Planning Project team 14/26
  • 15. Process Identify project steps Step 1 Initiation Staffing / Quality process Risks / requirements Features Step 2 Step 3 specifications / design Step 4 Integration/ Step 5 Development Acceptance / Workshop Delivery Deployment / support Setting Magento Go live Specifications Delivery and Technical Graphic charter Acceptance platform Production Architecture integration deployment deployment Document Custom Internal acceptance Operational developement qualification Web design Client acceptance Documentations support Go live support Validation / tests document Steering and Quality process management 15/26
  • 16. our approach 16/26
  • 17. our approach why Magento ? > an industrialized and recognized solution in the market of e-commerce software - efficient and respectful of standards (security, architecture, ...) - a vibrant community, - popular solution that facilitates the recovery of activity in-house or by a third party. > an open source software foundation scalable and interoperable - open source that allows own customizations to evolve, - integration capability with significant third-party products (via web services or connectors and Magento internal API). 17/26
  • 18. our approach an appropriate project organization Technical host manager Customer Project manager Reporting CV CV CV CV Project director Project Project manager Quality engineer manager Technical expert Technical expert Developer ERP Provider Developer Developer Integration technical team 18/26
  • 19. our approach methodology and experience appropriate to large project scope > experience - IT&L@bs has real experience on large projects that require : • to interface and work with other supplier companies • organize the site into production in line with the overall project schedule > approach with Quality Assurance (CMMI 3) - monitoring of a quality permits : • well reference the different actors and roles • better track and follow the requirements for the project and its processes (via the project dashboard) • track and share risks • optimize actions definition and implementation 19/26
  • 20. IT&L@bs bid 20/26
  • 21. Workload workload total by project steps > Workload display bys steps and profiles Total workload Project Project Steps Expert DEV (men / day) Director Leader Project Initiation 10 1 5 3 1 Specifications and technical 32 3 8,5 20,5 design Development & unit tests 76 21 55 Technical integration & internal 17 7 10 acceptance test Delivery / client acceptance tests 18 2 9 7 & deployment Project steering 21 3 18 Risks Management 10 1 3,5 5,5 3 months guarantee 12 4 8 Total 196 4 29 56 107 21/26
  • 22. our bid commercial bid Total in € (excluding Steps Workload / travel VAT) Project Initiation 10 6 530,00 € Specifications and technical design 32 18 005,00 € Development & unit tests 76 41 750,00 € Technical integration & internal acceptance test 17 9 500,00 € Delivery / client acceptance tests & deployment 18 10 470,00 € Project steering 21 14 640,00 € Risks Management 10 5 695,00 € 3 months guarantee 12 6 640,00 € Options 4 2 120,00 € Travel expenses 5 travels 2 731,20 € Total 196 115 961,20 € Total (including options) 200 118 081,20 € > General Terms of sales (available in Annex) 22/26
  • 23. our bid billing schedule (without options) > Billing terms and conditions and schedule Description Milestone Total HTVA 30% (order validation) T0 34 788,00 € 20 % delivery of specifications & technical T0+4,5 weeks 23 192,00 € design 25 % delivery for client T0+ 12,5 weeks 28 990,30 € acceptance test 25 % operational En of operational 28 990,90 € acceptance period ended acceptance Total 115 961,20 € HT > General Terms of sales (available in Annex) 23/26
  • 24. our bid project schedule > schedule proposal with a T0 at 09/03/2012 Step Marker Cumulative time Start date Launch T0 + 2 weeks 2 weeks 09/03/2012 Design and T1 + 4,5 weeks 2,5 weeks 09/17/2012 specifications Development T2 + 10,5 weeks 6 weeks 10/04/2012 Internal tests (VAU) T3 + 12,5 weeks 2 weeks 11/19/2012 and delivery T4 + 15 weeks End of acceptance acceptance 2,5 weeks 12/03/2012 support support Operationnal End of warranty tests ended + 3 3 months 12/20/2012 month > proposed dates • production delivery date : 12/03/2012 • service phase start date : 12/20/2012 24/26
  • 25. our resources 25/26
  • 26. Gérald Noc Anthony Le Postec "Portal" segment manager Presales manager Phone : +33 2 51 85 16 35 Phone : +33 2.51.85.16.21 Fax : +33 2 51 85 16 58 Fax : +33 2 51 85 16 58 Mobile : +33 6 72 79 72 04 Mobile : +33 6.78.53.18.42 gerald.noc@orange.com anthony.lepostec@orange.com Orange Business Services Orange Business Services Europarc La Chantrerie Europarc La Chantrerie 9, boulevard Nicéphore Niepce 9, boulevard Nicéphore Niepce 44300 Nantes 44300 Nantes IT&Labs Nantes 26/26