SlideShare ist ein Scribd-Unternehmen logo
1 von 3
Downloaden Sie, um offline zu lesen
A Study on Productivity Improvement in Production
Line by Implementation of Lean Principles
Nur El Syahira Binti Shari
Department of Manufacturing Engineering Technology
Faculty of Engineering Technology
Universiti Teknikal Malaysia Melaka
elsyahira11@gmail.com
Tan Hauw Sen Rimo
Department of Manufacturing Engineering Technology
Faculty of Engineering Technology
Universiti Teknikal Malaysia Melaka
tanhauwsr@utem.edu.my
Mohd Soufhwee Abd. Rahman
Department of Manufacturing Engineering Technology
Faculty of Engineering Technology
Universiti Teknikal Malaysia Melaka
soufhwee@utem.edu.my
Abstract— This project is specifically concerned on the
productivity improvement in production line by implementation
of lean principles. In order to improve the productivity of the
industry, the wastes need to be reduced. There are two major
purposes of this project; to reduce bottleneck at production line
by using one-piece-flow method and to minimize overprocessing
at production line by using new standardized work.
Keywords—lean manufacturing; bottlenecks; overprocessing;
one-piece-flow; standardized work
I. INTRODUCTION
Lean manufacturing focusing on the way to eliminate waste
and to improve the efficiency in manufacturing environment.
There are seven types of wastes that exist in manufacturing;
transportation, inventory, motion, waiting, overproduction,
overprocessing and defect. These wastes can affect the
production and productivity of the company or industry if
being left alone. The scopes of this project are to concentrate
on the problems in secondary assembly production line that
were cause by bottlenecks and overprocessing cause by the
operator only. This project was carried out in the
manufacturing industry. There are two types of lean tools that
were used in this project which is one-piece-flow and
standardized work. One-piece-flow method was applied to
reduce bottleneck at the production line and the standardized
work was used to evaluate operator performance by prepared
new standardized work.
II. RESEARCH METHODOLOGY
A. Data Collection
 The data collection is gathered at the secondary
assembly production line for model Assy Stand P-
Base. The standard time was calculated.
 The reasons for bottlenecks and overprocessing were
identified.
B. Data Analysis
 From the standard time calculated before, the
workstation that had the highest and second highest
standard time was identified as shown in Fig. 1.
Fig. 1. The Standard Time of Process
C. Problem Solving
 New standard time was calculated and line balancing
was made.
 New process flow made from line balancing then
implement standardized work to minimize
overprocessing by operators.
 Improved the layout of the workstation to implement
one-piece-flow to reduce bottlenecks at the
production line.
III. RESULT AND DISCUSSION
Through the standardized work method, the overprocessing
can be minimized. One of the reasons why the overprocessing
occurred is because of the operator skill itself. So, when all the
operators used were from final assembly and secondary
assembly line, the standard time or cycle time of the operator
was decreased.
When the standard time decreased, the line balancing helps to
distribute the workload between operators equally. In this
process, although the bottlenecks occurred at station 3, the
changes cannot be made in here because of the processes in
station 3 are quiet complicated than others. That is why the
changes were made before and after station 3 which is station
2 and station 4.
As for bottlenecks in station 5, the solution was made by
combining station 4 and station 5 together. The results from
line balancing and new standardized work are shown at Fig. 4.
After the implementation, the standard time of processes was
improved from 39.90 seconds to 29.48 seconds.
Fig. 4 The Improvement at Process
After the new standardized work made and new workstations
layout was implemented, it promoted a good flow of the
processes because the processes at all stations became
continuous and the bottlenecks reduction can be achieved. The
data about the bottlenecks were taken from September until
November for 50 samples at each month. The reductions of
the bottleneck were shown in Fig. 5.
Besides, the production outputs also increased from 80 parts
per hour to 112 parts per hour as shown in Fig. 6. Hence, the
methods applied can increase the productivity of the
production line.
Fig. 5 Bottlenecks Reduction
Fig. 6 The Output Comparison
IV. CONCLUSIONS
The implementation of lean principles in the secondary
assembly line for product Assy Stand P-Base; standardized
work and one-piece-flow in this case study brings benefits for
manufacturers to improve the production performance in the
industry. The standardized method helps to minimize
overprocessing in operators. The one-piece-flow method helps
to reduce bottlenecks in production line. Hence, from the
implementation of lean principles, a lot of benefits can be
achieved by the company and the most important things are
the manufacturers can increase the productivity and will
ultimately decrease cost and gain more profits as the results of
applying lean principles in the production line.
ACKNOWLEDGMENT
The author would like to thank her supervisor and co-
supervisor, Mr Tan Hauw Sen Rimo and Mr Soufhwee Abd.
Rahman and also Mr. Shamsul and Mr Murad for providing
guidance for her bachelor degree project at Universiti
Teknikal Malaysia Melaka (UTeM) and in the chosen
industry.
REFERENCES
[1] The Machine That Changed The World, 1990
[2] Triumph of The Lean Production System, 1988
Executive Summary El

Weitere ähnliche Inhalte

Was ist angesagt?

lean management- case study on jaguar
lean management- case study on jaguarlean management- case study on jaguar
lean management- case study on jaguarRachita Kochhar
 
Study on Lean Manufacturing Process in Garments Production
Study on Lean Manufacturing Process in Garments ProductionStudy on Lean Manufacturing Process in Garments Production
Study on Lean Manufacturing Process in Garments ProductionMomin Uddin
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
Ghafari Resume-Anthony Toney
Ghafari Resume-Anthony ToneyGhafari Resume-Anthony Toney
Ghafari Resume-Anthony ToneyAnthony Toney
 
Improving OHS & Productivity of RMG Industries By Analyzing Various KPIs
Improving OHS & Productivity of RMG Industries By Analyzing Various  KPIsImproving OHS & Productivity of RMG Industries By Analyzing Various  KPIs
Improving OHS & Productivity of RMG Industries By Analyzing Various KPIsKarina Islam
 
Modern Terchnological Tool in aid of Lean manufacture in garment unit
Modern Terchnological Tool in aid of Lean manufacture in garment unitModern Terchnological Tool in aid of Lean manufacture in garment unit
Modern Terchnological Tool in aid of Lean manufacture in garment unitIEI GSC
 
Lean manufacturing in automobile industry
Lean manufacturing in automobile industryLean manufacturing in automobile industry
Lean manufacturing in automobile industryMAX GALARZA HERNANDEZ
 
Group technology by lathu
Group technology by lathuGroup technology by lathu
Group technology by lathumidetstudents
 
Plant layout optimization in crane manufacturing using CRAFT and SLP
Plant layout optimization in crane manufacturing using CRAFT and SLPPlant layout optimization in crane manufacturing using CRAFT and SLP
Plant layout optimization in crane manufacturing using CRAFT and SLPEr Harshrajsinh Kher
 
Product layout
Product layoutProduct layout
Product layoutDhruv Shah
 
Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminarsomkar jagtap
 
Resume_(June 2015) Industrial Engineering
Resume_(June 2015) Industrial EngineeringResume_(June 2015) Industrial Engineering
Resume_(June 2015) Industrial EngineeringOmar El Maghraby
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturingJitesh Gaurav
 
Improving Productivity by Lean
Improving Productivity by LeanImproving Productivity by Lean
Improving Productivity by LeanANITHA BALA
 

Was ist angesagt? (20)

lean management- case study on jaguar
lean management- case study on jaguarlean management- case study on jaguar
lean management- case study on jaguar
 
Case 4
Case 4Case 4
Case 4
 
Study on Lean Manufacturing Process in Garments Production
Study on Lean Manufacturing Process in Garments ProductionStudy on Lean Manufacturing Process in Garments Production
Study on Lean Manufacturing Process in Garments Production
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Pom case aic netbook
Pom case aic netbookPom case aic netbook
Pom case aic netbook
 
Ghafari Resume-Anthony Toney
Ghafari Resume-Anthony ToneyGhafari Resume-Anthony Toney
Ghafari Resume-Anthony Toney
 
Improving OHS & Productivity of RMG Industries By Analyzing Various KPIs
Improving OHS & Productivity of RMG Industries By Analyzing Various  KPIsImproving OHS & Productivity of RMG Industries By Analyzing Various  KPIs
Improving OHS & Productivity of RMG Industries By Analyzing Various KPIs
 
How to Improve Productivity
How to Improve ProductivityHow to Improve Productivity
How to Improve Productivity
 
Modern Terchnological Tool in aid of Lean manufacture in garment unit
Modern Terchnological Tool in aid of Lean manufacture in garment unitModern Terchnological Tool in aid of Lean manufacture in garment unit
Modern Terchnological Tool in aid of Lean manufacture in garment unit
 
Lean manufacturing in automobile industry
Lean manufacturing in automobile industryLean manufacturing in automobile industry
Lean manufacturing in automobile industry
 
Group technology by lathu
Group technology by lathuGroup technology by lathu
Group technology by lathu
 
Implementation of lean manufacturing in apparel industry
Implementation of lean manufacturing in apparel industryImplementation of lean manufacturing in apparel industry
Implementation of lean manufacturing in apparel industry
 
Plant layout optimization in crane manufacturing using CRAFT and SLP
Plant layout optimization in crane manufacturing using CRAFT and SLPPlant layout optimization in crane manufacturing using CRAFT and SLP
Plant layout optimization in crane manufacturing using CRAFT and SLP
 
Process analysis
Process analysisProcess analysis
Process analysis
 
Product layout
Product layoutProduct layout
Product layout
 
Report on JIT , for Projects and Seminars
Report on JIT , for Projects and SeminarsReport on JIT , for Projects and Seminars
Report on JIT , for Projects and Seminars
 
Resume_(June 2015) Industrial Engineering
Resume_(June 2015) Industrial EngineeringResume_(June 2015) Industrial Engineering
Resume_(June 2015) Industrial Engineering
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Improving Productivity by Lean
Improving Productivity by LeanImproving Productivity by Lean
Improving Productivity by Lean
 
Plant layout
Plant layoutPlant layout
Plant layout
 

Andere mochten auch

Géographie
Géographie  Géographie
Géographie malenabs
 
Native Vs Hybrid Apps
Native Vs Hybrid AppsNative Vs Hybrid Apps
Native Vs Hybrid AppsGaurav Jain
 
Careers24-cv-Theo-Mpolokeng (1)
Careers24-cv-Theo-Mpolokeng (1)Careers24-cv-Theo-Mpolokeng (1)
Careers24-cv-Theo-Mpolokeng (1)THEO MPOLOKENG
 
10 Barang Fashion Yang Wajib Wanita Miliki
10 Barang Fashion Yang Wajib Wanita Miliki10 Barang Fashion Yang Wajib Wanita Miliki
10 Barang Fashion Yang Wajib Wanita Milikinataliamatulessy
 
الدورات الأمنية لعام 2016 - Gulfstd
الدورات الأمنية لعام 2016 - Gulfstdالدورات الأمنية لعام 2016 - Gulfstd
الدورات الأمنية لعام 2016 - GulfstdTraining Gulf
 
Endoscopy in Gastrointestinal Oncology - Slide 11 - G. Vanbiervliet - Indicat...
Endoscopy in Gastrointestinal Oncology - Slide 11 - G. Vanbiervliet - Indicat...Endoscopy in Gastrointestinal Oncology - Slide 11 - G. Vanbiervliet - Indicat...
Endoscopy in Gastrointestinal Oncology - Slide 11 - G. Vanbiervliet - Indicat...European School of Oncology
 
Developing instruction materials
Developing instruction materialsDeveloping instruction materials
Developing instruction materialscw8842
 

Andere mochten auch (12)

Géographie
Géographie  Géographie
Géographie
 
Native Vs Hybrid Apps
Native Vs Hybrid AppsNative Vs Hybrid Apps
Native Vs Hybrid Apps
 
DurgaPrasad_Resume_New
DurgaPrasad_Resume_NewDurgaPrasad_Resume_New
DurgaPrasad_Resume_New
 
Careers24-cv-Theo-Mpolokeng (1)
Careers24-cv-Theo-Mpolokeng (1)Careers24-cv-Theo-Mpolokeng (1)
Careers24-cv-Theo-Mpolokeng (1)
 
resume
resumeresume
resume
 
deepak resume
deepak resumedeepak resume
deepak resume
 
10 Barang Fashion Yang Wajib Wanita Miliki
10 Barang Fashion Yang Wajib Wanita Miliki10 Barang Fashion Yang Wajib Wanita Miliki
10 Barang Fashion Yang Wajib Wanita Miliki
 
Maintenance Human Factors
Maintenance Human FactorsMaintenance Human Factors
Maintenance Human Factors
 
الدورات الأمنية لعام 2016 - Gulfstd
الدورات الأمنية لعام 2016 - Gulfstdالدورات الأمنية لعام 2016 - Gulfstd
الدورات الأمنية لعام 2016 - Gulfstd
 
Endoscopy in Gastrointestinal Oncology - Slide 11 - G. Vanbiervliet - Indicat...
Endoscopy in Gastrointestinal Oncology - Slide 11 - G. Vanbiervliet - Indicat...Endoscopy in Gastrointestinal Oncology - Slide 11 - G. Vanbiervliet - Indicat...
Endoscopy in Gastrointestinal Oncology - Slide 11 - G. Vanbiervliet - Indicat...
 
Developing instruction materials
Developing instruction materialsDeveloping instruction materials
Developing instruction materials
 
Diplomado tic
Diplomado ticDiplomado tic
Diplomado tic
 

Ähnlich wie Executive Summary El

IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining CellIRJET Journal
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET Journal
 
Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringAmanuzzaman Aman
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining TimeIRJET Journal
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET Journal
 
om ch 2.5 Layouting.pptx
om ch 2.5 Layouting.pptxom ch 2.5 Layouting.pptx
om ch 2.5 Layouting.pptxYosefSisay3
 
A company is planning for its financing needs and uses the basic fixed order-...
A company is planning for its financing needs and uses the basic fixed order-...A company is planning for its financing needs and uses the basic fixed order-...
A company is planning for its financing needs and uses the basic fixed order-...ramuaa124
 
A company is planning for its financing needs and uses the basic fixed order-...
A company is planning for its financing needs and uses the basic fixed order-...A company is planning for its financing needs and uses the basic fixed order-...
A company is planning for its financing needs and uses the basic fixed order-...yearstart1
 
H0432045055
H0432045055H0432045055
H0432045055theijes
 
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean PrinciplesLead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean PrinciplesIRJET Journal
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET Journal
 
Ops 571 final exam guide (new, 2018) you have been called in as a consultant ...
Ops 571 final exam guide (new, 2018) you have been called in as a consultant ...Ops 571 final exam guide (new, 2018) you have been called in as a consultant ...
Ops 571 final exam guide (new, 2018) you have been called in as a consultant ...ramuaa124
 
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyProductivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyIRJET Journal
 
You have been called in as a consultant to set up a kanban control system
You have been called in as a consultant to set up a kanban control systemYou have been called in as a consultant to set up a kanban control system
You have been called in as a consultant to set up a kanban control systemramuaa130
 
Project Methodology - On The Fly
Project Methodology - On The FlyProject Methodology - On The Fly
Project Methodology - On The Flyibenari
 
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdfRahbiMalek
 
Asik Ali Battery Production and Maintenance
Asik Ali Battery Production and MaintenanceAsik Ali Battery Production and Maintenance
Asik Ali Battery Production and MaintenanceAsik Ali
 

Ähnlich wie Executive Summary El (20)

IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
 
Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial Engineering
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
 
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A ReviewIRJET- Optimization of Cycle Time by using Various Techniques: A Review
IRJET- Optimization of Cycle Time by using Various Techniques: A Review
 
om ch 2.5 Layouting.pptx
om ch 2.5 Layouting.pptxom ch 2.5 Layouting.pptx
om ch 2.5 Layouting.pptx
 
A company is planning for its financing needs and uses the basic fixed order-...
A company is planning for its financing needs and uses the basic fixed order-...A company is planning for its financing needs and uses the basic fixed order-...
A company is planning for its financing needs and uses the basic fixed order-...
 
A company is planning for its financing needs and uses the basic fixed order-...
A company is planning for its financing needs and uses the basic fixed order-...A company is planning for its financing needs and uses the basic fixed order-...
A company is planning for its financing needs and uses the basic fixed order-...
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
H0432045055
H0432045055H0432045055
H0432045055
 
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean PrinciplesLead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
Lead Time Reduction in Manufacturing Process of CNC Machines by Lean Principles
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
 
_TUBES.pptx
_TUBES.pptx_TUBES.pptx
_TUBES.pptx
 
Ops 571 final exam guide (new, 2018) you have been called in as a consultant ...
Ops 571 final exam guide (new, 2018) you have been called in as a consultant ...Ops 571 final exam guide (new, 2018) you have been called in as a consultant ...
Ops 571 final exam guide (new, 2018) you have been called in as a consultant ...
 
Joined document 24_5
Joined document 24_5Joined document 24_5
Joined document 24_5
 
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyProductivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
 
You have been called in as a consultant to set up a kanban control system
You have been called in as a consultant to set up a kanban control systemYou have been called in as a consultant to set up a kanban control system
You have been called in as a consultant to set up a kanban control system
 
Project Methodology - On The Fly
Project Methodology - On The FlyProject Methodology - On The Fly
Project Methodology - On The Fly
 
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
 
Asik Ali Battery Production and Maintenance
Asik Ali Battery Production and MaintenanceAsik Ali Battery Production and Maintenance
Asik Ali Battery Production and Maintenance
 

Executive Summary El

  • 1. A Study on Productivity Improvement in Production Line by Implementation of Lean Principles Nur El Syahira Binti Shari Department of Manufacturing Engineering Technology Faculty of Engineering Technology Universiti Teknikal Malaysia Melaka elsyahira11@gmail.com Tan Hauw Sen Rimo Department of Manufacturing Engineering Technology Faculty of Engineering Technology Universiti Teknikal Malaysia Melaka tanhauwsr@utem.edu.my Mohd Soufhwee Abd. Rahman Department of Manufacturing Engineering Technology Faculty of Engineering Technology Universiti Teknikal Malaysia Melaka soufhwee@utem.edu.my Abstract— This project is specifically concerned on the productivity improvement in production line by implementation of lean principles. In order to improve the productivity of the industry, the wastes need to be reduced. There are two major purposes of this project; to reduce bottleneck at production line by using one-piece-flow method and to minimize overprocessing at production line by using new standardized work. Keywords—lean manufacturing; bottlenecks; overprocessing; one-piece-flow; standardized work I. INTRODUCTION Lean manufacturing focusing on the way to eliminate waste and to improve the efficiency in manufacturing environment. There are seven types of wastes that exist in manufacturing; transportation, inventory, motion, waiting, overproduction, overprocessing and defect. These wastes can affect the production and productivity of the company or industry if being left alone. The scopes of this project are to concentrate on the problems in secondary assembly production line that were cause by bottlenecks and overprocessing cause by the operator only. This project was carried out in the manufacturing industry. There are two types of lean tools that were used in this project which is one-piece-flow and standardized work. One-piece-flow method was applied to reduce bottleneck at the production line and the standardized work was used to evaluate operator performance by prepared new standardized work. II. RESEARCH METHODOLOGY A. Data Collection  The data collection is gathered at the secondary assembly production line for model Assy Stand P- Base. The standard time was calculated.  The reasons for bottlenecks and overprocessing were identified. B. Data Analysis  From the standard time calculated before, the workstation that had the highest and second highest standard time was identified as shown in Fig. 1. Fig. 1. The Standard Time of Process C. Problem Solving  New standard time was calculated and line balancing was made.  New process flow made from line balancing then implement standardized work to minimize overprocessing by operators.  Improved the layout of the workstation to implement one-piece-flow to reduce bottlenecks at the production line. III. RESULT AND DISCUSSION Through the standardized work method, the overprocessing can be minimized. One of the reasons why the overprocessing occurred is because of the operator skill itself. So, when all the
  • 2. operators used were from final assembly and secondary assembly line, the standard time or cycle time of the operator was decreased. When the standard time decreased, the line balancing helps to distribute the workload between operators equally. In this process, although the bottlenecks occurred at station 3, the changes cannot be made in here because of the processes in station 3 are quiet complicated than others. That is why the changes were made before and after station 3 which is station 2 and station 4. As for bottlenecks in station 5, the solution was made by combining station 4 and station 5 together. The results from line balancing and new standardized work are shown at Fig. 4. After the implementation, the standard time of processes was improved from 39.90 seconds to 29.48 seconds. Fig. 4 The Improvement at Process After the new standardized work made and new workstations layout was implemented, it promoted a good flow of the processes because the processes at all stations became continuous and the bottlenecks reduction can be achieved. The data about the bottlenecks were taken from September until November for 50 samples at each month. The reductions of the bottleneck were shown in Fig. 5. Besides, the production outputs also increased from 80 parts per hour to 112 parts per hour as shown in Fig. 6. Hence, the methods applied can increase the productivity of the production line. Fig. 5 Bottlenecks Reduction Fig. 6 The Output Comparison IV. CONCLUSIONS The implementation of lean principles in the secondary assembly line for product Assy Stand P-Base; standardized work and one-piece-flow in this case study brings benefits for manufacturers to improve the production performance in the industry. The standardized method helps to minimize overprocessing in operators. The one-piece-flow method helps to reduce bottlenecks in production line. Hence, from the implementation of lean principles, a lot of benefits can be achieved by the company and the most important things are the manufacturers can increase the productivity and will ultimately decrease cost and gain more profits as the results of applying lean principles in the production line. ACKNOWLEDGMENT The author would like to thank her supervisor and co- supervisor, Mr Tan Hauw Sen Rimo and Mr Soufhwee Abd. Rahman and also Mr. Shamsul and Mr Murad for providing guidance for her bachelor degree project at Universiti Teknikal Malaysia Melaka (UTeM) and in the chosen industry. REFERENCES [1] The Machine That Changed The World, 1990 [2] Triumph of The Lean Production System, 1988