Summary:
12 Years’ experience in instrumentation, process control, DCS and safety systems
Excellent experience in YOKOGAWA systems such as:
CENTUM CS3000, CENTUM VP and PROSAFE_RS
(Engineering, installation, commissioning & start-up and maintenance)
Education Background:
Bachelors of Communication & Electronics Engineering
Faculty of Engineering Cairo university
Year of graduation: 2005
Graduation project: Distinction
Personal information:
Nationality: Egyptian
Profile: Male, Married
Date of birth: 13 July 1982
Military Status: Free
Current location: Giza _ Egypt / Yanbu _ KSA (valid KSA visa till January 2017)
Egypt Mobile: +20-1004235282
Saudi Mobile: +966-583893827
E-mail: mshawkym82@yahoo.com
Fields of competence:
• Yokogawa DCS & Safety system office engineering, documentation, FAT
activates, commissioning & startup activates and running plant troubleshooting
and maintenance experience in petrochemical and oil & gas projects.
• Cooperation with many big client; TOTAL, BP, BG, Exxon Mobil, PDO
• Cooperation with many Yokogawa offices worldwide; Yokogawa Europe –NL,
Yokogawa UK, Yokogawa Saudi Arabia, Yokogawa Abu-Dhabi and Yokogawa
Middle East (YME).
• Specialist in Yokogawa Centum CS3000/VP DCS system and ProSafe-PLC/RS
Safety System.
• Experience at site commissioning
• Experience in project reviews approvals & audits
• Experience client & vendor management for performance & delivery.
• Principles of process control and instrumentation.
• Presents and reports the project status to the top management.
• Attend technical meetings with customers; handle FAT, plant commissioning and
startup activities.
• Very good communication skills with colleagues.
• Willingness to travel extensively.
2. Mohamed Shawky Ashour
Senior Control System Engineer
2of4
Details of Work Experience:
1- YOKOGAWA Service Saudi Arabia (YSSA)
Date: February 2015 till now
Position: Senior Control System Engineer
- Supporting all engineering issues and activities related to Yokogawa DCS/SIS
as well as Performing all necessary enhancement upgrading of DCS/SIS.
- Performing all necessary modifications in complex logic for DCS/SIS.
- Maintenance Support.
Projects
a. Petro Rabigh-Rabigh-KSA
b. LUBEREF-Yanbu-KSA
c. YASREF-Yanbu-KSA
d. IBN RUSHD-Yanbu-KSA
2- YOKOGAWA Abu-Dhabi-UAE
Date: September 2011 till August 2013
Position: Control System Engineer
- Carrying out Site Acceptance Test (SAT) at site including supervision and
testing of control system installation.
- Loop checking and network trouble-shooting.
- Commissioning & Startup.
Projects
a. KHARIR POWER PLANT (KPP)-Yamen
b. KHARIR NEW WATER TREATMENT UNIT (WTU) -Yamen
c. TOTAL EXPLORATION & PRODUCTION YEMEN (TEPY) –Yamen
d. HABSHAN5-Abu Dhabi-UAE
3- YOKOGAWA Middle East (YME)-Bahrain
Date: May 2012 till June 2012
Position: Commissioning & Startup engineer
- Reviewing of ESD and FGS logics.
- Loop checking and network trouble-shooting.
- Commissioning & Startup.
Projects
a. AMAL STEAM SURFACE FACILITIES PROJECT-Oman
4- Burullus GAS Company (BGC) – Egypt
Project: Phase VII Extension – Alexandria - Egypt.
Date: March 2011 till September 2012
Position: Commissioning & Startup DCS engineer
- Supervision and testing of control system installation, including power distribution,
system interconnections, supervision of subcontractors.
- Carry-out SAT activities.
- Modification and configuration of FF bus signals.
3. Mohamed Shawky Ashour
Senior Control System Engineer
3of4
- Loop checking and commissioning.
5- Assuit Oil Refinery Company (ASORC)
Project: Crude Distillation Unit 1 Upgrade - Assuit - Egypt
Date: January 2011
Position: Commissioning & Startup DCS engineer
- Supervision and testing of control system installation, including power distribution,
system interconnections, supervision of subcontractors, loop checking and network
trouble-shooting.
- Interconnected CDU1 (Vnet/IP) and CDU2 (Vnet) into 2 domains via layer 2 switch
and a Vnet router.
- Site Acceptance Testing (SAT).
- Upgraded all HISs to CS3000 R3.09
6- Yokogawa Europe Solutions - Netherland
Project: Exxon Mobil Adriatic LNG (Offshore)-Venice- Italy
Date: June 2009 till August 2009
Position: Senior DCS Commissioning Engineer
- Carry out Maintenance Activities for the Distributed Control system (DCS) for
Yokogawa CS3000 R3.03.00
- Carry out all site modifications as software and hardware configurations.
- Operation support
7- SILVERTECH Middle East Company-Dubai-UAE
Date: April 2008 till June 2009
Position: Senior DCS Engineer
- Technical support
- Software modification.
- Carrying out of internal test, Pre-FAT and FAT of the following projects:
Projects:
a- Pressure Reducing and Metering Station (PRMS) for NASRIA TISHRIN
JANDAR AND MAHRDI stations -Syria
b- South Pars Integrated Fiber Optic Network (SPIFON) Project - Iran
c- South BAHREGANSAR Field Offshore and Onshore Facilities - Iran
8- Spanish Egyptian company for liquefied gas (SEGAS)
Project: SEGAS project – Damietta -Egypt
Date: September 2007 till April 2008
Position: DCS and safety systems maintenance engineer
- To make overall revision of system component status and make maintenance
reports and required analysis to check system performance to get proper
operation
4. Mohamed Shawky Ashour
Senior Control System Engineer
4of4
- Performing all needed modifications and new engineering for system software
and its related hardware changes required form client
- Make routine backups for systems database
9- YOKOGAWA UK
Date: August 2006 till March 2008
Position: DCS system engineer
- Creating required Database of the project from provided Documents such as
P&IDs, Loop Drawings and Function Manuals.
- Generating complex loops DDS (Detailed Design Specification) specifying all
required definitions and properties of loops.
- Complex loop testing, by building up required Function Blocks, Sequences,
Alarms, and Switches.
- Job progress reporting.
- Working and giving assistance with / to all other members.
Projects
a- Exxon Mobil-Beryl Alpha DCS and Alarm Management Upgrade - UK
b- British Petroleum-BP Wytch Farm Controls Replacement Project – UK
10- Burrullus Gas Company (BGC) – Alexandria - Egypt
Project: Simian, Sienna & Sapphire Gas Development Project – Alexandria - Egypt
Date: June 2005 till May 2006
Position: Instrument & Control System Commissioning Engineer
- Commissioning and start up activities for instrumentation and control systems
with Yokogawa Centum 3000.
- Carry out all site modifications this include add/delete/modify signals to the
existing configuration as software and hardware modifications
- Operation support after plant start-up
.
Training:
Basic Offshore Safety Induction and Emergency Training (BOSIET)
Location: Arab Academy for Science, Technology & Maritime Transport
Duration: 8 March 09 till 11 March 09
Global Technical Services training:
o Process control & Instrumentation
o Distributed control system (DCS), Engineering & operation of YOKOGAWA
centum CS 1000/3000
o YOKOGAWA Foundation field bus (FF)
o Programmable Logic Control system (PLC), Siemens PLC
o Emergency Shutdown System (ESD), YOKOGAWA Prosafe-PLC