1. Residential Housing “Trekanten”, Kristiansand Norway.
Bachelors project – Arch. Tech. and Construction Management
Introduction Conceptual update Design Development Technical Design
Project basis
Project objectives:
• Creation of climate-friendly apartments within financial range for first time
buyers aiding young people in becoming homeowners rather than tenants.
• Development of a worn-out and unused industrial area occupying valuable
space.
Project Thesis
News article#1 News article#2
CD DD TD
Selected planning phases
Project Thesis
Study work plan
2. Introduction Conceptual update Design Development Technical Design
Dissertation report
Cross laminated timber representing the modern
format of solid timber construction, came as a result of
sawmills overproduction of low-grade wood and the
industry’s ambition to pose a solution for wood in
multi-storey structures.
(Falk, 2005)
• System fundamentals
• Material physics
• Economic aspect
• Environmental aspect
Assembly of single-family dwelling, Sogn og Fjordane - Norway 2015
3. Introduction Conceptual update Design Development Technical Design
Procurement strategy and organisation
Design Responsibility matrix
Project Organisation- and Interdependencies
Contractual Agreements-and Correspondence
Contract for consulting
services
Client
Kristiansand
Eiendom (public)
Main contractor
AB 92
Sub-contractor Sub-contractor
Architect
OS3 ArchitectsA/S
Client advisor
ABR 89
ICT
External scrutinizer
ABR 89
ICT
Engineer
Multidisciplina ry
engineering A/S
ABR 89
ICT
ABR 89
ICT
Tender act
Tender act
AB 92 AB 92
Maincontracting
Power of attorney
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Paymentplan
Envrionmental programme
Tender Procedure
4. Conceptual update
Phase specific areas of focus:
1. Brief introduction to the proposed project.
2. Preliminary estimation of project budget, duration and operation costs.
5. Project Location and site utilisation
Project Location Plan Site Plan
Gross Building Area Plot utilisation
Unit typologies (A-C)
Floor plans
Floor plans (-1/5)
Elevations and sections Perspectives and shadow studies
Elevations
Sections
Perspectives
Shadow studies
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Materials selection
Elevation – Materials selection
6. Introduction Conceptual update Design Development Technical Design
Preliminary budget- and planning
Preliminary master-timeframe
Preliminary time- and cost-estimate
• Preliminary project budget: 42,881.826 kr.
Construction costs: 32,999.861 kr.
Soft costs: 9,881.965 kr.
• Preliminary total project duration:
Design- and planning: XXX.XXX (%)
Construction: XXX.XXX (%)
• Life cycle costs (30 years):
Operation cost per. year: 2,003.224 kr.
Operation cost per. 30 year: 60,096.709 kr.
Preliminary life-cycle costing (LCC)
71%
29%
Estimated Life cycle cost :
Investment cost Operation 30 years
7. Design Development
Phase specific areas of focus:
1. Structural composition and function in relation to loads and
materials
2. Analysis of fire safety and required passive measurements
3. Analysis of sound performance requirements
4. Planning of installations in regards to space requirements and
routing options
5. Scrutiny of building components in relation to requirements
6. Scrutiny of junctions between adjacent components
7. Elemental cost estimation and planning development
Project scrutiny
- A working tool for project
development
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
9. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Maximum CLT master plate: 2,95 x 13,8 m
13,8 m
2,95m
≥2,95m
Wall height exceeding 2,95 m
2,40 - 2,95
m
2,40 - 2,95
m
2,40 - 2,95
m
2,40 - 2,95
m
2,40 - 2,95
m
Panels must be laid down during
transportation and flipped to upright
position from truck during assembly.
Flipping of panels may be hazardous in
regards to shear loading of lifting screws.
Requires more individual lifts and time in
regards to jointing.
Wall height not exceeding 2,95 m
≤2,95m
Transport limitations:
Height: 3,0 m
Width: 2,40 m
Length: 13,5 m
Panels can be transported vertically and
requires no flipping during assembly.
Using wall panel of ex. 2,95 m will result in
reduced waste and work-flows in the factory
and on site.
CLT standard size table
1.1 Structural system
10. 0.0
50.0
100.0
150.0
200.0
250.0
300.0
350.0
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0
Dimension(mm)
Span (m)
Structural slab analysis - Span to thickness ratio
(Vibration limit governing CLT)
Concrete PX-slab CLT - Slab Brettstapel
0.0
50.0
100.0
150.0
200.0
250.0
300.0
350.0
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0
Dimension(mm)
Height (m)
Structural wall analysis - Height to thickness ratio
Concrete Exler (class 6) CLT Wall
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Dead load: 1,0 kN/m2 + self-weight Live load: 1,5 kN/m2 Dead load: 16,0 kN/m Live load: 4,5 kN/m
CLT slabs used in functions such as floor slabs exposed to live
loads, are in terms of span length primarily limited by vibration
criteria's which are difficult to satisfy in span lengths ≥ 6 – 6,5 m.
depending upon the load.
In functions where not exposed to live load, the SLS + ULS
criteria's can be met in spans up an approximate 8,0 m.
Dissertatation report
- Chap. 2 - Fundamentals
1.1 Structural system
12. 2.1 Analysis of fire safety and passive measurements
2.2.1 Analysis of passive measurements (component classification) 2.2.2 Analysis of fire safety
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Means of escape – Ground floor Means of escape – First-second floor
Means of escape – Third floor
Component classification – Transverse
Component classification – Longitudinal
13. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
2. Analysis of sound performance requirements
On the basis of experiences gained in solid
timber project such as Limnologen,
Sweden 2009, the acoustic climate
showed to be challenged by sound waves
under the normal frames of frequency.
Provided the issues with light-buildings
and transfer of sound, the building must
fulfil sound class B which is added the
spectral correlation Rw C 50-3150.
Dissertatation report
- Chap. 3. - Acoustics
Sintef Byggforsk
- Rapport 80
References
14. 3.1 Planning of installations
2.2.1 Ventilation systems – residential
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
2.2.1 Sprinkling systems – residential
Type A Type B Type C
Level - complete Scrutiny of residential
Sprinkling systems
Type A Type B Type C
Scrutiny of residential
ventilation systems
Dimensioning of ducts
15. 5. Scrutiny of building components in regards to requirements
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
16. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
5. Scrutiny of building components in regards to requirements
17. 5. Scrutiny of building components in regards to
requirements
Primary exterior wall
Performance requirements and component scrutiny
DocumentationAestctic inspiration
List of requirements Sketch proposals Property analysis
U-value TEKNOS fire
impregnation.
Documentation
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Vandkanten, Stavanger – AART .
Sintef - 84
18. 5. Scrutiny of building components in regards to
requirements
Primary floor slab
Performance requirements and component scrutiny
References
List of requirements Sketch proposals Property analysis
Sintef Byggforsk
- Rapport 80
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Documentation
Structural
calculation slab
REI 60
classification
Brekke & Strand
- Premis rapport
Structural utilisation slab (6m):
ULS:85% ULS-FIRE: 65% SLS:68%
19. Performance requirements and component scrutiny
References
List of requirements Sketch proposal Property analysis
Fleretasjerstrehus
- kap. 5
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Documentation
Fire design table REI 60
classification
Brekke & Strand
- Premis rapport
5. Scrutiny of building components in regards to
requirements
Unit partition wall
20. Architectural detail: A Adjacent building parts
Architectural detail: B Adjacent building parts
5. Scrutiny of junctions between adjacent
components
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
21. 5. Scrutiny of junctions between adjacent
components
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Architectural detail: E
Adjacent building parts
Architectural detail: D
Adjacent building parts
22. Calculation CLT unit costs
5. Elemental cost estimation and planning development
5.1 Elemental cost estimation
Digital quanity extracts
Elemental cost plan
- Sigma estiamtes (sig.)
Elemental cost plan
- report
Estimated project budget at design stage: 41,140.297 kr.
Deviation to preliminary estimate: 1,741.529 (4%)
5.2 Planning development
Master time frame - updated
Level based division of
resources
WBS based division of
resources
Construction time plan (.mpp)
A113 specifications
Estimated construction duration at design stage: 230 days
Total project duration: XXXXXXX days
Deviation to preliminary estimate: XXX.XXX days (33%)
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Model: 3L+4L+5
24. Technical Design
Phase specific areas of focus:
1. Reviewing of building part interfaces
2. Preparation of phase drawings and documentation
3. Carbon management
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
25. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1- Reviewing of building part interfaces
Architectural detail: A
Review basis – Design Development
Reviewed – Technical Design
26. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1- Reviewing of building part interfaces
Architectural detail: B
Review basis – Design Development
Reviewed – Technical Design
27. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1- Reviewing of building part interfaces
Architectural detail: C
Review basis – Design Development
Reviewed – Technical Design
28. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1- Reviewing of building part interfaces
Architectural detail: C
Review basis – Design Development
Reviewed – Technical Design
29. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Basement
Ground floor
First – second floor
Third floor
Roof level
5. Preparation of drawings for authoritties
5.1 Detailed plans - Arcictectural 5.1 Elevations
5.1 Sections
Typologies (A-C)
5.3 Fire safety
Fire safety – Ground floor
Fire safety – First – second floor
Fire safety – Third floor
30. Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Slabs above basement
Slabs above ground floor Slabs above first/second floor
Roof level
5. Preparation of drawings for authoritties
5.1 Detailed plans - Structural 5.2 Ventilation systems
Connection detail A Connection detail B
Type A Type B
Type C Building plan
Dimensioning of ducts
31. 5. Preparation of documentation
Application for
building permit
Calculated Energy
Frame - Incl. U-values
Defined line-losses
- DS 418
Calculation of shadows
5.1 Energy frame
5.2 Administration
5.3 Structural and fire documentation
Introduction Conceptual update Design Development Technical Design
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
CLT floor slabs CLT party walls CLT exterior walls
Project specification Fire documentation
(partial)
Plot utilisation
32. 5. Project cost and time management
5.1 Elemental cost and project budget update
Elemental cost plan
- Sigma estiamtes (sig.)
Elemental cost plan
- report
Estimated project budget at design stage: XXX.XXX
Deviation to preliminary estimate (CD): XXX.XXX (33%)
Deviation to elemental cost (DD): XXX.XXX (33%)
5.2 Planning development
Master time frame - updated Construction time plan (.mpp)
Estimated construction duration at design stage: 230 days
Total project duration: XXXXXXX days
Deviation to preliminary estimate: XXX.XXX days (33%)
Deviation to prior phase (DD): XXXXXX days (33%)
33. Introduction Conceptual update Design Development Technical Design
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Introduction Conceptual update Design Development Technical Design
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 201 2 3
39.55 156.94 49.11 181.52
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Sections EC - (t/C02)
Total EC for primary structure - wood as a non CO2 neutral material
EC - 427 t/CO2
Stairwells Basement Roof Main structure
39.55 156.94 0.004.48
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Sections EC - (t/C02)
Total EC for primary structure - wood as CO2 neutral material
EC - 196,4 t/CO2
Stairwells Basement Roof Main structure
39.55 156.94 0.00 247.55
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Sections EC - (t/C02)
Total EC for primary structure - CLT replaced with pre-fab concrete
EC - 444 t/CO2
Stairwells Basement Roof Main structure
5. Carbon management – Primary super structure
Data set – Wood as non C02 neutral
Data set – Wood as C02 neutral
Data set – CLT replaced with concrete