Final Project
Milestone 3
Heather Moore
3/23/2014
The following document outlines the creation of a 3D FlexSim simulation model. The model is a mock-up
of an airport security checkpoint that is looking for ways to speed up wait times and still thoroughly
check passengers for weapons and unapproved items.
IT 630 Final Project Heather Moore
1 | P a g e
Table of Contents
Executive Summary........................................................................................................................ 2
Problem formulation....................................................................................................................... 3
Description of simulation........................................................................................................ 3
Problem situation .................................................................................................................... 3
What-if questions.................................................................................................................... 3
Base model and alternative models................................................................................................. 6
Input analyses.................................................................................................................................. 7
Verification and Validation............................................................................................................. 8
Calculation of number of runs ........................................................................................................ 9
Output analyses............................................................................................................................. 10
Cost-benefit analysis..................................................................................................................... 10
Summary....................................................................................................................................... 11
Figures
Figure a - OFD Model 1.................................................................................................................. 4
Figure b - OFD Model 2 ................................................................................................................. 5
Figure c - Base Model..................................................................................................................... 6
Figure d - Alternative Model .......................................................................................................... 7
Figure e - Comparison of the two models....................................................................................... 9
Figure f - Average Staytime for Scanner 1 Model.......................................................................... 9
Figure g - Average Staytime for Scanner 2 Model....................................................................... 10
IT 630 Final Project Heather Moore
2 | P a g e
Executive Summary
The project required the creation of a real-world problem in FlexSim’s 3D simulation
software. We were to create a situation that we could demonstrate an issue and find a solution.
My model is an airport security check-point where the waiting time to go through the scanner
was excessive and needed to be shortened to ensure passengers reached their gate on time. The
first model demonstrated the wait times and flow of one metal detector and x-ray scanner while
the second model demonstrated the use of two metal detectors and x-ray scanners. The wait
times decreased a significant amount with the second model.
IT 630 Final Project Heather Moore
3 | P a g e
Problem formulation
Description of simulation
The simulation I am going to create is the security checkpoint at an airport. There will be
multiple scanners for luggage and people going through the checkpoint. Depending on the
number of people going to the gates will affect how busy or slow the checkpoint becomes. Some
passengers will not pass the initial security scan and will have to continue to the manual search
area to be cleared. This will affect overall time in the check-point which will slow down the
flow.
Problem situation
There are long lines of passengers going through the security checkpoint. The long waits
are causing people to be late for their flights. There needs to be a solution determined for
speeding up the lines but still maintaining the security of all passengers.
What-if questions
What if there was more than one scanner location for the passengers to move through?
IT 630 Final Project Heather Moore
4 | P a g e
System and simulation specification
Object Flow Diagrams
Figure a - OFD Model 1
IT 630 Final Project Heather Moore
5 | P a g e
Figure b - OFD Model 2
IT 630 Final Project Heather Moore
6 | P a g e
Base model and alternative models
Figure c - Base Model
The base model contains one metal detector scanner and one x-ray scanner for luggage.
Processing passengers through the metal detector is causing long wait times of about 80 minutes.
This is causing passengers to be late or miss their flights due to the long wait times. The base
model also has a manual search area for those passengers who are picked for further screening.
Currently the metal detector takes anywhere between 10 to 25 minutes to scan a passenger. If
they are selected for further scanning then they are sent to the manual scan station where it can
take another 5 to 20 minutes to process them.
The passenger’s luggage must go through an x-ray scanner that takes between 3 to 10
minutes to scan. If the content doesn’t pass the x-ray scan then it is moved to the manual search
area to be further inspected by the security. The manual search for the luggage takes between 5
to 10 minutes to be searched. The average wait time for the manual scan area is about 10 minutes
long.
IT 630 Final Project Heather Moore
7 | P a g e
Figure d - Alternative Model
The alternative model contains double the metal detectors and x-ray machines for faster
processing. The amount of time it takes to scan each person and luggage is the same for each
scanner but now there are two scanners doing the same amount of work as previously there was
only one. I anticipate that this will speed up the process time significantly.
Input analyses
The model runs a 16 hour day (960 minutes) to account for the airport being open from
7:00am to 11:00pm daily. There are two separate flow items created one that represents
passengers and the other that represents their luggage. Passengers were assigned item number 1
and luggage was assigned item number 2. These item numbers help control the flow of where
each is processed when going through the screening checkpoint. Each passenger is also randomly
assigned a shirt color to help tell each person apart and watch them flow through the model.
In the base model I originally had the queue send to port based on expression which sent
item 1 to port 1 and item 2 to port 2. The manual scan queue is still set this way but I quickly
realized this was not going to work for the alternative model’s first queue where there were more
ports so I was able to pull into the processor the relevant flow item by changing the setting for
IT 630 Final Project Heather Moore
8 | P a g e
Input under the Flow tab of the processor. This ensures that the passengers are going through the
metal detector and the luggage is going through the x-ray scanner. The processor then randomly
chooses weather to send the item to the manual scan queue or the corresponding sink. Once
processed through the manual scan all items flow to the sink.
The processor times were determined by taking into account that some people walk
slower, have trouble taking off their shoes, or loading their luggage on the x-ray scanner
therefore the times ranged from 10 to 25 minutes. The luggage processor was place at 3 to 10
minutes of time for the operator to scan the luggage. This time takes into consideration that some
bags will be packed more than others making it harder to fully x-ray. Both the manual search
processors were set to process items between 5 to 20 minutes so that the operator had time to
fully search the luggage or passenger if there were questions about what they were taking on the
plane.
Verification and Validation
I followed three sets of data to determine if the alternative model had better results than the
base model. The main one was the average wait time of the first queue in the check-point. This
showed a significant amount of time passengers were waiting to go through security. I also
tracked the number passengers and the number of luggage that was processed overall. This
showed that there were only about 55 people being processed through the security check-point
over the course of 16 hours. After adding the second check-point scanners the number of people
almost doubled.
IT 630 Final Project Heather Moore
9 | P a g e
Figure e - Comparison of the two models
Calculation of number of runs
Using the Simulation Experimenter tool I monitored the variable for Max Wait Time on the
first queue in the sequence.
Figure f - Average Staytime for Scanner 1 Model
IT 630 Final Project Heather Moore
10 | P a g e
Figure g - Average Staytime for Scanner 2 Model
Output analyses
What if there was more than one scanner location for the passengers to move through?
With the addition of a second scanning area the wait time decreased by 94%. This
significantly saves the passengers time when trying to catch their plane. There was also a 67%
increase in the number of passengers that were processed through the entire check-point. Lastly
the processed luggage was increased by 11%. Overall the addition of a second security scanning
area increased numbers across the board.
Cost-benefit analysis
My models did not look at the cost of running each security check-point. The second model
Airport Security Model Avg Wait Time
Passengers
Processed
Luggage
Processed
Scanner 1 95.84 55 98
Scanner 2 5.78 92 109
Totals 94% 67% 11%
IT 630 Final Project Heather Moore
11 | P a g e
would definitely cost more to run due to the increase in operating staff and extra machines.
Although looking at the number of passengers that went through on one work day it doesn’t
seem like the cost of running two scanners would be worth it for the number of passengers who
are traveling through the airport. Now if I had setup the sources differently to allow an increase
in the throughput of passengers this might be a better solution.
Summary
I learned a great deal by creating this model. I was able to apply what I had learned
during the course to my models to achieve the results I had envisioned. There is still a lot that I
could have incorporated into my models but I found many of the tutorials to be lacking in
explanation of how to use the system and how to manipulate the data to create the model I
wanted. I am really happy with the final result though. I have to admit at first I didn’t think I
would be able to successfully complete the final project.

Weitere Àhnliche Inhalte

Was ist angesagt?

Final Report-Poor Yorick's Coffee House
Final Report-Poor Yorick's Coffee HouseFinal Report-Poor Yorick's Coffee House
Final Report-Poor Yorick's Coffee House
karanchaudhry123
 
Project Presentation_fx7378_fy6055
Project Presentation_fx7378_fy6055Project Presentation_fx7378_fy6055
Project Presentation_fx7378_fy6055
Parag Kapile
 

Was ist angesagt? (20)

Simulation with Arena (Dental Clinic project)
Simulation with Arena (Dental Clinic project)Simulation with Arena (Dental Clinic project)
Simulation with Arena (Dental Clinic project)
 
Simulation project on Burger King
Simulation project on Burger KingSimulation project on Burger King
Simulation project on Burger King
 
Habanero Restaurant - Simulation Project
Habanero Restaurant - Simulation ProjectHabanero Restaurant - Simulation Project
Habanero Restaurant - Simulation Project
 
Stadium Queue Simulation
Stadium Queue SimulationStadium Queue Simulation
Stadium Queue Simulation
 
Project report subrahmanya_rashmi
Project report subrahmanya_rashmiProject report subrahmanya_rashmi
Project report subrahmanya_rashmi
 
Simulation Modeling on Campus Starbucks Coffee Center
Simulation Modeling on Campus Starbucks Coffee CenterSimulation Modeling on Campus Starbucks Coffee Center
Simulation Modeling on Campus Starbucks Coffee Center
 
Simulation Project Report
Simulation Project ReportSimulation Project Report
Simulation Project Report
 
Arena Simulation of Chipotle Restaurant
Arena Simulation of Chipotle RestaurantArena Simulation of Chipotle Restaurant
Arena Simulation of Chipotle Restaurant
 
Kroger Store Simulation Using Arena
Kroger Store Simulation Using ArenaKroger Store Simulation Using Arena
Kroger Store Simulation Using Arena
 
Final Report-Poor Yorick's Coffee House
Final Report-Poor Yorick's Coffee HouseFinal Report-Poor Yorick's Coffee House
Final Report-Poor Yorick's Coffee House
 
Barber Shop Simulation
Barber Shop SimulationBarber Shop Simulation
Barber Shop Simulation
 
Simulation with ARENA - SM Paints
Simulation with ARENA - SM PaintsSimulation with ARENA - SM Paints
Simulation with ARENA - SM Paints
 
Project Presentation_fx7378_fy6055
Project Presentation_fx7378_fy6055Project Presentation_fx7378_fy6055
Project Presentation_fx7378_fy6055
 
Simulation study of Gas Station
Simulation study of Gas StationSimulation study of Gas Station
Simulation study of Gas Station
 
Arena Model for Coffe Shop
Arena Model for Coffe ShopArena Model for Coffe Shop
Arena Model for Coffe Shop
 
Simulation for kfc order counter at rajiv gandhi international airport, hyder...
Simulation for kfc order counter at rajiv gandhi international airport, hyder...Simulation for kfc order counter at rajiv gandhi international airport, hyder...
Simulation for kfc order counter at rajiv gandhi international airport, hyder...
 
A Simulation Model of Starbucks
A Simulation Model of StarbucksA Simulation Model of Starbucks
A Simulation Model of Starbucks
 
Bakery Production Using Arena Simulation
Bakery Production Using Arena SimulationBakery Production Using Arena Simulation
Bakery Production Using Arena Simulation
 
Master Production Scheduling (MPS)
Master Production Scheduling (MPS) Master Production Scheduling (MPS)
Master Production Scheduling (MPS)
 
Chemical Client SIPOC
Chemical Client SIPOCChemical Client SIPOC
Chemical Client SIPOC
 

Ähnlich wie Computer Simulation Final Project

Thesis - CR_UAV
Thesis - CR_UAVThesis - CR_UAV
Thesis - CR_UAV
Nir Drucker
 
Automated_Drones_-_Giant_Step_in_Mining_Value_Chain
Automated_Drones_-_Giant_Step_in_Mining_Value_ChainAutomated_Drones_-_Giant_Step_in_Mining_Value_Chain
Automated_Drones_-_Giant_Step_in_Mining_Value_Chain
Sean Jefferys
 
Automatic Notch Indication and Identification of Compartment in Emergency
Automatic Notch Indication and Identification of Compartment in EmergencyAutomatic Notch Indication and Identification of Compartment in Emergency
Automatic Notch Indication and Identification of Compartment in Emergency
IJERA Editor
 
RDC-2016-ST-paper-final-Mukherjee.pdf
RDC-2016-ST-paper-final-Mukherjee.pdfRDC-2016-ST-paper-final-Mukherjee.pdf
RDC-2016-ST-paper-final-Mukherjee.pdf
Poulastya Mukherjee
 
Predicting Post-SafeTrack Metro Reliability
Predicting Post-SafeTrack Metro ReliabilityPredicting Post-SafeTrack Metro Reliability
Predicting Post-SafeTrack Metro Reliability
Micah Melling
 

Ähnlich wie Computer Simulation Final Project (20)

SIMUL8 Project
SIMUL8 ProjectSIMUL8 Project
SIMUL8 Project
 
IRJET- Intelligent Queue Management System at Airports using Image Processing...
IRJET- Intelligent Queue Management System at Airports using Image Processing...IRJET- Intelligent Queue Management System at Airports using Image Processing...
IRJET- Intelligent Queue Management System at Airports using Image Processing...
 
A Linear Programming Solution To The Gate Assignment Problem At Airport Termi...
A Linear Programming Solution To The Gate Assignment Problem At Airport Termi...A Linear Programming Solution To The Gate Assignment Problem At Airport Termi...
A Linear Programming Solution To The Gate Assignment Problem At Airport Termi...
 
2977
29772977
2977
 
Case study - Brussels Airport
Case study - Brussels Airport Case study - Brussels Airport
Case study - Brussels Airport
 
Thesis - CR_UAV
Thesis - CR_UAVThesis - CR_UAV
Thesis - CR_UAV
 
Real-Time Automated Overspeeding Detection and Identification System
Real-Time Automated Overspeeding Detection and Identification SystemReal-Time Automated Overspeeding Detection and Identification System
Real-Time Automated Overspeeding Detection and Identification System
 
Automated_Drones_-_Giant_Step_in_Mining_Value_Chain
Automated_Drones_-_Giant_Step_in_Mining_Value_ChainAutomated_Drones_-_Giant_Step_in_Mining_Value_Chain
Automated_Drones_-_Giant_Step_in_Mining_Value_Chain
 
Timing verification of automotive communication architectures using quantile ...
Timing verification of automotive communication architectures using quantile ...Timing verification of automotive communication architectures using quantile ...
Timing verification of automotive communication architectures using quantile ...
 
Whole.pdf
Whole.pdfWhole.pdf
Whole.pdf
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
 
IRJET - Autonomous Drone Delivery System: A Survey
IRJET - Autonomous Drone Delivery System: A SurveyIRJET - Autonomous Drone Delivery System: A Survey
IRJET - Autonomous Drone Delivery System: A Survey
 
Automatic Notch Indication and Identification of Compartment in Emergency
Automatic Notch Indication and Identification of Compartment in EmergencyAutomatic Notch Indication and Identification of Compartment in Emergency
Automatic Notch Indication and Identification of Compartment in Emergency
 
RDC-2016-ST-paper-final-Mukherjee.pdf
RDC-2016-ST-paper-final-Mukherjee.pdfRDC-2016-ST-paper-final-Mukherjee.pdf
RDC-2016-ST-paper-final-Mukherjee.pdf
 
Traffic Management using IoT and Deep Learning Techniques: A Literature Survey
Traffic Management using IoT and Deep Learning Techniques: A Literature SurveyTraffic Management using IoT and Deep Learning Techniques: A Literature Survey
Traffic Management using IoT and Deep Learning Techniques: A Literature Survey
 
VEHICLE DETECTION USING YOLO V3 FOR COUNTING THE VEHICLES AND TRAFFIC ANALYSIS
VEHICLE DETECTION USING YOLO V3 FOR COUNTING THE VEHICLES AND TRAFFIC ANALYSISVEHICLE DETECTION USING YOLO V3 FOR COUNTING THE VEHICLES AND TRAFFIC ANALYSIS
VEHICLE DETECTION USING YOLO V3 FOR COUNTING THE VEHICLES AND TRAFFIC ANALYSIS
 
IRJET- New Simulation Methodology for Dynamic Simulation Modeling of Construc...
IRJET- New Simulation Methodology for Dynamic Simulation Modeling of Construc...IRJET- New Simulation Methodology for Dynamic Simulation Modeling of Construc...
IRJET- New Simulation Methodology for Dynamic Simulation Modeling of Construc...
 
Integrating fuzzy and ant colony system for
Integrating fuzzy and ant colony system forIntegrating fuzzy and ant colony system for
Integrating fuzzy and ant colony system for
 
Timing verification of automotive communication architecture using quantile ...
Timing verification of automotive communication  architecture using quantile ...Timing verification of automotive communication  architecture using quantile ...
Timing verification of automotive communication architecture using quantile ...
 
Predicting Post-SafeTrack Metro Reliability
Predicting Post-SafeTrack Metro ReliabilityPredicting Post-SafeTrack Metro Reliability
Predicting Post-SafeTrack Metro Reliability
 

KĂŒrzlich hochgeladen

Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

KĂŒrzlich hochgeladen (20)

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 

Computer Simulation Final Project

  • 1. SNHU Final Project Milestone 3 Heather Moore 3/23/2014 The following document outlines the creation of a 3D FlexSim simulation model. The model is a mock-up of an airport security checkpoint that is looking for ways to speed up wait times and still thoroughly check passengers for weapons and unapproved items.
  • 2. IT 630 Final Project Heather Moore 1 | P a g e Table of Contents Executive Summary........................................................................................................................ 2 Problem formulation....................................................................................................................... 3 Description of simulation........................................................................................................ 3 Problem situation .................................................................................................................... 3 What-if questions.................................................................................................................... 3 Base model and alternative models................................................................................................. 6 Input analyses.................................................................................................................................. 7 Verification and Validation............................................................................................................. 8 Calculation of number of runs ........................................................................................................ 9 Output analyses............................................................................................................................. 10 Cost-benefit analysis..................................................................................................................... 10 Summary....................................................................................................................................... 11 Figures Figure a - OFD Model 1.................................................................................................................. 4 Figure b - OFD Model 2 ................................................................................................................. 5 Figure c - Base Model..................................................................................................................... 6 Figure d - Alternative Model .......................................................................................................... 7 Figure e - Comparison of the two models....................................................................................... 9 Figure f - Average Staytime for Scanner 1 Model.......................................................................... 9 Figure g - Average Staytime for Scanner 2 Model....................................................................... 10
  • 3. IT 630 Final Project Heather Moore 2 | P a g e Executive Summary The project required the creation of a real-world problem in FlexSim’s 3D simulation software. We were to create a situation that we could demonstrate an issue and find a solution. My model is an airport security check-point where the waiting time to go through the scanner was excessive and needed to be shortened to ensure passengers reached their gate on time. The first model demonstrated the wait times and flow of one metal detector and x-ray scanner while the second model demonstrated the use of two metal detectors and x-ray scanners. The wait times decreased a significant amount with the second model.
  • 4. IT 630 Final Project Heather Moore 3 | P a g e Problem formulation Description of simulation The simulation I am going to create is the security checkpoint at an airport. There will be multiple scanners for luggage and people going through the checkpoint. Depending on the number of people going to the gates will affect how busy or slow the checkpoint becomes. Some passengers will not pass the initial security scan and will have to continue to the manual search area to be cleared. This will affect overall time in the check-point which will slow down the flow. Problem situation There are long lines of passengers going through the security checkpoint. The long waits are causing people to be late for their flights. There needs to be a solution determined for speeding up the lines but still maintaining the security of all passengers. What-if questions What if there was more than one scanner location for the passengers to move through?
  • 5. IT 630 Final Project Heather Moore 4 | P a g e System and simulation specification Object Flow Diagrams Figure a - OFD Model 1
  • 6. IT 630 Final Project Heather Moore 5 | P a g e Figure b - OFD Model 2
  • 7. IT 630 Final Project Heather Moore 6 | P a g e Base model and alternative models Figure c - Base Model The base model contains one metal detector scanner and one x-ray scanner for luggage. Processing passengers through the metal detector is causing long wait times of about 80 minutes. This is causing passengers to be late or miss their flights due to the long wait times. The base model also has a manual search area for those passengers who are picked for further screening. Currently the metal detector takes anywhere between 10 to 25 minutes to scan a passenger. If they are selected for further scanning then they are sent to the manual scan station where it can take another 5 to 20 minutes to process them. The passenger’s luggage must go through an x-ray scanner that takes between 3 to 10 minutes to scan. If the content doesn’t pass the x-ray scan then it is moved to the manual search area to be further inspected by the security. The manual search for the luggage takes between 5 to 10 minutes to be searched. The average wait time for the manual scan area is about 10 minutes long.
  • 8. IT 630 Final Project Heather Moore 7 | P a g e Figure d - Alternative Model The alternative model contains double the metal detectors and x-ray machines for faster processing. The amount of time it takes to scan each person and luggage is the same for each scanner but now there are two scanners doing the same amount of work as previously there was only one. I anticipate that this will speed up the process time significantly. Input analyses The model runs a 16 hour day (960 minutes) to account for the airport being open from 7:00am to 11:00pm daily. There are two separate flow items created one that represents passengers and the other that represents their luggage. Passengers were assigned item number 1 and luggage was assigned item number 2. These item numbers help control the flow of where each is processed when going through the screening checkpoint. Each passenger is also randomly assigned a shirt color to help tell each person apart and watch them flow through the model. In the base model I originally had the queue send to port based on expression which sent item 1 to port 1 and item 2 to port 2. The manual scan queue is still set this way but I quickly realized this was not going to work for the alternative model’s first queue where there were more ports so I was able to pull into the processor the relevant flow item by changing the setting for
  • 9. IT 630 Final Project Heather Moore 8 | P a g e Input under the Flow tab of the processor. This ensures that the passengers are going through the metal detector and the luggage is going through the x-ray scanner. The processor then randomly chooses weather to send the item to the manual scan queue or the corresponding sink. Once processed through the manual scan all items flow to the sink. The processor times were determined by taking into account that some people walk slower, have trouble taking off their shoes, or loading their luggage on the x-ray scanner therefore the times ranged from 10 to 25 minutes. The luggage processor was place at 3 to 10 minutes of time for the operator to scan the luggage. This time takes into consideration that some bags will be packed more than others making it harder to fully x-ray. Both the manual search processors were set to process items between 5 to 20 minutes so that the operator had time to fully search the luggage or passenger if there were questions about what they were taking on the plane. Verification and Validation I followed three sets of data to determine if the alternative model had better results than the base model. The main one was the average wait time of the first queue in the check-point. This showed a significant amount of time passengers were waiting to go through security. I also tracked the number passengers and the number of luggage that was processed overall. This showed that there were only about 55 people being processed through the security check-point over the course of 16 hours. After adding the second check-point scanners the number of people almost doubled.
  • 10. IT 630 Final Project Heather Moore 9 | P a g e Figure e - Comparison of the two models Calculation of number of runs Using the Simulation Experimenter tool I monitored the variable for Max Wait Time on the first queue in the sequence. Figure f - Average Staytime for Scanner 1 Model
  • 11. IT 630 Final Project Heather Moore 10 | P a g e Figure g - Average Staytime for Scanner 2 Model Output analyses What if there was more than one scanner location for the passengers to move through? With the addition of a second scanning area the wait time decreased by 94%. This significantly saves the passengers time when trying to catch their plane. There was also a 67% increase in the number of passengers that were processed through the entire check-point. Lastly the processed luggage was increased by 11%. Overall the addition of a second security scanning area increased numbers across the board. Cost-benefit analysis My models did not look at the cost of running each security check-point. The second model Airport Security Model Avg Wait Time Passengers Processed Luggage Processed Scanner 1 95.84 55 98 Scanner 2 5.78 92 109 Totals 94% 67% 11%
  • 12. IT 630 Final Project Heather Moore 11 | P a g e would definitely cost more to run due to the increase in operating staff and extra machines. Although looking at the number of passengers that went through on one work day it doesn’t seem like the cost of running two scanners would be worth it for the number of passengers who are traveling through the airport. Now if I had setup the sources differently to allow an increase in the throughput of passengers this might be a better solution. Summary I learned a great deal by creating this model. I was able to apply what I had learned during the course to my models to achieve the results I had envisioned. There is still a lot that I could have incorporated into my models but I found many of the tutorials to be lacking in explanation of how to use the system and how to manipulate the data to create the model I wanted. I am really happy with the final result though. I have to admit at first I didn’t think I would be able to successfully complete the final project.