SlideShare ist ein Scribd-Unternehmen logo
1 von 24
Certified Associate Project Management
CAPM® Exam Prep – Week 3
Prof. Muzette Charles, PMP | mcharles2@pace.edu
Scope Management
Chapter 5
“Is the process of defining what work is required and making sure all of that work &
only that work is done successfully.”
• “Completion of the project scope is measured against the PMP.”
• “Completion of the product scope is measured against the product requirements.”
Process Process Group Key Deliverables
5.1 Plan Scope Management Planning Scope & Requirement
Management Plans
5.2 Collect Requirements Planning Requirements Document
5.3 Define Scope Planning Project Scope Statement
5.4 Create WBS Planning WBS, WBS Dictionary
5.5 Validate Scope Monitoring & Controlling Acceptance Deliverables
5.6 Control Scope Monitoring & Controlling Change Requests
Scope Management
Chapter 5
Plan Scope Management
Process 1
Key Points
 “Documents how the project scope is defined, validated, controlled & managed throughout the project”
 Process generates 2 management plans that both become part of the PMP
 “The plan helps to reduce the risk of project scope creep”
Scope Management
Chapter 5
Collect Requirements
Process 2
Key Points
 Is the process of determining & documenting stakeholder’s needs & requirements in detail
 Critical to project’s success as missed requirements could mean major changes & conflicts
Scope Management
Chapter 5
Collect Requirements
Process 2
Key Points
 Project manager chooses the best Tools & Techniques to gather info:
 Interviews, Focus Groups, Facilitated Workshops,
 Brainstorming; Nominal, Multicriteria Analysis, Affinity diagram, Mind Maps
 Group Decision; Unanimity/Delphi Tech, Majority, Plurality, Dictatorship, Consensus
 Questionnaires, Surveys, Observations, Prototypes, Benchmarking
 Context Diagrams, Document Analysis
 Requirements Documentation: Acceptance Criteria used to set Scope Baseline
 Requirements Traceability Matrix: “helps to ensure each req. adds value by linking to a
project objective”
Scope Management
Chapter 5
Define Scope
Process 3
Key Points
 The process of developing a detailed description of the project & product/deliverable
 Defines requirement boundaries – of those collected included or excluded from project scope
 Tools: Product Analysis, Alternatives Generation (different ways to do same work efficiently)
Scope Management
Chapter 5
Create WBS
Process 4
Key Points
 “Is the hierarchical decomposition of the total scope of the work to be done by the project…
into smaller more manageable parts/deliverables.”
 Is the process of subdividing, breaking down, decomposing the project scope into
manageable work packages that is a visual to the entire team.
 Scope baseline: comprised of WBS, WBS dictionary & Project Scope Statement
Scope Management
Chapter 5
Create WBS
Process 4
Key Points
 WBS is the most important process in Scope Management & foundation of the project
 must be graphical & can be organized by Phase or Category
 used as a basis to estimate costs & time at the work package level
 The entire project is represented in the WBS, if not, then it’s not part of the project
 Control Accounts: Unique accounting codes assigned to track completion of work
 Created with help of the team’s experience to be realistic
 Helps gain the team’s buy-in & builds the team
 Keeps up team momentum by letting ppl see their importance to complete their work
 Helps prevent Scope Creep: impact of an uncontrolled change to scope, time, cost
Scope Management
Chapter 5
Validate Scope
Process 5
Key Points
 “Is the process of formalizing acceptance of completed project deliverables.”
 Involves frequent formal meetings with sponsor /customer to gain formal acceptance of deliverables
 Recommended to validate scope at the end of each phase and/or multiple times in a project
 Validate Scope process: the customer checks & approves deliverables
 Control Quality process: the QC dept checks deliverables to see that requirements are met.
Scope Management
Chapter 5
Control Scope
Process 6
Key Points
 “Is the process of monitoring the project status (scope performance aka work completed) by managing
changes between the work performance data against the scope baseline.”
 Is a proactive process lead by the Project Manager to prevent project changes
 Incontrolled adjustments to project constraints lead to Scope Creep
Scope Management
Chapter 5
Schedule Management
Chapter 6
“… includes the processes required to manage the timely completion of the project.”
Process Process Group Key Deliverables
6.1 Plan Schedule Management Planning Schedule Management Plan
6.2 Define Activities Planning Activities List
6.3 Sequence Activities Planning Schedule Network Diagrams
6.4 Estimate Activity Durations Planning Activity Resource Requirements
6.5 Develop Schedule Planning Schedule Baseline
6.6 Control Schedule Monitoring & Controlling Change Requests
Schedule Management
Chapter 6
Plan Schedule Management
Process 1
Key Points
 “The process of policies, procedures & documentation for planning, developing, managing, executing & controlling
the project schedule.. throughout the project.”
 Defines units of measurements: Hrs/Days/Wks and Levels of Accuracy: +/- 10%
 Reporting formats: Status meetings ex. Weekly on Thursdays
Schedule Management
Chapter 6
Define Activities
Process 2
Key Points
 “The process of identifying & documenting the specific actions to be performed to produce the project deliverables.”
 Work packages are broken down (decomposed) into activities at a level small enough to estimate, schedule, execute,
monitor & control
 Rolling Wave Planning: used in large (Progressively Elaborated) projects, plan as you go, as milestones get closer
 Activity List: list of every activity required to complete project
 Activity Attributes: description of every activity with its’ Predecessor, Successor & Constraints
Schedule Management
Chapter 6
Sequence Activities
Process 3
Key Points
 “… is the process of identifying & documenting relationships among project activities.”
 Network diagramming how the logical sequence of activities & milestones will be performed to obtain the greatest
efficiency given all constraints
 Justifies time estimates, shows the workflow & interdependencies, identifies areas to compress schedule
Schedule Management
Chapter 6
Sequence Activities
Process 3 Key Points
 Precedence Diagramming (PDM) / Activity on Node (AON): Must common to show activities & their dependencies
 Types of Dependencies: Mandatory, Discretionary, External & Internal
 Identify: Predecessor & Successor activities, # of paths
 Finish-to-Start (FS): most commonly used relationship / SF dependency is rarely used
 Lead Time: gives the successor activity time to start before the predecessor finishes
 Lag Time: purposefully delays time between predecessor & successor activities
Schedule Management
Chapter 6
Schedule Management
Chapter 6
Estimate Activity Durations
Process 4
Key Points
 “Estimating the # of work periods needed to complete individual activities with estimated resources.”
 Provides the amount of time each activity will take to complete… is a major input to Develop Schedule process
 Resource Calendar: shows the availability, capabilities, skills of HR & quantity & availability of equipment
 Estimating Tools: Analogous (ave. similar projects), Parametric (historical), Three Point
Schedule Management
Chapter 6
Estimate Activity Durations
Process 4
Key Points
 Duration Estimating Tools:
 Analogous: (ave. of past similar projects)
 Three Point: Simple Average (P+O+M)/3 , Weighted Average (P+4M+O)/6
 Standard Deviation: (P – O)/6
 Group Decision: Most used as involving Team Members gets their Buy-In
 Reserve Analysis:
 Management Reserves – funds set aside for Unknown scheduling risks
 Contingency Reserves – funds set aside for Known project risks
Schedule Management
Chapter 6
Develop Schedule
Process 5
Key Points
 “… activity sequences, durations, resource requirements & schedule constraints are analyzed to generate a schedule
of planned start, finish & milestone dates.”
 Project Schedule is approved, realistic, iterative & serves as the baseline to track progress
 Team members confirm their assigned activities do not conflict with resource calendars or other projects
Schedule Management
Chapter 6
Develop Schedule
Process 5
Key Points
Tools - Critical Path Method:
 Is a string of activities that make up the longest path of durations for the project to be completed
 every single activity on the CP must finish on time for the project to finish on time
 A delay on the CP will delay the entire project
 Float/Slack – amount of time an activity can SLIP before it delays the project – Equals Zero on CP
 Total Float, Free Float, Project Float
 ES & EF – how much freedom PM can move Activity Start Dates wo/ causing problems
 LS & LF – How much “play” PM has in the schedule
 Schedule Compression – when a timeframe is unrealistic, compress the schedule wo/ changing the scope
 Fast Tracking or Crashing
 Resource Optimization – adjusting use of resources: Resource Leveling, Smoothing
 Critical Chain Method – assigning each activity to occur as late as possible
Schedule Management
Chapter 6
Control Schedule
Process 6
Key Points
 “Monitor status of project activities to update progress & manage changes to the schedule baseline.”
 PM stays in Control of the project by continuingly measuring the Schedule against the Plan
 Reviewing Work Performance Data & Schedule Performance
 Change Requests: are submitted to take corrective & preventative actions to minimize risks
Schedule Management
Chapter 6
CAPM Exam Prep
Group Exercise – PMP Subsidiary Plans

Weitere ähnliche Inhalte

Was ist angesagt?

Project management
Project managementProject management
Project managementtwilight89
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMMudassir Iqbal
 
2018 Project Management Workshop Schedule - Project Management Training - Dco...
2018 Project Management Workshop Schedule - Project Management Training - Dco...2018 Project Management Workshop Schedule - Project Management Training - Dco...
2018 Project Management Workshop Schedule - Project Management Training - Dco...Dcolearning
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 
Project Time Management
Project Time Management Project Time Management
Project Time Management Waqar Ali
 
Project time management
Project time managementProject time management
Project time managementImran Jamil
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Managingtripleconstraint aam
Managingtripleconstraint aamManagingtripleconstraint aam
Managingtripleconstraint aamAldo Arecco
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Managementgrmkslideshare
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope ManagementTalha Siddiqui
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
6. Schedule Management
6. Schedule Management6. Schedule Management
6. Schedule ManagementSanjay Rajpoot
 
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Indra Pandu Prasetyo
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
Project Time Management
Project Time ManagementProject Time Management
Project Time ManagementSerdar Temiz
 
[Guide] How to create a realistic project schedule
[Guide] How to create a realistic project schedule[Guide] How to create a realistic project schedule
[Guide] How to create a realistic project scheduleDmitriy Nizhebetskiy
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 

Was ist angesagt? (19)

Project management
Project managementProject management
Project management
 
Project schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPMProject schedule Management - PMP/CAPM
Project schedule Management - PMP/CAPM
 
Project time management
Project time managementProject time management
Project time management
 
2018 Project Management Workshop Schedule - Project Management Training - Dco...
2018 Project Management Workshop Schedule - Project Management Training - Dco...2018 Project Management Workshop Schedule - Project Management Training - Dco...
2018 Project Management Workshop Schedule - Project Management Training - Dco...
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
 
Project time management
Project time managementProject time management
Project time management
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Managingtripleconstraint aam
Managingtripleconstraint aamManagingtripleconstraint aam
Managingtripleconstraint aam
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Management
 
Project Tracking and Scope Management
Project Tracking and Scope ManagementProject Tracking and Scope Management
Project Tracking and Scope Management
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
6. Schedule Management
6. Schedule Management6. Schedule Management
6. Schedule Management
 
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
 
06 project time management
06  project time management06  project time management
06 project time management
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
[Guide] How to create a realistic project schedule
[Guide] How to create a realistic project schedule[Guide] How to create a realistic project schedule
[Guide] How to create a realistic project schedule
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 

Ähnlich wie CAPM M Charles Week3 Chapter5-6

A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability frameworkRobert Greca, PMP, SA
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4Qussay Karam
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaGlobalSkillup
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelyChetan Khanzode
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
Project Management @ Ektoo
Project Management @ EktooProject Management @ Ektoo
Project Management @ Ektooshofiulalom
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptxGagan331641
 

Ähnlich wie CAPM M Charles Week3 Chapter5-6 (20)

CAPM Week 2 Chapter 5
CAPM Week 2 Chapter 5CAPM Week 2 Chapter 5
CAPM Week 2 Chapter 5
 
A project portfolio management capability framework
A project portfolio management capability frameworkA project portfolio management capability framework
A project portfolio management capability framework
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
Project Management @ Ektoo
Project Management @ EktooProject Management @ Ektoo
Project Management @ Ektoo
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
6396901
63969016396901
6396901
 
CAPM week 1 chapter 3
CAPM week 1 chapter 3CAPM week 1 chapter 3
CAPM week 1 chapter 3
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 

Mehr von Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

Mehr von Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 
CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8
 

Kürzlich hochgeladen

Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...KokoStevan
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterMateoGardella
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 

Kürzlich hochgeladen (20)

Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch Letter
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 

CAPM M Charles Week3 Chapter5-6

  • 1. Certified Associate Project Management CAPM® Exam Prep – Week 3 Prof. Muzette Charles, PMP | mcharles2@pace.edu
  • 2. Scope Management Chapter 5 “Is the process of defining what work is required and making sure all of that work & only that work is done successfully.” • “Completion of the project scope is measured against the PMP.” • “Completion of the product scope is measured against the product requirements.” Process Process Group Key Deliverables 5.1 Plan Scope Management Planning Scope & Requirement Management Plans 5.2 Collect Requirements Planning Requirements Document 5.3 Define Scope Planning Project Scope Statement 5.4 Create WBS Planning WBS, WBS Dictionary 5.5 Validate Scope Monitoring & Controlling Acceptance Deliverables 5.6 Control Scope Monitoring & Controlling Change Requests
  • 3. Scope Management Chapter 5 Plan Scope Management Process 1 Key Points  “Documents how the project scope is defined, validated, controlled & managed throughout the project”  Process generates 2 management plans that both become part of the PMP  “The plan helps to reduce the risk of project scope creep”
  • 4. Scope Management Chapter 5 Collect Requirements Process 2 Key Points  Is the process of determining & documenting stakeholder’s needs & requirements in detail  Critical to project’s success as missed requirements could mean major changes & conflicts
  • 5. Scope Management Chapter 5 Collect Requirements Process 2 Key Points  Project manager chooses the best Tools & Techniques to gather info:  Interviews, Focus Groups, Facilitated Workshops,  Brainstorming; Nominal, Multicriteria Analysis, Affinity diagram, Mind Maps  Group Decision; Unanimity/Delphi Tech, Majority, Plurality, Dictatorship, Consensus  Questionnaires, Surveys, Observations, Prototypes, Benchmarking  Context Diagrams, Document Analysis  Requirements Documentation: Acceptance Criteria used to set Scope Baseline  Requirements Traceability Matrix: “helps to ensure each req. adds value by linking to a project objective”
  • 6. Scope Management Chapter 5 Define Scope Process 3 Key Points  The process of developing a detailed description of the project & product/deliverable  Defines requirement boundaries – of those collected included or excluded from project scope  Tools: Product Analysis, Alternatives Generation (different ways to do same work efficiently)
  • 7. Scope Management Chapter 5 Create WBS Process 4 Key Points  “Is the hierarchical decomposition of the total scope of the work to be done by the project… into smaller more manageable parts/deliverables.”  Is the process of subdividing, breaking down, decomposing the project scope into manageable work packages that is a visual to the entire team.  Scope baseline: comprised of WBS, WBS dictionary & Project Scope Statement
  • 8. Scope Management Chapter 5 Create WBS Process 4 Key Points  WBS is the most important process in Scope Management & foundation of the project  must be graphical & can be organized by Phase or Category  used as a basis to estimate costs & time at the work package level  The entire project is represented in the WBS, if not, then it’s not part of the project  Control Accounts: Unique accounting codes assigned to track completion of work  Created with help of the team’s experience to be realistic  Helps gain the team’s buy-in & builds the team  Keeps up team momentum by letting ppl see their importance to complete their work  Helps prevent Scope Creep: impact of an uncontrolled change to scope, time, cost
  • 9. Scope Management Chapter 5 Validate Scope Process 5 Key Points  “Is the process of formalizing acceptance of completed project deliverables.”  Involves frequent formal meetings with sponsor /customer to gain formal acceptance of deliverables  Recommended to validate scope at the end of each phase and/or multiple times in a project  Validate Scope process: the customer checks & approves deliverables  Control Quality process: the QC dept checks deliverables to see that requirements are met.
  • 10. Scope Management Chapter 5 Control Scope Process 6 Key Points  “Is the process of monitoring the project status (scope performance aka work completed) by managing changes between the work performance data against the scope baseline.”  Is a proactive process lead by the Project Manager to prevent project changes  Incontrolled adjustments to project constraints lead to Scope Creep
  • 12. Schedule Management Chapter 6 “… includes the processes required to manage the timely completion of the project.” Process Process Group Key Deliverables 6.1 Plan Schedule Management Planning Schedule Management Plan 6.2 Define Activities Planning Activities List 6.3 Sequence Activities Planning Schedule Network Diagrams 6.4 Estimate Activity Durations Planning Activity Resource Requirements 6.5 Develop Schedule Planning Schedule Baseline 6.6 Control Schedule Monitoring & Controlling Change Requests
  • 13. Schedule Management Chapter 6 Plan Schedule Management Process 1 Key Points  “The process of policies, procedures & documentation for planning, developing, managing, executing & controlling the project schedule.. throughout the project.”  Defines units of measurements: Hrs/Days/Wks and Levels of Accuracy: +/- 10%  Reporting formats: Status meetings ex. Weekly on Thursdays
  • 14. Schedule Management Chapter 6 Define Activities Process 2 Key Points  “The process of identifying & documenting the specific actions to be performed to produce the project deliverables.”  Work packages are broken down (decomposed) into activities at a level small enough to estimate, schedule, execute, monitor & control  Rolling Wave Planning: used in large (Progressively Elaborated) projects, plan as you go, as milestones get closer  Activity List: list of every activity required to complete project  Activity Attributes: description of every activity with its’ Predecessor, Successor & Constraints
  • 15. Schedule Management Chapter 6 Sequence Activities Process 3 Key Points  “… is the process of identifying & documenting relationships among project activities.”  Network diagramming how the logical sequence of activities & milestones will be performed to obtain the greatest efficiency given all constraints  Justifies time estimates, shows the workflow & interdependencies, identifies areas to compress schedule
  • 16. Schedule Management Chapter 6 Sequence Activities Process 3 Key Points  Precedence Diagramming (PDM) / Activity on Node (AON): Must common to show activities & their dependencies  Types of Dependencies: Mandatory, Discretionary, External & Internal  Identify: Predecessor & Successor activities, # of paths  Finish-to-Start (FS): most commonly used relationship / SF dependency is rarely used  Lead Time: gives the successor activity time to start before the predecessor finishes  Lag Time: purposefully delays time between predecessor & successor activities
  • 18. Schedule Management Chapter 6 Estimate Activity Durations Process 4 Key Points  “Estimating the # of work periods needed to complete individual activities with estimated resources.”  Provides the amount of time each activity will take to complete… is a major input to Develop Schedule process  Resource Calendar: shows the availability, capabilities, skills of HR & quantity & availability of equipment  Estimating Tools: Analogous (ave. similar projects), Parametric (historical), Three Point
  • 19. Schedule Management Chapter 6 Estimate Activity Durations Process 4 Key Points  Duration Estimating Tools:  Analogous: (ave. of past similar projects)  Three Point: Simple Average (P+O+M)/3 , Weighted Average (P+4M+O)/6  Standard Deviation: (P – O)/6  Group Decision: Most used as involving Team Members gets their Buy-In  Reserve Analysis:  Management Reserves – funds set aside for Unknown scheduling risks  Contingency Reserves – funds set aside for Known project risks
  • 20. Schedule Management Chapter 6 Develop Schedule Process 5 Key Points  “… activity sequences, durations, resource requirements & schedule constraints are analyzed to generate a schedule of planned start, finish & milestone dates.”  Project Schedule is approved, realistic, iterative & serves as the baseline to track progress  Team members confirm their assigned activities do not conflict with resource calendars or other projects
  • 21. Schedule Management Chapter 6 Develop Schedule Process 5 Key Points Tools - Critical Path Method:  Is a string of activities that make up the longest path of durations for the project to be completed  every single activity on the CP must finish on time for the project to finish on time  A delay on the CP will delay the entire project  Float/Slack – amount of time an activity can SLIP before it delays the project – Equals Zero on CP  Total Float, Free Float, Project Float  ES & EF – how much freedom PM can move Activity Start Dates wo/ causing problems  LS & LF – How much “play” PM has in the schedule  Schedule Compression – when a timeframe is unrealistic, compress the schedule wo/ changing the scope  Fast Tracking or Crashing  Resource Optimization – adjusting use of resources: Resource Leveling, Smoothing  Critical Chain Method – assigning each activity to occur as late as possible
  • 22. Schedule Management Chapter 6 Control Schedule Process 6 Key Points  “Monitor status of project activities to update progress & manage changes to the schedule baseline.”  PM stays in Control of the project by continuingly measuring the Schedule against the Plan  Reviewing Work Performance Data & Schedule Performance  Change Requests: are submitted to take corrective & preventative actions to minimize risks
  • 24. CAPM Exam Prep Group Exercise – PMP Subsidiary Plans