Lockout/Tagout
1910.147(a)(1) Scope
• Covers servicing and maintenance of
  machines and equipment in which
  – Unexpected energization or start up or
  – Release of stored energy could cause
  – Injury to employees
• Normal operation is
  covered in 1910
  Subpart O
1910.147(a)(1)(ii) Exemptions
• Construction, agriculture and maritime
  employment;
• Electrical Utilities;
• Electrical equipment (covered by Subpart S)
• Oil and gas well drilling and servicing
• So why comply?
Control of Hazardous Energy
• Why use lockout/tagout?
  – Protects maintenance personnel
    from power being reapplied by
    mistake
  – Recommended by API RP 54 for
    electrical systems in drilling and
    servicing operations
  – Recognized hazard
1910.147(a)(2) Application
• Service and maintenance:
  – Employee required to remove or bypass a guard
    or safety device
  – Employee required to place part of body into
    area that would be a danger zone during
    machine operation cycle
1910.147(a)(2) Application
• Exception: Minor adjustments and servicing
  activities during normal production if
  – Routine
  – Repetitive
  – Integral to production
• Provided that alternative measures provide
  effective protection
1910.147(a)(2) Application

• Does not apply to cord and plug
  connected equipment for which
  – Exposure to hazard is controlled by
    unplugging and
  – Plug under exclusive control of
    employee performing service or
    maintenance
1910.147(a)(2) Application
• Does not apply to hot tap operations in
  transmission and distribution operations in
  pressurized pipelines provided that:
  – Continuity of service is essential,
  – Shutdown of system is impractical, and
  – Documented procedures and special equipment
    provide proven effective protection for
    employees
1910.147(a)(3) Purpose
• Establish a program and utilize procedures
  for affixing appropriate lockout devices or
  tagout devices to energy isolating devices
• Prevent unexpected energization, start up or
  release of stored energy in order to prevent
  injury to employees
• Training and procedural requirements for other
  sections’ LO/TO requirements
Affected employee
• Job requires employee to
  – operate or use a machine or equipment on
    which servicing or maintenance is being
    performed under lockout or tagout, or
  – work in an area in which such servicing or
    maintenance is being performed
Authorized employee
• Locks out or tags out machines or equipment
  in order to perform servicing or maintenance
  on that machine or equipment
• Affected employee whose duties include
  servicing or maintenance under this section
Energized
• Connected to an energy source OR
• Containing residual or stored energy
Energy isolating device
• A mechanical device that physically prevents
  the transmission or release or energy
  –   Circuit breakers included
  –   NOT push buttons
  –   NOT selector switches
  –   NOT control circuits
Energy source
• Any source of:
  –   Electrical,
  –   Mechanical,
  –   Hydraulic,
  –   Pneumatic,
  –   Chemical,
  –   Thermal, or
  –   Other energy

                     What kind of energy
                     did the rock have?
Lockout



• Placement of a lockout device on an energy
  isolating device, in accordance with an
  established procedure, ensuring that energy
  isolating device and equipment being
  controlled cannot be operated until lockout
  device is removed
Lockout device


• Device that uses a positive
  means such as a lock, either
  key or combination type, to
  hold an energy isolating device
  in the safe position and prevent
  the energizing of a machine or
  equipment
• Blank flanges and bolted slip
  blinds included
Servicing and/or maintenance
• Workplace activities such as:
  –   Constructing,
  –   Installing,
  –   Setting up,
  –   Adjusting,
  –   Inspecting,
  –   Modifying, and
  –   Maintaining and/or servicing machines or
      equipment
Tagout



• Placement of tagout device
  – on an energy isolating device,
  – in accordance with an established procedure,
  – to indicate that energy
    isolating device and
    equipment being controlled
    may not be operated until
    tagout device is removed
General Requirements

1910.147(c)
Energy control program
•   Energy control procedures
•   Employee training
•   Periodic inspections
•   Any employee who services/maintains any
    equipment where unexpected energizing or
    stored energy release could cause injury
    isolates and renders it inoperative first.
1910.147(c)(ii) General Requirements



• If an energy isolating device is
  capable of being locked out, the
  employer's energy control
  program shall utilize lockout,
  unless the employer can
  demonstrate that the utilization of
  a tagout system will provide full
  employee protection
1910.147(c)(iii) General Requirements
• Energy isolating devices designed to accept
  lockout devices whenever:
  – Replacement or major repair, renovation or
    modification of equipment is performed or
  – New machines or equipment are installed
1910.147(c)(3) Full employee protection



• When tagout device used on energy isolation
  device capable of being locked out:
  – Same location as potential lockout device
  – Demonstrably equivalent program
• May require additional safety elements
1910.147(c)(4) Energy control
 procedure
• Procedures shall be developed, documented
  and utilized for the control of potentially
  hazardous energy when employees are
  engaged in the activities covered by this
  section.
  – Exception with all 8 elements listed in standard
1910.147(c)(4) Energy control
 procedure
• Outline scope, purpose, authorization, rules,
  techniques for control of hazardous energy,
  including:
  – Specific intended use of the procedure;
  – Specific steps for shutting down, isolating,
    blocking and securing equipment
  – Specific steps for placement, removal, transfer
    of lockout/tagout devices and responsibility for
    them
  – Specific requirements for testing equipment to
    verify effectiveness of lockout devices, tagout
    devices, and other energy control measures
1910.147(c)(5) Protective materials and
 hardware
• Locks, tags, chains, wedges, key blocks,
  adapter pins, self-locking fasteners, or other
  hardware shall be provided by the employer
  for isolating, securing or blocking of equipment
  from energy sources
1910.147(c)(5) Protective materials and
 hardware
• Lockout and tagout devices must be:
  –   Singularly identified
  –   The only device(s) used for controlling energy
  –   Not used for other purposes
  –   And shall meet the following
      requirements:
1910.147(c)(5) Protective materials and
 hardware
• Capable of withstanding environment for
  maximum time period
• Moisture or corrosives must not make tag
  deteriorate
• Standardized:
  –   Color
  –   Shape
  –   Size
  –   Print/Format
1910.147(c)(5) Protective materials and
 hardware
• Lockout devices:
  – Substantial enough to prevent removal without
    excessive force or unusual techniques such as
    bolt cutters
• Tagout devices:
  – Substantial enough to prevent inadvertent or
    accidental removal
  – Non-reusable attachment means
  – Attachable by hand, self-lockable
  – At least equivalent to nylon cable tie
1910.147(c)(5) Protective materials and
 hardware
• Lockout and tagout devices indicate identity of
  employee applying devices
1910.147(c)(6) Periodic Inspection
• Energy control procedure inspected at least
  annually:
  – By authorized employee not using the procedure
    being inspected
  – Correct any deviations
  – Review employee responsibilities with:
     • each authorized employee – lockout
     • each affected or authorized employee – tagout
1910.147 (c)(7) Training and
 communication
• Ensure employees understand purpose and
  function of energy control program
• Ensure employees acquire skills required for
  safe application, usage, removal of energy
  controls
Employee Training Requirements
• Authorized employee:
  – Recognition of hazardous energy sources
  – Type and amount of energy in workplace
  – Methods and means for energy isolation
• Affected employee:
  – Purpose and use of procedure
• Other employees in area:
  – Procedure and prohibition on restarting
Employee Training Requirements for
 Tagout
• Train on limitations of tags:
  – Warning devices do not provide physical
    restraint that a lock would
  – Tag not to be removed without owner’s
    authorization, bypassed, ignored, defeated
  – Must be legible / understandable to work
  – Must withstand environmental conditions
  – False sense of security
  – Attach securely: avoid accidental removal
Employee Retraining
• For all authorized or affected employees when:
  –   Job assignment changes
  –   Equipment or processes present new hazard
  –   Energy control procedure changes
  –   Knowledge / use of program is inadequate
• Certify employee training up to date
1910.147(c)(8) Energy Isolation
• Only the authorized employees performing the
  servicing or maintenance may apply
  lockout/tagout
1910.147(c)(9) Notification of
 Employees
• Affected employees must be notified
  – By employer or authorized employee
  – Of application and removal of lockout and
    tagout devices
  – Before controls are applied
  – After controls are removed
Order of Operation for Application of
Control
1. Preparation for shutdown
2. Equipment shutdown – orderly
3. Equipment isolation
4. Lockout or tagout device application
5. Stored energy relieved; continue while
   reaccumulating
6. Verification of isolation
  –   Test and return to “off” position
1910.147(e) Release from Lockout
• Before lockout or tagout devices removed and
  energy restored, ensure:
• Machine or equipment:
  – Inspect area; remove nonessential items
  – Ensure equipment components intact
• Employees:
  – Ensure all employees safe or removed
  – Before restart, notify affected employees of
    removal
1910.147(e) Release from Lockout
• Each lockout/tagout device removed by
  employee who applied the device
  – If not available, removed under employer
    direction
  – Specific procedures and training from energy
    control program must be in use!
      • Verify that applying employee is not at facility
      • Make all reasonable efforts to contact/notify
      • Ensure authorized employee knows of removal
        before resuming work at facility
1910.147(f)(1) Testing or Positioning
• Temporary removal of lockout/tagout devices
  for testing/positioning:
  –   Clear tools and materials
  –   Remove employees from equipment area
  –   Remove lockout/tagout devices (as in (e))
  –   Energize and test or position
  –   Deenergize systems and reapply energy control
      measures to continue servicing
1910.147(f)(2) Outside Personnel
• Contractors and other outside personnel:
  – On-site employer and outside employer inform
    each other of lockout/tagout procedures
  – On-site employer complies with outside
    employer’s energy control program
1910.147(f)(3) Group Lockout or Tagout
• Procedure must provide protection equivalent
  to personal lockout/tagout device
• Primary responsibility is vested in an
  authorized employee for a set number of
  employees working under the protection of a
  group lockout or tagout device (such as an
  operations lock);
1910.147(f)(3) Group Lockout or Tagout
• When more than one crew, craft, department,
  etc. is involved:
  – Designated authorized employee takes
    lockout/tagout control responsibility
  – Coordinates affected work forces
  – Ensures continuity of protection
1910.147(f)(3) Group Lockout or Tagout
• Each authorized employee affixes personal
  lockout/tagout device to group lockout device
  when beginning work
• Each removes personal device when stopping
  work on this equipment
1910.147(f)(4) Shift or Personnel
 Changes
• Specific procedures in energy control plan
• Ensure continuity of lockout/tagout protection
• Orderly transfer of lockout/tagout device
  protection between shifts
• Minimize exposure to hazards from
  unexpected energization or release

Weitere ähnliche Inhalte

Was ist angesagt?

8 steps-to-ensure-proper-lockout-tagout
8 steps-to-ensure-proper-lockout-tagout8 steps-to-ensure-proper-lockout-tagout
8 steps-to-ensure-proper-lockout-tagoutCreative Safety Supply
 
Lockout Tagout
Lockout TagoutLockout Tagout
Lockout Tagoutvtsiri
 
ONTAP - Lock Out, Tag Out
ONTAP - Lock Out, Tag OutONTAP - Lock Out, Tag Out
ONTAP - Lock Out, Tag OutWRDSB
 
Lockout tagout
Lockout tagoutLockout tagout
Lockout tagoutNoel Regalado
 
Lockout Tag Out
Lockout Tag OutLockout Tag Out
Lockout Tag Outsspuent
 
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGYLOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGYjasonmorgan
 
Confined space entry natt7029
Confined space entry   natt7029Confined space entry   natt7029
Confined space entry natt7029Piyushjauhari3
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxVasudevaRajuDantulur1
 
Permit to work system
Permit to work systemPermit to work system
Permit to work systemAsif Khan
 
Working at-height
Working at-height Working at-height
Working at-height Reliance
 
Lock Out - Tag Out - Try Out Safety Course 2014
Lock Out - Tag Out - Try Out Safety Course 2014Lock Out - Tag Out - Try Out Safety Course 2014
Lock Out - Tag Out - Try Out Safety Course 2014H&K Equipment Group
 
Bloqueo de energias 2020
Bloqueo de energias 2020Bloqueo de energias 2020
Bloqueo de energias 2020Jose Barrueto
 
Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009Noel Regalado
 

Was ist angesagt? (20)

8 steps-to-ensure-proper-lockout-tagout
8 steps-to-ensure-proper-lockout-tagout8 steps-to-ensure-proper-lockout-tagout
8 steps-to-ensure-proper-lockout-tagout
 
Lockout Tagout
Lockout TagoutLockout Tagout
Lockout Tagout
 
LOTO
LOTO LOTO
LOTO
 
LOTO Training.ppt
LOTO Training.pptLOTO Training.ppt
LOTO Training.ppt
 
ONTAP - Lock Out, Tag Out
ONTAP - Lock Out, Tag OutONTAP - Lock Out, Tag Out
ONTAP - Lock Out, Tag Out
 
Lockout tagout
Lockout tagoutLockout tagout
Lockout tagout
 
Lockout Tag Out
Lockout Tag OutLockout Tag Out
Lockout Tag Out
 
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGYLOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
LOCKOUT-TAGOUT-SAFETY PRESENTATION-CONTROL OF HAZARDOUS ENERGY
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
 
Electrical Safety by OSHA
Electrical Safety by OSHAElectrical Safety by OSHA
Electrical Safety by OSHA
 
Machine guards
Machine guardsMachine guards
Machine guards
 
Confined space entry natt7029
Confined space entry   natt7029Confined space entry   natt7029
Confined space entry natt7029
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Fall Protection by Osha
Fall Protection by Osha Fall Protection by Osha
Fall Protection by Osha
 
Permit to work system
Permit to work systemPermit to work system
Permit to work system
 
Working at-height
Working at-height Working at-height
Working at-height
 
Lock Out - Tag Out - Try Out Safety Course 2014
Lock Out - Tag Out - Try Out Safety Course 2014Lock Out - Tag Out - Try Out Safety Course 2014
Lock Out - Tag Out - Try Out Safety Course 2014
 
Loto training
Loto trainingLoto training
Loto training
 
Bloqueo de energias 2020
Bloqueo de energias 2020Bloqueo de energias 2020
Bloqueo de energias 2020
 
Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009Lockout tagout safety awareness - online 2009
Lockout tagout safety awareness - online 2009
 

Andere mochten auch

0051 travamento seguran%e7a-92sld
0051 travamento seguran%e7a-92sld0051 travamento seguran%e7a-92sld
0051 travamento seguran%e7a-92sldSávio Gomes
 
Controle e bloqueio de energia
Controle e bloqueio de energiaControle e bloqueio de energia
Controle e bloqueio de energiaAdony Amorim
 
29 bloqueio efetivo de energia
29   bloqueio efetivo de energia29   bloqueio efetivo de energia
29 bloqueio efetivo de energiaCristiano Silva
 
Bloqueios de energia
Bloqueios de energiaBloqueios de energia
Bloqueios de energiasandra brizolla
 

Andere mochten auch (6)

Programa de controle de energias perigosas pcep
Programa de controle de energias perigosas   pcepPrograma de controle de energias perigosas   pcep
Programa de controle de energias perigosas pcep
 
0051 travamento seguran%e7a-92sld
0051 travamento seguran%e7a-92sld0051 travamento seguran%e7a-92sld
0051 travamento seguran%e7a-92sld
 
Controle e bloqueio de energia
Controle e bloqueio de energiaControle e bloqueio de energia
Controle e bloqueio de energia
 
Curso loto
Curso lotoCurso loto
Curso loto
 
29 bloqueio efetivo de energia
29   bloqueio efetivo de energia29   bloqueio efetivo de energia
29 bloqueio efetivo de energia
 
Bloqueios de energia
Bloqueios de energiaBloqueios de energia
Bloqueios de energia
 

Ă„hnlich wie Lockout tagout

loto.ppt
loto.pptloto.ppt
loto.pptmurrtex
 
Lockout-Tagout 2023.ppt
Lockout-Tagout 2023.pptLockout-Tagout 2023.ppt
Lockout-Tagout 2023.pptMichaelCazes1
 
Overcoming The Challenges of Implementing a Lockout Program
Overcoming The Challenges of Implementing a Lockout ProgramOvercoming The Challenges of Implementing a Lockout Program
Overcoming The Challenges of Implementing a Lockout ProgramTENAQUIP
 
lockout-tagout-training.ppt
lockout-tagout-training.pptlockout-tagout-training.ppt
lockout-tagout-training.pptROHITSINGH83692
 
LOTO.pptx
LOTO.pptxLOTO.pptx
LOTO.pptxNoeAranel
 
LOTO Training.pdf
LOTO Training.pdfLOTO Training.pdf
LOTO Training.pdfSyedWasim23
 
Loto.ppt
Loto.pptLoto.ppt
Loto.ppthdiana818
 
Lockout tagout2
Lockout tagout2Lockout tagout2
Lockout tagout2Noel Regalado
 
Lockout tagout standard
Lockout tagout standardLockout tagout standard
Lockout tagout standardAnbr Cama
 
Lockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsLockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsJohn Newquist
 
Lockout tagout standard
Lockout tagout standardLockout tagout standard
Lockout tagout standardAnbr Cama
 
The complete procedure of Logout & tagout
The complete procedure of Logout & tagoutThe complete procedure of Logout & tagout
The complete procedure of Logout & tagoutSaqib Mansoor Ahmed
 
Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...
Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...
Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...Triumvirate Environmental
 
SAFE MAINTENANCE HEAVEY MACHINESlockout_tagout.pptx
SAFE MAINTENANCE HEAVEY MACHINESlockout_tagout.pptxSAFE MAINTENANCE HEAVEY MACHINESlockout_tagout.pptx
SAFE MAINTENANCE HEAVEY MACHINESlockout_tagout.pptxindiaisagreatcountry
 
maintenance type and lockout tag out.pptx
maintenance type and lockout tag out.pptxmaintenance type and lockout tag out.pptx
maintenance type and lockout tag out.pptxkaranmahato19
 

Ă„hnlich wie Lockout tagout (20)

Lockout Tagout by FirstSource
Lockout Tagout by FirstSourceLockout Tagout by FirstSource
Lockout Tagout by FirstSource
 
loto.ppt
loto.pptloto.ppt
loto.ppt
 
Lockout-Tagout 2023.ppt
Lockout-Tagout 2023.pptLockout-Tagout 2023.ppt
Lockout-Tagout 2023.ppt
 
Aa loto53013
Aa loto53013Aa loto53013
Aa loto53013
 
Aa loto53013b
Aa loto53013bAa loto53013b
Aa loto53013b
 
Overcoming The Challenges of Implementing a Lockout Program
Overcoming The Challenges of Implementing a Lockout ProgramOvercoming The Challenges of Implementing a Lockout Program
Overcoming The Challenges of Implementing a Lockout Program
 
lockout-tagout-training.ppt
lockout-tagout-training.pptlockout-tagout-training.ppt
lockout-tagout-training.ppt
 
LOTO.pptx
LOTO.pptxLOTO.pptx
LOTO.pptx
 
LOTO Training.pdf
LOTO Training.pdfLOTO Training.pdf
LOTO Training.pdf
 
Loto.ppt
Loto.pptLoto.ppt
Loto.ppt
 
Energy Control Program by MCIEAST
Energy Control Program by MCIEASTEnergy Control Program by MCIEAST
Energy Control Program by MCIEAST
 
Lockout tagout2
Lockout tagout2Lockout tagout2
Lockout tagout2
 
Lockout tagout standard
Lockout tagout standardLockout tagout standard
Lockout tagout standard
 
Lockout Minor Servicing Exceptions
Lockout Minor Servicing ExceptionsLockout Minor Servicing Exceptions
Lockout Minor Servicing Exceptions
 
Lockout tagout standard
Lockout tagout standardLockout tagout standard
Lockout tagout standard
 
The complete procedure of Logout & tagout
The complete procedure of Logout & tagoutThe complete procedure of Logout & tagout
The complete procedure of Logout & tagout
 
Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...
Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...
Complying with OSHA's Lockout/Tagout Rules: Control Hazardous Energy and Ensu...
 
SAFE MAINTENANCE HEAVEY MACHINESlockout_tagout.pptx
SAFE MAINTENANCE HEAVEY MACHINESlockout_tagout.pptxSAFE MAINTENANCE HEAVEY MACHINESlockout_tagout.pptx
SAFE MAINTENANCE HEAVEY MACHINESlockout_tagout.pptx
 
LOTO1
LOTO1LOTO1
LOTO1
 
maintenance type and lockout tag out.pptx
maintenance type and lockout tag out.pptxmaintenance type and lockout tag out.pptx
maintenance type and lockout tag out.pptx
 

KĂĽrzlich hochgeladen

Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 

KĂĽrzlich hochgeladen (20)

Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
CĂłdigo Creativo y Arte de Software | Unidad 1
CĂłdigo Creativo y Arte de Software | Unidad 1CĂłdigo Creativo y Arte de Software | Unidad 1
CĂłdigo Creativo y Arte de Software | Unidad 1
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 

Lockout tagout

  • 2. 1910.147(a)(1) Scope • Covers servicing and maintenance of machines and equipment in which – Unexpected energization or start up or – Release of stored energy could cause – Injury to employees • Normal operation is covered in 1910 Subpart O
  • 3. 1910.147(a)(1)(ii) Exemptions • Construction, agriculture and maritime employment; • Electrical Utilities; • Electrical equipment (covered by Subpart S) • Oil and gas well drilling and servicing • So why comply?
  • 4. Control of Hazardous Energy • Why use lockout/tagout? – Protects maintenance personnel from power being reapplied by mistake – Recommended by API RP 54 for electrical systems in drilling and servicing operations – Recognized hazard
  • 5. 1910.147(a)(2) Application • Service and maintenance: – Employee required to remove or bypass a guard or safety device – Employee required to place part of body into area that would be a danger zone during machine operation cycle
  • 6. 1910.147(a)(2) Application • Exception: Minor adjustments and servicing activities during normal production if – Routine – Repetitive – Integral to production • Provided that alternative measures provide effective protection
  • 7. 1910.147(a)(2) Application • Does not apply to cord and plug connected equipment for which – Exposure to hazard is controlled by unplugging and – Plug under exclusive control of employee performing service or maintenance
  • 8. 1910.147(a)(2) Application • Does not apply to hot tap operations in transmission and distribution operations in pressurized pipelines provided that: – Continuity of service is essential, – Shutdown of system is impractical, and – Documented procedures and special equipment provide proven effective protection for employees
  • 9. 1910.147(a)(3) Purpose • Establish a program and utilize procedures for affixing appropriate lockout devices or tagout devices to energy isolating devices • Prevent unexpected energization, start up or release of stored energy in order to prevent injury to employees • Training and procedural requirements for other sections’ LO/TO requirements
  • 10. Affected employee • Job requires employee to – operate or use a machine or equipment on which servicing or maintenance is being performed under lockout or tagout, or – work in an area in which such servicing or maintenance is being performed
  • 11. Authorized employee • Locks out or tags out machines or equipment in order to perform servicing or maintenance on that machine or equipment • Affected employee whose duties include servicing or maintenance under this section
  • 12. Energized • Connected to an energy source OR • Containing residual or stored energy
  • 13. Energy isolating device • A mechanical device that physically prevents the transmission or release or energy – Circuit breakers included – NOT push buttons – NOT selector switches – NOT control circuits
  • 14. Energy source • Any source of: – Electrical, – Mechanical, – Hydraulic, – Pneumatic, – Chemical, – Thermal, or – Other energy What kind of energy did the rock have?
  • 15. Lockout • Placement of a lockout device on an energy isolating device, in accordance with an established procedure, ensuring that energy isolating device and equipment being controlled cannot be operated until lockout device is removed
  • 16. Lockout device • Device that uses a positive means such as a lock, either key or combination type, to hold an energy isolating device in the safe position and prevent the energizing of a machine or equipment • Blank flanges and bolted slip blinds included
  • 17. Servicing and/or maintenance • Workplace activities such as: – Constructing, – Installing, – Setting up, – Adjusting, – Inspecting, – Modifying, and – Maintaining and/or servicing machines or equipment
  • 18. Tagout • Placement of tagout device – on an energy isolating device, – in accordance with an established procedure, – to indicate that energy isolating device and equipment being controlled may not be operated until tagout device is removed
  • 20. Energy control program • Energy control procedures • Employee training • Periodic inspections • Any employee who services/maintains any equipment where unexpected energizing or stored energy release could cause injury isolates and renders it inoperative first.
  • 21. 1910.147(c)(ii) General Requirements • If an energy isolating device is capable of being locked out, the employer's energy control program shall utilize lockout, unless the employer can demonstrate that the utilization of a tagout system will provide full employee protection
  • 22. 1910.147(c)(iii) General Requirements • Energy isolating devices designed to accept lockout devices whenever: – Replacement or major repair, renovation or modification of equipment is performed or – New machines or equipment are installed
  • 23. 1910.147(c)(3) Full employee protection • When tagout device used on energy isolation device capable of being locked out: – Same location as potential lockout device – Demonstrably equivalent program • May require additional safety elements
  • 24. 1910.147(c)(4) Energy control procedure • Procedures shall be developed, documented and utilized for the control of potentially hazardous energy when employees are engaged in the activities covered by this section. – Exception with all 8 elements listed in standard
  • 25. 1910.147(c)(4) Energy control procedure • Outline scope, purpose, authorization, rules, techniques for control of hazardous energy, including: – Specific intended use of the procedure; – Specific steps for shutting down, isolating, blocking and securing equipment – Specific steps for placement, removal, transfer of lockout/tagout devices and responsibility for them – Specific requirements for testing equipment to verify effectiveness of lockout devices, tagout devices, and other energy control measures
  • 26. 1910.147(c)(5) Protective materials and hardware • Locks, tags, chains, wedges, key blocks, adapter pins, self-locking fasteners, or other hardware shall be provided by the employer for isolating, securing or blocking of equipment from energy sources
  • 27. 1910.147(c)(5) Protective materials and hardware • Lockout and tagout devices must be: – Singularly identified – The only device(s) used for controlling energy – Not used for other purposes – And shall meet the following requirements:
  • 28. 1910.147(c)(5) Protective materials and hardware • Capable of withstanding environment for maximum time period • Moisture or corrosives must not make tag deteriorate • Standardized: – Color – Shape – Size – Print/Format
  • 29. 1910.147(c)(5) Protective materials and hardware • Lockout devices: – Substantial enough to prevent removal without excessive force or unusual techniques such as bolt cutters • Tagout devices: – Substantial enough to prevent inadvertent or accidental removal – Non-reusable attachment means – Attachable by hand, self-lockable – At least equivalent to nylon cable tie
  • 30. 1910.147(c)(5) Protective materials and hardware • Lockout and tagout devices indicate identity of employee applying devices
  • 31. 1910.147(c)(6) Periodic Inspection • Energy control procedure inspected at least annually: – By authorized employee not using the procedure being inspected – Correct any deviations – Review employee responsibilities with: • each authorized employee – lockout • each affected or authorized employee – tagout
  • 32. 1910.147 (c)(7) Training and communication • Ensure employees understand purpose and function of energy control program • Ensure employees acquire skills required for safe application, usage, removal of energy controls
  • 33. Employee Training Requirements • Authorized employee: – Recognition of hazardous energy sources – Type and amount of energy in workplace – Methods and means for energy isolation • Affected employee: – Purpose and use of procedure • Other employees in area: – Procedure and prohibition on restarting
  • 34. Employee Training Requirements for Tagout • Train on limitations of tags: – Warning devices do not provide physical restraint that a lock would – Tag not to be removed without owner’s authorization, bypassed, ignored, defeated – Must be legible / understandable to work – Must withstand environmental conditions – False sense of security – Attach securely: avoid accidental removal
  • 35. Employee Retraining • For all authorized or affected employees when: – Job assignment changes – Equipment or processes present new hazard – Energy control procedure changes – Knowledge / use of program is inadequate • Certify employee training up to date
  • 36. 1910.147(c)(8) Energy Isolation • Only the authorized employees performing the servicing or maintenance may apply lockout/tagout
  • 37. 1910.147(c)(9) Notification of Employees • Affected employees must be notified – By employer or authorized employee – Of application and removal of lockout and tagout devices – Before controls are applied – After controls are removed
  • 38. Order of Operation for Application of Control 1. Preparation for shutdown 2. Equipment shutdown – orderly 3. Equipment isolation 4. Lockout or tagout device application 5. Stored energy relieved; continue while reaccumulating 6. Verification of isolation – Test and return to “off” position
  • 39. 1910.147(e) Release from Lockout • Before lockout or tagout devices removed and energy restored, ensure: • Machine or equipment: – Inspect area; remove nonessential items – Ensure equipment components intact • Employees: – Ensure all employees safe or removed – Before restart, notify affected employees of removal
  • 40. 1910.147(e) Release from Lockout • Each lockout/tagout device removed by employee who applied the device – If not available, removed under employer direction – Specific procedures and training from energy control program must be in use! • Verify that applying employee is not at facility • Make all reasonable efforts to contact/notify • Ensure authorized employee knows of removal before resuming work at facility
  • 41. 1910.147(f)(1) Testing or Positioning • Temporary removal of lockout/tagout devices for testing/positioning: – Clear tools and materials – Remove employees from equipment area – Remove lockout/tagout devices (as in (e)) – Energize and test or position – Deenergize systems and reapply energy control measures to continue servicing
  • 42. 1910.147(f)(2) Outside Personnel • Contractors and other outside personnel: – On-site employer and outside employer inform each other of lockout/tagout procedures – On-site employer complies with outside employer’s energy control program
  • 43. 1910.147(f)(3) Group Lockout or Tagout • Procedure must provide protection equivalent to personal lockout/tagout device • Primary responsibility is vested in an authorized employee for a set number of employees working under the protection of a group lockout or tagout device (such as an operations lock);
  • 44. 1910.147(f)(3) Group Lockout or Tagout • When more than one crew, craft, department, etc. is involved: – Designated authorized employee takes lockout/tagout control responsibility – Coordinates affected work forces – Ensures continuity of protection
  • 45. 1910.147(f)(3) Group Lockout or Tagout • Each authorized employee affixes personal lockout/tagout device to group lockout device when beginning work • Each removes personal device when stopping work on this equipment
  • 46. 1910.147(f)(4) Shift or Personnel Changes • Specific procedures in energy control plan • Ensure continuity of lockout/tagout protection • Orderly transfer of lockout/tagout device protection between shifts • Minimize exposure to hazards from unexpected energization or release