SlideShare ist ein Scribd-Unternehmen logo
1 von 9
Downloaden Sie, um offline zu lesen
Foundation Engineering 1
Example (1): Estimate the
allowable group capacity for the
(3 × 5) pile group shown with
spacing s = 0.75 m in both
directions. Use F.S. = 3.
Solution
( a ) Single pile action
Qu = Qb + Qs
( i ) Point bearing capacity;
Qb = Ab ( ̅. ́ ) ≤ Ab (11000) kN
̅ = (15 ‒ 9.8) × 4 + (20 ‒ 9.8) × 9 = 112.6 kPa
From Fig. (8.5); = = 30
ϕ = 36ᵒ  ́ = 60
̅. ́ = 112.6 × 60 = 6756 < 11000 kPa
Qb = (0.3)2
× 6756 = 477.6 kN
( ii ) Skin friction capacity;
 For the first soil layer;
Qs1 = As1 . fs1
fs1 = k1 . ̅ . tanδ1 ≤ 100 kPa
From Table (8.3); for concrete pile; δ1 = 0.75 × 28 = 21ᵒ
̅ = (15 ‒ 9.8) × 2.5 = 13 kPa
fs1 = 0.6 × 13 × tan 21 = 2.99 kPa < 100 kPa o.k.
Qs1 = ( π × 0.3 × 3 ) × 2.99 = 8.5 kN
 For the second soil layer;
Qs2 = As2 . fs2
fs2 = k2 . ̅ . tanδ2 ≤ 100 kPa
From Table (8.3); δ2 = 0.75 × 36 = 27ᵒ
̅ = (15 ‒ 9.8) × 4 + (20 ‒ 9.8) × 4.5 = 66.7 kPa
0.75m 0.75m
W.T. G.L.
9
m
3
m
1
m
(Concrete piles with 0.3m dia.)
Loose sand
ϕ = 28 ᵒ
γsat = 15 kN/m3
Ks = 0.6
Sand
)med - dense)
ϕ = 36 ᵒ
γsat = 20 kN/m3
Ks = 0.7
Foundation Engineering 2
fs2 = 0.7 × 66.7 × tan 27 = 23.79 kPa < 100 kPa o.k.
Qs2 = ( π × 0.3 × 9 ) × 23.79 = 201.8 kN
⸫ Qu = Qb + Qs1 + Qs2 = 477.6 + 8.5 + 201.8 = 687.9 kN
Gu = 15 × 687.9 = 10318.5 kN
( b ) Block action
B = (3 ‒ 1) × 0.75 + 0.3 = 1.8 m
L = (5 ‒ 1) × 0.75 + 0.3 = 3.3 m
Ab = B × L = 1.8 × 3.3 = 5.94 m2
As = 2 (B + L) × ∆ L = 2 (1.8 + 3.3) × ∆ L = 10.2 ∆ L
( i ) Point bearing capacity;
Gb = Ab . ̅. ́
From Fig. (8.5); = = 5
ϕ = 36ᵒ  ́ = 70
Gb = 5.94 × 112.6 × 70 = 46819.1 kN
( ii ) Skin friction capacity;
 For the first soil layer;
Gs1 = As1 . fs1
For block action; δ1 = 1 = 28ᵒ
fs1 = 0.6 × 13 × tan28 = 4.15 kPa
⸫ Gs1 = (10.2 × 3) × 4.15 = 127.0 kN
 For the second soil layer;
Gs2 = As2 . fs2
For block action; δ2 = 2 = 36ᵒ
fs2 = 0.7 × 66.7 × tan36 = 33.92 kPa
⸫ Gs2 = (10.2 × 9) × 33.92 = 3113.9 kN
⸫ Gu = Gb + Gs1 + Gs2 = 46819.1 + 127 + 3113.9 = 50060.0 kN
Single pile action controls
⸫ Gu = 10318.5 kN
Ga = = = 3439.5 kN
Foundation Engineering 3
Example (2 - HW): Estimate the required number
of 350 mm diameter, 9m length bored piles to
withstand 2000 kN column load for the profile
shown in the figure. Suggest a reasonable layout
with 1m spacing and check the block action. Take
FS = 2.6.
Solution
Qu = Qb + Qs
Qb = Ab (c. ́ + ̅. ́ ) ; for  = 0; ̅. ́ = 0 and ́ = 9
Qb = × 125 × 9 = 108.238 kN
Qs = Qs1 + Qs2 + Qs3 = As1 . fs1 + As2 . fs2 + As3 . fs3
fs = α . c + k . ̅ . tanδ ≤ 100 kPa
for  = 0; k . ̅ . tanδ = 0
For bored piles in clay, Skempton suggested;  = 0.45
fs1 = 0.45 × 100 = 45 kPa < 100 kPA o.k.
fs2 = 0.45 × 110 = 49.5 kPa < 100 kPA o.k.
fs3 = 0.45 × 125 = 56.25 kPa < 100 kPA o.k.
As1 = As2 = As3 = π (0.35) × 3 = 3.299 m2
Qs = 3.299 (45 + 49.5 + 56.25) = 497.324 kN
Qu = 108.238 + 497.324 = 605.562 kN
Qa = = 232.908 kN
N = = 8.6 ; say 9 piles
Use square group (3×3) piles with a spacing of (1m);
3m
3m
3m
 = 0
 = 0
 = 0
c = 100 kPa
c = 110 kPa
c = 125 kPa
Foundation Engineering 4
Check group action;
a = b = 2 × 1 + 0.35 = 2.35 m
Qu = Qb + Qs
Qb = Ab (c . ́ )
From Fig. (3.7); for = = 3.82 ; Nc = 8.95
Qb = (2.35)2
× 125 × 8.95 = 6178.3 kN
Qs = c1 . As1 + c2 . As2 + c3 . As3
As1 = As2 = As3 = (4 × 2.35) × 3 = 28.2 m2
Qs = 28.2 (100 + 110 + 125) = 9447 kN
Qu = 6178.3 + 9447 = 15625.3 kN
Qa = = 6009.7 kN ˃ 2000 kN OK
b
a
Foundation Engineering 5
Example (3 - HW): Compute the
efficiency of the 3 × 6 pile group
shown. Use the following additional
data;
d = 0.4 m
Qu = 600 kN
Gu = 36000 kN
Solution
( i ) Converse-Labarre equation;
( ) [ ]
= 21.8ᵒ
m = 3
n = 6
( ) [ ] = 0.64 or 64%
( ii ) Poulos and Davis equation;
N = 18 ,
Qu = 600 kN
Gu = 36000 kN
= 1.09
Eg = 0.92 or 92%
1
m
1m
Foundation Engineering 6
Example ( 4 ): Estimate the consolidation settlement for the pile group shown
Solution
Lp = 9.0 m , ho = 0
h = = = 3 m
4 m
4 m × 3 m
W.T.
G.L.
Dense sand
EL. 106 m
EL. 104 m
EL. 95 m
2300 kN
EL. 102 m
EL. 94 m
EL. 89 m
EL. 92 m
Clay ( I )
γsat = 19.2 kN/m3
Cc = 0.23
eo = 0.8
γ = 17 kN/m3
Clay ( II ) γsat = 18.2 kN/m3
Cc = 0.34 , eo = 1.08
Clay ( III ) γsat = 20 kN/m3
Cc = 0.2 , eo = 0.7
4 m
4 m × 3 m
W.T.
G.L.
2
m
Dense sand
2300 kN
4
m
2
m
2
m
3
m
3
m
 𝜎𝑜 , ∆𝜎
 𝜎𝑜 , ∆𝜎
 𝜎𝑜 , ∆𝜎
 𝜎𝑜 , ∆𝜎
4
m
Clay ( I )
γsat = 19.2 kN/m3
Cc = 0.23
eo = 0.8
γ = 17 kN/m3
Clay ( II ) γsat = 18.2 kN/m3
Cc = 0.34 , eo = 1.08
Clay ( III ) γsat = 20 kN/m3
Cc = 0.2 , eo = 0.7
Foundation Engineering 7
Sc = ∑ , (Sc)i = log
Layer Z
Area (m2
)
A = (4 + z) (3 + Z)
∆ =
(kN/m2
) (kN/m2
)
1 1 20 115 4×17 + 5 (19.2  9.8) = 115
2 3 42 54.8 115 + 2 (19.2  9.8) = 133.8
3 5 72 31.9 133.8 + 1 (19.2  9.8) + 1 (18.2  9.8) = 151.6
4 7.5 120.75 19.0 151.6 + 1 (18.2  9.8) + 1.5 (20  9.8) = 175.3
Sc1 = log = 7.7 cm
Sc2 = log = 3.8 cm
Sc3 = log = 2.71 cm
Sc4 = log = 1.6 cm
Sc = ∑ = 15.81 cm
Foundation Engineering 8
Example ( 5 ): the pile group
shown is subjected to the following
loads;
V = 6000 kN , mx = 4800 kN.m ,
H = 800 kN , my = 3000 kN.m .
Compute the vertical and horizontal
forces on the corner piles
Solution
Center of gravity of piles;
̅
∑
∑
, ̅
∑
∑
̅ = 5.5 m
̅ = 4.33 m
Locate the coordinate system at
the c.g. of piles.
ex = 5.0 – 5.5 = -0.5 m
ey =5.0 – 4.33 = 0.67 m
∑ ∑
x2
= 3(6.5)2
+ 3(1.5)2
+ 3( 2.5)2
+ 3( 5.5)2
= 243 m2
y2
= 4(3.67)2
+ 4(0.67)2
+ 4( 4.33)2
= 130.67 m2
Mx = mx + V . ey = 4800 + 6000 × 0.67 = 8820 kN.m
My = my + V . ex = 3000 + 6000 × (-0.5) = 0
3
m
1
5
m
5 m
4 m 5 m
y
x
c.g.
2
3 4
my
mx
3 m
3
m
1
5
m
5 m
4 m 5 m
5.5 m
y
x
c.g.
2
3 4
my
mx
3 m
4.33
m
Foundation Engineering 9
= 500 + 67.5 y
500 + 67.5 (3.67) = 747.7 kN
500 + 67.5 ( 4.33) = 207.7 kN
= = 66.67 kN

Weitere ähnliche Inhalte

Ähnlich wie Ch.9-Examples 2.pdf

Problems on bearing capacity of soil
Problems on bearing capacity of soilProblems on bearing capacity of soil
Problems on bearing capacity of soilLatif Hyder Wadho
 
Examples on stress distribution
Examples on stress distributionExamples on stress distribution
Examples on stress distributionMalika khalil
 
Mecánica de Fluidos_Merle C. Potter, David C. Wiggert_3ed Solucionario
Mecánica de Fluidos_Merle C. Potter, David C. Wiggert_3ed SolucionarioMecánica de Fluidos_Merle C. Potter, David C. Wiggert_3ed Solucionario
Mecánica de Fluidos_Merle C. Potter, David C. Wiggert_3ed SolucionarioEdgar Ortiz Sánchez
 
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Make Mannan
 
presentation_41.pptx
presentation_41.pptxpresentation_41.pptx
presentation_41.pptxShathaTaha2
 
Examples on effective stress
Examples on effective stressExamples on effective stress
Examples on effective stressMalika khalil
 
Numerical problem , single ,group pile capacity (usefulsearch.org) (useful se...
Numerical problem , single ,group pile capacity (usefulsearch.org) (useful se...Numerical problem , single ,group pile capacity (usefulsearch.org) (useful se...
Numerical problem , single ,group pile capacity (usefulsearch.org) (useful se...Make Mannan
 
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...Hossam Shafiq II
 
Shallow and Deep Founation Design Calucations
Shallow and Deep Founation Design CalucationsShallow and Deep Founation Design Calucations
Shallow and Deep Founation Design CalucationsTyler Edgington
 
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Make Mannan
 
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Make Mannan
 
(Neamen)solution manual for semiconductor physics and devices 3ed
(Neamen)solution manual for semiconductor physics and devices 3ed(Neamen)solution manual for semiconductor physics and devices 3ed
(Neamen)solution manual for semiconductor physics and devices 3edKadu Brito
 
기초공학 - 11-2 Pile Foundations.pdf
기초공학 - 11-2 Pile Foundations.pdf기초공학 - 11-2 Pile Foundations.pdf
기초공학 - 11-2 Pile Foundations.pdfShallomNkhoma
 
Sachpazis_Trapezoid Foundation Analysis & Design. Calculation according to EN...
Sachpazis_Trapezoid Foundation Analysis & Design. Calculation according to EN...Sachpazis_Trapezoid Foundation Analysis & Design. Calculation according to EN...
Sachpazis_Trapezoid Foundation Analysis & Design. Calculation according to EN...Dr.Costas Sachpazis
 

Ähnlich wie Ch.9-Examples 2.pdf (20)

Solucionario_Felder.pdf
Solucionario_Felder.pdfSolucionario_Felder.pdf
Solucionario_Felder.pdf
 
Maths book2 Text book answer
Maths book2 Text book answerMaths book2 Text book answer
Maths book2 Text book answer
 
Problems on bearing capacity of soil
Problems on bearing capacity of soilProblems on bearing capacity of soil
Problems on bearing capacity of soil
 
Examples on stress distribution
Examples on stress distributionExamples on stress distribution
Examples on stress distribution
 
Mecánica de Fluidos_Merle C. Potter, David C. Wiggert_3ed Solucionario
Mecánica de Fluidos_Merle C. Potter, David C. Wiggert_3ed SolucionarioMecánica de Fluidos_Merle C. Potter, David C. Wiggert_3ed Solucionario
Mecánica de Fluidos_Merle C. Potter, David C. Wiggert_3ed Solucionario
 
Example problem
Example problemExample problem
Example problem
 
problemas resueltos
problemas resueltosproblemas resueltos
problemas resueltos
 
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)Best numerical problem group pile capacity (usefulsearch.org) (useful search)
Best numerical problem group pile capacity (usefulsearch.org) (useful search)
 
presentation_41.pptx
presentation_41.pptxpresentation_41.pptx
presentation_41.pptx
 
Examples on effective stress
Examples on effective stressExamples on effective stress
Examples on effective stress
 
Numerical problem , single ,group pile capacity (usefulsearch.org) (useful se...
Numerical problem , single ,group pile capacity (usefulsearch.org) (useful se...Numerical problem , single ,group pile capacity (usefulsearch.org) (useful se...
Numerical problem , single ,group pile capacity (usefulsearch.org) (useful se...
 
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
12-Examples on Compression Members (Steel Structural Design & Prof. Shehab Mo...
 
Shallow and Deep Founation Design Calucations
Shallow and Deep Founation Design CalucationsShallow and Deep Founation Design Calucations
Shallow and Deep Founation Design Calucations
 
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
 
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
 
1 perhitungan-balok
1 perhitungan-balok1 perhitungan-balok
1 perhitungan-balok
 
Temperature changes problems
Temperature changes problemsTemperature changes problems
Temperature changes problems
 
(Neamen)solution manual for semiconductor physics and devices 3ed
(Neamen)solution manual for semiconductor physics and devices 3ed(Neamen)solution manual for semiconductor physics and devices 3ed
(Neamen)solution manual for semiconductor physics and devices 3ed
 
기초공학 - 11-2 Pile Foundations.pdf
기초공학 - 11-2 Pile Foundations.pdf기초공학 - 11-2 Pile Foundations.pdf
기초공학 - 11-2 Pile Foundations.pdf
 
Sachpazis_Trapezoid Foundation Analysis & Design. Calculation according to EN...
Sachpazis_Trapezoid Foundation Analysis & Design. Calculation according to EN...Sachpazis_Trapezoid Foundation Analysis & Design. Calculation according to EN...
Sachpazis_Trapezoid Foundation Analysis & Design. Calculation according to EN...
 

Kürzlich hochgeladen

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 

Kürzlich hochgeladen (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

Ch.9-Examples 2.pdf

  • 1. Foundation Engineering 1 Example (1): Estimate the allowable group capacity for the (3 × 5) pile group shown with spacing s = 0.75 m in both directions. Use F.S. = 3. Solution ( a ) Single pile action Qu = Qb + Qs ( i ) Point bearing capacity; Qb = Ab ( ̅. ́ ) ≤ Ab (11000) kN ̅ = (15 ‒ 9.8) × 4 + (20 ‒ 9.8) × 9 = 112.6 kPa From Fig. (8.5); = = 30 ϕ = 36ᵒ  ́ = 60 ̅. ́ = 112.6 × 60 = 6756 < 11000 kPa Qb = (0.3)2 × 6756 = 477.6 kN ( ii ) Skin friction capacity;  For the first soil layer; Qs1 = As1 . fs1 fs1 = k1 . ̅ . tanδ1 ≤ 100 kPa From Table (8.3); for concrete pile; δ1 = 0.75 × 28 = 21ᵒ ̅ = (15 ‒ 9.8) × 2.5 = 13 kPa fs1 = 0.6 × 13 × tan 21 = 2.99 kPa < 100 kPa o.k. Qs1 = ( π × 0.3 × 3 ) × 2.99 = 8.5 kN  For the second soil layer; Qs2 = As2 . fs2 fs2 = k2 . ̅ . tanδ2 ≤ 100 kPa From Table (8.3); δ2 = 0.75 × 36 = 27ᵒ ̅ = (15 ‒ 9.8) × 4 + (20 ‒ 9.8) × 4.5 = 66.7 kPa 0.75m 0.75m W.T. G.L. 9 m 3 m 1 m (Concrete piles with 0.3m dia.) Loose sand ϕ = 28 ᵒ γsat = 15 kN/m3 Ks = 0.6 Sand )med - dense) ϕ = 36 ᵒ γsat = 20 kN/m3 Ks = 0.7
  • 2. Foundation Engineering 2 fs2 = 0.7 × 66.7 × tan 27 = 23.79 kPa < 100 kPa o.k. Qs2 = ( π × 0.3 × 9 ) × 23.79 = 201.8 kN ⸫ Qu = Qb + Qs1 + Qs2 = 477.6 + 8.5 + 201.8 = 687.9 kN Gu = 15 × 687.9 = 10318.5 kN ( b ) Block action B = (3 ‒ 1) × 0.75 + 0.3 = 1.8 m L = (5 ‒ 1) × 0.75 + 0.3 = 3.3 m Ab = B × L = 1.8 × 3.3 = 5.94 m2 As = 2 (B + L) × ∆ L = 2 (1.8 + 3.3) × ∆ L = 10.2 ∆ L ( i ) Point bearing capacity; Gb = Ab . ̅. ́ From Fig. (8.5); = = 5 ϕ = 36ᵒ  ́ = 70 Gb = 5.94 × 112.6 × 70 = 46819.1 kN ( ii ) Skin friction capacity;  For the first soil layer; Gs1 = As1 . fs1 For block action; δ1 = 1 = 28ᵒ fs1 = 0.6 × 13 × tan28 = 4.15 kPa ⸫ Gs1 = (10.2 × 3) × 4.15 = 127.0 kN  For the second soil layer; Gs2 = As2 . fs2 For block action; δ2 = 2 = 36ᵒ fs2 = 0.7 × 66.7 × tan36 = 33.92 kPa ⸫ Gs2 = (10.2 × 9) × 33.92 = 3113.9 kN ⸫ Gu = Gb + Gs1 + Gs2 = 46819.1 + 127 + 3113.9 = 50060.0 kN Single pile action controls ⸫ Gu = 10318.5 kN Ga = = = 3439.5 kN
  • 3. Foundation Engineering 3 Example (2 - HW): Estimate the required number of 350 mm diameter, 9m length bored piles to withstand 2000 kN column load for the profile shown in the figure. Suggest a reasonable layout with 1m spacing and check the block action. Take FS = 2.6. Solution Qu = Qb + Qs Qb = Ab (c. ́ + ̅. ́ ) ; for  = 0; ̅. ́ = 0 and ́ = 9 Qb = × 125 × 9 = 108.238 kN Qs = Qs1 + Qs2 + Qs3 = As1 . fs1 + As2 . fs2 + As3 . fs3 fs = α . c + k . ̅ . tanδ ≤ 100 kPa for  = 0; k . ̅ . tanδ = 0 For bored piles in clay, Skempton suggested;  = 0.45 fs1 = 0.45 × 100 = 45 kPa < 100 kPA o.k. fs2 = 0.45 × 110 = 49.5 kPa < 100 kPA o.k. fs3 = 0.45 × 125 = 56.25 kPa < 100 kPA o.k. As1 = As2 = As3 = π (0.35) × 3 = 3.299 m2 Qs = 3.299 (45 + 49.5 + 56.25) = 497.324 kN Qu = 108.238 + 497.324 = 605.562 kN Qa = = 232.908 kN N = = 8.6 ; say 9 piles Use square group (3×3) piles with a spacing of (1m); 3m 3m 3m  = 0  = 0  = 0 c = 100 kPa c = 110 kPa c = 125 kPa
  • 4. Foundation Engineering 4 Check group action; a = b = 2 × 1 + 0.35 = 2.35 m Qu = Qb + Qs Qb = Ab (c . ́ ) From Fig. (3.7); for = = 3.82 ; Nc = 8.95 Qb = (2.35)2 × 125 × 8.95 = 6178.3 kN Qs = c1 . As1 + c2 . As2 + c3 . As3 As1 = As2 = As3 = (4 × 2.35) × 3 = 28.2 m2 Qs = 28.2 (100 + 110 + 125) = 9447 kN Qu = 6178.3 + 9447 = 15625.3 kN Qa = = 6009.7 kN ˃ 2000 kN OK b a
  • 5. Foundation Engineering 5 Example (3 - HW): Compute the efficiency of the 3 × 6 pile group shown. Use the following additional data; d = 0.4 m Qu = 600 kN Gu = 36000 kN Solution ( i ) Converse-Labarre equation; ( ) [ ] = 21.8ᵒ m = 3 n = 6 ( ) [ ] = 0.64 or 64% ( ii ) Poulos and Davis equation; N = 18 , Qu = 600 kN Gu = 36000 kN = 1.09 Eg = 0.92 or 92% 1 m 1m
  • 6. Foundation Engineering 6 Example ( 4 ): Estimate the consolidation settlement for the pile group shown Solution Lp = 9.0 m , ho = 0 h = = = 3 m 4 m 4 m × 3 m W.T. G.L. Dense sand EL. 106 m EL. 104 m EL. 95 m 2300 kN EL. 102 m EL. 94 m EL. 89 m EL. 92 m Clay ( I ) γsat = 19.2 kN/m3 Cc = 0.23 eo = 0.8 γ = 17 kN/m3 Clay ( II ) γsat = 18.2 kN/m3 Cc = 0.34 , eo = 1.08 Clay ( III ) γsat = 20 kN/m3 Cc = 0.2 , eo = 0.7 4 m 4 m × 3 m W.T. G.L. 2 m Dense sand 2300 kN 4 m 2 m 2 m 3 m 3 m  𝜎𝑜 , ∆𝜎  𝜎𝑜 , ∆𝜎  𝜎𝑜 , ∆𝜎  𝜎𝑜 , ∆𝜎 4 m Clay ( I ) γsat = 19.2 kN/m3 Cc = 0.23 eo = 0.8 γ = 17 kN/m3 Clay ( II ) γsat = 18.2 kN/m3 Cc = 0.34 , eo = 1.08 Clay ( III ) γsat = 20 kN/m3 Cc = 0.2 , eo = 0.7
  • 7. Foundation Engineering 7 Sc = ∑ , (Sc)i = log Layer Z Area (m2 ) A = (4 + z) (3 + Z) ∆ = (kN/m2 ) (kN/m2 ) 1 1 20 115 4×17 + 5 (19.2  9.8) = 115 2 3 42 54.8 115 + 2 (19.2  9.8) = 133.8 3 5 72 31.9 133.8 + 1 (19.2  9.8) + 1 (18.2  9.8) = 151.6 4 7.5 120.75 19.0 151.6 + 1 (18.2  9.8) + 1.5 (20  9.8) = 175.3 Sc1 = log = 7.7 cm Sc2 = log = 3.8 cm Sc3 = log = 2.71 cm Sc4 = log = 1.6 cm Sc = ∑ = 15.81 cm
  • 8. Foundation Engineering 8 Example ( 5 ): the pile group shown is subjected to the following loads; V = 6000 kN , mx = 4800 kN.m , H = 800 kN , my = 3000 kN.m . Compute the vertical and horizontal forces on the corner piles Solution Center of gravity of piles; ̅ ∑ ∑ , ̅ ∑ ∑ ̅ = 5.5 m ̅ = 4.33 m Locate the coordinate system at the c.g. of piles. ex = 5.0 – 5.5 = -0.5 m ey =5.0 – 4.33 = 0.67 m ∑ ∑ x2 = 3(6.5)2 + 3(1.5)2 + 3( 2.5)2 + 3( 5.5)2 = 243 m2 y2 = 4(3.67)2 + 4(0.67)2 + 4( 4.33)2 = 130.67 m2 Mx = mx + V . ey = 4800 + 6000 × 0.67 = 8820 kN.m My = my + V . ex = 3000 + 6000 × (-0.5) = 0 3 m 1 5 m 5 m 4 m 5 m y x c.g. 2 3 4 my mx 3 m 3 m 1 5 m 5 m 4 m 5 m 5.5 m y x c.g. 2 3 4 my mx 3 m 4.33 m
  • 9. Foundation Engineering 9 = 500 + 67.5 y 500 + 67.5 (3.67) = 747.7 kN 500 + 67.5 ( 4.33) = 207.7 kN = = 66.67 kN