SlideShare ist ein Scribd-Unternehmen logo
1 von 56
Project Management Professional
PMP® Exam Prep – Week 2
Prof. Muzette Charles, PMP | mcharles2@pace.edu
Integration Management
Chapter 4
“Is the Project Manager’s core responsibilities”
“…. is a group of processes required to ensure that the
various elements of the project are properly coordinated.”
Process Process Group Key Deliverables
4.1 Develop Project Charter Initiating Project Charter
4.2 Develop Project Management Plan Planning Project Management Plan
4.3 Direct and Manage Executing Project Deliverables
4.4 Manage Project Knowledge Executing Document Lessons Learned
4.5 Monitor and Control Project Work Monitoring & Controlling Change Requests
4.6 Perform Integrated Change Control Monitoring & Controlling Approved Change Requests
4.7 Close Project or Phase Closing Finalize Contracts, Payments, Transition
Project Integration Management
Chapter 4
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
Key Points
 A project charter formally authorizes the project
 Gives the objectives and business case
 Identifies & authorizes Project Manager use of organizational resources for project use
 Generic enough not to change often
 Written by a Manager higher in authority than Project Manager
 Includes name, description, deliverables, milestone dates
 Stakeholder list
 Assumptions & contraints
 A project does not start unless it has a Project charter
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
INPUTS
 Statement of Work (SOW) - from external customer describing project deliverables
 Business Case - from internal whether the project’s Cost-Benefit makes sense
TOOLS
 Expert Judgement – gaining advice from experts in other dept, outside consultants, industry groups
 Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page
when making a project decision
What does the term “sunk cost” mean?
A. Past investment in an initiative that must be
considered in deciding to authorize a project
B. Sum of all economic investments in a project
C. All previous irretrievable investments in a
project
D. The cumulative losses from projects in this
program or portfolio
Discussion Question
Answer: C
While A is correct in identifying sunk costs as past
investments, it is incorrect in saying that these costs should
be a consideration for authorization. The analysis starts with
a clean slate, considering future costs and benefits.
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
• Clearly definedSpecific
• Can be evaluated objectivelyMeasurable
• Can be met under current
constraints and assumptionsAttainable
• Support organizational goalsRelevant
• Set a deadline for attainmentTime-bound
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
Answer:
The goal could include a time frame and
criteria for measurement, for example:
Deliver by end of fourth quarter 2015 a new
complaint-handling process that results in 25%
fewer instances of escalation and a 50% increase in
customer satisfaction, as of first quarter 2014.
Chapter 4, Topic 1
How could this project goal statement be
improved?
Deliver a new complaint-handling process that meets
customer service requirements and increases revenue
through improved customer retention.
Discussion Question
Project Integration Management
Chapter 4
Develop Project Management Plan (PMP)
Process 2
Key Points
 Key benefit: creates the central document that defines all of the project work
 How the project will be executed, monitored & controlled
 Subsidiary plans are integrated into ONE comprehensive PMP
 The PMP is developed by the Project Manager with inputs from the team, stakeholders & management
 Project baseline refers to the original version of the PMP
 Once the PMP is baselined, it may only be changed by raising a change request
 Progressive Elaboration is the process of taking a project from concept to detailed design
 Kick-off meeting happens after the planning phase and before the project execution. It is typically used
to communicate responsibilities of key stakeholders.
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Direct & Manage Project Work
Process 3
Key Points
 Key benefit of this process is to provide overall management of the project work
 To lead & perform work as defined in the PMP
 Create deliverables to meet planned project work
 Manage team members & provide them with training
 Obtain, manage & use resources ex. Materials, Equipment, Facilities
 Establish & manage communications internal & external channels
 Manage Stakeholders, Sellers, Risks, Change Requests
Project Integration Management
Chapter 4
Direct & Manage Project Work
Process 3
Project Integration Management
Chapter 4
Manage Project Knowledge
Process 4
Key Points
 Use prior organizational knowledge to produce or improve project outcomes
 Knowledge created by the project used to support operations and future projects
 Use existing knowledge and create new knowledge
 Contribute to organizational lessons learned
Project Integration Management
Chapter 4
Manage Project Work
Process 4
Knowledge Management
Category
Type of
Information
Means of
Communication
Challenges
Explicit • Words
• Pictures
• Numbers
Verbal
Print
Digital
Lack of context
Tacit • Insights
• Experiences
• “Know-how”
Personal
transfer
Needs a trusting
environment
that fosters
communication
Project Integration Management
Chapter 4
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Key Points
 Key benefit: allows stakeholders to understand current state of the project, any steps taken
and budget, schedule & scope forecasts
 Tracks, reviews & reports actual progress & performance against the PMP objectives
 Is conducted from project inception through completion
 Control includes corrective & preventative actions
 Identify & analyze existing and new risks
 Work Authorization System - PM’s system to ensure work is performed at the right time & in
the right sequence (found in the EEF – PMIS)
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Key Points
 Change Requests
 are submitted when issues are found while project work is being performed
 is a formal (written) proposal to modify any document, baseline, deliverable
 Change Log – all WRITTEN requests approved or not
 PM has authority to make changes IF constraints are not effected
 Types of Changes
 Corrective Action – taken when actual deviations from the performance baseline
 Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting
 Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Project Integration Management
Chapter 4
Perform Integrated Change Control
Process 6
Key Points
 Key benefit: allows documented changes to be considered in an integrated manner to the
overall project while reducing risks to other areas of the project
 Reviews, approves & manages all change requests to the PMP, OPA, deliverables, etc
 Is conducted from project inception through completion
 Is the ultimate responsibility of the Project Manager to carefully & continuously manage
changes
 Changes can be requested by any stakeholder involved in the project
 Every “documented” change must be approved or rejected by a “responsible person”
 Or by the CCB – Change Control Board
Project Integration Management
Chapter 4
Perform Integrated Change Control
Process 6
Uncontrolled Changes to Project Scope
 Uncontrolled changes create risks of
exceeding schedule and budget, decreasing
quality, having inaccurate documentation,
and damaging deliverables.
 Project managers can help by:
– Clearly communicating to all
stakeholders what is and is not in
scope.
– Using the integrated change control
process.
Scope creep
“Uncontrolled expansion
to product or project
scope without adjust-
ments to time, cost, and
resources”
Gold plating
Uncontrolled
“improvements” made
with best intentions by
team
Project Integration Management
Chapter 4
A government body says that they need to add a citizen
body to the stakeholders on a new emergency services
center project. How should the project manager
respond?
A. Add the stakeholder to the stakeholder register.
B. Explain that the new stakeholder will increase
project risks.
C. Explain that this cannot be done since the project has
already been scoped.
D. Initiate the change control process.
Discussion Question
Answer: D
This could become a case of scope creep unless the influence of
this stakeholder is fully understood and accepted by the
sponsor. It could be a very beneficial act, but its effect on
scope, timeline, and budget must be understood.
Chapter 4, Topic 6
A project consultant notes that a recently released
technology will increase the functionality of the
deliverable. How should the project manager
respond?
A. Thank the consultant and do nothing, since this
is beyond scope.
B. Ask the sponsor for direction.
C. Analyze the impact on the project.
D. Submit a change request to the CCB.
Discussion Question
Answer: C
This is a common type of question on the PMP exam.
Remember that the first thing a project manager does is to try
to understand the impact of a change on the project, for good
and bad.
Chapter 4, Topic 6
Configuration Management
 Control of changes to the deliverable and/or its
components
 Integrated change control for configuration includes:
– Identifying configurable items
– Maintaining version control
– Verifying and auditing configuration
Project Integration Management
Chapter 4
Change Log
Comprehensive list of changes approved (and rejected)
during the project
 Description
 Date
 Impacts
 Status
 Owner
Chapter 4, Topic 6
PROJECT CHANGE LOG
Project Name: Project Sponsor:
# Description: Owner: Date: Project Impact: Status:
1
2
3
Project Integration Management
Chapter 4
Project Integration Management
Chapter 4
Close Project or Phase
Process 7
Key Points
 Provides lessons learned, formal ending of the project work & release of the organization’s
resources to pursue new endeavors
 Finalizes all activities across all PM Process Groups
 PM measures the scope baseline against the PMP
 Complete & close all contracts, procurement agreements, financials,
 Archive OPA historical records, reports, etc
 For projects terminated before completion, PM engages all stakeholders to investigate &
document reasons why
Closing Activities
Deliverables
accepted
Documents
archived
Project
assessed
Team
released
Customer
acceptance of
validated product
Transition into next
phase or service
Customer review of
project
Project
management plan
All project
documents
Lessons learned
captured and
added to
knowledge base
Team member
performance
reviews
Formal release
to function or
other projects
Project Integration Management
Chapter 4
Project Integration Management
Chapter 4
Close Project or Phase
Process 7
Project Integration Management
Chapter 4
Key Points
 A project charter formally authorizes the project
 Statement of Work (SOW) - from external customer describing project deliverables
 Business Case - from internal whether the project’s Cost-Benefit makes sense
 Expert Judgment – gaining advice from experts in other dept, outside consultants, industry
groups
 Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the
same page when making a project decision
 Subsidiary plans & Baselines are integrated into ONE comprehensive PMP
Project Integration Management
Chapter 4
Key Points
 The PMP is developed by the Project Manager with inputs from the team, stakeholders &
management
 Project baseline refers to the original version of the PMP
 Once the PMP is baselined, it may only be changed by raising a change request
 Progressive Elaboration is the process of taking a project from concept to detailed design
 Monitor & Control is conducted from project inception through completion
 Control includes corrective & preventative Actions aka Changes
 Corrective Action – taken when actual deviations from the performance baseline
 Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting
 Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
 Changes can be made by Crashing or Fast Tracking
Project Integration Management
Chapter 4 - Summary
Scope Management
Chapter 5
“Is the process of defining what work is required and making sure all of that work &
only that work is done successfully.”
• “Completion of the project scope is measured against the PMP.”
• “Completion of the product scope is measured against the product requirements.”
Process Process Group Key Deliverables
5.1 Plan Scope Management Planning Scope & Requirement
Management Plans
5.2 Collect Requirements Planning Requirements Document
5.3 Define Scope Planning Project Scope Statement
5.4 Create WBS Planning WBS, WBS Dictionary
5.5 Validate Scope Monitoring & Controlling Acceptance Deliverables
5.6 Control Scope Monitoring & Controlling Change Requests
Product
Scope
Project
Scope
Set of “features and functions
that characterize a product,
service, or result”
“The work performed to deliver a
product, service, or result with the
specified features and functions”
Measured against product
requirements
Measured against the project
management plan
Scope Management
Chapter 5
Scope Management
Chapter 5
Plan Scope Management
Process 1
Key Points
 “Documents how the project scope is defined, validated, controlled & managed throughout the project”
 Process generates 2 management plans that both become part of the PMP
 “The plan helps to reduce the risk of project scope creep”
The project charter is listed as an input to this
process. What key information does it provide?
A. Probable risks and their impacts and priorities
B. High-level project and product description
C. List of similar projects in knowledge base
D. Stakeholder register
Discussion Question
Answer: B
The high-level description in the charter is developed
from an early statement of work (SOW). The SOW will
be progressively elaborated during Planning and
integrated change control.
Scope Management
Chapter 5
Collect Requirements
Process 2
Key Points
 Is the process of determining & documenting stakeholder’s needs & requirements in detail
 Critical to project’s success as missed requirements could mean major changes & conflicts
Scope Management
Chapter 5
Collect Requirements
Process 2
Key Points
 Project manager chooses the best Tools & Techniques to gather info:
 Interviews, Focus Groups, Facilitated Workshops,
 Brainstorming; Nominal, Multicriteria Analysis, Affinity diagram, Mind Maps
 Group Decision; Unanimity/Delphi Tech, Majority, Plurality, Dictatorship, Consensus
 Questionnaires, Surveys, Observations, Prototypes, Benchmarking
 Context Diagrams, Document Analysis
 Requirements Documentation: Acceptance Criteria used to set Scope Baseline
 Requirements Traceability Matrix: “helps to ensure each req. adds value by linking to a
project objective”
Scope Management
Chapter 5
Collect Requirements
Process 2
Scope Management
Chapter 5
Collect Requirements
Process 2
Scope Management
Chapter 5
Define Scope
Process 3
Key Points
 The process of developing a detailed description of the project & product/deliverable
 Defines requirement boundaries – of those collected included or excluded from project scope
 Tools: Product Analysis, Alternatives Generation (different ways to do same work efficiently)
Project Scope Statement
 Project scope description
 Acceptance criteria
 Deliverables
 Project exclusion
 Constraints
 Assumptions
First of three pivotal scope documents
Scope Management
Chapter 5
Define Scope
Process 3
Scope Management
Chapter 5
Create WBS
Process 4
Key Points
 “Is the hierarchical decomposition of the total scope of the work to be done by the project…
into smaller more manageable parts/deliverables.”
 Is the process of subdividing, breaking down, decomposing the project scope into
manageable work packages that is a visual to the entire team.
 Scope baseline: comprised of WBS, WBS dictionary & Project Scope Statement
Scope Management
Chapter 5
Create WBS
Process 4
Key Points
 WBS is the most important process in Scope Management & foundation of the project
 must be graphical & can be organized by Phase or Category
 used as a basis to estimate costs & time at the work package level
 The entire project is represented in the WBS, if not, then it’s not part of the project
 Control Accounts: Unique accounting codes assigned to track completion of work
 Created with help of the team’s experience to be realistic
 Helps gain the team’s buy-in & builds the team
 Keeps up team momentum by letting ppl see their importance to complete their work
 Helps prevent Scope Creep: impact of an uncontrolled change to scope, time, cost
Scope Management
Chapter 5
Create WBS
Process 4
Work Breakdown Structure (WBS)
 Project level
 Control account
Optional point consolidating
scope, budget, and schedule
to support measurement
 Planning package
Optional grouping of work
packages
 Work package
Smallest practical breakdown
of work for estimation and
management
Scope Management
Chapter 5
Work Breakdown Structure (WBS)
 Project level
 Control account
Optional point consolidating
scope, budget, and schedule
to support measurement
 Planning package
Optional grouping of work
packages
 Work package
Smallest practical breakdown
of work for estimation and
management
Scope Management
Chapter 5
WBS Dictionary
Detailed information about each
work package in the WBS:
 Code of account identifier
 Description of work
 Assumptions and constraints
 Responsible organization
 Acceptance criteria
 Technical references
Added through progressive
elaboration:
Schedule milestones and activities
Required resources
Cost estimates
Quality requirements
Agreement information (contracts)
Scope Management
Chapter 5
PLAN
PROJECT
MANAGEMENT
PLAN
PROJECT SCOPE
STATEMENT
WBS
WBS
DICTIONARY
SCOPE
BASELINE
Once approved, these documents can be changed
only through the integrated change control process.
WBS DICTIONARY
Scope Management
Chapter 5
Scope Baseline
Create WBS
Process 4
Scope Management
Chapter 5
Validate Scope
Process 5
Key Points
 “Is the process of formalizing acceptance of completed project deliverables.”
 Involves frequent formal meetings with sponsor /customer to gain formal acceptance of deliverables
 Recommended to validate scope at the end of each phase and/or multiple times in a project
 Validate Scope process: the customer checks & approves deliverables
 Control Quality process: the QC dept checks deliverables to see that requirements are met.
A deliverable has passed internal quality control, but the
customer refuses to accept it because the quality is not at the
expected level. What will happen next?
A. The contract will be referred to the legal department.
B. Control Quality will be repeated.
C. Manage Quality will be repeated.
D. The project manager will facilitate further
discussions with the customer.
Discussion Question
Answer: D
If the deliverable fulfills the scope baseline but does not meet
customer expectations, the project manager will facilitate
group discussions and decision making about the next step,
which could involve change to both the product and the
agreement.
Scope Management
Chapter 5
Control Scope
Process 6
Key Points
 “Is the process of monitoring the project status (scope performance aka work completed) by managing
changes between the work performance data against the scope baseline.”
 Is a proactive process lead by the Project Manager to prevent project changes
 Incontrolled adjustments to project constraints lead to Scope Creep
Scope Management
Chapter 5
PMP Exam Prep
Group Exercise – PMP Subsidiary Plans

Weitere ähnliche Inhalte

Was ist angesagt?

PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope managementejlp12
 
Chapter 1 An Overview Of Project Management
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project ManagementMahesh Bendigeri
 
project Scope management
project Scope management project Scope management
project Scope management Mohamed , PMP
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Project Management Certification Notes
Project Management Certification NotesProject Management Certification Notes
Project Management Certification NotesRishabh Dev
 
Project management frame work part 2
Project management frame work part 2Project management frame work part 2
Project management frame work part 2Mohamed , PMP
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management Ahmad Maharma, PMP,RMP
 
Programme management and project evaluation
Programme management and project evaluationProgramme management and project evaluation
Programme management and project evaluationtumetr1
 
Project management frame work part 3
Project management frame work part 3Project management frame work part 3
Project management frame work part 3Mohamed , PMP
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slidesdotesch
 

Was ist angesagt? (20)

PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope management
 
Chapter 1 An Overview Of Project Management
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project Management
 
project Scope management
project Scope management project Scope management
project Scope management
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
2. project scope management
2. project scope management2. project scope management
2. project scope management
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Project Management Certification Notes
Project Management Certification NotesProject Management Certification Notes
Project Management Certification Notes
 
Project management frame work part 2
Project management frame work part 2Project management frame work part 2
Project management frame work part 2
 
Chap04 project integration management
Chap04 project integration managementChap04 project integration management
Chap04 project integration management
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
GAFM Academy Module 1 Project Quality Management
GAFM Academy Module 1  Project Quality ManagementGAFM Academy Module 1  Project Quality Management
GAFM Academy Module 1 Project Quality Management
 
Programme management and project evaluation
Programme management and project evaluationProgramme management and project evaluation
Programme management and project evaluation
 
Project management frame work part 3
Project management frame work part 3Project management frame work part 3
Project management frame work part 3
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Chap08 project quality management
Chap08 project quality  managementChap08 project quality  management
Chap08 project quality management
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slides
 

Ähnlich wie PMP Muzette Charles_Sp2019_Week2_Chapter4_5

Ähnlich wie PMP Muzette Charles_Sp2019_Week2_Chapter4_5 (20)

CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptx
 
Day 2 PMP.pptx
Day 2 PMP.pptxDay 2 PMP.pptx
Day 2 PMP.pptx
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
4 integration
4 integration4 integration
4 integration
 
PROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENTPROJECT PLANNING AND MANAGEMENT
PROJECT PLANNING AND MANAGEMENT
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration management
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
Project management
Project managementProject management
Project management
 
Project managment 3
Project managment 3Project managment 3
Project managment 3
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 
Lec 01 - Introduction.pptx
Lec 01 - Introduction.pptxLec 01 - Introduction.pptx
Lec 01 - Introduction.pptx
 

Mehr von Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

Mehr von Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 
CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8
 
CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7
 

Kürzlich hochgeladen

Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.MateoGardella
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...KokoStevan
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 

Kürzlich hochgeladen (20)

Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 

PMP Muzette Charles_Sp2019_Week2_Chapter4_5

  • 1. Project Management Professional PMP® Exam Prep – Week 2 Prof. Muzette Charles, PMP | mcharles2@pace.edu
  • 2. Integration Management Chapter 4 “Is the Project Manager’s core responsibilities” “…. is a group of processes required to ensure that the various elements of the project are properly coordinated.” Process Process Group Key Deliverables 4.1 Develop Project Charter Initiating Project Charter 4.2 Develop Project Management Plan Planning Project Management Plan 4.3 Direct and Manage Executing Project Deliverables 4.4 Manage Project Knowledge Executing Document Lessons Learned 4.5 Monitor and Control Project Work Monitoring & Controlling Change Requests 4.6 Perform Integrated Change Control Monitoring & Controlling Approved Change Requests 4.7 Close Project or Phase Closing Finalize Contracts, Payments, Transition
  • 4. Project Integration Management Chapter 4 Develop Project Charter Process 1 Key Points  A project charter formally authorizes the project  Gives the objectives and business case  Identifies & authorizes Project Manager use of organizational resources for project use  Generic enough not to change often  Written by a Manager higher in authority than Project Manager  Includes name, description, deliverables, milestone dates  Stakeholder list  Assumptions & contraints  A project does not start unless it has a Project charter
  • 5. Project Integration Management Chapter 4 Develop Project Charter Process 1 INPUTS  Statement of Work (SOW) - from external customer describing project deliverables  Business Case - from internal whether the project’s Cost-Benefit makes sense TOOLS  Expert Judgement – gaining advice from experts in other dept, outside consultants, industry groups  Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page when making a project decision
  • 6. What does the term “sunk cost” mean? A. Past investment in an initiative that must be considered in deciding to authorize a project B. Sum of all economic investments in a project C. All previous irretrievable investments in a project D. The cumulative losses from projects in this program or portfolio Discussion Question Answer: C While A is correct in identifying sunk costs as past investments, it is incorrect in saying that these costs should be a consideration for authorization. The analysis starts with a clean slate, considering future costs and benefits.
  • 7. Project Integration Management Chapter 4 Develop Project Charter Process 1
  • 8. • Clearly definedSpecific • Can be evaluated objectivelyMeasurable • Can be met under current constraints and assumptionsAttainable • Support organizational goalsRelevant • Set a deadline for attainmentTime-bound Project Integration Management Chapter 4 Develop Project Charter Process 1
  • 9. Answer: The goal could include a time frame and criteria for measurement, for example: Deliver by end of fourth quarter 2015 a new complaint-handling process that results in 25% fewer instances of escalation and a 50% increase in customer satisfaction, as of first quarter 2014. Chapter 4, Topic 1 How could this project goal statement be improved? Deliver a new complaint-handling process that meets customer service requirements and increases revenue through improved customer retention. Discussion Question
  • 10. Project Integration Management Chapter 4 Develop Project Management Plan (PMP) Process 2 Key Points  Key benefit: creates the central document that defines all of the project work  How the project will be executed, monitored & controlled  Subsidiary plans are integrated into ONE comprehensive PMP  The PMP is developed by the Project Manager with inputs from the team, stakeholders & management  Project baseline refers to the original version of the PMP  Once the PMP is baselined, it may only be changed by raising a change request  Progressive Elaboration is the process of taking a project from concept to detailed design  Kick-off meeting happens after the planning phase and before the project execution. It is typically used to communicate responsibilities of key stakeholders.
  • 11. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 12. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 13. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 14. Project Integration Management Chapter 4 Direct & Manage Project Work Process 3 Key Points  Key benefit of this process is to provide overall management of the project work  To lead & perform work as defined in the PMP  Create deliverables to meet planned project work  Manage team members & provide them with training  Obtain, manage & use resources ex. Materials, Equipment, Facilities  Establish & manage communications internal & external channels  Manage Stakeholders, Sellers, Risks, Change Requests
  • 15. Project Integration Management Chapter 4 Direct & Manage Project Work Process 3
  • 16. Project Integration Management Chapter 4 Manage Project Knowledge Process 4 Key Points  Use prior organizational knowledge to produce or improve project outcomes  Knowledge created by the project used to support operations and future projects  Use existing knowledge and create new knowledge  Contribute to organizational lessons learned
  • 17. Project Integration Management Chapter 4 Manage Project Work Process 4
  • 18. Knowledge Management Category Type of Information Means of Communication Challenges Explicit • Words • Pictures • Numbers Verbal Print Digital Lack of context Tacit • Insights • Experiences • “Know-how” Personal transfer Needs a trusting environment that fosters communication Project Integration Management Chapter 4
  • 19. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5 Key Points  Key benefit: allows stakeholders to understand current state of the project, any steps taken and budget, schedule & scope forecasts  Tracks, reviews & reports actual progress & performance against the PMP objectives  Is conducted from project inception through completion  Control includes corrective & preventative actions  Identify & analyze existing and new risks  Work Authorization System - PM’s system to ensure work is performed at the right time & in the right sequence (found in the EEF – PMIS)
  • 20. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5 Key Points  Change Requests  are submitted when issues are found while project work is being performed  is a formal (written) proposal to modify any document, baseline, deliverable  Change Log – all WRITTEN requests approved or not  PM has authority to make changes IF constraints are not effected  Types of Changes  Corrective Action – taken when actual deviations from the performance baseline  Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting  Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
  • 21. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5
  • 22. Project Integration Management Chapter 4 Perform Integrated Change Control Process 6 Key Points  Key benefit: allows documented changes to be considered in an integrated manner to the overall project while reducing risks to other areas of the project  Reviews, approves & manages all change requests to the PMP, OPA, deliverables, etc  Is conducted from project inception through completion  Is the ultimate responsibility of the Project Manager to carefully & continuously manage changes  Changes can be requested by any stakeholder involved in the project  Every “documented” change must be approved or rejected by a “responsible person”  Or by the CCB – Change Control Board
  • 23. Project Integration Management Chapter 4 Perform Integrated Change Control Process 6
  • 24. Uncontrolled Changes to Project Scope  Uncontrolled changes create risks of exceeding schedule and budget, decreasing quality, having inaccurate documentation, and damaging deliverables.  Project managers can help by: – Clearly communicating to all stakeholders what is and is not in scope. – Using the integrated change control process. Scope creep “Uncontrolled expansion to product or project scope without adjust- ments to time, cost, and resources” Gold plating Uncontrolled “improvements” made with best intentions by team Project Integration Management Chapter 4
  • 25. A government body says that they need to add a citizen body to the stakeholders on a new emergency services center project. How should the project manager respond? A. Add the stakeholder to the stakeholder register. B. Explain that the new stakeholder will increase project risks. C. Explain that this cannot be done since the project has already been scoped. D. Initiate the change control process. Discussion Question Answer: D This could become a case of scope creep unless the influence of this stakeholder is fully understood and accepted by the sponsor. It could be a very beneficial act, but its effect on scope, timeline, and budget must be understood. Chapter 4, Topic 6
  • 26. A project consultant notes that a recently released technology will increase the functionality of the deliverable. How should the project manager respond? A. Thank the consultant and do nothing, since this is beyond scope. B. Ask the sponsor for direction. C. Analyze the impact on the project. D. Submit a change request to the CCB. Discussion Question Answer: C This is a common type of question on the PMP exam. Remember that the first thing a project manager does is to try to understand the impact of a change on the project, for good and bad. Chapter 4, Topic 6
  • 27. Configuration Management  Control of changes to the deliverable and/or its components  Integrated change control for configuration includes: – Identifying configurable items – Maintaining version control – Verifying and auditing configuration Project Integration Management Chapter 4
  • 28. Change Log Comprehensive list of changes approved (and rejected) during the project  Description  Date  Impacts  Status  Owner Chapter 4, Topic 6 PROJECT CHANGE LOG Project Name: Project Sponsor: # Description: Owner: Date: Project Impact: Status: 1 2 3 Project Integration Management Chapter 4
  • 29. Project Integration Management Chapter 4 Close Project or Phase Process 7 Key Points  Provides lessons learned, formal ending of the project work & release of the organization’s resources to pursue new endeavors  Finalizes all activities across all PM Process Groups  PM measures the scope baseline against the PMP  Complete & close all contracts, procurement agreements, financials,  Archive OPA historical records, reports, etc  For projects terminated before completion, PM engages all stakeholders to investigate & document reasons why
  • 30. Closing Activities Deliverables accepted Documents archived Project assessed Team released Customer acceptance of validated product Transition into next phase or service Customer review of project Project management plan All project documents Lessons learned captured and added to knowledge base Team member performance reviews Formal release to function or other projects Project Integration Management Chapter 4
  • 31. Project Integration Management Chapter 4 Close Project or Phase Process 7
  • 32. Project Integration Management Chapter 4 Key Points  A project charter formally authorizes the project  Statement of Work (SOW) - from external customer describing project deliverables  Business Case - from internal whether the project’s Cost-Benefit makes sense  Expert Judgment – gaining advice from experts in other dept, outside consultants, industry groups  Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page when making a project decision  Subsidiary plans & Baselines are integrated into ONE comprehensive PMP
  • 33. Project Integration Management Chapter 4 Key Points  The PMP is developed by the Project Manager with inputs from the team, stakeholders & management  Project baseline refers to the original version of the PMP  Once the PMP is baselined, it may only be changed by raising a change request  Progressive Elaboration is the process of taking a project from concept to detailed design  Monitor & Control is conducted from project inception through completion  Control includes corrective & preventative Actions aka Changes  Corrective Action – taken when actual deviations from the performance baseline  Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting  Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong  Changes can be made by Crashing or Fast Tracking
  • 35. Scope Management Chapter 5 “Is the process of defining what work is required and making sure all of that work & only that work is done successfully.” • “Completion of the project scope is measured against the PMP.” • “Completion of the product scope is measured against the product requirements.” Process Process Group Key Deliverables 5.1 Plan Scope Management Planning Scope & Requirement Management Plans 5.2 Collect Requirements Planning Requirements Document 5.3 Define Scope Planning Project Scope Statement 5.4 Create WBS Planning WBS, WBS Dictionary 5.5 Validate Scope Monitoring & Controlling Acceptance Deliverables 5.6 Control Scope Monitoring & Controlling Change Requests
  • 36. Product Scope Project Scope Set of “features and functions that characterize a product, service, or result” “The work performed to deliver a product, service, or result with the specified features and functions” Measured against product requirements Measured against the project management plan Scope Management Chapter 5
  • 37. Scope Management Chapter 5 Plan Scope Management Process 1 Key Points  “Documents how the project scope is defined, validated, controlled & managed throughout the project”  Process generates 2 management plans that both become part of the PMP  “The plan helps to reduce the risk of project scope creep”
  • 38. The project charter is listed as an input to this process. What key information does it provide? A. Probable risks and their impacts and priorities B. High-level project and product description C. List of similar projects in knowledge base D. Stakeholder register Discussion Question Answer: B The high-level description in the charter is developed from an early statement of work (SOW). The SOW will be progressively elaborated during Planning and integrated change control.
  • 39. Scope Management Chapter 5 Collect Requirements Process 2 Key Points  Is the process of determining & documenting stakeholder’s needs & requirements in detail  Critical to project’s success as missed requirements could mean major changes & conflicts
  • 40. Scope Management Chapter 5 Collect Requirements Process 2 Key Points  Project manager chooses the best Tools & Techniques to gather info:  Interviews, Focus Groups, Facilitated Workshops,  Brainstorming; Nominal, Multicriteria Analysis, Affinity diagram, Mind Maps  Group Decision; Unanimity/Delphi Tech, Majority, Plurality, Dictatorship, Consensus  Questionnaires, Surveys, Observations, Prototypes, Benchmarking  Context Diagrams, Document Analysis  Requirements Documentation: Acceptance Criteria used to set Scope Baseline  Requirements Traceability Matrix: “helps to ensure each req. adds value by linking to a project objective”
  • 41. Scope Management Chapter 5 Collect Requirements Process 2
  • 42. Scope Management Chapter 5 Collect Requirements Process 2
  • 43. Scope Management Chapter 5 Define Scope Process 3 Key Points  The process of developing a detailed description of the project & product/deliverable  Defines requirement boundaries – of those collected included or excluded from project scope  Tools: Product Analysis, Alternatives Generation (different ways to do same work efficiently)
  • 44. Project Scope Statement  Project scope description  Acceptance criteria  Deliverables  Project exclusion  Constraints  Assumptions First of three pivotal scope documents Scope Management Chapter 5 Define Scope Process 3
  • 45. Scope Management Chapter 5 Create WBS Process 4 Key Points  “Is the hierarchical decomposition of the total scope of the work to be done by the project… into smaller more manageable parts/deliverables.”  Is the process of subdividing, breaking down, decomposing the project scope into manageable work packages that is a visual to the entire team.  Scope baseline: comprised of WBS, WBS dictionary & Project Scope Statement
  • 46. Scope Management Chapter 5 Create WBS Process 4 Key Points  WBS is the most important process in Scope Management & foundation of the project  must be graphical & can be organized by Phase or Category  used as a basis to estimate costs & time at the work package level  The entire project is represented in the WBS, if not, then it’s not part of the project  Control Accounts: Unique accounting codes assigned to track completion of work  Created with help of the team’s experience to be realistic  Helps gain the team’s buy-in & builds the team  Keeps up team momentum by letting ppl see their importance to complete their work  Helps prevent Scope Creep: impact of an uncontrolled change to scope, time, cost
  • 48. Work Breakdown Structure (WBS)  Project level  Control account Optional point consolidating scope, budget, and schedule to support measurement  Planning package Optional grouping of work packages  Work package Smallest practical breakdown of work for estimation and management Scope Management Chapter 5
  • 49. Work Breakdown Structure (WBS)  Project level  Control account Optional point consolidating scope, budget, and schedule to support measurement  Planning package Optional grouping of work packages  Work package Smallest practical breakdown of work for estimation and management Scope Management Chapter 5
  • 50. WBS Dictionary Detailed information about each work package in the WBS:  Code of account identifier  Description of work  Assumptions and constraints  Responsible organization  Acceptance criteria  Technical references Added through progressive elaboration: Schedule milestones and activities Required resources Cost estimates Quality requirements Agreement information (contracts) Scope Management Chapter 5
  • 51. PLAN PROJECT MANAGEMENT PLAN PROJECT SCOPE STATEMENT WBS WBS DICTIONARY SCOPE BASELINE Once approved, these documents can be changed only through the integrated change control process. WBS DICTIONARY Scope Management Chapter 5 Scope Baseline Create WBS Process 4
  • 52. Scope Management Chapter 5 Validate Scope Process 5 Key Points  “Is the process of formalizing acceptance of completed project deliverables.”  Involves frequent formal meetings with sponsor /customer to gain formal acceptance of deliverables  Recommended to validate scope at the end of each phase and/or multiple times in a project  Validate Scope process: the customer checks & approves deliverables  Control Quality process: the QC dept checks deliverables to see that requirements are met.
  • 53. A deliverable has passed internal quality control, but the customer refuses to accept it because the quality is not at the expected level. What will happen next? A. The contract will be referred to the legal department. B. Control Quality will be repeated. C. Manage Quality will be repeated. D. The project manager will facilitate further discussions with the customer. Discussion Question Answer: D If the deliverable fulfills the scope baseline but does not meet customer expectations, the project manager will facilitate group discussions and decision making about the next step, which could involve change to both the product and the agreement.
  • 54. Scope Management Chapter 5 Control Scope Process 6 Key Points  “Is the process of monitoring the project status (scope performance aka work completed) by managing changes between the work performance data against the scope baseline.”  Is a proactive process lead by the Project Manager to prevent project changes  Incontrolled adjustments to project constraints lead to Scope Creep
  • 56. PMP Exam Prep Group Exercise – PMP Subsidiary Plans

Hinweis der Redaktion

  1. Formally starts a New project or Phase, PM named early so he/she assists in Proj. Charter / High-level planning estimating to see if the proj can be dlvrd by the time & wi/budget that’s requested… basically does the project have a chance to be successful b4 $ & resources are committed?