SlideShare ist ein Scribd-Unternehmen logo
1 von 60
Construction Oriented Engineering
&
Expectation From Others

BY: M. Asim Shehzad
Contents

Constructability and Its Advantages
Construction Oriented Engineering & Objectives

Procurement Enabling Engineering

Construction Enabling Engineering

Expectations From Others
Constructability
Constructability is the optimum use of construction
knowledge and experience in planning, design, procurement,
and construction to achieve overall Project Objectives.
OR
Putting construction knowledge work early in project
development and intertwining that construction knowledge
throughout the conceptual, design and procurement phases
to allow for the most efficient, practical and cost efficient
construction techniques to be used.
3
Basic Objectives Of Constructability
Identify and define objectives to enhance the probability of a
cost efficient, build able project.
Identify the key engineering and procurement deliverables
that will have the greatest bearing on the ability to construct the
project
 Identify where early construction input is needed.
Identify construction related enhancements that can improve
overall safety, quality, costs and schedule.
Identify the major execution challenges.
Transfer of constructability information to the next phases of
the project.
Key Constructability Issues
1.Schedule is Construction Sensitive.
2.Design is ‘simple’.
3.Design elements are standardized to take advantage of repetition.
4.Design Facilitate fabrication, transportation and installation.
5.Layouts are accessible to fabrication, installation and operation workers, material and equipment.
6.Effect of environmental conditions on construction is minimized.
7.Specifications simplify construction.
8. Accurate Construction estimates that reflect construction methods and strategies.
9.Early construction involvement is considered in developing plans and strategies.
Typical functional Project constructability Organization
Project Management Team
Construction Manager

Technical Manager
Project
Engineering
Manager

Project construction
Manager

Constructability
Coordinator

Construction Knowledge Resources

Company wide
Constructability
Organization

Discipline Lead

Discipline Lead

Construction Knowledge Resources

Project Constructability Organization

Discipline Lead
Ability To Influence Cost

High

Project Duration

Ability to Influence Cost

Conceptual Engineering

Preliminary Engineering

Maximum benefits occur when people with
construction knowledge and experience
become involved early in the project

Detailed Design

Procurement

Maximum Influence Period

Construction
Start Up

Low

Constructability
Conclusion
Constructability, if properly defined structured and used, will ensure that
construction knowledge and experience is used as early as possible in the
planning and design process to ensure design and implementation with plan
practicality and cost effectiveness.

Constructability is simply the utilization of construction knowledge,
experience and efficiency into design and execution planning of the project
components. Constructability issues touch on virtually all aspects of execution
including safety, scheduling, detailed design, procurements,
material/equipment delivery, contracting, temporary facilities/infrastructure
needs, commissioning and the project management team organization.
Construction Oriented
Engineering
COE

To execute Engineering work in such
a way that enables Procurement and
Construction stages.
&
Provide operational ease to comply
with construction strategies.
Objectives Of COE
• Achieve Project Objectives-Meet The Construction Schedule
• Right Design at Right Time
• Avoid Changes & Rework

• Comprehensive Design With Minimum Objections From Client
• Complete & Clear Design – Constructible & Build able
• Material Proposed Is Suitable
• Available In Market
• Economical To Work With

• E is well integrated with P and C Work Processes
EPC Engineering Sequence
Studies
OM cost estimate
Basic Engineering
Criteria & Specs
MTO Estimate

Purchase Requisition
Calculations
Detailed Engineering
 Definitive Design /Estimate
Issue “Engineering
“Deliverables” to construction
Field Changes
Produce “As-Built”
Project -Close out
EPC Procurement Sequence
Develop Bidders Lists
Purchase Order Pro-Forma
Contracts Pro-Forma
Transportation & Logistics.
Specifications (Engg.)
Quantities (Engg.)
Solicit / Evaluate Bids
Award P.O. /Contracts
Shop Inspections
Track Status
Expediting
Transport & Receive
Warehouse
Maintain
Release to
Construction
EPC Construction Sequence
General Construction Plan
Site Layout Plan
Temporary Facilities
Geo-Tech
Mass Earth-Work
Structural Concrete
Structural Steel
Equipment (mech. & elect.)
Piping
Raceway
Instrumentation & Control

Note: Construction is supported by
field Engineers.

System Turn-over
Start –Up & Commissioning
Performance Run
Turn-Over to end -user
Sequential to Concurrent Execution
Jan

Feb

Mar April May June July

Aug

Sep

Oct

Nov

Dec

SEQUENCTIAL
ENGINEERING

PROCUREMENT

CONSTRUCTION

CONCURRENT
ENGINEERING
PROCUREMENT
CONSTRUCTION
Concurrent Design Components
Engineering is concurrently integrated with Procurement & Construction:
Jan

Feb

Mar April May June July

Aug

Sep

Oct

Nov

ENGINEERING

Bill of
Quantity 1

Bill of
Quantity 2

Drawings1

Drawings2

PROCUREMENT
Vendor Info1

Vendor Info2

CONSTRUCTION
16

Dec
Concurrent Design Components
Effect of any delay would squeeze construction time or require an EOT:
Jan

Feb

Mar April May June July
ENGINEERING

Bill of
Quantity 1

Aug

Sep

Oct

Nov

Dec

Delay

Bill of
Quantity 2

Drawings
1

PROCUREMENT

Delay

Vendor
Info1

Drawings
2

Vendor
Info2

Vendor
Info2

CONSTRUCTION
17

Construction Squeezed
Construction & Project Success
 Construction is a downstream activity
 E &P success is generally measured in terms of construction
 Construction is intact if E & P components are construction oriented

ENGINEERING

PROCUREMENT

CONSTRUCTION
Impact Of Variables Over Time
Stack Holder Influence, Uncertainty and Risk
MAX

Impact

Cost of Changes

MIN
0

Engineering
Project
Procurement
Progress Construction
Project

MAX

10
0

30
10

30
0

60

80

70
3

95
95

10

100%
100%

50

80

95

100%

Schedule Control

Sensibility
Cost Control
MIN

MAXIMUM CONTROL LIES IN THIS AREA

TROUBLE SHOOTING
Critical Engineering Phases
Jan

Feb

Mar

April

May

June

July

Aug

Sep

Oct

Nov

Dec

ENGINEERING

Initial MTO

Final MTO

Procurement Enabling Engineering

PROCUREMENT

Construction Enabling Engineering

Const’n Dwgs
IFC with HOLD

IFC

CONSTRUCTION

Early Procurement Enabling Engg

Early Construction Enabling Engg.
Procurement Enabling
Engineering
Procurement Enabling Engineering
ENGINEERING

Engineering

Specialized
Equip
Data sheet

Mech Equip
data Sheets

MTO’s
Piping & Bulk

MCC &
Panels details
.

PROCUREMENT

Procurement

Specialized
Equip
Order
Construction

Mech
Equip
Order

MCC
Panels
Order

CONSTRUCTION

.
.

Quantities
Decided

.

.

22

Specialized
Equip
Erection

Piping
Work
Construction

Material
Acquired

MCC
Building
Construction
Procurement Enabling Engineering
Early Procurement Enabling Phase
Long lead items have to be ordered early.
All equipment and packages & bulk materials to be purchased
soon as their technical definition allows.
The earlier the PO’s are placed, sooner the vendor information
available for DE with vendors.

Challenges:

Integration of technical information
with vendors.
Procurement Enabling Engineering
o Mechanical Equipment
o Bulk Materials
o Piping & Fittings
o Steel Structure
o E&I Bulk
o E&I Related Procurements
o MCC Buildings
Mechanical Equipments
Main Process
Equipment

Rotating
Equipment

Package
Fire
Equipment Equipment

Major Tasks are:








Determination of Capacities
Early release of RFQ’s & TBE’s
Long Delivery Time (Dictate project schedule)
Functional Requirement & Standard Packages
Economy & Operational Spares
Vendor shop load & Management

Pressure
Vessels

Heat
Exchanger
Equipment RFQ’s / TBE’s
Approval Cycle

Vendor Management

RFQ
PFD’s

P&ID’
s

Heat &
Mass
Balance

Client
Review

•Data Sheets
•Function Specification of
main package
•Process Philosophy
Documents
•Process Descriptions
•Operation Philosophy
•ESD Philosophy
•Depressurization
Philosophy

OK
P.O Issued

Not OK
Vendor
Data

Vendor
Shop Load
Deliveries

Challenges:
 Coordination & Approval Cycle (RFQ’s & TBE’s)
 Specs, Budget & Decision making
 Vendor Data (GA’s, Connection details and Loads)
26
Piping Bulk
Piping covers major portion of construction work that is linked with
pre-com and commissioning works.

Major concerns are:
Material delivery time,
Fabrication, Erection, Testing and Painting /
Insulation
Accuracy level of MTO’s and Reordering duration
Piping material specs, availability and economy
Purchase terms (type of order)
Flaw less Material Management and Control
MTO’s
Estimate MTO
Estimate stage take off i.e. drawing numbers is not known yet, may be
done via flow diagrams, plot plans, equipment lists, sketches etc.
Bulk MTO
Materials can be identified to a specific drawing/line number.
However,
Drawings are unchecked .
Changes may still occur in design.
Material requirements will change.
However, It has detailed info, so initial purchase can be done i.e.
above 4” main pipes.
Final MTO
As the project design finalizes, final stage takeoff is performed ,
and final drawings are issued as “IFC’s” .
MTO Stages
MTO Stages
Manual Designing
3D Modeling

Other Modeling Info

Accuracy

1st
•Plot plan
•P&ID’s
Plot plan
•P&ID’s

•Equipment Location
and orientation
•Pipe racks,
•Major piping
•operational access
•Escape routes
•Main E&I cable
trays/trenches
•Underground sewer
stem

70%

2nd

3rd

•Piping Layout Plan
•P&ID’s

IFC ISO’s

60% Model Review

90% Model Review

•Major Piping (upto 2”
dia) including control
valves
•Major access ways,
ladder, & platforms
•Secondary steelworks
and bracings
•Pipe supports location
and types
•Local control panels
•Fire fighting
equipments
•Instrument
transmitters and
outline of junction
boxes

•Access ways, ladder,
platforms
•All Piping,
•All offline instruments
•Issuance of Drawing

85%

95-100%
Material Management & Control
Material management should start by importing the Material Requirements
(BOM or MTO) from the design system (PDMS, PDS, CAD Works etc) .

Objectives:

Tracking changes to the requirements as the design
progresses.
Generation of inquiries and purchase orders for materials.
Expediting and recording material deliveries.
Control of material deliveries.
Control of material issues and movements.
Inventory/Stock control management.
Management of material traceability.
Progress monitoring
Steel Structure
Steel structure design drawings for Pipe racks
and steel structures indicating the sizes of
profiles & dimensions.
Required for critical structures like pipe rack.
Commercial viability & availability of profiles.
Delivery and fabrication time.
E&I Related Procurements
 MCC, Power Gen, Switch Gear & UPS,
Transformers
 Cables

3
AFE

 JB’s (Classified)

Converter
Basic
Unit

 Control System

Motor

 Control Valves
 MCC Building

3

Inverter
Critical E&I Related Procurement
MCC Switch Gear,Power Gen, Transformer, UPS, MCC Building:
EPC Engineering
Vendor Package
Management

Building Design

Power
Producer
Consumer
List

Load
List

Vendor
Packages
Piping
Layout

Main Cable
Routing

MCC
Switch
Gear /
Vendor

HV

Substation
Panel Layout

MV

LV

Transformer
Vendor

Civil
Architectural
Drawings

Equipment
Arrangement
Drawings
MCC
Building
Design

UPS Vendor

Cable Entry Locations

Soil Investigation
Report
Building detailed design
The EPC Engineers , define building needs and produce guide drawings as
mentioned below and outsource detail design.
Architectural drawings, showing all dimensions of the buildings (building
housing machinery, E&I for technical rooms etc).
Equipment dimensions and weight, for the design of supporting floors.
Equipment access requirements (size of doors, handling).
Building blast resistance requirement.
Cable entry requirements: raised/false floor, floor openings.
Climate requirements (temperature etc), and equipment heat dissipation.
Fire & Gas detectors and equipment layout.
Telecom equipment layout (LAN etc.).
Tie-in points for connection of the building to the PLANT’s utilities.
Other Vendors Involved are:
HVAC Vendor does the detailed HVAC design (equipment selection, flow
diagram, ductwork routing).
Fire & Gas Design.
Telecom cable routing.
Lighting and small power Design .
All the above entail an extensive co-ordination among all these trades , to avoid interferences.
Critical E&I Related Procurement

Extensive Coordination between Disciplines, Vendors , Clients and
Construction.
Finalization of Consumer List.
 Finalization of MCC Switch Gear.
Economy of the Package.
Vendor Data for finalization of MCC Building Design.

Challenges:
MCC Building Construction is on Critical
Path, dependent on coordination among
multiple parties and its delay could impact
the Pre-Commissioning.
Cable, JB’s (Classified)
Cables:
Main Cable
Routing

Cable MTO
(HV ,MV ,LV)

Equipment
Layout

JB’s (Classified):
Larger Delivery Period.

Challenges:
Accuracy of
Schedule(Cable Drums)
Early Ordering
Economy
Control Valves & Control System
Control Valves:
•Process Data Sheets
•Hydraulic
Studies(line sizing)
•Flow Conditions

Data
Sheets for
Motorized
Valves

Control System:
•Specifications
•I / O Counts
•System Architectural
Drawings

DCS
ESD
F&G

Challenges:
Generally Long Lead
Coordination With Vendor
Economy
Construction Enabling
Engineering
Construction Enabling Engineering
ENGINEERING

Engineering

Foundation
Drawings

Pipe Rack
Civil Work

Steel
Structure
Drawings

Building
Detailed
Drawings

Procurement

Under
Ground
Facilities

ISO’s

Tanks CP
Plates

PROCUREMENT
CONSTRUCTION

Construction

Foundation
Construction

Pipe Rack
Construction
& erection

Steel
Structure
erection
39

Construction
of
Building

Mech
Piping
work

Under
Ground
Facilities
Construction

Tanks CP
Plates
constrction
Construction Enabling Engineering
Early Construction Enabling Phase
Initiating early construction activities
Integrating information from vendors to detail engineering.
Must issue IFC design with a provision of time to construction for shop drawing
An economical and constructible design.

Challenges:
engineering development is highly dependent
on information from vendors.
Earlier activities are in fact designed at the end
delays will typically result in idle manpower
and equipment, lack of work front, low
productivity, impact on critical path
EPC Interfaces & Integration
Const,n Phase

Phase 1

Phase 2

Phase 3

Award
Eng’g
Completed
Early Procurements

Early Construction

P&ID, Plot

Piping Layout

Engineering

REQ

Procurement

Const 90% Completion

MTO/Const Dwg
FDN Dwg
Vendor Docs
Equipment/Bulk
Material P.O

Main EQ PO
LLI

Vendor Dwg

Fabrication
Jig/Anchor Bolt

Catalyst/Chemical

Main
Delivered

Construction
Site Development &

Pre commissioning &

Temp Work.

Engineering
Project
Progress Procurement
Construction

Project

0

10
0

Comm’g
Completed

Final Const DWG

30
10

60

30

80

70

0

3

10

Schedule Control
MIN

Cost Control
41

95

100%

95

MAX

Sensibility

Start-Up

FDN Start

100%
50

80

95

100%
60 70 80 90 100

Critical Path Of A Typical Project
75 % Piping Material
Delivered

IFC Plot Plan &
P&IDs
50% Equipment
Ordered

Piping PreFabrication
Piping Erection

Engineering

30 40

50

Progress %

50 % ISO’s

a

Mechanical
Completion

Equipment
Erection

10 20

B

0

Time (as % of Project Duration)

0

10

20

Design Office
Building Period

30

40

Design Office
Peak Period

a=Design office peak

50

60

Piping Construction
Build-up Material
Period

70

80

Piping Erection
Peak Period

90

100

Piping
Completion

B=Piping erection peak
Construction Enabling Engineering
• Foundations
• Pipe Rack Construction
• Piping Work
• Underground Facilities
• Tank Construction
• Road Crossing

• MCC Building
Foundations
Engineering is the integrator of the equipment vendor data & foundation design
Critical Foundations are Pipe Rack Foundations
Major Equipment Foundations

Process
simulations

Equipment list &
duty

Equipment
Inquiry &
Selection
Vendor
Engineering
Vendor Data &
Drawing

Getting the design input
early

Foundation
Drawing
Pipe Rack Construction

Pipe-rack construction is the
predecessor of piping, mechanical
installations and E&I works.
Consequently optimizing this
resource intensive activity will lead
to smooth and shorter project
duration.
Construction management team
to develop proactive strategies and
alternate solutions to optimize
resources for pipe rack construction
and installation works.
Pipe Rack Construction
Drawings are issued with sizing
of members with consideration of
material delivery time and shop
fabrication drawings.
For pre-fabrication structure,
the supplier will produce all shop
drawings and erection details.
In case of pre-fabrication
structure a coordination is
required to finalize rack
foundation

46
Piping Construction

Piping is a critical activity, so issuance of piping ISO’s is crucial.
Construction require further time to translate design ISO’s into spooling
drawings.
Additionally, effective installation of piping will require availability of pipe
supports.

Challenges:
Work Front in the start is less w.r.t. available ISO’s
and Material
Frequent changes as the design is not freeze in
the beginning
Manufacturing support in a bulk is a production
challenge
Piping Work
Green

Const,n Phase

Piping ISO’s

50%ISO’s

Yellow

Final ISO’s

Pipe Supports

75% Piping
Material delivered

30% Equipment
Arrived

Procurement
(Piping)

Construction

Red

100%
Material

100%
Equipment
MC

Re-Order

Spooling Drawing

(Piping)

Pipe Supports
Fabrication

30% Fabrication

Mechanical
Completion
Pre-Com

Pipe Fabrication

COM

U/G Must
Complete

Pipe Erection

Pre-Com
Start
3D Modeling

3D Modeling
Isometrics
Major Activities

4” above piping on racks & sleepers
Early Pre-Comm – Golden Joints

Spooling Drawings

U/G piping Must Finish

Spooling
Drawings

Stress Analysis

Small bore field piping must start

Stress Analysis

Stress Analysis

Blast Studies

Conflict Resolution

Blast Studies

Blast Studies

As built modifications

48

Isometrics

3D Modeling
Isometrics
Spooling Drawings
Underground Facilities
Underground networks are major
cause of delay in construction
activities.
All underground networks such
as drainage, sewage pipes with
associated pits, pipe support
foundations, cable trenches in
paved areas, inspection pits,
gutters and oil water pits etc.
Underground Facilities
Civil Works Installation drawings complete
with all underground objects and networks, are
required very early, as its pre-requisite for
mechanical works to proceed.
Plant erection cannot proceed for lack of

access until underground facilities are installed
and area is backfilled.
Installation on pipe-rack and structural works
cannot proceed until all undergrounds are laid
and the cranes have access.

50
Tanks CP & Construction

Civil Foundation
Soil Reactivity Test
CP Design & Approvals
Work Order & CP-Materials
Tank Design and MTO
Tank Plates Delivery
Plate Rolling & Fabrication
Tank Welding & Erection
Clean Doors, Nozzles,
VBT & Hydro testing
Sand Blasting & Painting
Insulation & Cladding
Box-Up

51
Tanks Construction Challenges
Challenges:
Early Vendor Selection &
Issuance of WO
Material Procurement
A series of long &
Interdependent Activities
Involvement &
Interdependencies of Multiple
Parties
Stringent QC Requirements
Qualified Manpower
Dependency
Congested Surrounding Access
Changes Cause Resource Idling
High Risk Job
Any Rework Involve Huge
Volume of Work

52
MCC Building Construction
Soil Investigation
Substation Layout
Excavation
Lean Concrete
Detailed Building Erection
Mechanical Installation of
Equipment
Earth Mesh Connections
Equipment Testing
Cable Laying
Cable Continuity Check
 Cable Termination
Testing & Pre-commissioning

Challenges:
Late finalization of building design
Long list of activities and finishing details
Its start is dependent on design parameters and end is driving the pre-com activities.
Expectation From Others
Integrating Construction
Integrate the work processes

Develop Engineering/Construction
Strategies

Constructability reviews
Pre-fabrication
Engineering schedule to match
construction priorities/sequences
Engineering deliverables tailored
to construction execution needs.
Changes
Avoid Changes
Sources of changes
Inherited/Open technical issues
Design development & reviews
Client’s new requirements
3rd party at interface
Avoidable/
Unavoidable
?

Resist avoidable changes-Contractual management
Impact of changes is exponential with time: implement early!
System to identify all impacts and track implementation of changes.
Expectations

A cohesive participation of stack holders internal
interface management.
Inter-Functional Coordination
Project Control
CPM Schedule
Budget
Trends

Interface / Data
exchange

Procurement
Engineering
Specifications
Quantities
Material Requisitions
Design Drawings

Purchase Order
Work Orders
Transportation & Logistics
Ex-Works/ Inspection
Expediting
Receiving / Releasing

Construction
Constructability
Construction Planning
Resource-Planning
Other Expectations

Plan must be based on Up-to date BOQ quantities to plan adequate
resources
Visibility of actual progress against the up-dated work volumes( Let
100%" keep changing till end)
 Precisely Engineering monitoring and indisputably identified.
Earned progress must be supported with milestone e.g. PO issued for a
non-due and non LLI could show wrong status.
Vendor info must be monitored for all equipments and packages for
further development of detailed engineering.
Piping MTO’s status must be monitored in actual figures.
Engineering issued and actual executed quantities must be monitored
as well.
The biggest constraint is out-of-sequence issues: engineering may have
issued drawings with generating work (such as lack of access or prerequisite for another work).
On Behalf of Construction
Management
LOGO

Weitere ähnliche Inhalte

Was ist angesagt?

Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
Piping Design Course in Hyderabad
Piping Design Course in HyderabadPiping Design Course in Hyderabad
Piping Design Course in HyderabadSanjary Edu
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Rajiv Kumar
 
Front End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingFront End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingDEVELOP
 
Power Piping ASME Guide.PDF
Power Piping ASME Guide.PDFPower Piping ASME Guide.PDF
Power Piping ASME Guide.PDFTeddy Setiady
 
Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler U...
Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler U...Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler U...
Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler U...IQPC Australia
 
Commissioning & Interface With Engineering
Commissioning & Interface With EngineeringCommissioning & Interface With Engineering
Commissioning & Interface With Engineeringasim569
 
Phần ii các bước thực hiện thi công piping cho dự án
Phần ii các bước thực hiện thi công piping cho dự ánPhần ii các bước thực hiện thi công piping cho dự án
Phần ii các bước thực hiện thi công piping cho dự ánNguyen Tung
 
Piping material-specification
Piping material-specificationPiping material-specification
Piping material-specificationChiragShah127
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionJaswin Sood
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.pptTecnicoItca
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 
Piping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikPiping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikMOHAMAD ANWAR MALIK
 

Was ist angesagt? (20)

Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Piping Design Course in Hyderabad
Piping Design Course in HyderabadPiping Design Course in Hyderabad
Piping Design Course in Hyderabad
 
Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3Process piping design & engineering per asme b 31.3
Process piping design & engineering per asme b 31.3
 
Front End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control TrainingFront End Engineering Design (FEED) Project Control Training
Front End Engineering Design (FEED) Project Control Training
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
Power Piping ASME Guide.PDF
Power Piping ASME Guide.PDFPower Piping ASME Guide.PDF
Power Piping ASME Guide.PDF
 
Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler U...
Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler U...Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler U...
Modularisation – The Next Step - Presentation by Bill Meyer, Foster Wheeler U...
 
Commissioning & Interface With Engineering
Commissioning & Interface With EngineeringCommissioning & Interface With Engineering
Commissioning & Interface With Engineering
 
Phần ii các bước thực hiện thi công piping cho dự án
Phần ii các bước thực hiện thi công piping cho dự ánPhần ii các bước thực hiện thi công piping cho dự án
Phần ii các bước thực hiện thi công piping cho dự án
 
Piping material-specification
Piping material-specificationPiping material-specification
Piping material-specification
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling rendition
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Piping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malikPiping supervisor Cv.mohamad anwar malik
Piping supervisor Cv.mohamad anwar malik
 

Ähnlich wie COE

Resume_Supply chain Specialist
Resume_Supply chain SpecialistResume_Supply chain Specialist
Resume_Supply chain SpecialistRahul Ramachandran
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendationsubk1411
 
Francisco Cortez Resume 2015
Francisco Cortez Resume 2015Francisco Cortez Resume 2015
Francisco Cortez Resume 2015Francisco Cortez
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectIRJET Journal
 
Construction Management Jump StartChapter 5Project Sta.docx
Construction Management Jump StartChapter 5Project Sta.docxConstruction Management Jump StartChapter 5Project Sta.docx
Construction Management Jump StartChapter 5Project Sta.docxmelvinjrobinson2199
 
glossary-of-construction-terms.pdf
glossary-of-construction-terms.pdfglossary-of-construction-terms.pdf
glossary-of-construction-terms.pdfCarlStevenAtencio
 
Pankaj Resume - Construction Project Manager
Pankaj Resume - Construction Project ManagerPankaj Resume - Construction Project Manager
Pankaj Resume - Construction Project ManagerPankaj Singh
 
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2Habibie Razak
 
Resume - Shibu Thomas rev
Resume - Shibu Thomas revResume - Shibu Thomas rev
Resume - Shibu Thomas revShibu Thomas
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Youssef Altaweel- Resume -05-07-2016-
Youssef Altaweel- Resume -05-07-2016-Youssef Altaweel- Resume -05-07-2016-
Youssef Altaweel- Resume -05-07-2016-Youssef Altaweel
 

Ähnlich wie COE (20)

Sr.Mech.Design Engr. 30.03.15
Sr.Mech.Design Engr. 30.03.15Sr.Mech.Design Engr. 30.03.15
Sr.Mech.Design Engr. 30.03.15
 
Pes profile
Pes profilePes profile
Pes profile
 
Resume_Supply chain Specialist
Resume_Supply chain SpecialistResume_Supply chain Specialist
Resume_Supply chain Specialist
 
SANTHOSH KUMAR UP RCV
SANTHOSH KUMAR UP RCVSANTHOSH KUMAR UP RCV
SANTHOSH KUMAR UP RCV
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
Francisco Cortez Resume 2015
Francisco Cortez Resume 2015Francisco Cortez Resume 2015
Francisco Cortez Resume 2015
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction Project
 
Construction Management Jump StartChapter 5Project Sta.docx
Construction Management Jump StartChapter 5Project Sta.docxConstruction Management Jump StartChapter 5Project Sta.docx
Construction Management Jump StartChapter 5Project Sta.docx
 
Diosdado CV (updated)(1)
Diosdado CV (updated)(1)Diosdado CV (updated)(1)
Diosdado CV (updated)(1)
 
glossary-of-construction-terms.pdf
glossary-of-construction-terms.pdfglossary-of-construction-terms.pdf
glossary-of-construction-terms.pdf
 
Zakir cv
Zakir cvZakir cv
Zakir cv
 
Zakir cv
Zakir cvZakir cv
Zakir cv
 
Zakir cv
Zakir cvZakir cv
Zakir cv
 
Pankaj Resume - Construction Project Manager
Pankaj Resume - Construction Project ManagerPankaj Resume - Construction Project Manager
Pankaj Resume - Construction Project Manager
 
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
 
Resume - Shibu Thomas rev
Resume - Shibu Thomas revResume - Shibu Thomas rev
Resume - Shibu Thomas rev
 
Construction process
Construction processConstruction process
Construction process
 
Vinay CV Arch
Vinay CV ArchVinay CV Arch
Vinay CV Arch
 
Youssef Altaweel- Resume -05-07-2016-
Youssef Altaweel- Resume -05-07-2016-Youssef Altaweel- Resume -05-07-2016-
Youssef Altaweel- Resume -05-07-2016-
 

Mehr von Muhammad Asim Shehzad (7)

Australian immigration process
Australian immigration processAustralian immigration process
Australian immigration process
 
NRL
NRLNRL
NRL
 
Mtbe (2)
Mtbe (2)Mtbe (2)
Mtbe (2)
 
EMT manual
EMT manualEMT manual
EMT manual
 
New procedures for Organizational development
New procedures for Organizational developmentNew procedures for Organizational development
New procedures for Organizational development
 
Wind Farm design and Construction
Wind Farm design and ConstructionWind Farm design and Construction
Wind Farm design and Construction
 
Abu parco
Abu parcoAbu parco
Abu parco
 

Kürzlich hochgeladen

Kurla Call Girls Pooja Nehwal📞 9892124323 ✅ Vashi Call Service Available Nea...
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅  Vashi Call Service Available Nea...Kurla Call Girls Pooja Nehwal📞 9892124323 ✅  Vashi Call Service Available Nea...
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅ Vashi Call Service Available Nea...Pooja Nehwal
 
Government polytechnic college-1.pptxabcd
Government polytechnic college-1.pptxabcdGovernment polytechnic college-1.pptxabcd
Government polytechnic college-1.pptxabcdshivubhavv
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130Suhani Kapoor
 
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call GirlsCBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girlsmodelanjalisharma4
 
Case Study of Hotel Taj Vivanta, Pune
Case Study of Hotel Taj Vivanta, PuneCase Study of Hotel Taj Vivanta, Pune
Case Study of Hotel Taj Vivanta, PuneLukeKholes
 
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Delhi Call girls
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsCharles Obaleagbon
 
Design Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptxDesign Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptxTusharBahuguna2
 
Fashion trends before and after covid.pptx
Fashion trends before and after covid.pptxFashion trends before and after covid.pptx
Fashion trends before and after covid.pptxVanshNarang19
 
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...babafaisel
 
Peaches App development presentation deck
Peaches App development presentation deckPeaches App development presentation deck
Peaches App development presentation decktbatkhuu1
 
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️soniya singh
 
DragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxDragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxmirandajeremy200221
 
Stark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptxStark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptxjeswinjees
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...Pooja Nehwal
 
VVIP Pune Call Girls Dange Chowk (8250192130) Pune Escorts Nearby with Comple...
VVIP Pune Call Girls Dange Chowk (8250192130) Pune Escorts Nearby with Comple...VVIP Pune Call Girls Dange Chowk (8250192130) Pune Escorts Nearby with Comple...
VVIP Pune Call Girls Dange Chowk (8250192130) Pune Escorts Nearby with Comple...Call Girls in Nagpur High Profile
 
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...BarusRa
 

Kürzlich hochgeladen (20)

Kurla Call Girls Pooja Nehwal📞 9892124323 ✅ Vashi Call Service Available Nea...
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅  Vashi Call Service Available Nea...Kurla Call Girls Pooja Nehwal📞 9892124323 ✅  Vashi Call Service Available Nea...
Kurla Call Girls Pooja Nehwal📞 9892124323 ✅ Vashi Call Service Available Nea...
 
Government polytechnic college-1.pptxabcd
Government polytechnic college-1.pptxabcdGovernment polytechnic college-1.pptxabcd
Government polytechnic college-1.pptxabcd
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
 
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call GirlsCBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
CBD Belapur Individual Call Girls In 08976425520 Panvel Only Genuine Call Girls
 
Case Study of Hotel Taj Vivanta, Pune
Case Study of Hotel Taj Vivanta, PuneCase Study of Hotel Taj Vivanta, Pune
Case Study of Hotel Taj Vivanta, Pune
 
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
Best VIP Call Girls Noida Sector 47 Call Me: 8448380779
 
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
young call girls in Vivek Vihar🔝 9953056974 🔝 Delhi escort Service
 
WAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past QuestionsWAEC Carpentry and Joinery Past Questions
WAEC Carpentry and Joinery Past Questions
 
Design Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptxDesign Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptx
 
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Mukherjee Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
Fashion trends before and after covid.pptx
Fashion trends before and after covid.pptxFashion trends before and after covid.pptx
Fashion trends before and after covid.pptx
 
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
Kala jadu for love marriage | Real amil baba | Famous amil baba | kala jadu n...
 
Peaches App development presentation deck
Peaches App development presentation deckPeaches App development presentation deck
Peaches App development presentation deck
 
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
 
DragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptxDragonBall PowerPoint Template for demo.pptx
DragonBall PowerPoint Template for demo.pptx
 
꧁❤ Hauz Khas Call Girls Service Hauz Khas Delhi ❤꧂ 9999965857 ☎️ Hard And Sex...
꧁❤ Hauz Khas Call Girls Service Hauz Khas Delhi ❤꧂ 9999965857 ☎️ Hard And Sex...꧁❤ Hauz Khas Call Girls Service Hauz Khas Delhi ❤꧂ 9999965857 ☎️ Hard And Sex...
꧁❤ Hauz Khas Call Girls Service Hauz Khas Delhi ❤꧂ 9999965857 ☎️ Hard And Sex...
 
Stark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptxStark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptx
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
 
VVIP Pune Call Girls Dange Chowk (8250192130) Pune Escorts Nearby with Comple...
VVIP Pune Call Girls Dange Chowk (8250192130) Pune Escorts Nearby with Comple...VVIP Pune Call Girls Dange Chowk (8250192130) Pune Escorts Nearby with Comple...
VVIP Pune Call Girls Dange Chowk (8250192130) Pune Escorts Nearby with Comple...
 
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...AMBER GRAIN EMBROIDERY | Growing folklore elements |  Root-based materials, w...
AMBER GRAIN EMBROIDERY | Growing folklore elements | Root-based materials, w...
 

COE

  • 1. Construction Oriented Engineering & Expectation From Others BY: M. Asim Shehzad
  • 2. Contents Constructability and Its Advantages Construction Oriented Engineering & Objectives Procurement Enabling Engineering Construction Enabling Engineering Expectations From Others
  • 3. Constructability Constructability is the optimum use of construction knowledge and experience in planning, design, procurement, and construction to achieve overall Project Objectives. OR Putting construction knowledge work early in project development and intertwining that construction knowledge throughout the conceptual, design and procurement phases to allow for the most efficient, practical and cost efficient construction techniques to be used. 3
  • 4. Basic Objectives Of Constructability Identify and define objectives to enhance the probability of a cost efficient, build able project. Identify the key engineering and procurement deliverables that will have the greatest bearing on the ability to construct the project  Identify where early construction input is needed. Identify construction related enhancements that can improve overall safety, quality, costs and schedule. Identify the major execution challenges. Transfer of constructability information to the next phases of the project.
  • 5. Key Constructability Issues 1.Schedule is Construction Sensitive. 2.Design is ‘simple’. 3.Design elements are standardized to take advantage of repetition. 4.Design Facilitate fabrication, transportation and installation. 5.Layouts are accessible to fabrication, installation and operation workers, material and equipment. 6.Effect of environmental conditions on construction is minimized. 7.Specifications simplify construction. 8. Accurate Construction estimates that reflect construction methods and strategies. 9.Early construction involvement is considered in developing plans and strategies.
  • 6. Typical functional Project constructability Organization Project Management Team Construction Manager Technical Manager Project Engineering Manager Project construction Manager Constructability Coordinator Construction Knowledge Resources Company wide Constructability Organization Discipline Lead Discipline Lead Construction Knowledge Resources Project Constructability Organization Discipline Lead
  • 7. Ability To Influence Cost High Project Duration Ability to Influence Cost Conceptual Engineering Preliminary Engineering Maximum benefits occur when people with construction knowledge and experience become involved early in the project Detailed Design Procurement Maximum Influence Period Construction Start Up Low Constructability
  • 8. Conclusion Constructability, if properly defined structured and used, will ensure that construction knowledge and experience is used as early as possible in the planning and design process to ensure design and implementation with plan practicality and cost effectiveness. Constructability is simply the utilization of construction knowledge, experience and efficiency into design and execution planning of the project components. Constructability issues touch on virtually all aspects of execution including safety, scheduling, detailed design, procurements, material/equipment delivery, contracting, temporary facilities/infrastructure needs, commissioning and the project management team organization.
  • 10. COE To execute Engineering work in such a way that enables Procurement and Construction stages. & Provide operational ease to comply with construction strategies.
  • 11. Objectives Of COE • Achieve Project Objectives-Meet The Construction Schedule • Right Design at Right Time • Avoid Changes & Rework • Comprehensive Design With Minimum Objections From Client • Complete & Clear Design – Constructible & Build able • Material Proposed Is Suitable • Available In Market • Economical To Work With • E is well integrated with P and C Work Processes
  • 12. EPC Engineering Sequence Studies OM cost estimate Basic Engineering Criteria & Specs MTO Estimate Purchase Requisition Calculations Detailed Engineering  Definitive Design /Estimate Issue “Engineering “Deliverables” to construction Field Changes Produce “As-Built” Project -Close out
  • 13. EPC Procurement Sequence Develop Bidders Lists Purchase Order Pro-Forma Contracts Pro-Forma Transportation & Logistics. Specifications (Engg.) Quantities (Engg.) Solicit / Evaluate Bids Award P.O. /Contracts Shop Inspections Track Status Expediting Transport & Receive Warehouse Maintain Release to Construction
  • 14. EPC Construction Sequence General Construction Plan Site Layout Plan Temporary Facilities Geo-Tech Mass Earth-Work Structural Concrete Structural Steel Equipment (mech. & elect.) Piping Raceway Instrumentation & Control Note: Construction is supported by field Engineers. System Turn-over Start –Up & Commissioning Performance Run Turn-Over to end -user
  • 15. Sequential to Concurrent Execution Jan Feb Mar April May June July Aug Sep Oct Nov Dec SEQUENCTIAL ENGINEERING PROCUREMENT CONSTRUCTION CONCURRENT ENGINEERING PROCUREMENT CONSTRUCTION
  • 16. Concurrent Design Components Engineering is concurrently integrated with Procurement & Construction: Jan Feb Mar April May June July Aug Sep Oct Nov ENGINEERING Bill of Quantity 1 Bill of Quantity 2 Drawings1 Drawings2 PROCUREMENT Vendor Info1 Vendor Info2 CONSTRUCTION 16 Dec
  • 17. Concurrent Design Components Effect of any delay would squeeze construction time or require an EOT: Jan Feb Mar April May June July ENGINEERING Bill of Quantity 1 Aug Sep Oct Nov Dec Delay Bill of Quantity 2 Drawings 1 PROCUREMENT Delay Vendor Info1 Drawings 2 Vendor Info2 Vendor Info2 CONSTRUCTION 17 Construction Squeezed
  • 18. Construction & Project Success  Construction is a downstream activity  E &P success is generally measured in terms of construction  Construction is intact if E & P components are construction oriented ENGINEERING PROCUREMENT CONSTRUCTION
  • 19. Impact Of Variables Over Time Stack Holder Influence, Uncertainty and Risk MAX Impact Cost of Changes MIN 0 Engineering Project Procurement Progress Construction Project MAX 10 0 30 10 30 0 60 80 70 3 95 95 10 100% 100% 50 80 95 100% Schedule Control Sensibility Cost Control MIN MAXIMUM CONTROL LIES IN THIS AREA TROUBLE SHOOTING
  • 20. Critical Engineering Phases Jan Feb Mar April May June July Aug Sep Oct Nov Dec ENGINEERING Initial MTO Final MTO Procurement Enabling Engineering PROCUREMENT Construction Enabling Engineering Const’n Dwgs IFC with HOLD IFC CONSTRUCTION Early Procurement Enabling Engg Early Construction Enabling Engg.
  • 22. Procurement Enabling Engineering ENGINEERING Engineering Specialized Equip Data sheet Mech Equip data Sheets MTO’s Piping & Bulk MCC & Panels details . PROCUREMENT Procurement Specialized Equip Order Construction Mech Equip Order MCC Panels Order CONSTRUCTION . . Quantities Decided . . 22 Specialized Equip Erection Piping Work Construction Material Acquired MCC Building Construction
  • 23. Procurement Enabling Engineering Early Procurement Enabling Phase Long lead items have to be ordered early. All equipment and packages & bulk materials to be purchased soon as their technical definition allows. The earlier the PO’s are placed, sooner the vendor information available for DE with vendors. Challenges: Integration of technical information with vendors.
  • 24. Procurement Enabling Engineering o Mechanical Equipment o Bulk Materials o Piping & Fittings o Steel Structure o E&I Bulk o E&I Related Procurements o MCC Buildings
  • 25. Mechanical Equipments Main Process Equipment Rotating Equipment Package Fire Equipment Equipment Major Tasks are:       Determination of Capacities Early release of RFQ’s & TBE’s Long Delivery Time (Dictate project schedule) Functional Requirement & Standard Packages Economy & Operational Spares Vendor shop load & Management Pressure Vessels Heat Exchanger
  • 26. Equipment RFQ’s / TBE’s Approval Cycle Vendor Management RFQ PFD’s P&ID’ s Heat & Mass Balance Client Review •Data Sheets •Function Specification of main package •Process Philosophy Documents •Process Descriptions •Operation Philosophy •ESD Philosophy •Depressurization Philosophy OK P.O Issued Not OK Vendor Data Vendor Shop Load Deliveries Challenges:  Coordination & Approval Cycle (RFQ’s & TBE’s)  Specs, Budget & Decision making  Vendor Data (GA’s, Connection details and Loads) 26
  • 27. Piping Bulk Piping covers major portion of construction work that is linked with pre-com and commissioning works. Major concerns are: Material delivery time, Fabrication, Erection, Testing and Painting / Insulation Accuracy level of MTO’s and Reordering duration Piping material specs, availability and economy Purchase terms (type of order) Flaw less Material Management and Control
  • 28. MTO’s Estimate MTO Estimate stage take off i.e. drawing numbers is not known yet, may be done via flow diagrams, plot plans, equipment lists, sketches etc. Bulk MTO Materials can be identified to a specific drawing/line number. However, Drawings are unchecked . Changes may still occur in design. Material requirements will change. However, It has detailed info, so initial purchase can be done i.e. above 4” main pipes. Final MTO As the project design finalizes, final stage takeoff is performed , and final drawings are issued as “IFC’s” .
  • 29. MTO Stages MTO Stages Manual Designing 3D Modeling Other Modeling Info Accuracy 1st •Plot plan •P&ID’s Plot plan •P&ID’s •Equipment Location and orientation •Pipe racks, •Major piping •operational access •Escape routes •Main E&I cable trays/trenches •Underground sewer stem 70% 2nd 3rd •Piping Layout Plan •P&ID’s IFC ISO’s 60% Model Review 90% Model Review •Major Piping (upto 2” dia) including control valves •Major access ways, ladder, & platforms •Secondary steelworks and bracings •Pipe supports location and types •Local control panels •Fire fighting equipments •Instrument transmitters and outline of junction boxes •Access ways, ladder, platforms •All Piping, •All offline instruments •Issuance of Drawing 85% 95-100%
  • 30. Material Management & Control Material management should start by importing the Material Requirements (BOM or MTO) from the design system (PDMS, PDS, CAD Works etc) . Objectives: Tracking changes to the requirements as the design progresses. Generation of inquiries and purchase orders for materials. Expediting and recording material deliveries. Control of material deliveries. Control of material issues and movements. Inventory/Stock control management. Management of material traceability. Progress monitoring
  • 31. Steel Structure Steel structure design drawings for Pipe racks and steel structures indicating the sizes of profiles & dimensions. Required for critical structures like pipe rack. Commercial viability & availability of profiles. Delivery and fabrication time.
  • 32. E&I Related Procurements  MCC, Power Gen, Switch Gear & UPS, Transformers  Cables 3 AFE  JB’s (Classified) Converter Basic Unit  Control System Motor  Control Valves  MCC Building 3 Inverter
  • 33. Critical E&I Related Procurement MCC Switch Gear,Power Gen, Transformer, UPS, MCC Building: EPC Engineering Vendor Package Management Building Design Power Producer Consumer List Load List Vendor Packages Piping Layout Main Cable Routing MCC Switch Gear / Vendor HV Substation Panel Layout MV LV Transformer Vendor Civil Architectural Drawings Equipment Arrangement Drawings MCC Building Design UPS Vendor Cable Entry Locations Soil Investigation Report
  • 34. Building detailed design The EPC Engineers , define building needs and produce guide drawings as mentioned below and outsource detail design. Architectural drawings, showing all dimensions of the buildings (building housing machinery, E&I for technical rooms etc). Equipment dimensions and weight, for the design of supporting floors. Equipment access requirements (size of doors, handling). Building blast resistance requirement. Cable entry requirements: raised/false floor, floor openings. Climate requirements (temperature etc), and equipment heat dissipation. Fire & Gas detectors and equipment layout. Telecom equipment layout (LAN etc.). Tie-in points for connection of the building to the PLANT’s utilities. Other Vendors Involved are: HVAC Vendor does the detailed HVAC design (equipment selection, flow diagram, ductwork routing). Fire & Gas Design. Telecom cable routing. Lighting and small power Design . All the above entail an extensive co-ordination among all these trades , to avoid interferences.
  • 35. Critical E&I Related Procurement Extensive Coordination between Disciplines, Vendors , Clients and Construction. Finalization of Consumer List.  Finalization of MCC Switch Gear. Economy of the Package. Vendor Data for finalization of MCC Building Design. Challenges: MCC Building Construction is on Critical Path, dependent on coordination among multiple parties and its delay could impact the Pre-Commissioning.
  • 36. Cable, JB’s (Classified) Cables: Main Cable Routing Cable MTO (HV ,MV ,LV) Equipment Layout JB’s (Classified): Larger Delivery Period. Challenges: Accuracy of Schedule(Cable Drums) Early Ordering Economy
  • 37. Control Valves & Control System Control Valves: •Process Data Sheets •Hydraulic Studies(line sizing) •Flow Conditions Data Sheets for Motorized Valves Control System: •Specifications •I / O Counts •System Architectural Drawings DCS ESD F&G Challenges: Generally Long Lead Coordination With Vendor Economy
  • 39. Construction Enabling Engineering ENGINEERING Engineering Foundation Drawings Pipe Rack Civil Work Steel Structure Drawings Building Detailed Drawings Procurement Under Ground Facilities ISO’s Tanks CP Plates PROCUREMENT CONSTRUCTION Construction Foundation Construction Pipe Rack Construction & erection Steel Structure erection 39 Construction of Building Mech Piping work Under Ground Facilities Construction Tanks CP Plates constrction
  • 40. Construction Enabling Engineering Early Construction Enabling Phase Initiating early construction activities Integrating information from vendors to detail engineering. Must issue IFC design with a provision of time to construction for shop drawing An economical and constructible design. Challenges: engineering development is highly dependent on information from vendors. Earlier activities are in fact designed at the end delays will typically result in idle manpower and equipment, lack of work front, low productivity, impact on critical path
  • 41. EPC Interfaces & Integration Const,n Phase Phase 1 Phase 2 Phase 3 Award Eng’g Completed Early Procurements Early Construction P&ID, Plot Piping Layout Engineering REQ Procurement Const 90% Completion MTO/Const Dwg FDN Dwg Vendor Docs Equipment/Bulk Material P.O Main EQ PO LLI Vendor Dwg Fabrication Jig/Anchor Bolt Catalyst/Chemical Main Delivered Construction Site Development & Pre commissioning & Temp Work. Engineering Project Progress Procurement Construction Project 0 10 0 Comm’g Completed Final Const DWG 30 10 60 30 80 70 0 3 10 Schedule Control MIN Cost Control 41 95 100% 95 MAX Sensibility Start-Up FDN Start 100% 50 80 95 100%
  • 42. 60 70 80 90 100 Critical Path Of A Typical Project 75 % Piping Material Delivered IFC Plot Plan & P&IDs 50% Equipment Ordered Piping PreFabrication Piping Erection Engineering 30 40 50 Progress % 50 % ISO’s a Mechanical Completion Equipment Erection 10 20 B 0 Time (as % of Project Duration) 0 10 20 Design Office Building Period 30 40 Design Office Peak Period a=Design office peak 50 60 Piping Construction Build-up Material Period 70 80 Piping Erection Peak Period 90 100 Piping Completion B=Piping erection peak
  • 43. Construction Enabling Engineering • Foundations • Pipe Rack Construction • Piping Work • Underground Facilities • Tank Construction • Road Crossing • MCC Building
  • 44. Foundations Engineering is the integrator of the equipment vendor data & foundation design Critical Foundations are Pipe Rack Foundations Major Equipment Foundations Process simulations Equipment list & duty Equipment Inquiry & Selection Vendor Engineering Vendor Data & Drawing Getting the design input early Foundation Drawing
  • 45. Pipe Rack Construction Pipe-rack construction is the predecessor of piping, mechanical installations and E&I works. Consequently optimizing this resource intensive activity will lead to smooth and shorter project duration. Construction management team to develop proactive strategies and alternate solutions to optimize resources for pipe rack construction and installation works.
  • 46. Pipe Rack Construction Drawings are issued with sizing of members with consideration of material delivery time and shop fabrication drawings. For pre-fabrication structure, the supplier will produce all shop drawings and erection details. In case of pre-fabrication structure a coordination is required to finalize rack foundation 46
  • 47. Piping Construction Piping is a critical activity, so issuance of piping ISO’s is crucial. Construction require further time to translate design ISO’s into spooling drawings. Additionally, effective installation of piping will require availability of pipe supports. Challenges: Work Front in the start is less w.r.t. available ISO’s and Material Frequent changes as the design is not freeze in the beginning Manufacturing support in a bulk is a production challenge
  • 48. Piping Work Green Const,n Phase Piping ISO’s 50%ISO’s Yellow Final ISO’s Pipe Supports 75% Piping Material delivered 30% Equipment Arrived Procurement (Piping) Construction Red 100% Material 100% Equipment MC Re-Order Spooling Drawing (Piping) Pipe Supports Fabrication 30% Fabrication Mechanical Completion Pre-Com Pipe Fabrication COM U/G Must Complete Pipe Erection Pre-Com Start 3D Modeling 3D Modeling Isometrics Major Activities 4” above piping on racks & sleepers Early Pre-Comm – Golden Joints Spooling Drawings U/G piping Must Finish Spooling Drawings Stress Analysis Small bore field piping must start Stress Analysis Stress Analysis Blast Studies Conflict Resolution Blast Studies Blast Studies As built modifications 48 Isometrics 3D Modeling Isometrics Spooling Drawings
  • 49. Underground Facilities Underground networks are major cause of delay in construction activities. All underground networks such as drainage, sewage pipes with associated pits, pipe support foundations, cable trenches in paved areas, inspection pits, gutters and oil water pits etc.
  • 50. Underground Facilities Civil Works Installation drawings complete with all underground objects and networks, are required very early, as its pre-requisite for mechanical works to proceed. Plant erection cannot proceed for lack of access until underground facilities are installed and area is backfilled. Installation on pipe-rack and structural works cannot proceed until all undergrounds are laid and the cranes have access. 50
  • 51. Tanks CP & Construction Civil Foundation Soil Reactivity Test CP Design & Approvals Work Order & CP-Materials Tank Design and MTO Tank Plates Delivery Plate Rolling & Fabrication Tank Welding & Erection Clean Doors, Nozzles, VBT & Hydro testing Sand Blasting & Painting Insulation & Cladding Box-Up 51
  • 52. Tanks Construction Challenges Challenges: Early Vendor Selection & Issuance of WO Material Procurement A series of long & Interdependent Activities Involvement & Interdependencies of Multiple Parties Stringent QC Requirements Qualified Manpower Dependency Congested Surrounding Access Changes Cause Resource Idling High Risk Job Any Rework Involve Huge Volume of Work 52
  • 53. MCC Building Construction Soil Investigation Substation Layout Excavation Lean Concrete Detailed Building Erection Mechanical Installation of Equipment Earth Mesh Connections Equipment Testing Cable Laying Cable Continuity Check  Cable Termination Testing & Pre-commissioning Challenges: Late finalization of building design Long list of activities and finishing details Its start is dependent on design parameters and end is driving the pre-com activities.
  • 55. Integrating Construction Integrate the work processes Develop Engineering/Construction Strategies Constructability reviews Pre-fabrication Engineering schedule to match construction priorities/sequences Engineering deliverables tailored to construction execution needs.
  • 56. Changes Avoid Changes Sources of changes Inherited/Open technical issues Design development & reviews Client’s new requirements 3rd party at interface Avoidable/ Unavoidable ? Resist avoidable changes-Contractual management Impact of changes is exponential with time: implement early! System to identify all impacts and track implementation of changes.
  • 57. Expectations A cohesive participation of stack holders internal interface management.
  • 58. Inter-Functional Coordination Project Control CPM Schedule Budget Trends Interface / Data exchange Procurement Engineering Specifications Quantities Material Requisitions Design Drawings Purchase Order Work Orders Transportation & Logistics Ex-Works/ Inspection Expediting Receiving / Releasing Construction Constructability Construction Planning Resource-Planning
  • 59. Other Expectations Plan must be based on Up-to date BOQ quantities to plan adequate resources Visibility of actual progress against the up-dated work volumes( Let 100%" keep changing till end)  Precisely Engineering monitoring and indisputably identified. Earned progress must be supported with milestone e.g. PO issued for a non-due and non LLI could show wrong status. Vendor info must be monitored for all equipments and packages for further development of detailed engineering. Piping MTO’s status must be monitored in actual figures. Engineering issued and actual executed quantities must be monitored as well. The biggest constraint is out-of-sequence issues: engineering may have issued drawings with generating work (such as lack of access or prerequisite for another work).
  • 60. On Behalf of Construction Management LOGO