SlideShare ist ein Scribd-Unternehmen logo
1 von 21
Downloaden Sie, um offline zu lesen
Lecture NO.3
Muhammad Bilal
Ms. Engineering Management
WHAT IS Work Breakdown
Structure WBS
Work Breakdown structure (WBS):
A hierarchical method that successively
subdivides the work of the project into smaller
detail.
Or
The outcome of this hierarchical process is
called the work breakdown structure (WBS).
Or
The work of the project can be successively
subdivided into smaller and smaller work
elements.
Work Breakdown Structure
WBS
– Complex projects consist of numerous smaller
subprojects, interrelated tasks, and work
elements.
– The procedure for subdividing the overall project
into smaller elements is called the work
breakdown structure or WBS, and its purpose is
to define the total project into “ pieces of work”
called work packages.
– Dividing the project into work packages makes it
easier to prepare project schedules and cost
estimates, and to assign management and task
responsibilities
Work Breakdown Structure
WBS (Cont…)
– The first step in creating a WBS is to divide the
total project into major categories.
– These major categories then are divided into
subcategories that, in turn, are subdivided, and so
on.
– This level-by-level breakdown continues so that
the scope and complexity of work elements is
reduced with each level of breakdown.
– The objective of the procedure is to reduce the
project into work elements that are so clearly
defined that they, individually, can be accurately
budgeted, scheduled, and controlled.
Work Breakdown Structure
WBS (Cont…)
– A typical WBS might consist of the following
four levels (the number of levels varies, as
does the name of the element description at
each level; different project methodologies use
different terms):
Work Breakdown Structure
WBS (Cont…)
– Level 1 represents the total project.
– At Level 2 the project is broken down into several
(usually between 4 and 10) major elements or
subprojects.
– These subprojects should conform to the
deliverables or work areas specified in the scope
statement.
– All of the subprojects when taken together must
make up the total project effort.
– Each subproject, in turn, is broken down into
activities, the sum of which must comprise
everything in the subproject.
Work Breakdown Structure
WBS (Cont…)
– When the process is completed, the tasks at the
lowest levels, whatever the levels might be, are
termed work packages; these work packages
become the basis for further planning steps.
– In the table above, that the term “ work package ”
that appeared
at Level 4 is for illustration only.
– The actual number of levels in the WBS varies, as
does the name of the element description at each
level. In fact, the levels and names are often
prescribed by the project methodology in use.
Work Breakdown Structure
WBS (Cont…)
– Figure shows a typical WBS. Note the
different levels and usage of different names
for each.
Figure: Work Breakdown Structure WBS
Figure: Work Breakdown Structure WBS
Figure: Work Breakdown Structure WBS
Work Packages
– How far down does the breakdown go?
– Simply, as far as needed to completely define all
work necessary for the project.
– Sometimes a Level 2 breakdown will be adequate,
though usually a Level 3 or higher-level breakdown
will be necessary.
– The work in each “ box ” of the WBS must be “ well
defined ” ; if it is not, then the box must be
subdivided into smaller boxes.
Work Packages (Cont…)
– What is necessary for a box to be “ well defined? ” The
box should include the following
1.Clear, comprehensive SOW:
The work task defined well enough so the parties
responsible know exactly what they must do.
2. Resource requirements:
The labor, skills, equipment, facilities, and materials for
the task.
3. Time:
Estimated time necessary to perform the task.
4. Costs:
Estimated costs for the required resources, management,
and related expenses for the task.
5. Responsibility:
The parties, individuals, and job titles responsible for
performing the task and approving it.
Work Packages (Cont…)
6. Outcomes:
The deliverables, end-items, or end-results and
associated requirements and specifications for the task.
7. Inputs:
The preconditions or predecessors necessary to begin the
task.
8. Quality assurance:
The entry, process, and exit conditions to which the task
must conform; these are specified in the quality plan.
9. Risk:
Uncertainty about time, cost, and resources, identified as
high, medium, or low risk, with migration and
contingencies measures for high risks.
10. Other:
Additional information as necessary.
Work Packages (Cont…)
– If any of the properties listed cannot be defined, the
task in the box is too broad and must be broken
down further.
– In most cases, all or most of these properties can be
eventually determined by breaking tasks down into
small-enough pieces.
– A well-defined piece, which by definition includes
the properties summarized in Figure is called a
work package.
Work Packages (Cont…)
– As illustrated in Figure different portions of the
project will require different levels of breakdown to
define work packages, meaning that work packages
in different portions of the project might appear at
different levels.
Organization Breakdown
Structure (OBS)
– What is Organization Breakdown Structure:
Organization Breakdown Structure (OBS) is a
structure used to assign responsibility for work
packages.
• The OBS depicts how the firm has organized to
discharge work responsibility.
• The purposes of the OBS are to provide a framework
to summarize organization unit work performance,
identify organization units responsible for work
packages, and tie the organizational unit to cost
control accounts.
Organization Breakdown
Structure (OBS)
– The OBS defines the organization sub deliverables in a
hierarchical pattern in successively smaller and
smaller units. Frequently, the traditional organization
structure can be used.
– Even if the project is completely performed by a team,
it is necessary to break down the team structure for
assigning responsibility for budgets, time, and
technical performance.
Organization Breakdown
Structure (OBS)
– As in the WBS, the OBS assigns the lowest
organizational unit the responsibility for work
packages within a cost account.
– Herein lies one major strength of using WBS and OBS;
they can be integrated as shown in Figure Below.
Figure: Integration of WBS and OBS
Explanation of the above Figure

Weitere ähnliche Inhalte

Was ist angesagt?

Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jIIT delhi
 
The Value of Infrastructure Asset Management
The Value of Infrastructure Asset ManagementThe Value of Infrastructure Asset Management
The Value of Infrastructure Asset ManagementC.S. Davidson
 
Creating a work breakdown structure with microsoft project
Creating a work breakdown structure with microsoft projectCreating a work breakdown structure with microsoft project
Creating a work breakdown structure with microsoft projectNirtiSingla
 
Concept of floating foundation
Concept of floating foundationConcept of floating foundation
Concept of floating foundationMilind Rao
 
organizational breakdown structure (OBS)
organizational breakdown structure (OBS)organizational breakdown structure (OBS)
organizational breakdown structure (OBS)Nikhil Raj
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureCOEPD HR
 
Total Quality Management In Construction
Total Quality Management In ConstructionTotal Quality Management In Construction
Total Quality Management In ConstructionMohammed EL Bakri EL Beeli
 
Productivity improvement in construction
Productivity  improvement in constructionProductivity  improvement in construction
Productivity improvement in constructionKabilanP1
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Engineering Economics|Work Breakdown Structure
Engineering Economics|Work Breakdown StructureEngineering Economics|Work Breakdown Structure
Engineering Economics|Work Breakdown Structureumair khan
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-projecthlksd
 
Sequence of general works of building construction
Sequence of general works of building constructionSequence of general works of building construction
Sequence of general works of building constructionChelluri Srihari
 
Construction Software – Design , Analysis , Estimate & ERP
Construction Software – Design , Analysis , Estimate & ERPConstruction Software – Design , Analysis , Estimate & ERP
Construction Software – Design , Analysis , Estimate & ERPSSudhaVelan
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
LOW COST EARTHQUAKE RESISTANT TECHNIQUES
LOW COST EARTHQUAKE RESISTANT TECHNIQUESLOW COST EARTHQUAKE RESISTANT TECHNIQUES
LOW COST EARTHQUAKE RESISTANT TECHNIQUESSachinKotian10
 

Was ist angesagt? (20)

Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
The Value of Infrastructure Asset Management
The Value of Infrastructure Asset ManagementThe Value of Infrastructure Asset Management
The Value of Infrastructure Asset Management
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Creating a work breakdown structure with microsoft project
Creating a work breakdown structure with microsoft projectCreating a work breakdown structure with microsoft project
Creating a work breakdown structure with microsoft project
 
Concept of floating foundation
Concept of floating foundationConcept of floating foundation
Concept of floating foundation
 
organizational breakdown structure (OBS)
organizational breakdown structure (OBS)organizational breakdown structure (OBS)
organizational breakdown structure (OBS)
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Total Quality Management In Construction
Total Quality Management In ConstructionTotal Quality Management In Construction
Total Quality Management In Construction
 
Productivity improvement in construction
Productivity  improvement in constructionProductivity  improvement in construction
Productivity improvement in construction
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Engineering Economics|Work Breakdown Structure
Engineering Economics|Work Breakdown StructureEngineering Economics|Work Breakdown Structure
Engineering Economics|Work Breakdown Structure
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-project
 
Sequence of general works of building construction
Sequence of general works of building constructionSequence of general works of building construction
Sequence of general works of building construction
 
ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1
 
Construction Software – Design , Analysis , Estimate & ERP
Construction Software – Design , Analysis , Estimate & ERPConstruction Software – Design , Analysis , Estimate & ERP
Construction Software – Design , Analysis , Estimate & ERP
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
LOW COST EARTHQUAKE RESISTANT TECHNIQUES
LOW COST EARTHQUAKE RESISTANT TECHNIQUESLOW COST EARTHQUAKE RESISTANT TECHNIQUES
LOW COST EARTHQUAKE RESISTANT TECHNIQUES
 

Ă„hnlich wie Lect 3 wbs&obs

WBS-final-1.Project Management and Ethics.pptx
WBS-final-1.Project Management and Ethics.pptxWBS-final-1.Project Management and Ethics.pptx
WBS-final-1.Project Management and Ethics.pptxFillHackjack
 
Untitled document (24).pdf
Untitled document (24).pdfUntitled document (24).pdf
Untitled document (24).pdfAsadUllah174251
 
Work breakdown structure (WBS) PRESENTATION.pptx
Work breakdown structure (WBS) PRESENTATION.pptxWork breakdown structure (WBS) PRESENTATION.pptx
Work breakdown structure (WBS) PRESENTATION.pptxErzaScarlet64
 
Work Break Down Structure
Work Break Down StructureWork Break Down Structure
Work Break Down StructureSomtel
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIMudassir Iqbal
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown StructureNicola2903
 
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
workbreakdownstructureppt-130410021152-phpapp02 (1).pdfworkbreakdownstructureppt-130410021152-phpapp02 (1).pdf
workbreakdownstructureppt-130410021152-phpapp02 (1).pdfDipakBorse6
 
Workbreakdownstructureppt 130410021152-phpapp02
Workbreakdownstructureppt 130410021152-phpapp02Workbreakdownstructureppt 130410021152-phpapp02
Workbreakdownstructureppt 130410021152-phpapp02sayyed sabir
 
PositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxPositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxChantellPantoja184
 
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docxevonnehoggarth79783
 
CSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxCSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxmydrynan
 
Work Breakdown Structure Aritrya Kumar.pptx
Work Breakdown Structure Aritrya Kumar.pptxWork Breakdown Structure Aritrya Kumar.pptx
Work Breakdown Structure Aritrya Kumar.pptxARITRYAKUMAR
 
WBSssssssssssssssssssssssssssssssssssss.pptx
WBSssssssssssssssssssssssssssssssssssss.pptxWBSssssssssssssssssssssssssssssssssssss.pptx
WBSssssssssssssssssssssssssssssssssssss.pptxRedhaElhuni
 
SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx
 SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx
SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docxaryan532920
 
SEN-22413 - UNIT - V.pptx
SEN-22413 -  UNIT - V.pptxSEN-22413 -  UNIT - V.pptx
SEN-22413 - UNIT - V.pptxFreefireGarena22
 
The Work Breakdown StructureAwork breakdown structure (WBS) brea.docx
The Work Breakdown StructureAwork breakdown structure (WBS) brea.docxThe Work Breakdown StructureAwork breakdown structure (WBS) brea.docx
The Work Breakdown StructureAwork breakdown structure (WBS) brea.docxssusera34210
 
Chapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).pptChapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).pptssuser8cd298
 

Ă„hnlich wie Lect 3 wbs&obs (20)

WBS-final-1.Project Management and Ethics.pptx
WBS-final-1.Project Management and Ethics.pptxWBS-final-1.Project Management and Ethics.pptx
WBS-final-1.Project Management and Ethics.pptx
 
Untitled document (24).pdf
Untitled document (24).pdfUntitled document (24).pdf
Untitled document (24).pdf
 
Work breakdown structure (WBS) PRESENTATION.pptx
Work breakdown structure (WBS) PRESENTATION.pptxWork breakdown structure (WBS) PRESENTATION.pptx
Work breakdown structure (WBS) PRESENTATION.pptx
 
Work Break Down Structure
Work Break Down StructureWork Break Down Structure
Work Break Down Structure
 
Control account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMIControl account, work and planning package - PMP/CAPM from PMI
Control account, work and planning package - PMP/CAPM from PMI
 
Work breakdown Structure
Work breakdown StructureWork breakdown Structure
Work breakdown Structure
 
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
workbreakdownstructureppt-130410021152-phpapp02 (1).pdfworkbreakdownstructureppt-130410021152-phpapp02 (1).pdf
workbreakdownstructureppt-130410021152-phpapp02 (1).pdf
 
Workbreakdownstructureppt 130410021152-phpapp02
Workbreakdownstructureppt 130410021152-phpapp02Workbreakdownstructureppt 130410021152-phpapp02
Workbreakdownstructureppt 130410021152-phpapp02
 
PositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxPositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docx
 
Babu 143
Babu 143Babu 143
Babu 143
 
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
 
CSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxCSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docx
 
Work Breakdown Structure Aritrya Kumar.pptx
Work Breakdown Structure Aritrya Kumar.pptxWork Breakdown Structure Aritrya Kumar.pptx
Work Breakdown Structure Aritrya Kumar.pptx
 
WBSssssssssssssssssssssssssssssssssssss.pptx
WBSssssssssssssssssssssssssssssssssssss.pptxWBSssssssssssssssssssssssssssssssssssss.pptx
WBSssssssssssssssssssssssssssssssssssss.pptx
 
SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx
 SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx
SEQ CHAPTER h r 3work breakdown structure A Work Breakdown St.docx
 
SEN-22413 - UNIT - V.pptx
SEN-22413 -  UNIT - V.pptxSEN-22413 -  UNIT - V.pptx
SEN-22413 - UNIT - V.pptx
 
Final_Module_2.ppt
Final_Module_2.pptFinal_Module_2.ppt
Final_Module_2.ppt
 
The Work Breakdown StructureAwork breakdown structure (WBS) brea.docx
The Work Breakdown StructureAwork breakdown structure (WBS) brea.docxThe Work Breakdown StructureAwork breakdown structure (WBS) brea.docx
The Work Breakdown StructureAwork breakdown structure (WBS) brea.docx
 
Wbs, gant charts
Wbs, gant chartsWbs, gant charts
Wbs, gant charts
 
Chapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).pptChapter 2 Work Break down Structure (1).ppt
Chapter 2 Work Break down Structure (1).ppt
 

KĂĽrzlich hochgeladen

VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girladitipandeya
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 

KĂĽrzlich hochgeladen (20)

VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 

Lect 3 wbs&obs

  • 1. Lecture NO.3 Muhammad Bilal Ms. Engineering Management
  • 2. WHAT IS Work Breakdown Structure WBS Work Breakdown structure (WBS): A hierarchical method that successively subdivides the work of the project into smaller detail. Or The outcome of this hierarchical process is called the work breakdown structure (WBS). Or The work of the project can be successively subdivided into smaller and smaller work elements.
  • 3. Work Breakdown Structure WBS – Complex projects consist of numerous smaller subprojects, interrelated tasks, and work elements. – The procedure for subdividing the overall project into smaller elements is called the work breakdown structure or WBS, and its purpose is to define the total project into “ pieces of work” called work packages. – Dividing the project into work packages makes it easier to prepare project schedules and cost estimates, and to assign management and task responsibilities
  • 4. Work Breakdown Structure WBS (Cont…) – The first step in creating a WBS is to divide the total project into major categories. – These major categories then are divided into subcategories that, in turn, are subdivided, and so on. – This level-by-level breakdown continues so that the scope and complexity of work elements is reduced with each level of breakdown. – The objective of the procedure is to reduce the project into work elements that are so clearly defined that they, individually, can be accurately budgeted, scheduled, and controlled.
  • 5. Work Breakdown Structure WBS (Cont…) – A typical WBS might consist of the following four levels (the number of levels varies, as does the name of the element description at each level; different project methodologies use different terms):
  • 6. Work Breakdown Structure WBS (Cont…) – Level 1 represents the total project. – At Level 2 the project is broken down into several (usually between 4 and 10) major elements or subprojects. – These subprojects should conform to the deliverables or work areas specified in the scope statement. – All of the subprojects when taken together must make up the total project effort. – Each subproject, in turn, is broken down into activities, the sum of which must comprise everything in the subproject.
  • 7. Work Breakdown Structure WBS (Cont…) – When the process is completed, the tasks at the lowest levels, whatever the levels might be, are termed work packages; these work packages become the basis for further planning steps. – In the table above, that the term “ work package ” that appeared at Level 4 is for illustration only. – The actual number of levels in the WBS varies, as does the name of the element description at each level. In fact, the levels and names are often prescribed by the project methodology in use.
  • 8. Work Breakdown Structure WBS (Cont…) – Figure shows a typical WBS. Note the different levels and usage of different names for each.
  • 9. Figure: Work Breakdown Structure WBS
  • 10. Figure: Work Breakdown Structure WBS
  • 11. Figure: Work Breakdown Structure WBS
  • 12. Work Packages – How far down does the breakdown go? – Simply, as far as needed to completely define all work necessary for the project. – Sometimes a Level 2 breakdown will be adequate, though usually a Level 3 or higher-level breakdown will be necessary. – The work in each “ box ” of the WBS must be “ well defined ” ; if it is not, then the box must be subdivided into smaller boxes.
  • 13. Work Packages (Cont…) – What is necessary for a box to be “ well defined? ” The box should include the following 1.Clear, comprehensive SOW: The work task defined well enough so the parties responsible know exactly what they must do. 2. Resource requirements: The labor, skills, equipment, facilities, and materials for the task. 3. Time: Estimated time necessary to perform the task. 4. Costs: Estimated costs for the required resources, management, and related expenses for the task. 5. Responsibility: The parties, individuals, and job titles responsible for performing the task and approving it.
  • 14. Work Packages (Cont…) 6. Outcomes: The deliverables, end-items, or end-results and associated requirements and specifications for the task. 7. Inputs: The preconditions or predecessors necessary to begin the task. 8. Quality assurance: The entry, process, and exit conditions to which the task must conform; these are specified in the quality plan. 9. Risk: Uncertainty about time, cost, and resources, identified as high, medium, or low risk, with migration and contingencies measures for high risks. 10. Other: Additional information as necessary.
  • 15. Work Packages (Cont…) – If any of the properties listed cannot be defined, the task in the box is too broad and must be broken down further. – In most cases, all or most of these properties can be eventually determined by breaking tasks down into small-enough pieces. – A well-defined piece, which by definition includes the properties summarized in Figure is called a work package.
  • 16. Work Packages (Cont…) – As illustrated in Figure different portions of the project will require different levels of breakdown to define work packages, meaning that work packages in different portions of the project might appear at different levels.
  • 17. Organization Breakdown Structure (OBS) – What is Organization Breakdown Structure: Organization Breakdown Structure (OBS) is a structure used to assign responsibility for work packages. • The OBS depicts how the firm has organized to discharge work responsibility. • The purposes of the OBS are to provide a framework to summarize organization unit work performance, identify organization units responsible for work packages, and tie the organizational unit to cost control accounts.
  • 18. Organization Breakdown Structure (OBS) – The OBS defines the organization sub deliverables in a hierarchical pattern in successively smaller and smaller units. Frequently, the traditional organization structure can be used. – Even if the project is completely performed by a team, it is necessary to break down the team structure for assigning responsibility for budgets, time, and technical performance.
  • 19. Organization Breakdown Structure (OBS) – As in the WBS, the OBS assigns the lowest organizational unit the responsibility for work packages within a cost account. – Herein lies one major strength of using WBS and OBS; they can be integrated as shown in Figure Below.
  • 20. Figure: Integration of WBS and OBS
  • 21. Explanation of the above Figure