Objectives of the Meeting
1/ Provide information about the work that has been completed, is underway and planned between now and spring 2018
2/ Answer questions, find potential solutions and discuss the issues
Good Neighbourly Relations Committee Meeting - Brossard - November 15, 2017
1. Good Neighbourly Relations Committee
Meeting
City of Brossard : November 15 2017
New Champlain Bridge Corridor Project
Centre communautaire Nathalie Croteau
Please note that the English version is used
only for refernce purposes. In case of
disrepancy between the English and French
versions, the French version shall prevail.
2. Projet de corridor du nouveau pont Champlain 2
Committee Members
Residents
Luis Oscar Corrales
Ginette Dufresne
Marc Gagné
Nabil Halouani
Jacques Picard
Goreti Fernandes
Marc Turcotte – Representative from a community
organization
Éric Jutras – Member of the business community
Partners
Dan Genest – The Signature on the Saint-Laurent team
Benoît Fillion – City of Brossard
Lara Raoub– (in replacement of Chantale Côté)
Infrastructure Canada
3. Projet de corridor du nouveau pont Champlain
1. Provide information about the work that has been
completed, is underway and planned between now and
spring 2018
2. Answer questions, find potential solutions and discuss the
issues
Objectives of the Meeting
3
4. Projet de corridor du nouveau pont Champlain
Agenda
4
Série Item Durée Heure
1. Opening 10 min. 19h00 à 19h10
2. Work completed, underway and to come
• Eastern approach area
• Hwy-10 area
• Cable-stayed bridge area
40 min. 19h10
à 19h50
3. Question period 20 min. 19h50 à 20h10
4. Varia 15 min. 20h10 à 20h25
5. Adjournment: next meeting and topic 5 min. 20h25 à 20h30
5. Projet de corridor du nouveau pont Champlain
Work Completed over the Past Few Months
6. Projet de corridor du nouveau pont Champlain
• Summer and fall seasons : good work progress in general
on the East Approach
End of the works of wall and building for the east
abutment
More than 95% of the piers segments were installed
(86 out of 90)
pre-assembly of girders (90 girders on 176 delivered,
including 35 already pre-assembled)
• Four complaints since May 15 2017
7. Projet de corridor du nouveau pont Champlain
Main Priorities for the Upcoming Months-
South Shore
8. Projet de corridor du nouveau pont Champlain
South Shore: Overview
8
Construction of a new bike access to
the New Champlain Bridge Adjustment of ramps for
access and exit to the New
Champlain Bridge
New Champlain Bridge
Construction
Works mainly completed at the opening of the
New Champlain Bridge in late 2018
9. Projet de corridor du nouveau pont Champlain
Location of Work Areas
City of Brossard
Cable-stayed
bridge
10. Projet de corridor du nouveau pont Champlain
Highway 10
• Soil management and equipment storage
• Configuration of the Highway 10
East Approch
• Installation of pier caps
• Installation of the superstructure
• Development of the east abutment
Cable-stayed bridge
• Construction of main pylon, rear and principal spans
›
South Shore
Priorities : Fall 2017 to Spring 2018
10
11. Projet de corridor du nouveau pont Champlain
Description of Activity
Approximate Duration of Works
Planned Work Period
Legend: Work and Impacts
• Traffic and Public Transportation:
• Proximity of Residential Areas:
• Boating:
• Bike Paths:
Minor impact
Medium impact
Major impact
Indication by level colour code
11
12. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come -
East Approach
Design and planning underway so modifications are possible
13. Projet de corridor du nouveau pont Champlain
Objective: Construction of East Approach of the new Champlain Bridge
Underway and upcoming Works:
• Pre-assembly and installation Placement of prefabricated segments of piers and
pier caps
• Continue the construction of the abutment
• Construction of the span above road 132
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels)
are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic are
too significant
East Approach Area
13
14. Projet de corridor du nouveau pont Champlain
Nov
2015
May Nov
2016
May Nov.
2017
Nov
2018
May
East Approach: Timetable
14
Feb
2016
Aug Feb
2017
Aug. Feb.
2018
Aug.
Construction of
footings and pier
bases
Installation of piers and pier
caps
Assembly of superstructure and
deck
Finishing work
15. Projet de corridor du nouveau pont Champlain
15
Works and Impacts: East Approach
Pre-assembly and placement of prefabricated
segments, pier caps and girders
Duration: 9 months
Projected period: Fall 2017 to Summer 2018
16. Projet de corridor du nouveau pont Champlain
Development of East Abutment
Duration: more than a year
Projected period: until the bridge opening
Works and Impacts: East Approach
17. Projet de corridor du nouveau pont Champlain
Construction of spans over Route 132
Duration : 6 months
Projected period: Fall 2017 to spring 2018
Works in progress and to come
• Erection of temporary scaffolding : fall 2017 / winter 2018
• Installation of south span : winter 2018
• Installation of the transit corridor span : winter 2018
• Installation of the north span : spring 2018 17
Works and Impacts: East Approach
18. Projet de corridor du nouveau pont Champlain
Installation of spans over route 132
Closure of a weekend by corridor
Dates to be confirmed and communicated in advance
18
Alternating zone
for shops
Alternating zone
for residents
20. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Highway 10
Design and planning underway so modifications are possible
21. Projet de corridor du nouveau pont Champlain
Highway 10 Area
21
Objective: Area reserved for soil management for the work site and
reconfiguration of highway links
Underway and upcoming Works
• Soil and equipment storage
• Creation of a retaining basin for permanent drainage and a permanent access
ramp to the Highway 10S
• Implementation of the new temporary configuration of the Highway 10
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise
levels) are significant
• Night-time trucking from the West Approach to the East Approach
22. Projet de corridor du nouveau pont Champlain 22
Works and Impacts: Highway 10
Soil management and equipment storage
Duration : throughout the project
Projected period: 2016 to 2019
23. Projet de corridor du nouveau pont Champlain
Creation of retaining basins and of a permanent access
ramp to the highway 10
Duration: 4 months
Projected period : Fall 2017 / winter 2018
23
Works and Impacts: Highway 10
24. Projet de corridor du nouveau pont Champlain
Works and Impacts:
Status report on tree cutting
• Tree cutting required for new developments (retention basins, permanent ramp and temporary
reconfiguration of Highway 10) and to clear construction sites
• Application process for authorization from the City of Brossard
• 927 authorized trees vs 875 cut trees
• Permits obtained require replanting the same number of trees as those cut
• Project landscaping plan provides for the planting of 5,000 trees
• Obligation to restore construction sites to their natural state or equivalent at the end of the project 24
25. Projet de corridor du nouveau pont Champlain
Taschereau
Implementation of the new temporary configuration of
the Highway 10
Duration : 8 months
Projected period : September 2017 to April 2018
Work in progress and to come :
• Removal of supersignalization
• Earthworks and pavement creation
• Commissioning planned : May 2018
25
Works and Impacts: Highway 10
26. Projet de corridor du nouveau pont Champlain 26
Works and Impacts: Highway 10
Installation of permanent anti-noise walls
Duration : three months
Projected period: spring 201
27. Projet de corridor du nouveau pont Champlain
Key Activities Underway and to Come
Cable-stayed Bridge
Design and planning underway so modifications are possible
28. Projet de corridor du nouveau pont Champlain
Cable-stayed Bridge: Timetable
28
2. Pylon foundations
October 2015 to April 20161. Jetty
August to October 2015
6. Main span
June 2017 to November
2018
3. Rear span
November 2015 to april 2018
5. Upper pylon
June to June 2018
4. Lower pylon
until lower crossbeam
August 2016 to June 2017
29. Projet de corridor du nouveau pont Champlain
Rear span of the cable-stayed bridge
50% of the rear span completed.
End of the installation in spring 2018.
30. Projet de corridor du nouveau pont Champlain
Upper pylon at 50% of its elevation.
Main span started
End of the installation in fall 2018.
30
Main span of the cable-stayed bridge
32. Projet de corridor du nouveau pont Champlain
Anticipated impacts
• Road traffic
• Noise
32
33. Projet de corridor du nouveau pont Champlain
Traffic
33
Configuration – Disruptions Schedule Duration
Installation of foundations and temporary
scaffolding
November 2017
to February 2018
3 weeks
Last passage of pier caps pieces
November 27
2017
1 night
Installation of superstructure and deck
above Highway 132 traffic lanes
Winter/Spring
2018
One weekend by span
Route Deviation from route 132 & boul.
Marie-Victorin
May 2018 One weekend
34. Projet de corridor du nouveau pont Champlain 34
Passage of Pier Caps Pieces
35. Projet de corridor du nouveau pont Champlain 35
B1: Turenne area
B2: Voltaire area
B3: Tisserand area
Noise Management
Preparatory works Highway
132
Area
Activity
Period
D/E/N
Exposed
sensitive
area
Ambient
noise dBA
Criterion
dBA
Estimated
noise dBA
Required
measures
EastApproach
Placement of prefabricated segments of
piers, pier caps and girders
D B1 / B2 60 / 62 75 61/ 64 Not required
Construction of the spans over road 132 D / E B2 62 75 / 67 61 / 64 Not required
Construction of the retaining walls D B2 62 75 71 Not required
Hgw
10
Création de bassins de rétention et de la
nouvelle bretelle d’accès à l’A10S
D B3 58 75 69 to 72 Not required
Mise en place de la nouvelle
configuration de l’A10
D B3 58 75 72
Not required
Installation of permanent anti-noise
walls
D B2 62 75 75
Monitoring
required
Cable-
Stayed
Miscellaneous work D B1 / B2 60 / 62 75 62 / 63 Not required
36. Projet de corridor du nouveau pont Champlain
B1 : Secteur Turenne
B2 : Secteur Voltaire
B3 : Secteur Tisserand
Gestion du bruit
Secteur
Activité
Période
J / S / N
Zone
sensible
exposée
Bruit
ambiant
dBA
Critère
dBA
Bruit
estimé
dBA
Mesures
requises
Approcheest
Pré-assemblage et mise en place des segments
d’interface, des chevêtres et des poutres-caisson
J B1 / B2 60 / 62 75 61 / 64 Non
Construction des travées au-dessus de la Route
132
J / S B2 62 75 / 67 61 / 64 Non
Construction des murs de soutènement J B2 62 75 71 Non
A10
Création de bassins de rétention et de la nouvelle
bretelle d’accès à l’A10S
J B3 58 75
69 à
72
non
Mise en place de la nouvelle configuration de l’A10 J B3 58 75 72 non
Installation des murs anti-bruit J B2 62 75 75
Suivi
requis
Pont
haubané
Travaux divers J B1 / B2 60 / 62 75 62 / 63 Non
36
38. Projet de corridor du nouveau pont Champlain
A timetable under pressure
• First challenge : the manufacturing and transport of parts
manufactured off-site since summer 2016
• Second challenge: strikes affecting the construction industry
in 2017
38
39. Projet de corridor du nouveau pont Champlain
Acceleration strategy
› Acceleration measures
• Increase the workforce for additional shifts and weekend shifts
• Add additional equipment
• Develop new temporary infrastructures : additional storage on site and
relocation of parking for labor
• Increase the number of executives: construction management, health and
safety, quality and environment
Focus of acceleration measures
• The cable-stayed bridge
• The pre-assembly of the superstructure on the west approach and its
subsequent installation.
39
40. Projet de corridor du nouveau pont Champlain
Follow-up on Interventions
40
SSL
• Date for the installations of anti-noise walls
• Landscaping
Ville de Brossard
• Follow-up on the antinoise wall along the ramp between the Highway 10
and 132 Road
42. Projet de corridor du nouveau pont Champlain
Site visit of the new elected
officials: 1st December 2017
(TBC)
Good Neighbourly Relations
Committee :
March 21 or 28 2018 (TBC)
Site visit of the Good
Neighbourly Relations
Committee : Spring 2018
(TBC)
Next meetings
43. Projet de corridor du nouveau pont Champlain
• Newsletter: sign up online
• Notice sent by post to citizen, if required, and local newspaper notices
• Sign up / contact us:
Website: www.newchamplain.ca
Phone us at: (514) 876-1020
Twitter: @NOUV_CHAMPLAIN