SlideShare ist ein Scribd-Unternehmen logo
1 von 14
Resource Management
          Technical vs. Financial –
          Making the Connection




Sharyl Butler                   Kenesha Starling
Technical Manager               Financial Manager
Introduction
 Projects begin as a box of puzzle pieces with several team
  members using their expertise to fit the pieces together
 Two of the most critical pieces are the technical
  requirements and the resources needed to meet those
  requirements
 Traditionally, the link between the Technical and Financial
  manager is not very strong
    Changes to traditional
      behaviors are needed to
      strengthen this link


                                                                2
Behaviors (Traditional)
Technical Manager
   Provides work requirements
   Determines skill mix required to meet requirements
   Determines work done by contractor vs. civil servant
   Manages travel requirements
   Manages performance of contractor/civil servant
   Major focus is on technical requirements
   Fully dependent on Financial Manager for financials



                                                           3
Behaviors (Traditional)
Financial Manager
 Manages all phases of budget; formulation and implementation
 Recommends resource allocations based on funding, priorities and
    needs
   Designs, develops and interprets financial statements for Technical
    Managers
   Interprets agency and center financial regulations and policies
   Assures that financial accounting practices are maintained
   Major focus is on funding requirements
   Fully dependent on Technical Manager for task knowledge



                                                                          4
Why change what we are doing today?




                                      5
Shortcomings of Traditional Behaviors:
         Problems Encountered
 Scenario A: Technical Manager (TM) directs COTR to
  authorize additional hours for contract X in order to
  incorporate additional high priority requirements from program
  Y but fails to communicate this to the Financial Manager (FM)
     Problem: Contract overruns because TM failed to
     communicate new requirements to FM and no additional
     funding was available
     Problem: Unplanned workforce reductions and other
     planned tasks were cut in order to get the task back on
     plan


                                                                   6
Shortcomings of Traditional Behaviors:
         Problems Encountered
 Scenario B: Program Y informs the TM that the schedule for
  task Z slipped to the right because of necessary redesigns.
  Therefore, the TM tells the COTR to direct contractor X to
  focus on several other high priority task for program Y
  causing them to burn available hours and overtime thus
  increasing costs. On the other hand, the FM asks the COTR
  to direct contractor X’ s business manager that the slip is
  unfortunate but timely because of overrun trends so they
  should use this time to focus on other areas.
     Problem: Because there was a lack of communication
     between the FM and TM and conflicting/inconsistent
     direction given either an unplanned request for additional
     funds will be needed or unplanned layoffs will be
     necessary.                                                   7
Shortcomings of Traditional Behaviors:
         Problems Encountered
 Scenario C: FM receives monthly financial statement for
  contract X and notices they have been burning at a higher
  hourly rate than planned. The FM decides they will observe
  this a few months longer before bringing it to the attention of
  the TM. Six months go by and the FM finally mentions this to
  the TM.
      Problem: In order to complete tasks originally agreed
      upon, the TM must make an unplanned request for
      funding increases because of the FM’s lack of
      communication about financial issues and forecasting



                                                                    8
Shortcomings of Traditional Behaviors:
          Problems Encountered
 Scenario D: During a technical, cost and schedule review (TCSR)
  the TM recommends to Program Manager Y that additional funds be
  provided to cover costs for additional hours needed to complete task
  X on time. Program manager Y questions the TM because earlier
  that morning, the FM briefed him that task X was under running and
  if no additional tasks were needed $100K would be returned to the
  program.
      Problem: Because the TM and FM didn’t tag-up prior to the
      TCSR, Program Manager Y begins to question the integrity of the
      data received from both because of the inconsistency. They are
      sent away to create a cohesive story and provide a combined
      recommendation in a week. This leads to conflict between the
      TM and FM as they both feel the other “threw them under the
      bus”.

                                                                         9
These are serious problems!
How do we overcome them?




                              10
Changes to Traditional
                     Behaviors That Work
 Transparent and timely communication between Technical and Financial
    manager is required
   Develop a trusting relationship between technical and financial managers
       Open dialogue
       Sharing of confidential information
   Technical manager shares technical requirements and priorities with
    Financial manager
   Financial manager analyzes cost impacts and recommends options to
    maintain funding levels
   Both managers assure that approved changes to the
    baseline requirements are reviewed and assessed for
    budgetary impacts
                                                                               11
Changes to Traditional
            Behaviors That Work (con’t)
 Managers work together to develop options for addressing
  budget and resource issues
     Research cost saving methods
     Use “yes, if…” terminology, instead of “no”
 Joint development of regular project Technical, Cost and
  Schedule Reviews
 Basic knowledge transfer
    Terminology (NOA, WADs, etc.)
    Schedules (PPBE, milestones, etc)

                                                             12
Final Words
 The link between Technical and Financial management is
  critical to a project’s success
 Frequent communication between the Technical and
  Financial manager is crucial throughout the project’s
  lifecycle as technical and funding requirements are often
  dynamic




                                                              13
Suggested Training
   Crossing Department Lines
   Finance for Non-Financial Managers
   Essentials of Project Management for non-Project Managers
   Project Control: Fundamentals of Overhead and Other Indirect Cost
   Appropriations Law
   Business Education Program
   JSC CFO University courses
   Mentoring from technical/financial experts




                                                                        14

Weitere ähnliche Inhalte

Was ist angesagt?

Taking the Creep Out of Scope Creep
Taking the Creep Out of Scope CreepTaking the Creep Out of Scope Creep
Taking the Creep Out of Scope CreepComputer Aid, Inc
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbierNASAPMC
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinalNASAPMC
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Resolving TIAs
Resolving TIAsResolving TIAs
Resolving TIAsChris Carson
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
D10 Project Management
D10 Project ManagementD10 Project Management
D10 Project ManagementLeanleaders.org
 
Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tonyNASAPMC
 
Project management 101
Project management 101Project management 101
Project management 101Sujatha TS
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahaniNASAPMC
 
Project lifecycle management @ Pharma Project Management Conference - 2014, M...
Project lifecycle management @ Pharma Project Management Conference - 2014, M...Project lifecycle management @ Pharma Project Management Conference - 2014, M...
Project lifecycle management @ Pharma Project Management Conference - 2014, M...Megha Kotak, PMP
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
The Project Management Process - Week 10 Global Issues in IT projects
The Project Management Process - Week 10   Global Issues in IT projectsThe Project Management Process - Week 10   Global Issues in IT projects
The Project Management Process - Week 10 Global Issues in IT projectsCraig Brown
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 
Introduction to Project Management (workshop) - v.2
Introduction to Project Management (workshop) - v.2Introduction to Project Management (workshop) - v.2
Introduction to Project Management (workshop) - v.2Mena M. Eissa
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/FailurePeter Salmon
 
PSIS 4145-IS SP2013 Lecture 2 Project Initiation and Management 20130112
PSIS 4145-IS SP2013 Lecture 2 Project Initiation and Management 20130112PSIS 4145-IS SP2013 Lecture 2 Project Initiation and Management 20130112
PSIS 4145-IS SP2013 Lecture 2 Project Initiation and Management 20130112McDonald Stewart
 

Was ist angesagt? (20)

Taking the Creep Out of Scope Creep
Taking the Creep Out of Scope CreepTaking the Creep Out of Scope Creep
Taking the Creep Out of Scope Creep
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbier
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Resolving TIAs
Resolving TIAsResolving TIAs
Resolving TIAs
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
D10 Project Management
D10 Project ManagementD10 Project Management
D10 Project Management
 
Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tony
 
Basic Project Management Qc Session1
Basic Project Management  Qc Session1Basic Project Management  Qc Session1
Basic Project Management Qc Session1
 
Project management 101
Project management 101Project management 101
Project management 101
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahani
 
Project lifecycle management @ Pharma Project Management Conference - 2014, M...
Project lifecycle management @ Pharma Project Management Conference - 2014, M...Project lifecycle management @ Pharma Project Management Conference - 2014, M...
Project lifecycle management @ Pharma Project Management Conference - 2014, M...
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
The Project Management Process - Week 10 Global Issues in IT projects
The Project Management Process - Week 10   Global Issues in IT projectsThe Project Management Process - Week 10   Global Issues in IT projects
The Project Management Process - Week 10 Global Issues in IT projects
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
Introduction to Project Management (workshop) - v.2
Introduction to Project Management (workshop) - v.2Introduction to Project Management (workshop) - v.2
Introduction to Project Management (workshop) - v.2
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/Failure
 
PSIS 4145-IS SP2013 Lecture 2 Project Initiation and Management 20130112
PSIS 4145-IS SP2013 Lecture 2 Project Initiation and Management 20130112PSIS 4145-IS SP2013 Lecture 2 Project Initiation and Management 20130112
PSIS 4145-IS SP2013 Lecture 2 Project Initiation and Management 20130112
 

Andere mochten auch

Inter mitchell
Inter mitchellInter mitchell
Inter mitchellNASAPMC
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardoNASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathyNASAPMC
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNASAPMC
 
Newman.steve
Newman.steveNewman.steve
Newman.steveNASAPMC
 
Miller.charles
Miller.charlesMiller.charles
Miller.charlesNASAPMC
 
Sally godfreyheatherrarick
Sally godfreyheatherrarickSally godfreyheatherrarick
Sally godfreyheatherrarickNASAPMC
 
Rothenberg.joe
Rothenberg.joeRothenberg.joe
Rothenberg.joeNASAPMC
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseNASAPMC
 
Nick.chrissotimos
Nick.chrissotimosNick.chrissotimos
Nick.chrissotimosNASAPMC
 
Terri tramel 01-27-12
Terri tramel 01-27-12Terri tramel 01-27-12
Terri tramel 01-27-12NASAPMC
 
Book.steve
Book.steveBook.steve
Book.steveNASAPMC
 
David.atwell
David.atwellDavid.atwell
David.atwellNASAPMC
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.johnNASAPMC
 
Sand.steven
Sand.stevenSand.steven
Sand.stevenNASAPMC
 
Adesh.jain
Adesh.jainAdesh.jain
Adesh.jainNASAPMC
 
John.baniszewski
John.baniszewskiJohn.baniszewski
John.baniszewskiNASAPMC
 
Ross.howard
Ross.howardRoss.howard
Ross.howardNASAPMC
 
2012 02-22 rittweger orlando ipmc
2012 02-22 rittweger orlando ipmc2012 02-22 rittweger orlando ipmc
2012 02-22 rittweger orlando ipmcNASAPMC
 
Diaz franklin
Diaz franklinDiaz franklin
Diaz franklinNASAPMC
 

Andere mochten auch (20)

Inter mitchell
Inter mitchellInter mitchell
Inter mitchell
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardo
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Newman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_caseNewman lengyel dartpm-chal_case
Newman lengyel dartpm-chal_case
 
Newman.steve
Newman.steveNewman.steve
Newman.steve
 
Miller.charles
Miller.charlesMiller.charles
Miller.charles
 
Sally godfreyheatherrarick
Sally godfreyheatherrarickSally godfreyheatherrarick
Sally godfreyheatherrarick
 
Rothenberg.joe
Rothenberg.joeRothenberg.joe
Rothenberg.joe
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
 
Nick.chrissotimos
Nick.chrissotimosNick.chrissotimos
Nick.chrissotimos
 
Terri tramel 01-27-12
Terri tramel 01-27-12Terri tramel 01-27-12
Terri tramel 01-27-12
 
Book.steve
Book.steveBook.steve
Book.steve
 
David.atwell
David.atwellDavid.atwell
David.atwell
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
 
Sand.steven
Sand.stevenSand.steven
Sand.steven
 
Adesh.jain
Adesh.jainAdesh.jain
Adesh.jain
 
John.baniszewski
John.baniszewskiJohn.baniszewski
John.baniszewski
 
Ross.howard
Ross.howardRoss.howard
Ross.howard
 
2012 02-22 rittweger orlando ipmc
2012 02-22 rittweger orlando ipmc2012 02-22 rittweger orlando ipmc
2012 02-22 rittweger orlando ipmc
 
Diaz franklin
Diaz franklinDiaz franklin
Diaz franklin
 

Ă„hnlich wie Sharyl butler

The Future of Oilsands Projects – Productivity Improvement & the Role o...
The Future of Oilsands  Projects – Productivity Improvement  & the Role o...The Future of Oilsands  Projects – Productivity Improvement  & the Role o...
The Future of Oilsands Projects – Productivity Improvement & the Role o...Nick Anderson
 
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt  Final RptImprovement of Hospital Project Cost and Schedule Mgmt  Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt Final RptEd Kozak
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1Imoh Etuk
 
1 ch1
1 ch11 ch1
1 ch1perdogdu
 
Data Center Transformation Program Planning and Design
Data Center Transformation Program Planning and DesignData Center Transformation Program Planning and Design
Data Center Transformation Program Planning and DesignJoseph Schwartz
 
Finance and Operations in FM 11
Finance and Operations in FM 11Finance and Operations in FM 11
Finance and Operations in FM 11barnbyvilla
 
Relocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxRelocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxcarlt4
 
Relocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxRelocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxdebishakespeare
 
Managing Process Improvement
Managing Process ImprovementManaging Process Improvement
Managing Process ImprovementBill Fox
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train WrecksPete Luan
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
From planning-to-execution-wp-352123
From planning-to-execution-wp-352123From planning-to-execution-wp-352123
From planning-to-execution-wp-352123Vishvendu pandey
 
LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2Jose Figueroa
 
Schwalbe-07ProjectCost.ppt
Schwalbe-07ProjectCost.pptSchwalbe-07ProjectCost.ppt
Schwalbe-07ProjectCost.pptmanojgandhi1
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docxwrite22
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docxwrite31
 

Ă„hnlich wie Sharyl butler (20)

The Future of Oilsands Projects – Productivity Improvement & the Role o...
The Future of Oilsands  Projects – Productivity Improvement  & the Role o...The Future of Oilsands  Projects – Productivity Improvement  & the Role o...
The Future of Oilsands Projects – Productivity Improvement & the Role o...
 
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt  Final RptImprovement of Hospital Project Cost and Schedule Mgmt  Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
1 ch1
1 ch11 ch1
1 ch1
 
Data Center Transformation Program Planning and Design
Data Center Transformation Program Planning and DesignData Center Transformation Program Planning and Design
Data Center Transformation Program Planning and Design
 
SampleCAR
SampleCARSampleCAR
SampleCAR
 
Finance and Operations in FM 11
Finance and Operations in FM 11Finance and Operations in FM 11
Finance and Operations in FM 11
 
Unlocking pmo profitability
Unlocking pmo profitabilityUnlocking pmo profitability
Unlocking pmo profitability
 
Unlocking pmo profitability
Unlocking pmo profitabilityUnlocking pmo profitability
Unlocking pmo profitability
 
Relocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxRelocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docx
 
Relocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docxRelocation of Us headquarters Technology firmJi Pete.docx
Relocation of Us headquarters Technology firmJi Pete.docx
 
Managing Process Improvement
Managing Process ImprovementManaging Process Improvement
Managing Process Improvement
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
From planning-to-execution-wp-352123
From planning-to-execution-wp-352123From planning-to-execution-wp-352123
From planning-to-execution-wp-352123
 
LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2LavaCon Best Practices For Multiple Technical Projects V1R2
LavaCon Best Practices For Multiple Technical Projects V1R2
 
Schwalbe-07ProjectCost.ppt
Schwalbe-07ProjectCost.pptSchwalbe-07ProjectCost.ppt
Schwalbe-07ProjectCost.ppt
 
Cognitive 544 pa_art
Cognitive 544 pa_artCognitive 544 pa_art
Cognitive 544 pa_art
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
 

Mehr von NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Mehr von NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

KĂĽrzlich hochgeladen

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Call Girls Jp Nagar Just Call đź‘— 7737669865 đź‘— Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call đź‘— 7737669865 đź‘— Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call đź‘— 7737669865 đź‘— Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call đź‘— 7737669865 đź‘— Top Class Call Girl Service Bang...amitlee9823
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 

KĂĽrzlich hochgeladen (20)

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Call Girls Jp Nagar Just Call đź‘— 7737669865 đź‘— Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call đź‘— 7737669865 đź‘— Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call đź‘— 7737669865 đź‘— Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call đź‘— 7737669865 đź‘— Top Class Call Girl Service Bang...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 

Sharyl butler

  • 1. Resource Management Technical vs. Financial – Making the Connection Sharyl Butler Kenesha Starling Technical Manager Financial Manager
  • 2. Introduction  Projects begin as a box of puzzle pieces with several team members using their expertise to fit the pieces together  Two of the most critical pieces are the technical requirements and the resources needed to meet those requirements  Traditionally, the link between the Technical and Financial manager is not very strong  Changes to traditional behaviors are needed to strengthen this link 2
  • 3. Behaviors (Traditional) Technical Manager  Provides work requirements  Determines skill mix required to meet requirements  Determines work done by contractor vs. civil servant  Manages travel requirements  Manages performance of contractor/civil servant  Major focus is on technical requirements  Fully dependent on Financial Manager for financials 3
  • 4. Behaviors (Traditional) Financial Manager  Manages all phases of budget; formulation and implementation  Recommends resource allocations based on funding, priorities and needs  Designs, develops and interprets financial statements for Technical Managers  Interprets agency and center financial regulations and policies  Assures that financial accounting practices are maintained  Major focus is on funding requirements  Fully dependent on Technical Manager for task knowledge 4
  • 5. Why change what we are doing today? 5
  • 6. Shortcomings of Traditional Behaviors: Problems Encountered  Scenario A: Technical Manager (TM) directs COTR to authorize additional hours for contract X in order to incorporate additional high priority requirements from program Y but fails to communicate this to the Financial Manager (FM) Problem: Contract overruns because TM failed to communicate new requirements to FM and no additional funding was available Problem: Unplanned workforce reductions and other planned tasks were cut in order to get the task back on plan 6
  • 7. Shortcomings of Traditional Behaviors: Problems Encountered  Scenario B: Program Y informs the TM that the schedule for task Z slipped to the right because of necessary redesigns. Therefore, the TM tells the COTR to direct contractor X to focus on several other high priority task for program Y causing them to burn available hours and overtime thus increasing costs. On the other hand, the FM asks the COTR to direct contractor X’ s business manager that the slip is unfortunate but timely because of overrun trends so they should use this time to focus on other areas. Problem: Because there was a lack of communication between the FM and TM and conflicting/inconsistent direction given either an unplanned request for additional funds will be needed or unplanned layoffs will be necessary. 7
  • 8. Shortcomings of Traditional Behaviors: Problems Encountered  Scenario C: FM receives monthly financial statement for contract X and notices they have been burning at a higher hourly rate than planned. The FM decides they will observe this a few months longer before bringing it to the attention of the TM. Six months go by and the FM finally mentions this to the TM. Problem: In order to complete tasks originally agreed upon, the TM must make an unplanned request for funding increases because of the FM’s lack of communication about financial issues and forecasting 8
  • 9. Shortcomings of Traditional Behaviors: Problems Encountered  Scenario D: During a technical, cost and schedule review (TCSR) the TM recommends to Program Manager Y that additional funds be provided to cover costs for additional hours needed to complete task X on time. Program manager Y questions the TM because earlier that morning, the FM briefed him that task X was under running and if no additional tasks were needed $100K would be returned to the program. Problem: Because the TM and FM didn’t tag-up prior to the TCSR, Program Manager Y begins to question the integrity of the data received from both because of the inconsistency. They are sent away to create a cohesive story and provide a combined recommendation in a week. This leads to conflict between the TM and FM as they both feel the other “threw them under the bus”. 9
  • 10. These are serious problems! How do we overcome them? 10
  • 11. Changes to Traditional Behaviors That Work  Transparent and timely communication between Technical and Financial manager is required  Develop a trusting relationship between technical and financial managers Open dialogue Sharing of confidential information  Technical manager shares technical requirements and priorities with Financial manager  Financial manager analyzes cost impacts and recommends options to maintain funding levels  Both managers assure that approved changes to the baseline requirements are reviewed and assessed for budgetary impacts 11
  • 12. Changes to Traditional Behaviors That Work (con’t)  Managers work together to develop options for addressing budget and resource issues Research cost saving methods Use “yes, if…” terminology, instead of “no”  Joint development of regular project Technical, Cost and Schedule Reviews  Basic knowledge transfer Terminology (NOA, WADs, etc.) Schedules (PPBE, milestones, etc) 12
  • 13. Final Words  The link between Technical and Financial management is critical to a project’s success  Frequent communication between the Technical and Financial manager is crucial throughout the project’s lifecycle as technical and funding requirements are often dynamic 13
  • 14. Suggested Training  Crossing Department Lines  Finance for Non-Financial Managers  Essentials of Project Management for non-Project Managers  Project Control: Fundamentals of Overhead and Other Indirect Cost  Appropriations Law  Business Education Program  JSC CFO University courses  Mentoring from technical/financial experts 14