AN EFFECTIVE RISK
MANAGEMENT AND
CHANGE CONTROL
PLATFORMS IN THE
DELIVERY OF MAJOR
PROJECTS.
19 MAY 2016
WELCOME – ABOUT ME
LET’S TALK ABOUT PEDRAM
THE REAL RISK PRACTITIONER
WELCOME – ABOUT ME
ABOUT ME
THE REBEL PRACTITIONER
WELCOME TO
RISK MANAGEMENT
IN BELFAST
TO BE COVERED TODAY…..
• Reasons for failure in Major Infrastructure Projects
• The What and the How of Risk Management and Change Control
• The Golden Circle (for Risk)
• Why?
Analysis undertaken by EY in
2015 shows that
approximately US$682B is
wasted on underperforming
projects across the globe
annually.
FIRST, LET’S TALK ABOUT
REASONS FOR FAILURE
2015 REPORT
• Failure to adapt and tailor approach to the project type and complexity.
• Treating project symptoms rather than root causes
• Missing residual, predictive and discrete risks - skewing the project risk picture
• Assuming that major projects are run the same as smaller projects
AVOIDING THESE CAUSES OF FAILURE IS THE KEY TO UNLOCKING THE
VALUE OF YOUR PROGRAM INVESTMENTS.
Source: EY: Predicting Project Risks improves Success - 2015
WHAT IS PROJECT
RISK MANAGEMENT?
MY PERCEPTION….
UNDERSTAND WHAT IT IS: THE DEFINITION
Risk definition: The effect of uncertainty on objectives
An EFFECT is a deviation from the expected – positive or negative
Risk has two types:
1. Inherent (Uncertainty, Planned)
2. Contingent (Risk Event, Unplanned)
RISK VS CHANGE
RISK might happen = Consequence/s X Likelihood/s
CHANGE has happened = only Consequence/s
UNDERSTAND HOW IT HAPPENS: THE PROCESS
ISO 31000 : 2009, Risk Management – Principles and guidelines
WHAT ABOUT
CHANGE CONTROL?
MY PERCEPTION….
UNDERSTAND WHAT IT IS: THE DEFINITION
• The definition of change: to make or become different from expected.
• Two types of change; Product change and Project change
• Potential impacts need to be considered when evaluating a change request;
Scope, Schedule, Cost, Quality, Process and Deliverable/s, Risk
Source: AECEI
UNDERSTAND HOW IT HAPPENS: THE PROCESS
Source: Aquenta
PROJECT MONTHLY COST REPORT
• First month of the Project
• Current Budget = Total Forecast at Completion
• Prior to any PCNs
PCN IN PROCESS
• PCN submitted for an Increase in Scope
• In process – Trended this month
PCN APPROVED
• PCN for increase in scope Approved
• Change Order implemented this month
SO WHO’S RESPONSIBLE FOR
MANAGING RISK IN MAJOR PROJECTS?
THE PROJECT MANAGER AND THEIR TEAM
MORE THAN THE RISK MANAGER
SO WE NOW KNOW WHAT RISK AND CHANGE
CONTROL ARE AND HOW THEY HAPPEN
Reference: The Golden Circle by Simon Sinek (used by Mike McCloskey for Risk Management)
What’s missing? The WHY!
CONNECTING TO THE WHY IS WHAT WILL
REALLY MAKE AN IMPACT ON MAJOR
PROJECT OUTCOMES AND EFFECT POSITIVE CHANGE.
THE EVIDENCE IS CLEAR
THE ELECTIVE MUTE PRINCIPLE
MY OBSERVATIONS
MY OBSERVATIONS
1. Too much time spent in quantitative analysis…not
enough management
2. We need to spend more time investing in understanding
in behavioural techniques within the project team
3. Working together to improve project outcomes will deliver
a better response to business cases
4. The risk management process doesn’t start and end with
a list, it’s cyclical and the learnings need to roll through to
the subsequent projects and provide real benefit
SOURCE: HENRY FORD
THE FINAL ASSERTION
Risk Management has become a
process, more than an intrinsic
philosophy…because people
understand what they do and
how they do it – they just don’t
understand WHY they do it
Mike McCloskey
Managing Director | Aquenta Consulting
P: +61 409 919 105
E: mike.mccloskey@aquenta.com.au

Weitere ähnliche Inhalte

Was ist angesagt?

Estimation & project planning
Estimation & project planningEstimation & project planning
Estimation & project planning
dia22
 
Estimation & project planning
Estimation & project planningEstimation & project planning
Estimation & project planning
alle_tode
 
Learning_Unit_1
Learning_Unit_1Learning_Unit_1
Learning_Unit_1
Jack Ong
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
jisothomas
 

Was ist angesagt? (19)

Risk Management Presentation to Doyle Property Club
Risk Management Presentation to Doyle Property ClubRisk Management Presentation to Doyle Property Club
Risk Management Presentation to Doyle Property Club
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
 
Estimation & project planning
Estimation & project planningEstimation & project planning
Estimation & project planning
 
PROJECT GUIDLINES
PROJECT GUIDLINESPROJECT GUIDLINES
PROJECT GUIDLINES
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Project Auditing
Project AuditingProject Auditing
Project Auditing
 
Riskmanagement 130215051514-phpapp01
Riskmanagement 130215051514-phpapp01Riskmanagement 130215051514-phpapp01
Riskmanagement 130215051514-phpapp01
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
 
Project Appraising Methodology
Project Appraising MethodologyProject Appraising Methodology
Project Appraising Methodology
 
Riskmanagement 130215051514-phpapp01
Riskmanagement 130215051514-phpapp01Riskmanagement 130215051514-phpapp01
Riskmanagement 130215051514-phpapp01
 
Risk management
Risk managementRisk management
Risk management
 
Estimation & project planning
Estimation & project planningEstimation & project planning
Estimation & project planning
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Budgeting and cost estimation
Budgeting and cost estimationBudgeting and cost estimation
Budgeting and cost estimation
 
Learning_Unit_1
Learning_Unit_1Learning_Unit_1
Learning_Unit_1
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
 
risk management
risk managementrisk management
risk management
 
Projects, Investment, Profitability
Projects, Investment, ProfitabilityProjects, Investment, Profitability
Projects, Investment, Profitability
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 

Ähnlich wie Risk Management and Change Controls Presentation

Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
Mircea Tomescu
 

Ähnlich wie Risk Management and Change Controls Presentation (20)

Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics right
 
PMO Manual v2.0 June-18.pptx
PMO Manual v2.0 June-18.pptxPMO Manual v2.0 June-18.pptx
PMO Manual v2.0 June-18.pptx
 
Risk Management
Risk Management Risk Management
Risk Management
 
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen... Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 
Risk Management as an enabler for project success
Risk Management as an enabler for project successRisk Management as an enabler for project success
Risk Management as an enabler for project success
 
Developing a Project Logic/Results Framework - Session 9 Managing Project Pre...
Developing a Project Logic/Results Framework - Session 9 Managing Project Pre...Developing a Project Logic/Results Framework - Session 9 Managing Project Pre...
Developing a Project Logic/Results Framework - Session 9 Managing Project Pre...
 
Introduction to Project Management for Researchers
Introduction to Project Management for ResearchersIntroduction to Project Management for Researchers
Introduction to Project Management for Researchers
 
London 2012 Olympics, Managing and controlling contingency
London 2012 Olympics, Managing and controlling contingencyLondon 2012 Olympics, Managing and controlling contingency
London 2012 Olympics, Managing and controlling contingency
 
CPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docxCPMGT_300 Week_5__Project Life Cycle Paper.docx
CPMGT_300 Week_5__Project Life Cycle Paper.docx
 
Managing the Unknown v2
Managing the Unknown v2Managing the Unknown v2
Managing the Unknown v2
 
Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022Advanced project risk reporting webinar, 21 September 2022
Advanced project risk reporting webinar, 21 September 2022
 
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
 
Session 21 4th edition PMP
Session 21 4th edition PMPSession 21 4th edition PMP
Session 21 4th edition PMP
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Capital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_GasCapital_projects_life_cycle_managemant_Oil_and_Gas
Capital_projects_life_cycle_managemant_Oil_and_Gas
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham Zeinoun
 
Development Planning and Project Management.pdf
Development Planning and Project Management.pdfDevelopment Planning and Project Management.pdf
Development Planning and Project Management.pdf
 
Capital Program Assessment Overview
Capital Program Assessment OverviewCapital Program Assessment Overview
Capital Program Assessment Overview
 
project mgmt chapter 1.pptx
project mgmt chapter 1.pptxproject mgmt chapter 1.pptx
project mgmt chapter 1.pptx
 
BSBPMG540 Manage Project Integration.docx
BSBPMG540 Manage Project Integration.docxBSBPMG540 Manage Project Integration.docx
BSBPMG540 Manage Project Integration.docx
 

Risk Management and Change Controls Presentation

  • 1. M AY 2 0 1 6 AN EFFECTIVE RISK MANAGEMENT AND CHANGE CONTROL PLATFORMS IN THE DELIVERY OF MAJOR PROJECTS. 19 MAY 2016
  • 2. WELCOME – ABOUT ME LET’S TALK ABOUT PEDRAM THE REAL RISK PRACTITIONER
  • 3. WELCOME – ABOUT ME ABOUT ME THE REBEL PRACTITIONER
  • 5. TO BE COVERED TODAY….. • Reasons for failure in Major Infrastructure Projects • The What and the How of Risk Management and Change Control • The Golden Circle (for Risk) • Why?
  • 6. Analysis undertaken by EY in 2015 shows that approximately US$682B is wasted on underperforming projects across the globe annually. FIRST, LET’S TALK ABOUT REASONS FOR FAILURE
  • 7. 2015 REPORT • Failure to adapt and tailor approach to the project type and complexity. • Treating project symptoms rather than root causes • Missing residual, predictive and discrete risks - skewing the project risk picture • Assuming that major projects are run the same as smaller projects AVOIDING THESE CAUSES OF FAILURE IS THE KEY TO UNLOCKING THE VALUE OF YOUR PROGRAM INVESTMENTS. Source: EY: Predicting Project Risks improves Success - 2015
  • 8. WHAT IS PROJECT RISK MANAGEMENT?
  • 10. UNDERSTAND WHAT IT IS: THE DEFINITION Risk definition: The effect of uncertainty on objectives An EFFECT is a deviation from the expected – positive or negative Risk has two types: 1. Inherent (Uncertainty, Planned) 2. Contingent (Risk Event, Unplanned)
  • 11. RISK VS CHANGE RISK might happen = Consequence/s X Likelihood/s CHANGE has happened = only Consequence/s
  • 12. UNDERSTAND HOW IT HAPPENS: THE PROCESS ISO 31000 : 2009, Risk Management – Principles and guidelines
  • 15. UNDERSTAND WHAT IT IS: THE DEFINITION • The definition of change: to make or become different from expected. • Two types of change; Product change and Project change • Potential impacts need to be considered when evaluating a change request; Scope, Schedule, Cost, Quality, Process and Deliverable/s, Risk Source: AECEI
  • 16. UNDERSTAND HOW IT HAPPENS: THE PROCESS Source: Aquenta
  • 17. PROJECT MONTHLY COST REPORT • First month of the Project • Current Budget = Total Forecast at Completion • Prior to any PCNs
  • 18. PCN IN PROCESS • PCN submitted for an Increase in Scope • In process – Trended this month
  • 19. PCN APPROVED • PCN for increase in scope Approved • Change Order implemented this month
  • 20. SO WHO’S RESPONSIBLE FOR MANAGING RISK IN MAJOR PROJECTS? THE PROJECT MANAGER AND THEIR TEAM MORE THAN THE RISK MANAGER
  • 21. SO WE NOW KNOW WHAT RISK AND CHANGE CONTROL ARE AND HOW THEY HAPPEN
  • 22. Reference: The Golden Circle by Simon Sinek (used by Mike McCloskey for Risk Management) What’s missing? The WHY!
  • 23. CONNECTING TO THE WHY IS WHAT WILL REALLY MAKE AN IMPACT ON MAJOR PROJECT OUTCOMES AND EFFECT POSITIVE CHANGE.
  • 24. THE EVIDENCE IS CLEAR THE ELECTIVE MUTE PRINCIPLE
  • 26. MY OBSERVATIONS 1. Too much time spent in quantitative analysis…not enough management 2. We need to spend more time investing in understanding in behavioural techniques within the project team 3. Working together to improve project outcomes will deliver a better response to business cases 4. The risk management process doesn’t start and end with a list, it’s cyclical and the learnings need to roll through to the subsequent projects and provide real benefit SOURCE: HENRY FORD
  • 27. THE FINAL ASSERTION Risk Management has become a process, more than an intrinsic philosophy…because people understand what they do and how they do it – they just don’t understand WHY they do it
  • 28.
  • 29. Mike McCloskey Managing Director | Aquenta Consulting P: +61 409 919 105 E: mike.mccloskey@aquenta.com.au