SLIDE NUMBER: 1
Project Name : Vidhansabha Remaining works
Presented By : MohitMadhav Planning&monitoring
Head
Client : BCD-2
SLIDE NUMBER: 2
Project Code :2023
Month : June’2015 DIV / REGION : Water Division
Project HSE Statistics
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 36
Project Code :
N A
ADD ADDITIONAL SLIDES IF NECESSARY
SLIDE NUMBER: 4
Previous Month’s Guidance & POA
S. No. Plan of Action / Guidance Due Date Action Taken
1 GRC elements B-2 and B-4 Completed.
2 False ceiling 15.07.15
Ground floor North wing
Rooms completed (Board,
putty) as for front available.
3 Sanitary fixers Fixing completed at B-4
4 Aluminum Partitions
Full height & Half height
partitions completed at B-4
5 Expansion joint 15.07.15
Vidhansabha Ground floor
completed. First floor is
under progress
6 Trench
400 Rmt work is under
progress
7 STP
Excavation upto 5.5 mt done
de watering under progress
7
Flooring, Wall tiles and floor
tiles
15.07.15
North wing GF Completed.
Vid. And South wing under
progress.
Project Code :
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 5
Previous Months Critical Issues & Key Requirements
Critical Issues Action Taken
STP Dewatering Non BOQ Item Client is to be approved
Trench Front availability VID Front portion to Be cleared
False ceiling
No front availability for boards fixing. North
wing rooms completed
Wall tiles and floor tiles
North wing Ground floor toilets completed,
South wing Ground floor toilet is in progress
and Center wing toilets not available.
Wall paneling No front availability at VID.
Electrical Fixtures No front availability at VID.
Key Requirements Action Taken
SS Hand railing Material as dispatched with in couple of days
6mm double Glass
Work under progress at North wing. South
and center wing front not available.
Project Code :
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 6
Original Contract Value 61.81 cr.
Revised Contract Value NA
Project Duration (Months) 12 months
Contractual Start Date 23-01-14
Actual Start Date 15-02-14
Contractual End Date 22-01-15
Probable Date Of Completion 6 months
E.O.T. Submitted Up To 30th
June-15
E.O.T. Granted Up To 30th
June-15
Project Data
Project Code :
Targeted For the Project (Since Inception) – As Per Annual Budget 32.65 cr
Targeted For the Project (Since Inception) – As Per Revised
Must Do Work For the Project (Since Inception) – As Per Contractual
Schedule
Value of Work Completed (Since Inception) 3.01Cr
% Work Completed Against As Per Annual Budget (Since Inception) 9.24%
Balance Value of the Work (Closing Order Book) 29.63 cr
Work Front available (Live Order Book) 28.00cr
Time Lapsed
% Time Lapsed (As Per EOT Granted)
Balance Time Left
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 6
Over All Project Progress
Project Code :
Particulars Values
Cumulative Target in this Financial Year Till Date
(As Per ABP)
32.65 cr
Completion in this Financial Year till date 3.01cr
% Completion this Financial Year 9.24%
Shortfall in this Financial Year Till Date 29.63cr
Reasons for Variance Due to Environmental clearance and No front availability
Initial Delay NA
Sub Contractor Execution delays NA
Fund Constraints NA
Procurement Delays
80% items are from out of country (Sky light, Fire doors,
Glass Bricks , Electrical Fixtures Etc..)
Manpower Constraints Due to festival and cropping and summer season
Work Front Delays False ceiling , AV & Trench, Wall paneling
Other Delays (Please Specify) Sufficient front available in vidhansabha.
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 7
Project Performance in this Financial Year
Project Code :
Major Activities
Value of Work
Schedule
Value of Work
Completed
Shortfalls
(Values)
Reasons / Remarks
6mm and 6mm double glass 1.00cr 0.13cr
Work under progress
GRC Elements 1.65cr 0.76cr
Sky light 0.67cr 0.09cr
Flooring 3.69cr 1.17cr
Water proofing 0.99cr 0.29cr
Expansion joint 4.30cr 0.88cr
Trench 2.01cr 0.29cr
False ceiling 2.57cr 0.15cr
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 8
Project Performance – This Month
Project Code :
Cash Flows
Projected for the
Month
(As Per ABP)
Actual – for
the Month
Projected Till
Date
(As Per ABP)
Actual – Till
Date
Cash In Flow - - -
Cash Out Flow - - -
Net Cash Flow - - -
Fund
Support
Fund Based - -
Non - Fund Based
(Peak Limits
Utilized)
- - -
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 12
Cash Flows
Project Code :
Staff Nos Available
Additional Numbers
Required
Technical Staff
Engineers 02 -
Supervisors 01 -
Non Technical Staff
F & A 01 -
Stores 01 -
Safety 0 -
HR & Admin 0 -
N.M.R 0 -
Total
Specify Requirement If any
Tech Staff -
Non Tech & Supervisor -
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 26
Staff at Site
Project Code :
Particulars Nos Available
Additional Numbers
Required
Skilled Workers
Plumber 02
Al. partitions 15
Flooring 15
GRC 5
Sloped proof treatment work 15
False ceiling 10
Trench 20
Dewatering 2
Total ( Per Day) 84
ADD ADDITIONAL SLIDES IF NECESSARY
SLIDE NUMBER: 27
Manpower at Site
Project Code :
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 35
Critical Issues Plan Of Actions Responsibility
Any Specific Requirements / Complaints / Comments
from Client
Action Taken
 
Critical Issues & Client Feed Back
Project Code :
Major Activities Planned
Value of Work As Per Latest Schedule
(Annual Budget)
Value of Work Now Targeted
(PEP)
SS Railing 0.20Cr
Flooring 0.51 cr
Water proofing 0.47 cr
Excavation 0.067cr
Steel 0.30cr
False ceiling 0.13 cr
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 37
Look Ahead for Next Month
Project Code :
Target for Next Month Values (In Lakhs)
Targeted Achievement 4.00 cr
Targeted Billing 3.5 cr
Targeted Collections (Cash Inflow)
Projected Cash Outflow -
Fund Based Requirement -
Non - Fund Based Requirement -
ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 38
Look Ahead Targets
Project Code :
ADD ADDITIONAL SLIDES IF NECESSARY
SLIDE NUMBER: 16

Weitere ähnliche Inhalte

Was ist angesagt?

Profile Pathways Constructions.
Profile Pathways Constructions.Profile Pathways Constructions.
Profile Pathways Constructions.Pankaj Kumar
 
Mega kuningan office tower for investor
Mega kuningan office tower for investorMega kuningan office tower for investor
Mega kuningan office tower for investorAditya Tumbuan
 
مهندس ميكانيكا دراسات
مهندس ميكانيكا دراساتمهندس ميكانيكا دراسات
مهندس ميكانيكا دراساتAbd Ellatif Gebril
 
SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE Project
 
Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosPraveen Malik, PMP
 
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit FeesAlamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Feesahcitycouncil
 
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasCalculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasPraveen Malik, PMP
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev ehesands2437
 
Dealing with construction permits in malaysia doing business - world bank g...
Dealing with construction permits in malaysia   doing business - world bank g...Dealing with construction permits in malaysia   doing business - world bank g...
Dealing with construction permits in malaysia doing business - world bank g...Jaclyn Hwang
 
Project status one page
Project status one pageProject status one page
Project status one pageBim Akinfenwa
 
Speed To Market_Office_ROI
Speed To Market_Office_ROISpeed To Market_Office_ROI
Speed To Market_Office_ROIAustin Berke
 
Monthly Progress Report-October, 201511
Monthly Progress Report-October, 201511Monthly Progress Report-October, 201511
Monthly Progress Report-October, 201511Elias Ibrahim
 
E2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsE2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsAnatoly Ryabukha
 
Scheduling of “R” Shaped Residential Building
Scheduling of “R” Shaped Residential BuildingScheduling of “R” Shaped Residential Building
Scheduling of “R” Shaped Residential BuildingDES Engineers Ltd
 

Was ist angesagt? (19)

Profile Pathways Constructions.
Profile Pathways Constructions.Profile Pathways Constructions.
Profile Pathways Constructions.
 
Mega kuningan office tower for investor
Mega kuningan office tower for investorMega kuningan office tower for investor
Mega kuningan office tower for investor
 
مهندس ميكانيكا دراسات
مهندس ميكانيكا دراساتمهندس ميكانيكا دراسات
مهندس ميكانيكا دراسات
 
SLOPE intro we have a new project!
SLOPE intro we have a new project!SLOPE intro we have a new project!
SLOPE intro we have a new project!
 
Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different Scenarios
 
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit FeesAlamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
Alamo Heights Council Meeting 06.10.19 - Item #4 Permit Fees
 
civil designer
civil designercivil designer
civil designer
 
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasCalculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev eh
 
Dealing with construction permits in malaysia doing business - world bank g...
Dealing with construction permits in malaysia   doing business - world bank g...Dealing with construction permits in malaysia   doing business - world bank g...
Dealing with construction permits in malaysia doing business - world bank g...
 
Project status one page
Project status one pageProject status one page
Project status one page
 
Speed To Market_Office_ROI
Speed To Market_Office_ROISpeed To Market_Office_ROI
Speed To Market_Office_ROI
 
Monthly Progress Report-October, 201511
Monthly Progress Report-October, 201511Monthly Progress Report-October, 201511
Monthly Progress Report-October, 201511
 
Tippo International
Tippo InternationalTippo International
Tippo International
 
E2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsE2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costs
 
محمد جمال
محمد جمالمحمد جمال
محمد جمال
 
Monthly Cost Report May 15
Monthly Cost Report May 15Monthly Cost Report May 15
Monthly Cost Report May 15
 
Tippo International
Tippo InternationalTippo International
Tippo International
 
Scheduling of “R” Shaped Residential Building
Scheduling of “R” Shaped Residential BuildingScheduling of “R” Shaped Residential Building
Scheduling of “R” Shaped Residential Building
 

Ähnlich wie june'15

Detailed Project Status Report Template
Detailed Project Status Report TemplateDetailed Project Status Report Template
Detailed Project Status Report TemplateTechno-PM PTY LTD
 
How The City of San Antonio Increased Payments For Street Maintenance Using L...
How The City of San Antonio Increased Payments For Street Maintenance Using L...How The City of San Antonio Increased Payments For Street Maintenance Using L...
How The City of San Antonio Increased Payments For Street Maintenance Using L...GoLeanSixSigma.com
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...Скоробогатов Дмитрий
 
Project monitoring and monitoring tools
Project monitoring and monitoring toolsProject monitoring and monitoring tools
Project monitoring and monitoring toolsJed Abolencia
 
Project Status Sample
Project Status SampleProject Status Sample
Project Status Samplessuser9f52a61
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdfapoorvaguptaspn27
 
Chapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdfChapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdfFREDERICKOKPAISE
 
T0352 - Al Wajba presentation for the Construction Sequence
T0352 - Al Wajba presentation for the Construction SequenceT0352 - Al Wajba presentation for the Construction Sequence
T0352 - Al Wajba presentation for the Construction Sequencechethanshivram
 
Q2 Review[16061].pptx
Q2 Review[16061].pptxQ2 Review[16061].pptx
Q2 Review[16061].pptxSowmyaKB6
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management PlanAnuragBhat7
 

Ähnlich wie june'15 (20)

Detailed Project Status Report Template
Detailed Project Status Report TemplateDetailed Project Status Report Template
Detailed Project Status Report Template
 
How The City of San Antonio Increased Payments For Street Maintenance Using L...
How The City of San Antonio Increased Payments For Street Maintenance Using L...How The City of San Antonio Increased Payments For Street Maintenance Using L...
How The City of San Antonio Increased Payments For Street Maintenance Using L...
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
Project monitoring and monitoring tools
Project monitoring and monitoring toolsProject monitoring and monitoring tools
Project monitoring and monitoring tools
 
JDE Projects Month End Course - Work Orders
JDE Projects Month End Course - Work OrdersJDE Projects Month End Course - Work Orders
JDE Projects Month End Course - Work Orders
 
Quality application
Quality applicationQuality application
Quality application
 
DZ04-Program narrative_R1
DZ04-Program narrative_R1DZ04-Program narrative_R1
DZ04-Program narrative_R1
 
Project HSE Progress .pptx
Project HSE  Progress  .pptxProject HSE  Progress  .pptx
Project HSE Progress .pptx
 
Project Status Sample
Project Status SampleProject Status Sample
Project Status Sample
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
 
Chapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdfChapter 1 Introduction and Bar Charts.pdf
Chapter 1 Introduction and Bar Charts.pdf
 
TEAM LEADERSHIP
TEAM LEADERSHIPTEAM LEADERSHIP
TEAM LEADERSHIP
 
T0352 - Al Wajba presentation for the Construction Sequence
T0352 - Al Wajba presentation for the Construction SequenceT0352 - Al Wajba presentation for the Construction Sequence
T0352 - Al Wajba presentation for the Construction Sequence
 
PPT_Final_18-02-15
PPT_Final_18-02-15PPT_Final_18-02-15
PPT_Final_18-02-15
 
Q2 Review[16061].pptx
Q2 Review[16061].pptxQ2 Review[16061].pptx
Q2 Review[16061].pptx
 
Arrow Consulting PMP
Arrow Consulting PMPArrow Consulting PMP
Arrow Consulting PMP
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management Plan
 

june'15

  • 2. Project Name : Vidhansabha Remaining works Presented By : MohitMadhav Planning&monitoring Head Client : BCD-2 SLIDE NUMBER: 2 Project Code :2023 Month : June’2015 DIV / REGION : Water Division
  • 3. Project HSE Statistics ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 36 Project Code : N A
  • 4. ADD ADDITIONAL SLIDES IF NECESSARY SLIDE NUMBER: 4 Previous Month’s Guidance & POA S. No. Plan of Action / Guidance Due Date Action Taken 1 GRC elements B-2 and B-4 Completed. 2 False ceiling 15.07.15 Ground floor North wing Rooms completed (Board, putty) as for front available. 3 Sanitary fixers Fixing completed at B-4 4 Aluminum Partitions Full height & Half height partitions completed at B-4 5 Expansion joint 15.07.15 Vidhansabha Ground floor completed. First floor is under progress 6 Trench 400 Rmt work is under progress 7 STP Excavation upto 5.5 mt done de watering under progress 7 Flooring, Wall tiles and floor tiles 15.07.15 North wing GF Completed. Vid. And South wing under progress. Project Code :
  • 5. ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 5 Previous Months Critical Issues & Key Requirements Critical Issues Action Taken STP Dewatering Non BOQ Item Client is to be approved Trench Front availability VID Front portion to Be cleared False ceiling No front availability for boards fixing. North wing rooms completed Wall tiles and floor tiles North wing Ground floor toilets completed, South wing Ground floor toilet is in progress and Center wing toilets not available. Wall paneling No front availability at VID. Electrical Fixtures No front availability at VID. Key Requirements Action Taken SS Hand railing Material as dispatched with in couple of days 6mm double Glass Work under progress at North wing. South and center wing front not available. Project Code :
  • 6. ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 6 Original Contract Value 61.81 cr. Revised Contract Value NA Project Duration (Months) 12 months Contractual Start Date 23-01-14 Actual Start Date 15-02-14 Contractual End Date 22-01-15 Probable Date Of Completion 6 months E.O.T. Submitted Up To 30th June-15 E.O.T. Granted Up To 30th June-15 Project Data Project Code :
  • 7. Targeted For the Project (Since Inception) – As Per Annual Budget 32.65 cr Targeted For the Project (Since Inception) – As Per Revised Must Do Work For the Project (Since Inception) – As Per Contractual Schedule Value of Work Completed (Since Inception) 3.01Cr % Work Completed Against As Per Annual Budget (Since Inception) 9.24% Balance Value of the Work (Closing Order Book) 29.63 cr Work Front available (Live Order Book) 28.00cr Time Lapsed % Time Lapsed (As Per EOT Granted) Balance Time Left ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 6 Over All Project Progress Project Code :
  • 8. Particulars Values Cumulative Target in this Financial Year Till Date (As Per ABP) 32.65 cr Completion in this Financial Year till date 3.01cr % Completion this Financial Year 9.24% Shortfall in this Financial Year Till Date 29.63cr Reasons for Variance Due to Environmental clearance and No front availability Initial Delay NA Sub Contractor Execution delays NA Fund Constraints NA Procurement Delays 80% items are from out of country (Sky light, Fire doors, Glass Bricks , Electrical Fixtures Etc..) Manpower Constraints Due to festival and cropping and summer season Work Front Delays False ceiling , AV & Trench, Wall paneling Other Delays (Please Specify) Sufficient front available in vidhansabha. ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 7 Project Performance in this Financial Year Project Code :
  • 9. Major Activities Value of Work Schedule Value of Work Completed Shortfalls (Values) Reasons / Remarks 6mm and 6mm double glass 1.00cr 0.13cr Work under progress GRC Elements 1.65cr 0.76cr Sky light 0.67cr 0.09cr Flooring 3.69cr 1.17cr Water proofing 0.99cr 0.29cr Expansion joint 4.30cr 0.88cr Trench 2.01cr 0.29cr False ceiling 2.57cr 0.15cr ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 8 Project Performance – This Month Project Code :
  • 10. Cash Flows Projected for the Month (As Per ABP) Actual – for the Month Projected Till Date (As Per ABP) Actual – Till Date Cash In Flow - - - Cash Out Flow - - - Net Cash Flow - - - Fund Support Fund Based - - Non - Fund Based (Peak Limits Utilized) - - - ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 12 Cash Flows Project Code :
  • 11. Staff Nos Available Additional Numbers Required Technical Staff Engineers 02 - Supervisors 01 - Non Technical Staff F & A 01 - Stores 01 - Safety 0 - HR & Admin 0 - N.M.R 0 - Total Specify Requirement If any Tech Staff - Non Tech & Supervisor - ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 26 Staff at Site Project Code :
  • 12. Particulars Nos Available Additional Numbers Required Skilled Workers Plumber 02 Al. partitions 15 Flooring 15 GRC 5 Sloped proof treatment work 15 False ceiling 10 Trench 20 Dewatering 2 Total ( Per Day) 84 ADD ADDITIONAL SLIDES IF NECESSARY SLIDE NUMBER: 27 Manpower at Site Project Code :
  • 13. ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 35 Critical Issues Plan Of Actions Responsibility Any Specific Requirements / Complaints / Comments from Client Action Taken   Critical Issues & Client Feed Back Project Code :
  • 14. Major Activities Planned Value of Work As Per Latest Schedule (Annual Budget) Value of Work Now Targeted (PEP) SS Railing 0.20Cr Flooring 0.51 cr Water proofing 0.47 cr Excavation 0.067cr Steel 0.30cr False ceiling 0.13 cr ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 37 Look Ahead for Next Month Project Code :
  • 15. Target for Next Month Values (In Lakhs) Targeted Achievement 4.00 cr Targeted Billing 3.5 cr Targeted Collections (Cash Inflow) Projected Cash Outflow - Fund Based Requirement - Non - Fund Based Requirement - ADD ADDITIONAL SLIDES IF NECESSARYSLIDE NUMBER: 38 Look Ahead Targets Project Code :
  • 16. ADD ADDITIONAL SLIDES IF NECESSARY SLIDE NUMBER: 16