5. 5
Status Expected Completion Date
Trestle 100% Complete
Platform 100% Complete
Loading Arm 100% Complete
Pile Static Load Test 100% Complete
Pipe Line 80% 31-Jan-15
Mooring Dolphins 80% 25-Jan-15
Berthing Dolphins 75% 31-Jan-15
Catwalks 75% 5-Feb-15
Abutement & Access 50% 28-Jan-15
Electrical 30% 10-Feb-15
Marine Furniture (QRH,BAS,Fenders,..) 20% 12-Feb-15
Commissioning 4-Feb to 18-Feb-15
Construction
6. 6
Front View
10” FF Pipe4” Vapour Pipe6” LPG Pipe
2.5” Water
Pipe
U-Channel
Pipe Support
Concrete Pipe
Support
Pipe 13-Jan-15
FireFighting 80%
Vapour 80%
LPG 80%
Water 80%
7. 7
Invoice
No.
Descripti
on
Initial Amount
(JOD)
Agreed Amount
(JOD)
Issue Date Due Date
Settleme
nt Date
Overdue
Period
(days)
Status
001
Advance
payment
10%
1,723,255.00 1,723,255.00 5-Feb-14 6-Mar-14 8-Jun-14 94 Closed
002 IPC-1 2,356,981.61 1,926,073.33 7-May-14 2-Jul-14 19-Aug-14 48 Closed
003 IPC-2 1,092,297.77 969,456.65 7-Jun-14 2-Aug-14 1-Sep-14 30 Closed
004 IPC-3 1,507,114.54 1,245,493.82 12-Jul-14 6-Sep-14 1-Oct-14 25 Closed
005 IPC-4 1,174,215.32 1,583,941.28 11-Aug-14 6-Oct-14 10-Nov-14 35 Closed
006 IPC-5 1,617,218.84 1,006,200.22 8-Sep-14 3-Nov-14 12-Nov-14 9 Closed
007 IPC-6 2,638,679.75 1,919,859.74 7-Oct-14 2-Dec-14 12-Nov-14 Closed
008 IPC-7 1,571,120.29 1,005,264.70 29-Oct-14 24-Dec-14 30-Nov-14 Closed
009
IPC-8
1,864,144.68 993,963.07 2-Dec-14 27-Jan-15 Not Yet Open
010
IPC-9
1,366,814.24 1,212,026.19 2-Jan-15 27-Feb-15 Not Yet
Open
Issued 14-Jan-2015
8. .1Steel Water Tank to feed the fire fighting system
•Issued on Nov. 17th 2014 (202,425.00) JD, Progress : 30%
.2Firefighting Pumps Room
•Issued on 17th 2014 (40,700.0) JD, Progress : 95%
.3LPG and Vapour Return Tie-In to Existing Networks
•Issued on 17th 2014 (64,509.61) JD, Progress : 100%
.4Design, Supply and Installation of Main Power cable
•Issued on Dec. 24th (18,246.99) JD, Progress : 80%
.5Design, Supply and Installation of a Standby Power Generator
•Issued on Dec. 24th (18,198.69) JD, Progress : 80%
8