PRSENTATION OUTLINE
• CORE FACTS OF PPA
• FACTS OF PPA
• THE RISK INVOLVED IN SUCH ARRANGEMENTS
• THE CASE OF GHANA
MEANING OF PPA
• A Power Purchase Agreement (PPA) secures
the payment stream for a Build-Own Transfer
(BOT) or concession project for an
independent power plant (IPP). It is between
the purchaser "offtaker" (often a state-owned
electricity utility company) and a privately
owned power producer. The PPA outlined
here is not appropriate for electricity sold on
the world spot markets
Facts of PPA
• State agency enters into agreement for private
power company to establish plant to sell to
government agency
• It usually takes the form of Built Own
Transfer(BOT) , design, output and maintenance
specifications are given in the agreement
• A charge is determined usually realistic to cover
project cost in time including equity on return
• A third party sale usually enhance project
financing and cushion the offtaker(buyer)
• Breach of contracts ( contractors are usually
not required to damages resulting in delays)
• Termination period should be provided in
contracts
• Operation schedules should be included(
outages, maintenance, emergencies and
accounts/ records.
Risk areas in PPA
• Reduction in monthly tariff
• Breach of contractual agreements( producers not
oblige to pay any money or form of compensation)
• Difficulty in securing long term investment by
governments
• Some areas are technically and commercially
challenging to connect to grid
• Low tariff reduces motivation to invest
• Affordability issues are of great concern to investors
and governments
• Unreliable gas supply
When PPA IS NECESSARY
• When revenue for a project is uncertain given
market conditions
• When there is possibility of a cheaper options
from potential competitors
• When there is one major customer or fewer
bulk buyer(S)
• If purchaser wishes to secure security of
supply
FORMS OF PPAS
• Emergency power and mobile plants( Ghana
has a number of agreements under this)
• Small and rural projects( Kenya has
agreement under this type for contractor to
supply larger renewable generators with
capacity of more than 10MW, Tanzania had a
PPA involving a standardize mini grid
connection
• Medium size and large projects example of
this is PPA and implementation agreement
produced for Pakistan’s private power and
infrastructure board
The case of Ghana
• IPPs contribute about 776 megawatts to
electricity provision in Ghana
• IPPS IN GHANA
• Asogli power project(200mw)
• Tema power plant( 126mw)

Weitere ähnliche Inhalte

Was ist angesagt?

Electricity Markets Regulation - Lesson 2 - Market Design
Electricity Markets Regulation - Lesson 2 - Market DesignElectricity Markets Regulation - Lesson 2 - Market Design
Electricity Markets Regulation - Lesson 2 - Market DesignLeonardo ENERGY
 
Power generation cost analysis.power generation_cost_analysis
Power generation cost analysis.power generation_cost_analysisPower generation cost analysis.power generation_cost_analysis
Power generation cost analysis.power generation_cost_analysisRCREEE
 
DEMAND SIDE ENERGY MANAGEMENT
DEMAND SIDE ENERGY MANAGEMENTDEMAND SIDE ENERGY MANAGEMENT
DEMAND SIDE ENERGY MANAGEMENTNAVYASRI SIGIRI
 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatchvikram anand
 
Ancillary Services
Ancillary ServicesAncillary Services
Ancillary ServicesIPPAI
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
Electricity Markets and Principle Market Design Models
Electricity Markets and Principle Market Design ModelsElectricity Markets and Principle Market Design Models
Electricity Markets and Principle Market Design ModelsLeonardo ENERGY
 
Energy Efficiency financing & evaluation criteria
Energy Efficiency  financing & evaluation criteriaEnergy Efficiency  financing & evaluation criteria
Energy Efficiency financing & evaluation criteriaZAINI ABDUL WAHAB
 
Hydro electric power plant ppt
Hydro electric power plant pptHydro electric power plant ppt
Hydro electric power plant pptMohammad Nafey
 
Solar Energy Presentation - OPEX / RESCO / BOOT with 100% Funding
Solar Energy Presentation -  OPEX / RESCO / BOOT with 100% FundingSolar Energy Presentation -  OPEX / RESCO / BOOT with 100% Funding
Solar Energy Presentation - OPEX / RESCO / BOOT with 100% FundingEnerco Energy Solutions LLP
 
Wind Turbine Generators
Wind Turbine GeneratorsWind Turbine Generators
Wind Turbine GeneratorsJasjot Singh
 

Was ist angesagt? (20)

Electricity Markets Regulation - Lesson 2 - Market Design
Electricity Markets Regulation - Lesson 2 - Market DesignElectricity Markets Regulation - Lesson 2 - Market Design
Electricity Markets Regulation - Lesson 2 - Market Design
 
Power generation cost analysis.power generation_cost_analysis
Power generation cost analysis.power generation_cost_analysisPower generation cost analysis.power generation_cost_analysis
Power generation cost analysis.power generation_cost_analysis
 
Tariff electricity
Tariff electricityTariff electricity
Tariff electricity
 
Power Markets & Trading in India
Power Markets & Trading in IndiaPower Markets & Trading in India
Power Markets & Trading in India
 
Deviation settelment mechanism
Deviation settelment mechanismDeviation settelment mechanism
Deviation settelment mechanism
 
DEMAND SIDE ENERGY MANAGEMENT
DEMAND SIDE ENERGY MANAGEMENTDEMAND SIDE ENERGY MANAGEMENT
DEMAND SIDE ENERGY MANAGEMENT
 
Economic load dispatch
Economic load dispatchEconomic load dispatch
Economic load dispatch
 
Power trading
Power tradingPower trading
Power trading
 
Power Market regulation
Power Market regulationPower Market regulation
Power Market regulation
 
Ancillary Services
Ancillary ServicesAncillary Services
Ancillary Services
 
Energy management
Energy managementEnergy management
Energy management
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
Electricity Markets and Principle Market Design Models
Electricity Markets and Principle Market Design ModelsElectricity Markets and Principle Market Design Models
Electricity Markets and Principle Market Design Models
 
Energy Efficiency financing & evaluation criteria
Energy Efficiency  financing & evaluation criteriaEnergy Efficiency  financing & evaluation criteria
Energy Efficiency financing & evaluation criteria
 
Hydro electric power plant ppt
Hydro electric power plant pptHydro electric power plant ppt
Hydro electric power plant ppt
 
Renewable Energy Innovation
Renewable Energy InnovationRenewable Energy Innovation
Renewable Energy Innovation
 
Solar Power Plant Procurements
Solar Power Plant ProcurementsSolar Power Plant Procurements
Solar Power Plant Procurements
 
Power plant economics
Power plant economicsPower plant economics
Power plant economics
 
Solar Energy Presentation - OPEX / RESCO / BOOT with 100% Funding
Solar Energy Presentation -  OPEX / RESCO / BOOT with 100% FundingSolar Energy Presentation -  OPEX / RESCO / BOOT with 100% Funding
Solar Energy Presentation - OPEX / RESCO / BOOT with 100% Funding
 
Wind Turbine Generators
Wind Turbine GeneratorsWind Turbine Generators
Wind Turbine Generators
 

Andere mochten auch

Zambia draft Renewable Energy Feed-in Tarriff Power Purchase Agreement
Zambia draft Renewable Energy Feed-in Tarriff Power Purchase AgreementZambia draft Renewable Energy Feed-in Tarriff Power Purchase Agreement
Zambia draft Renewable Energy Feed-in Tarriff Power Purchase AgreementJerry Sakala
 
Partnership between government and mining companies in promoting
Partnership between government and mining companies in promotingPartnership between government and mining companies in promoting
Partnership between government and mining companies in promotingGrain Malunga
 
THE NATURE OF MINING CONTRACTS
THE NATURE OF MINING CONTRACTSTHE NATURE OF MINING CONTRACTS
THE NATURE OF MINING CONTRACTSGrain Malunga
 
Cc Power Purchase Agreement 04212009
Cc Power Purchase Agreement 04212009Cc Power Purchase Agreement 04212009
Cc Power Purchase Agreement 04212009Nicole Cocco
 
Land use agreement 2011 session 2
Land use agreement 2011 session 2Land use agreement 2011 session 2
Land use agreement 2011 session 2RCREEE
 
05 16 PRODUCTION SHARING AGREEMENT
05 16 PRODUCTION SHARING AGREEMENT05 16 PRODUCTION SHARING AGREEMENT
05 16 PRODUCTION SHARING AGREEMENTGrain Malunga
 
Power Purchase Agreements Presentation To Power Gen Electrotex Conference 2...
Power Purchase Agreements   Presentation To Power Gen Electrotex Conference 2...Power Purchase Agreements   Presentation To Power Gen Electrotex Conference 2...
Power Purchase Agreements Presentation To Power Gen Electrotex Conference 2...Deoye
 
Làm Sao Điều Trị Bốc Hỏa an Toàn
Làm Sao Điều Trị Bốc Hỏa an ToànLàm Sao Điều Trị Bốc Hỏa an Toàn
Làm Sao Điều Trị Bốc Hỏa an Toànada662
 
Acta Cryst nitros 2015
Acta Cryst nitros 2015Acta Cryst nitros 2015
Acta Cryst nitros 2015依雯 谢
 
10 Razones Principales
10 Razones Principales10 Razones Principales
10 Razones PrincipalesBeway
 
Business Management Simplified
Business Management SimplifiedBusiness Management Simplified
Business Management SimplifiedBeway
 
Feed-in tariff 25 year business model
Feed-in tariff 25 year business modelFeed-in tariff 25 year business model
Feed-in tariff 25 year business modelechelon sustain
 
Senior Administrator CV
Senior Administrator CVSenior Administrator CV
Senior Administrator CVSinéad Howard
 
Ai adva208 w6_a1_joseph_j
Ai adva208 w6_a1_joseph_jAi adva208 w6_a1_joseph_j
Ai adva208 w6_a1_joseph_jJeffery Joseph
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationJerry Sakala
 
Roioflearninglyndacom 150422124107-conversion-gate02
Roioflearninglyndacom 150422124107-conversion-gate02Roioflearninglyndacom 150422124107-conversion-gate02
Roioflearninglyndacom 150422124107-conversion-gate02nizar vikti
 

Andere mochten auch (18)

Zambia draft Renewable Energy Feed-in Tarriff Power Purchase Agreement
Zambia draft Renewable Energy Feed-in Tarriff Power Purchase AgreementZambia draft Renewable Energy Feed-in Tarriff Power Purchase Agreement
Zambia draft Renewable Energy Feed-in Tarriff Power Purchase Agreement
 
Partnership between government and mining companies in promoting
Partnership between government and mining companies in promotingPartnership between government and mining companies in promoting
Partnership between government and mining companies in promoting
 
THE NATURE OF MINING CONTRACTS
THE NATURE OF MINING CONTRACTSTHE NATURE OF MINING CONTRACTS
THE NATURE OF MINING CONTRACTS
 
Cc Power Purchase Agreement 04212009
Cc Power Purchase Agreement 04212009Cc Power Purchase Agreement 04212009
Cc Power Purchase Agreement 04212009
 
Land use agreement 2011 session 2
Land use agreement 2011 session 2Land use agreement 2011 session 2
Land use agreement 2011 session 2
 
05 16 PRODUCTION SHARING AGREEMENT
05 16 PRODUCTION SHARING AGREEMENT05 16 PRODUCTION SHARING AGREEMENT
05 16 PRODUCTION SHARING AGREEMENT
 
Power Purchase Agreements Presentation To Power Gen Electrotex Conference 2...
Power Purchase Agreements   Presentation To Power Gen Electrotex Conference 2...Power Purchase Agreements   Presentation To Power Gen Electrotex Conference 2...
Power Purchase Agreements Presentation To Power Gen Electrotex Conference 2...
 
BreckoffResume
BreckoffResumeBreckoffResume
BreckoffResume
 
Làm Sao Điều Trị Bốc Hỏa an Toàn
Làm Sao Điều Trị Bốc Hỏa an ToànLàm Sao Điều Trị Bốc Hỏa an Toàn
Làm Sao Điều Trị Bốc Hỏa an Toàn
 
Acta Cryst nitros 2015
Acta Cryst nitros 2015Acta Cryst nitros 2015
Acta Cryst nitros 2015
 
10 Razones Principales
10 Razones Principales10 Razones Principales
10 Razones Principales
 
Article for ARCS1
Article for ARCS1Article for ARCS1
Article for ARCS1
 
Business Management Simplified
Business Management SimplifiedBusiness Management Simplified
Business Management Simplified
 
Feed-in tariff 25 year business model
Feed-in tariff 25 year business modelFeed-in tariff 25 year business model
Feed-in tariff 25 year business model
 
Senior Administrator CV
Senior Administrator CVSenior Administrator CV
Senior Administrator CV
 
Ai adva208 w6_a1_joseph_j
Ai adva208 w6_a1_joseph_jAi adva208 w6_a1_joseph_j
Ai adva208 w6_a1_joseph_j
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentation
 
Roioflearninglyndacom 150422124107-conversion-gate02
Roioflearninglyndacom 150422124107-conversion-gate02Roioflearninglyndacom 150422124107-conversion-gate02
Roioflearninglyndacom 150422124107-conversion-gate02
 

Ähnlich wie POWER PURCHASE AGREEMENTS(PPA)

Contracts for difference
Contracts for differenceContracts for difference
Contracts for differenceGeoff White
 
Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort Priyank Jain
 
Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)Dr. Oliver Massmann
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyTNenergy
 
Project-model-Funding-schemes.pdf
Project-model-Funding-schemes.pdfProject-model-Funding-schemes.pdf
Project-model-Funding-schemes.pdfssuser09aa021
 
Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain PRIYANK JAIN
 
OREC Webinar: From Silicon Valley to Wall Street to Foggy Bottom:
OREC Webinar: From Silicon Valley to Wall Street to Foggy Bottom:OREC Webinar: From Silicon Valley to Wall Street to Foggy Bottom:
OREC Webinar: From Silicon Valley to Wall Street to Foggy Bottom:Carolyn Elefant
 
Introduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptxIntroduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptxmsounak95
 
D0 1 ricardo_infrastructure & service delivery
D0 1 ricardo_infrastructure & service deliveryD0 1 ricardo_infrastructure & service delivery
D0 1 ricardo_infrastructure & service deliveryRicardo Energy & Environment
 
Solving Nigeria's Power Problems
Solving Nigeria's Power ProblemsSolving Nigeria's Power Problems
Solving Nigeria's Power ProblemsOlumuyiwa Abiodun
 
Rsm GC Advisory RE Power Contracting & Trading - ver3
Rsm GC Advisory RE Power Contracting & Trading - ver3Rsm GC Advisory RE Power Contracting & Trading - ver3
Rsm GC Advisory RE Power Contracting & Trading - ver3RSM GC
 
coned-presentation-in-pdf-final.pdf
coned-presentation-in-pdf-final.pdfconed-presentation-in-pdf-final.pdf
coned-presentation-in-pdf-final.pdfJose Morales
 
Natural group corporate profile 2013
Natural group corporate profile 2013Natural group corporate profile 2013
Natural group corporate profile 2013Ritesh Pothan
 
Effective Employment of Solar PV MiniGrids in African Mining
Effective Employment of Solar PV MiniGrids in African MiningEffective Employment of Solar PV MiniGrids in African Mining
Effective Employment of Solar PV MiniGrids in African MiningIra Green
 

Ähnlich wie POWER PURCHASE AGREEMENTS(PPA) (20)

Contracts for difference
Contracts for differenceContracts for difference
Contracts for difference
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort
 
Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee Valley
 
Project-model-Funding-schemes.pdf
Project-model-Funding-schemes.pdfProject-model-Funding-schemes.pdf
Project-model-Funding-schemes.pdf
 
Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain
 
Wind Energy Available for Sale in Tamil Nadu
Wind Energy Available for Sale in Tamil NaduWind Energy Available for Sale in Tamil Nadu
Wind Energy Available for Sale in Tamil Nadu
 
OREC Webinar: From Silicon Valley to Wall Street to Foggy Bottom:
OREC Webinar: From Silicon Valley to Wall Street to Foggy Bottom:OREC Webinar: From Silicon Valley to Wall Street to Foggy Bottom:
OREC Webinar: From Silicon Valley to Wall Street to Foggy Bottom:
 
Epc contracts-in-the-power-sector
Epc contracts-in-the-power-sectorEpc contracts-in-the-power-sector
Epc contracts-in-the-power-sector
 
Digitalisation in the Energy Sector
Digitalisation in the Energy Sector Digitalisation in the Energy Sector
Digitalisation in the Energy Sector
 
EMconcept.pptx
EMconcept.pptxEMconcept.pptx
EMconcept.pptx
 
Introduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptxIntroduction to Virtual Power Purchase Agreement instruments.pptx
Introduction to Virtual Power Purchase Agreement instruments.pptx
 
D0 1 ricardo_infrastructure & service delivery
D0 1 ricardo_infrastructure & service deliveryD0 1 ricardo_infrastructure & service delivery
D0 1 ricardo_infrastructure & service delivery
 
Solving Nigeria's Power Problems
Solving Nigeria's Power ProblemsSolving Nigeria's Power Problems
Solving Nigeria's Power Problems
 
Rsm GC Advisory RE Power Contracting & Trading - ver3
Rsm GC Advisory RE Power Contracting & Trading - ver3Rsm GC Advisory RE Power Contracting & Trading - ver3
Rsm GC Advisory RE Power Contracting & Trading - ver3
 
Political Economy of Energy Reforms
Political Economy of Energy ReformsPolitical Economy of Energy Reforms
Political Economy of Energy Reforms
 
coned-presentation-in-pdf-final.pdf
coned-presentation-in-pdf-final.pdfconed-presentation-in-pdf-final.pdf
coned-presentation-in-pdf-final.pdf
 
Natural group corporate profile 2013
Natural group corporate profile 2013Natural group corporate profile 2013
Natural group corporate profile 2013
 
Effective Employment of Solar PV MiniGrids in African Mining
Effective Employment of Solar PV MiniGrids in African MiningEffective Employment of Solar PV MiniGrids in African Mining
Effective Employment of Solar PV MiniGrids in African Mining
 

POWER PURCHASE AGREEMENTS(PPA)

  • 2. PRSENTATION OUTLINE • CORE FACTS OF PPA • FACTS OF PPA • THE RISK INVOLVED IN SUCH ARRANGEMENTS • THE CASE OF GHANA
  • 3. MEANING OF PPA • A Power Purchase Agreement (PPA) secures the payment stream for a Build-Own Transfer (BOT) or concession project for an independent power plant (IPP). It is between the purchaser "offtaker" (often a state-owned electricity utility company) and a privately owned power producer. The PPA outlined here is not appropriate for electricity sold on the world spot markets
  • 4. Facts of PPA • State agency enters into agreement for private power company to establish plant to sell to government agency • It usually takes the form of Built Own Transfer(BOT) , design, output and maintenance specifications are given in the agreement • A charge is determined usually realistic to cover project cost in time including equity on return
  • 5. • A third party sale usually enhance project financing and cushion the offtaker(buyer) • Breach of contracts ( contractors are usually not required to damages resulting in delays) • Termination period should be provided in contracts • Operation schedules should be included( outages, maintenance, emergencies and accounts/ records.
  • 6. Risk areas in PPA • Reduction in monthly tariff • Breach of contractual agreements( producers not oblige to pay any money or form of compensation) • Difficulty in securing long term investment by governments • Some areas are technically and commercially challenging to connect to grid • Low tariff reduces motivation to invest • Affordability issues are of great concern to investors and governments • Unreliable gas supply
  • 7. When PPA IS NECESSARY • When revenue for a project is uncertain given market conditions • When there is possibility of a cheaper options from potential competitors • When there is one major customer or fewer bulk buyer(S) • If purchaser wishes to secure security of supply
  • 8. FORMS OF PPAS • Emergency power and mobile plants( Ghana has a number of agreements under this) • Small and rural projects( Kenya has agreement under this type for contractor to supply larger renewable generators with capacity of more than 10MW, Tanzania had a PPA involving a standardize mini grid connection
  • 9. • Medium size and large projects example of this is PPA and implementation agreement produced for Pakistan’s private power and infrastructure board
  • 10. The case of Ghana • IPPs contribute about 776 megawatts to electricity provision in Ghana • IPPS IN GHANA • Asogli power project(200mw) • Tema power plant( 126mw)